Instruction of Generator
Instruction of Generator
Q96M
Q96M SYE
Version:1
Prepared:汪云山
Checked:郑瑞华
Reviewed:史艳华
Approved:潘海升
Date:2008.4
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Content
Preface 6
1. General introduction 6
1.1 Summary 6
1.2 General characteristic of generator 9
1.2.1 Rated parameters 9
1.2.2 Dimensions and weights 9
1.2.3 Reactance and constants 10
1.2.4 Characteristic curves 11
1.2.5 Coolant 16
1.3 Generator maintenance, overhaul and storage 17
1.3.1 General 17
1.3.2 Tightness checking for hydrogen leaks 17
1.3.3 Hydrogen fire 18
1.3.4 General maintenance of generator during operation 18
1.3.5 Maintenance during a shut down 19
1.3.6 Storage of the generator 21
2 Generator stator 24
2.1 General structure 24
2.1.1 The frame 24
2.1.2 The terminal box 24
2.1.3 The coolers 24
2.1.4 The magnetic core 32
2.1.5 Stator winding 36
2.1.6 High voltage terminal leads 42
2.2 Generator fluid supply circuits 47
2.2.1 CO2 supply circuit 47
2.2.2 H2 or gas supply circuit 47
2.2.3 Deionized water supply circuit 47
2.3 Stator preservation 50
2.3.1 Generator at standstill-closed 50
2.3.2 Generator at standstill – open 52
2.4 Disassembly of a coolers 53
2.4.1 The disassembly of cooler 53
2.4.2 Cooler reassembly 59
2.4.3 Cooler maintenance operations 61
2.4.4 Storage and preservation at standstill 62
Page: 1
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
2.5 Stator winding maintenance 63
2.5.1 General requirement 63
2.5.2 Specific equipment 63
2.5.3 Testing the stator winding insulation resistance 64
2.5.4 Test the dielectric strength of the stator winding 65
2.5.5 Stator winding maintenance 66
2.6 Adjustment of the stator 66
2.6.1 Disassembly operations 66
2.6.2 Vertical adjustment 69
2.6.3 Transverse adjustment 69
2.6.4 Reassembly 69
3 Generator rotor 70
3.1 The generator rotor structure 70
3.1.1 The rotor shaft 70
3.1.2 Rotor winding 70
3.1.3 Retaining rings & centering rings 74
3.1.4 Axial fan 80
3.1.5 Excitation connections 80
3.1.6 Cooling of slip rings 82
3.2 Rotor removal and installation 85
3.2.1 Operations required for rotor removal 85
3.2.2 The work after rotor inserted 87
3.2.3 Removal of the generator rotor 87
3.2.4 Rotor installation 98
3.3 Maintenance of generator rotor 101
3.3.1 General requirement 101
3.3.2 Storage and conservation of rotor 101
3.4 Disassembly and reassembly of couplings - unit shaft alignment 104
3.4.1 Disassembly of turbine-generator 104
3.4.2 Reassembly of turbine-generator coupling - shaft alignment 105
3.5 Maintenance of rotor winding 105
3.5.1 Preparatory operations 105
3.5.2 Precautions to be taken during tests 106
3.6 Fan 109
3.6.1 Disassembly of main fan blades 109
3.6.2 Reassembly of main fan blades 109
Page: 2
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
4.1 End structures 111
4.1.1 Journal bearing 111
4.1.2 Lower half-bearing 111
4.1.3 Upper half bearing 117
4.1.4 End shield bearing 117
4.1.5 Clamping collar 117
4.1.6 Shaft seal 117
4.1.7 Oil deflectors 118
4.1.8 Ventilation guides 124
4.1.9 Axial alignment key 124
4.2 Maintenance operations for bearing and shaft seal rings 124
4.2.1 Assembly of the external support of the rotor 124
4.2.2 Removal of the journal bearings at the turbine and excitation ends 128
4.2.3 Assembly and disassembly of the bearings and accessories 141
4.2.4 Reassembly, assembly and maintenance of the shaft seal rings 156
4.2.5 Reassembly, assembly and maintenance of the oil deflectors 159
4.2.6 Disassembly and reassembly of hydrogen guides (fan nozzle rings) 168
4.2.7 Disassembly and reassembly of axial alignment system tooling 170
4.2.8 Disassembly and reassembly of bearing oil inlet and outlet pipes 171
5. Generator detection and protection 180
5.1 Stator detection and protection 180
5.1.1 Temperature sensors for magnetic core, copper shield 180
5.1.2 Temperature instrumentation of stator bars 181
5.1.3 Temperature instrumentation of cooling water of stator winding 181
5.1.4 Temperature instrumentation of circular phase connections 182
5.1.5 Temperature instrumentation of hydrogen 182
5.1.6 Leading-out of stator temperature instrumentation 187
5.1.7 Frame grounding 187
5.2 Temperature instrumentation of journal bearing 191
5.2.1 The thermocouple with rigid sheath 191
5.2.2 Temperature instrumentation of journal bearing 191
5.2.3 Temperature instrumentation of restraining bearing 191
5.3 Rotor detection and protection 192
5.3.1 Shaft vibration measurement 192
5.3.2 Detection of inter-turn insulation fault in rotor winding 192
5.3.3 Rotor grounding 202
5.3.4 Insulation of bearing excitation end 202
5.3.5 Insulation of restraining bearing 203
Page: 3
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
6 Generator installation 211
6.1 General requirements 211
6.2 Generator installation procedures 211
6.3 Foundation plate installation 213
6.4 Stator and terminal box installation 215
6.5 End shield bearing and winding cover-H2 fan nozzle ring installation 216
6.6 Brush and soundproof housing installation 217
6.6.1 Documents preparation 217
6.6.2 Seat box installation 217
6.6.3 Brush gear installation 217
6.6.4 Restraining bearing installation 217
6.6.5 Soundproof housing installation 218
6.7 High voltage terminal installation 218
6.7.1High voltage bushing installation 218
6.7.2 Current transformer and water manifold installation 219
6.7.3 Intermediate connection installation 220
7 Generator operation 221
7.1 Unit start-up 221
7.2 Unit shut-down 221
7.3 Monitoring in operation 222
7.4 Alarm and treatment 223
7.4.1 Stator winding temperature alarm and treatment 223
7.4.2 Hot hydrogen temperature alarm and treatment 225
7.4.3 Cold hydrogen temperature alarm and treatment 225
7.4.4 Stator core end structure and copper shield temperature alarm and treatment 225
7.4.5 Journal bearing temperature alarm and treatment 226
7.4.6 Shaft vibration alarm and treatment 226
7.5 Other protection items 227
Appendix A Visual examination and dye penetrate examination of journal bearing 229
Appendix B Hydrogen cooled turbine generator sealing glue operation instruction 231
Appendix C Storage condition of insulation material for installation 233
Appendix D calculation of perpendicular distance between arc and chord for centering by steel wire 234
Appendix E High terminal connection installation inside terminal box 235
Appendix F Supplement for Inspection and Test Item of the Generator 239
Page: 4
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Preface
This manual is used for reference only. It applies to the 330MW generators (type: T255-460) made by BSTG. For
the contents not specified in this manual, please refer to the IEC standards, the related ALSTOM standards and
factory standards.
This manual is about the main technical data , structures, installation, operation and maintenance of 330MW
generator (type T255-460) and so on.
This manual can only be used for the generator. The auxiliary system (including excitation system, seal oil systems,
cooling water system and hydrogen system, etc.) will be mentioned in separate specific manuals.
1.General introduction
1.1 Summary
The generator itself is basically composed of three distinct parts:
●the generator stator and end structures
●the generator rotor
●the brush gear
Static excitation system, including excitation transformer, provides DC power to the field (rotor) winding. This
system is described in a separate manual.
It should be noted that:
●the cooling of the machine with hydrogen under a pressure of 3 bars(g) and with the stator windings cooled by
water, on the one hand
●the necessity for a rigorous hydrogen tightness where the shaft comes out of the two ends of the stator, on the
other hand
leads to the addition of several ancillary devices or ‘auxiliaries' of the generator. These are:
●the supply system of the shaft sealing oil, the purpose of which is to prevent any hydrogen leaking from the
generator enclosure via the clearance between the stationary and rotating parts (shaft ends) at the ends of the stator
●the unit supplying deionized water to cool the bars of the stator winding
●the gas supply unit
—hydrogen for normal operation
—CO2 for the intermediate phases of filling or emptying the stator.
All of these auxiliary functions are dealt with in separate specific manuals.
It should be emphasized that the lubricating oil system of the turbine bearings also provides:
●the oil flow necessary to lubricate the generator journal bearings
●the oil flow necessary for hydrogen tightness at the ends of the generator shaft.
The description of the generator can therefore be divided into several essential categories:
●The general of the generator
●the generator stator
●The generator rotor
●the end structures
Page: 5
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
●the monitoring and measuring instruments and the generator protection devices.
●The installation of the generator
●The operation of the generator
Drawing 1-1 represents the longitudinal section of the generator.
Page: 6
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Drawing 1-2 represents the electrical and hydraulic diagram of the stator winding.
Page: 7
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 8
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
1.2 Main characteristic of generator
1.2.1 Rated parameters
Type T255-460
Rated speed 3000r/min
Active power 330MW
Power factor 0.85
Rated voltage 24kV
Voltage variation ±5%
Rated current 9339A
Number of poles 2
Frequency 50Hz
Excitation current 2495A
Insulation class F (Application class B)
Water temperature at inlet of H2 Cooler ≤38 ℃
Type of cooling:
—Cooling of magnetic core H2
—Cooling of stator winding deionized water
—Cooling of rotor winding H2
—Cooling of H.V. voltage terminals deionized water
Normal duty conditions:
—Stator water temperature rise 18K
—Rotor winding temperature rise 48K
—H2 pressure 0.3MPa(g)
—Deionized water temperature 46 ℃
—Power 330MW
Abnormal duty conditions:
—With one cooler out of operation 258.8MVA(220MW)
—Steady state negative phase-sequence current I2/IN 12%
2
—Transient negative phase-sequence current (I2/IN.) t 10s
Page: 11
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 12
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 13
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 14
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
Drawing 1-6
Page: 15
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
1.2.5 Coolant
(1) Hydrogen
Flow rate 36 m3/s
Losses to be evacuated maxi 2430 kW
Rated pressure 0.3 MPa(g)
Number of coolers 4 groups (2 pieces)
(2) Deionized water
Total flow rate (winding) 60 m3/h
Terminals connections 9 m3/h
Losses to be evacuated 1135 kW
Number of coolers 2
(3) Raw water
Rated temperature 38 °C
Overall flow rate: hydrogen coolers 325 m3/h
Water coolers 120 m3/h
(4) Journal bearing and oil seal
Journal bearings Elliptical
Diameter 450 mm (turbine end)
420 mm (excitation end)
Useful width 260 mm (turbine end)
280mm (excitation end)
Specific pressure 2.09 MPa
Oil flow rate 475 L/min (turbine end)
430 L/min (excitation end)
Losses 150kW (turbine end)
140 kW (excitation end)
Shaft seals:
—Type single circuit shaft sealing
—Number 2
—Diametric clearance on H2 side 0.16 mm
—Diametric clearance on air side 0.08 mm
—Oil flowrate 40 L/min (turbine end)
30 L/min (excitation end)
Restraining Bearing
—Type cylindrical
—Diameter 160mm
—Number 1
—Oil flowrate 24 L/min
(5) Slip ring and brush
—Slip ring diameter 410mm
Page: 16
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
slip ring width 168mm
slip ring material 50Mn
—Brush NCC634
dimensions 32×32
quantity 80
1.3.1 General
Maintenance work on a turbogenerator may only be carried out if certain requirements regarding
safety and working procedures are met.
They are:
—tightness and checking for hydrogen leaks
—maintenance of the unit in operation
—maintenance of the unit at standstill
—general instructions regarding storage
When the generator is at standstill for a short or long period of time, various precautions should
be taken. These instructions on preservation are given in chapter 2 (generator rotor) and in
chapter 3 (generator stator).
1.3.2 Tightness checking for hydrogen leaks
The tightness of a generator is systematically tested after maintenance work involving the
opening of the hydrogen enclosure. This check is performed with the generator full of air.
If there is an increase in hydrogen consumption while the generator is in operation it is
imperative to check for hydrogen leaks.
A difference shall be made between these two cases.
(1) Checking the tightness of the generator
With the generator closed and the seal oil circuit in service, fill the generator with air to the
nominal operating pressure.
With the temperature stabilized, the generator is said to be tight if the pressure falls by less than
0.004MPa in 24 hours.
If this is not the case, check for leaks using soapy water. Check the joints which have been
disassembled and reassembled and the shaft seals.
Check also that the seal oil circuit and the cooling circuits (coolers, pipe connections, valves etc)
are operating correctly. The generator may only be refilled with hydrogen if it is satisfactorily
tight.
(2) Checking for hydrogen leaks
Micro-leaks from different parts of the generator and its auxiliaries, and in particular
consumption of hydrogen by the seal oil circuit, mean that frequent topping up with hydrogen is
necessary in order to maintain the pressure in the generator enclosure as near as possible to its
Page: 17
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
normal value.
As soon as hydrogen make up become more frequent, in other words, when the hydrogen
consumption increases, attempts should be made to establish the cause immediately.
In order to do this, it is necessary:
to carefully monitor the conductivity of the stator cooling water
to monitor the temperature of the various cooling circuits (stator water, raw water, hydrogen,
air etc)
to check the overpressure valves
to try and locate the hydrogen leak
The leak may be located using a hydrogen detector or an analyzer placed against the bearing vent
holes, the vents of the various circuits, and the outer seals (coolers, terminals, bearing, etc).
The leak may be located by isolating each hydrogen cooler separately and monitoring the
increase in hydrogen consumption.
Monitoring the gas flow in the buffer tank of the stator winding cooling water circuit may yield
information also.
WARNING:
if an increase in the conductivity of the stator winding cooling water accompanies the
increased hydrogen consumption, the unit should be shut down and the constructor notified
do not make up the hydrogen if the consumption is abnormal
if the fall in pressure is more than 0.04 MPa in 24 hours , fill the generator with air and try
and locate the leak as explained in section (1)
once a leak has been detected, it is vital to identify the leaking hydrogen circuit and where
hydrogen might possibly accumulate (condenser, coolers, tank, pump, high points, etc). If
there is any doubt, proceed with a systematic search using an analyzer. Drain the zones
where hydrogen has been detected.
As soon as the leak has been identified, ensure that its repair will not require replacing the
hydrogen in the machine with air, and then commence work.
The generator shall only be started up again when the hydrogen tightness is correct.
1.3.3 Hydrogen fire
Hydrogen escaping through a leak may lead to the gas jet catching fire. The fire department can
only treat fires exterior to the generator itself. However the hydrogen frame may be extinguished
by removal of all hydrogen from the generator.
In the event of a hydrogen fire, rapidly evacuate all hydrogen from the generator and its
auxiliaries, full with carbon dioxide and alert the fire department
1.3.4 General maintenance of generator during operation
The suggested frequency of each operation represents a minimum level of precaution.
The user may increase the frequency of these operations at his own discretion.
The following table shows the maintenance operations to be carried out on the generator during
operation, together with their frequency.
Page: 18
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
The operations are described in the chapter s indicated.
Operations Frequency
Testing bearing insulation – opposite turbine end Weekly
Page: 19
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Item Operation description mo MO TYO chapter
Page: 20
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Item Operation description mo MO TYO chapter
US tests of foundation tie rods ×
4 coolers 2.4.3
Clearance of tube bundle and water boxes × × ×
Clearance of tube bundle at gas end × ×
Tightness tests at water side × ×
Blowing-purging and draining of pipework × × ×
E Rotor checking tests
Inter-turn short circuit detectors × ×
Visual inspection × ×
Blade liquid penetrate test ×
Visual inspection of blades × ×
Rotor tightness × ×
Geometrical checking of the shaft seal
× × 3.3.1
supporting surface
Visual inspection of the shaft seal and
× × ×
journal bearing supporting surfaces
Rotor insulation resistance × × ×
Visual inspection of the rotor winding × ×
Visual inspection of the turbine coupling × ×
Visual inspection of small shaft and the
× ×
coupling at excitation end.
F Brush gear and slip rings
Visual inspection of slip rings × × ×
Dimension check of slip rings × ×
Visual inspection of brushes, brush gear,
× × ×
brush holders, springs
Visual inspection of slip ring connection × × ×
Insulation resistance of brush gear × × ×
During storage, equipment is kept in good condition by protective covers and initial conditioning
and also by continual checks on the storage conditions. These checks are very important.
The equipment should be stored in closed buildings with heating facilities and concrete flooring
coated with anti-dust paint. It should be protected against dripping water and direct sunlight which
are likely to damage the protective agents. The flooring should be strong enough to withstand the
loads imposed on it.
The buildings should be organized so as to facilitate delivery and removal of equipment.
The equipment should be kept off the floor by crating or supports, with a plastic sheet between the
equipment and the support-It should be protected against insects and small rodents and should be
arranged so as to facilitate access for inspection, and if necessary, replace the packing.
Page: 21
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
A log book should be started as soon as the equipment arrives at the site of storage, to ensure that all
equipment is monitored during storage. The following information should be entered in the record
book:
2 daily temperature and humidity readings inside the storage building.
Storage conditions.
Inspections made, together with a general report on the state of the equipment and the storage
conditions, and the dates of such operations.
A detailed report (with date) of any anomalies observed during inspection.
A detailed report (with date) of readings taken in order to remedy any storage defects.
Parts protected by paint should be examined on arrival at the site of storage and every moth during
storage. Any paintwork damaged by knocks or slinging should be touched up and restored to its
initial condition. When replacing a drying agent or volatile inhibitor, use the same quantities as those
originally contained in the crate. The replacement products should be placed in the same position as
the original products.
Page: 23
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
2.Generator stator
2.1 General structure (See drawing 2-1)
The frame is a single block; this allows the stator to be assembled entirely at the factory, including
the stacking and clamping of the magnetic core and the definitive installation of the stator bars, their
wedges and connections.
In this way, the finished stator can be delivered to the plant.
As the frame must withstand the internal pressure of the hydrogen, the whole assembly, together
with its welded joints, is designed to give complete tightness, and is carefully tested after
manufacture.
The frame forms the outer casing of the turbo-generator.
It reassembles a tank, the ends of which have centrally located openings crossed by the shaft ends.
The frame is made up of a series of plates electrically welded together. The steel plates used are of
good welding quality.
It constitutes a practically cylindrical shell, and is provided with frame feet (support brackets) along
each side.
It is reinforced internally by rings placed perpendicular to the shaft axis.
These rings give the frame the necessary rigidity, and also support the bars holding the magnetic
core.
The frame also envelops the cooling circuit, and the axial subdivisions are designed to ensure
optimum distribution of gas to all parts of the generator.
Each end of the frame is fitted with a thick machined flange whose function is to support the shaft
bearing assembly.
It also has compartments containing the coolers and is dimensioned to withstand, without damage,
all the various stresses to which it is subjected (transport, tensional stress, etc.).
The terminal box is fastened to the underside of the frame, on the excitation end.
It is made up of welded plates, some non-magnetic.
The bottom plate has six openings in which the six generator outlet terminals are fitted.
The terminal box is hydrogen-cooled.
The terminal boxes are fastened on site by means of bolts.
The frame-terminal box tightness is maintained by a thin bead of weld applied during site erection.
This weld is sufficient for hydrogen tightness during operation and it allows fairly easy removal in
the event of subsequent interventions which would require the removal of the terminal box.
(1)Cooler chassis
The chassis (7) is constituted of metal profiles assembled in the form of a box. It serves to hold the
end tube sheets as well as two sheet metal pieces parallel to the gas flow and which act as guide
runners.
Inside the chassis are a series of intermediate tube sheets which support the cooling tubes.
The chassis permits the transportation and handling of the cooler without additional tools, and serves
to attach it inside the generator frame.
The chassis is protected by anti-rust paint.
(2)Tube nest and end tube sheets
The active part of the cooler unit consists of a nest of firmed tubes (6) running perpendicular to the
gas flow. The tubes can be finned by:
—either winding a wire around the tubes, aligned radially to the axis,
—or by a series of thin metal parallel sheets, traversed by all the tubes.
In both cases, the fins are made of materials offering good thermal conductivity (e.g. copper).
Page: 25
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 26
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 27
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
The end of each tube, free of fins, is expanded into a thick plate, the end tube sheet (4). The end tube
sheets provide for the even distribution of water into the tubes as well as attaching them to the
chassis.
One of the end tube sheets is firmly fastened to the chassis; the other sheet is only guided axially in
order to allow for differential expansion between the tubes and the chassis.
The tube nest is held within the chassis by intermediate support plates.
(3)Water supply
On each end tube sheet, water boxes or water manifolds (1) and (2) are fixed.
The water box on the inlet/outlet end (1) is fitted with an inlet pipe (8) and an outlet pipe (9). The
inside of the box is divided into compartments by dividing walls.
The water box on the opposite end is simply an enclosure of the end tube sheet.
This system provides a multi-pass flow within the tube nest which optimizes the efficiency of the
heat exchanger, reduces internal temperature differences, and groups the cooling pipe-work together.
As the coolers are placed horizontally on the generator, threaded plugs situated in the high and low
points of each water box indicate when they are full, enable gas bleeding, and allow draining of the
units.
The inside surfaces of the water boxes are protected by a coat of bituminous paint and the outside
receives a coat of anti-rust paint.
(4)Tightness of coolers
The coolers are in contact with three media: air, water and hydrogen. Because of this, there must be
perfect tightness between the coolers and the three media.
1) Tightness between the hydrogen circuit and ambient air
Drawing 2-3 represents the tightness system between the frame and the coolers.
The facing edges of the tube sheet (2) are machined smooth.
Between each sheet and the metal frame (3) is placed a rubber gasket (4) which is compressed
inside its housing by parts (5) and (6).
The frame (3) is bolted to the cooler extension (1) and tightness is provided by a gasket (7).
This system maintains perfect tightness between the cooler and the cooler extension while
allowing movement between the different parts.
2) Tightness between the hydrogen circuit and the water circuit
Here the tightness comes from the perfect quality of each cooling tube. This quality is checked
throughout the manufacturing process.
Tightness also comes from correctly expanding each tube in the tube sheets.
Absence of water-to-hydrogen and hydrogen-to-water leaks is checked by hydraulic tests
made on the finished cooler.
3) Tightness between the water circuit and the ambient air
This tightness is obtained by placing a flat gasket between the tube sheet and the water box
Page: 28
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
and then by adequate clamping between these two parts.
Before installation, hydrostatic pressure test and sealing test must be made.
Test pressure should be 0.8MPa gauge and applied for 15 minutes.
The sealing test shall be carried out according to JB/T6227 “checking method and evaluation
of the sealing ability of hydrogen-cooled machines”.
(5)position of the coolers in the generator(see drawing 2-4)
The coolers are mounted horizontally in the generator, the water being supplied from a unit
positioned diagonally to each end of the generator.
They are placed in the upper part of the frame, and are positioned symmetrically with respect to the
stator axis.
They are position (symmetrically) within the hydrogen circuit.
The coolers are connected in parallel on the water circuit.
Page: 29
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 30
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 31
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
2.1.4 The magnetic core
The magnetic core structure sees drawing 2-5
(1)Magnetic core segment
The magnetic core is made up of a stack of special grain-oriented magnetic steel segments, or
laminations.
These laminations are characterized by their method of manufacture - cold rolling - their low loss
and high permeability, and their special cold-rolled coating.
Each segment is further insulated with a thin coat of oil varnish containing colloidal silica.
This type of magnetic lamination presents several advantages:
As the maximum magnetic permeability is in the direction of the flux flow, the radial height of
the yoke can be reduced: This allows the construction of a single-block stator.
Considerable reduction of the magnetomotive force required in the yoke.
Lower overall core loss than with ordinary laminations.
high stacking factor, due to the high permeability of this cold-rolled steel
Protective coating, applied at the outset to both faces, which resists temperatures above 300°C
and reinforces the main electrical insulation provided by enamelling the punching.
The core stack is made up of many punching packets (1) each several centimeters thick, with
staggered joints between adjacent laminations within each packet.
Separating the packets are radial vent ducts (2), through which the hydrogen flows to cool the
magnetic core.
The first packets at each end of the core are provided with a specially reinforced insulation.
The spacer ribs on the vent ducts are non-magnetic.
In addition to the radial field flux, the core ends are also subject to a front fringing flux, whose axial
component increases with a low excitation current, particularly when operating with reactive load
absorption.
The additional losses caused by this fringing flux have necessitated specific design features at the
core ends in order to prevent unacceptable temperature rises:
The outermost laminations (2) are stepped (i.e. with progressive reduction in radial core height)
in order provide a better trap for the fringing flux, and to facilitate entry of hydrogen into the air
gap.
These laminations are glued together in their packets
The teeth of the end laminations are slit down to the level of the bottom of the slot in order to
minimize sling currents in the teeth.
The outer edge of each lamination is provided with dovetail slots which serve to fasten the core to
the key-bars (4) evenly spaced around the inner frame bore.
Page: 32
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
which rotates at the same speed as the rotor and produces a 4-node vibration mode.
In order to minimize the transmission of radial vibrations to the frame, end structures, and
foundations, the core is stacked on key-bars which are fastened to the frame via a special flexible
mounting.
Each key bar (1) is welded on the support ring (6), which is itself welded onto the spring bars (2)
which are the both welded onto the frame ring (3). This arrangement provides the vibration
decoupling between the magnetic core and the frame.
The flexible support system is designed to allow not only for radial displacement caused by
magnetic attraction and expansion, but also for tangential displacement arising from normal or
accidental torques. These displacements are, of course, relative to the fixed frame, which is anchored
to the foundations via the frame feet. The damping between the core and the frame is sufficient to
ensure that only a small percentage of core vibrations are transmitted across the support system: this
guarantees a low level of vibrations in the frame.
The inner face of the key-bars has a dove-tail section (5) onto which the core laminations (4) are
fixed.
(3)Core clamping plates-flux shields (see figure 2-5)
1) Core Clamping Plates
Two single-piece plates (6), one at each end of the stator, provide firm axial clamping of the
magnetic core assembly.
The clamping force exerted by these plates is transmitted to the core via clamping fingers (7),
welded onto the end laminations opposite each tooth; this arrangement ensures adequate distribution
of pressure from the plate of the core. This clamping force corresponds to an elastic deformation of
the two clamping plates, achieved by tightening the nuts (5) on the threaded ends of the key bars (4)
which tie the two plates together.
2) Flux shields
In view of the considerable alternating magnetic fields in the immediate vicinity of the clamping
plates, special precautions are taken to minimize stray load loss in these areas.
Both ends of the core are protected by an annular cooper damper screen, or flux shield (8), which is
shaped to fit the core clamping plate. These damper screens shield the core end assemblies from the
front leakage flux flowing between rotor and stator
(4)Cooling of magnetic core and core end
1) Magnetic core
Calories lost in the magnetic core (1) are removed by cold hydrogen flowing through the radial vent
ducts (2) under the action of the fans. These vent ducts are formed by splitting up the core, along its
whole length, into packets separated from each other by radial spacer ribs. Core cooling is thus of the
"radial" type.
2) Core end structures
Cold hydrogen flowing between the clamping fingers (7), and in the space between the flux shield
(8) and the clamping plate (6), removes the calories lost in these end structures.
Page: 33
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 34
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 35
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
2.1.5 Stator winding
(2) Radial and tangential wedging in the core (see drawing 2-9)
The high current levels in the conductor bars require wedging which is particularly resistant to
mechanical stresses and vibration. Bars are equipped with radial and tangential wedging in the stator
core slots.
1) Radial wedging
The slot bottom bar (1) pushes radially against the core (3) via the slot bottom pad (4). This pad is
made of thermo-setting resin which moulds itself to the bottom of the bar and thereby ensures
uniform contact pressure between the bar and the core. The slot bottom bars (1) and air gap bars (2)
are separated by an insulating wedge (5) and leveling strips (7). The bars are held radially by the
combined effort exerted by the slot closing wedges (6) and the tapered wedges (9) pushing against
the air gap bar (2) via ripple spring (8).
2) Tangential wedging
Each slot bottom bar (1) and air gap bar (2) is blocked tangentially by inserting a set of tapered
wedges (10) between the magnetic core (3) and the screwing in order to immobilize the bars in the
stator slots.
Page: 37
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 38
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 39
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 40
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 42
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 43
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 44
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 45
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
the generator enclosure, to use an intermediate gas so as to prevent the formation of such a mixture.
The gas used for this intermediate filling phase is carbon dioxide, which is neutral with respect to
both air and hydrogen.
Calorific losses of the stator winding are evacuated by deionized water circulating in the bars.
The following distinct circuits are thus necessary:
CO2 supply circuit
H2 or gas supply circuit
Deionized water supply circuit
Page: 47
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 48
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
(1)Seal oil circuit available
The stator winding cooling water circuit is in operation
The shaft seal oil circuit must be in operation
The filling of the machine with air is left to the discretion of the utility.
① Generator remains in H2 at rated pressure
The water-to-water exchanger must not be in operation: Either closes the secondary circuit, or
by-pass the primary circuit (i.e. the water circulating in the stator winding).
The stator winding cooling water is in circulation. The pressure must be at least 0.02 MPa below
that of the gas in the machine in order to prevent possible micro-leaks from making the winding
insulation damp.
This pressure is read on the pressure gauge mounted on the generator inlet line
② generator remains in H2 at reduced pressure
The H2 pressure must remain ≥ 0.05MPa gauge to prevent air from entering the machine.
The H2 pressure shall be adjusted according to the pressure setting range of the water circulating
in the stator winding to respect the difference previously defined, i.e. 0.02MPa minimum. (See
NOTE 1).
The requirements for stator cooling system should be done in accordance with item ①
③ Generator in air above atmospheric pressure (see NOTE 2)
The air pressure shall be adjusted according to the pressure setting range of the water circulating
in the stator winding ,i.e. item
The requirements for stator cooling system should be done in accordance with item
NOTE 1: The generator does usually not start-up in air condition. For special condition, detailed
instruction should be given.
NOTE 2:At any case, the duration that the generator is filled with CO 2 is not higher than 24 hours.
In general, it should be limited in 6 hours.
(2) The generator is filled with air at atmospheric pressure
The generator is filled with air at atmospheric pressure ( see NOTE 2 )
The stator water circuit exchanger is locked and isolated
The pumps of the stator winding cooling water circuit are mandatory stopped
The shaft seal oil circuit is stopped
① the stator winding cooling water circuit is in operation
a. Duration of standstill < 3 weeks
The exchanger is locked. The pumps of the first/ second circuit are stopped to prevent possible
micro-leaks from making the winding insulation damp
After having checked the generator bottom points when re-starting, the normal water con-
ductivity level must be restored (≤1.0μs/cm); to achieve this, circulate the cooling water through
the system for approx. 24 hours after bringing the H2 to its rated pressure.
b. Duration of standstill: between 3 weeks and 4 months
The stator water circuit exchanger is locked and isolated
Page: 49
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
The winding is drained by gravity. Blow through by means of the gas used for the
conditioning defined below
The circuit is either filled with dry and oil-free filtered air for stator windings with natural
aeration or air scavenging, or with inert gas (helium, nitrogen) for hydrogen conditioned stator
windings; in the later case, an alight overpressure is required with respect to the atmospheric
pressure in order to compensate for possible micro-leaks.
c. Duration of standstill: more than 4 months
The stator water circuit exchanger is locked and isolated
The winding is drained by gravity. To remove water pockets, carry out several blows through
operations with dry and oil-free filtered air for stator windings with natural aeration or air
scavenging, or with inert gas (helium, nitrogen) for hydrogen conditioned stator windings. After
having isolated the generator from the water circuit, vacuum-dry the winding and break vacuum
using dry and oil-free air (dry air can be replaced by nitrogen)
② The stator winding cooling water system
a. Duration of standstill < 3 weeks
The stator water circuit exchanger is locked and isolated. The pumps of the first/second
circuit are stopped to prevent possible micro-leaks from making the winding insulation
damp.
The circuit in operation can be disconnected from the other systems: In this case, before re-
starting, the conductivity level of the water left in the circuit must be complied from related
standards.
The circuit in operation can’t be disconnected with the other systems: In this case, drain the
water in circuit thoroughly, and then fill the circuit with water.
b. Duration of standstill: between 3 weeks and 4 months
The stator water circuit exchanger is locked and isolated. The pumps of the circuit are
stopped to prevent possible micro-leaks from making the winding insulation damp.
The winding is drained by gravity. Disconnected generator from other systems by blind
flange, then fill the generator with Nitrogen.
c. Duration of standstill: more than 4 months
The stator water circuit exchanger is locked and isolated
The winding is drained by gravity. To remove water pockets, carry out several blows through
operations with dry and oil-free filtered air for stator windings with natural aeration or air
scavenging, or with inert gas (helium, nitrogen) for hydrogen conditioned stator windings.
After having isolated the generator from the water circuit, vacuum-dry the winding and break
vacuum using dry and oil-free air (dry air can be replaced by nitrogen)
2.3.2 Generator at standstill - open
The shaft seal oil circuit is shut down
The generator is in air at atmospheric pressure
(1) The stator winding cooling water circuit is in operation
Page: 50
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
① Duration of standstill < 3 weeks
The stator water circuit exchanger is locked and isolate. The pumps of the circuit are stopped
to prevent possible micro-leaks from making the winding insulation damp.
Drain the generator bottom points to check before re-starting that there were no leaks during
the standstill period
After having checked the generator bottom points when re-starting, the normal water
conductivity level must be restored; to achieve this, circulate the cooling water through the
system for approx. 24 hours after bringing the H2 to its rated pressure.
② Duration of standstill: Between 3 weeks and 4 months
The stator water circuit exchanger is locked and isolated
The winding is drained by gravity. And filled with Nitrogen. Avoid using more Nitrogen,
disconnecting the other parts of circuit from generator by blind flange. The pressure is not need to be
higher than the atmospheric pressure.
③ Duration of standstill: More than 4 months
The stator water circuit exchanger is locked and isolated
The winding is drained by gravity. To remove water pockets, carry out several blows through
operations with dry and oil-free filtered air for stator windings with natural aeration or air
scavenging, or with inert gas (helium, nitrogen) for hydrogen conditioned stator windings.
After having isolated the generator from the water circuit, vacuum-dry the winding and break
vacuum using dry and oil-free air (dry air can be replaced by nitrogen)
(2) The stator winding cooling water circuit is not in operation
① Duration of standstill < 3 weeks
The stator water circuit exchanger is locked and isolated. The pumps of the circuit are stopped to
prevent possible micro-leaks from making the winding insulation damp.
Leave water in generator; disconnect the mechanism from other generator.
After having checked the generator bottom points when re-starting, the normal water
conductivity level must be restored; to achieve this, circulate the cooling water through the
system for approx. 24 hours after bringing the H2 to its rated pressure.
② Duration of standstill: Between 3 weeks and 4 months
The stator water circuit exchanger is locked and isolated.
The winding is drained by gravity. Fill generator with Nitrogen and its pressure is not need to be
higher than the atmospheric pressure.
③ Duration of standstill: More than 4 months
The stator water circuit exchanger is locked and isolated
The winding is drained by gravity. To remove water pockets, carry out several blows through
operations with dry and oil-free filtered air for stator windings with natural aeration or air
scavenging, or with inert gas (helium, nitrogen) for hydrogen conditioned stator windings.
After having isolated the generator from the water circuit, vacuum-dry the winding and break
vacuum using dry and oil-free air (dry air can be replaced by nitrogen)
Page: 51
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
2.4 Disassembly of coolers
2.4.1 The disassembly of a cooler involves:
(1) Preliminary disassembly
See drawing 2-16
—cutting off the cooling water supply
—removing the drain plug (4C)
—draining the internal water supply to the element
—disconnecting the water inlet and outlet pipework
Page: 52
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
4A frame 4B coolers
4C draining plug 4D horizontal holes for lifting lugs
Page: 53
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
4E vertical holes for lifting lugs 404 metal frames
405 seal ring 406 seal pad
407 clamping flange 408 clamping strip
409 clamping strip 412 screws
413 lock washer 414 screws
415 lock washer 416 screws
417 straight stop piece 418 plates
419 screw 420 nuts
421 lock plate vertically 422 screws
423 nut 424 lock plates vertically
425 lock washer 426 lock washer
427 screw 428 spring washer
430 seal ring 431 supports
432 washers
Page: 54
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 55
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Parts list for drawing 2-17 assembly of coolers
3A frame 3B coolers
3C cooler rib 3D man holes
3E U-shape pothook 3F metal string
3G screwed metal string 3H equipment for fastening string
3J traveling crane 3L trunnion
301 handling support 302 screws
305 support 306 pin
307 pin 311 wood supports upon request
320 lifting beam 321 screws
322 nut 328 support
Page: 56
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
See the drawings2-16 and 2-17。
For each water box:
—Identify the existing reference marking
—Remove the screws (430)
—Remove the support (431)
—Open the locks (428)
—Remove the nuts (427)
—Remove the locks (428)
—Separate the water box
—Remove the tightness seals (432)
—Plug the supply pipes
—Clean the contact surfaces of the water boxes and the tube sheets.
—Horizontally pull the cooler element inside its housing on 2600 mm, with the help of a traveling
crane.
—Wedge the cooling element as indicated in phase II in drawing 2-17, using a support (328) and a
wedging block (311) if requested.
Page: 57
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Remove the shackle (3E) and the sling (3F)
—Fit the cross beams (320) onto the supports (305) using screws (321) and (322)
—Fit the two handling assemblies onto the ribs (3C) of the cooler (3B)
—Position the gudgon (306)
—Fit the shackle (3E) and the sling (3F)
—Remove the support (328) and the wedge (311)
—Horizontally pull the cooling element by 4000 mm
—Reposition the wedging (328), (311)
—Fit the second handling element
—Fit the shackle (3E) and the sling (3F)
—Sling as indicated in phase II in drawing 2-17
—Remove the support (328) and the wedging (311)
—Horizontally pull the cooling element and place it in the horizontal position on an opposite wedge
—Plug the water inlet and outlet pipework.
(2)Preservation at standstill
When the generator is at standstill, certain precautions must be taken to prevent damage to the
coolers. The possibilities are as follows:
—the generator is at standstill for less than 15 days (a tolerance of 10 % is permitted) and the
'cooling
water" system is available.
Keep this system in operation and check that the water temperatures will not cause by-pass of the
water flow to the cooler.
During this period, make sure that each cooler is completely full
—the generator is at standstill for more than 15 days (with a tolerance of 10 %), the "cooling water'
Page: 61
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
system in or out of service.
Each cooler must be drained completely
—the "cooling water" system is out of service for at least 2 days (without tolerance). Each cooler
must be drained completely
—the "cooling water" system is out of service for less than 2 days.
If possible, make sure that each cooler is completely full before stopping the system.
During this period, do not perform any check or manoeuvre which could modify the water level in
the coolers. It is recommended that the cooler isolating valves should be closed.
The purpose of these precautions is to ensure that all possible steps are taken to prevent the
formation of the triple phase metal - water - gas" which causes serious corrosive phenomena.
Never apply d.c or a.c voltage to a water-filled stator winding with the pumps stopped.
Page: 65
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 66
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 67
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Correction of the stator angular position can be determined by measuring the parallelism of the
turbine-generator coupling faces in the vertical plane, (See chapter 3.4).
Once this value is known:
—Prepare the adjusting shims.
—Slightly lift one side of the stator by means of jacks (3E).
—Take out the existing adjusting shims and clean them.
—Modify the wedging thickness as described previously.
IMPORTANT: Use the minimum amount of shims possible in order to prevent buckling.
—Insert the wedging between feet (4E) and sole plates (4F).
—Lower the stator on its supports.
—Follow the same procedure for the other side of the stator.
NOTE: Lifting each side of the stator separately prevents unwanted transverse movements.
2.6.3 Transverse adjustment
Correction of the stator transverse position can be determined by measuring the parallelism of the
turbine-generator coupling faces in the horizontal plane (See chapter 3.4).
Once this value is known:
—Lift the stator by means of jacks (3E).
—Shift the stator transversely by means of screws (3B).
—Re-place the stator on its sole plates.
2.6.4 Reassembly
With the stator on its support:
—By means of nuts (404), re-tighten tie-rod (401) (402) and (403) of frame feet (4E) located at both
ends of the generator frame.
—Check the coupling as indicated in chapter 3.4.
—Remove jacks (3B).
—Remove jacks (3E) and shims (3G).
—Remove wedging (3F).
—Remove screws (301) and (302) and disassemble trunnions (3D).
—Using nuts (403) tense tie-rods (401) until an elongation required is obtained.
—Re-assemble the axial alignment key, turbine and excitation ends, as described in chapter 4.2.7
NOTE: The flexible support system is designed between the stator core and frame. To prevent
vibration between stator core and frame, the key bars at upper and lower part of the stator core are
fastened by bolts before transportation. After the stator are positioned on site, these bolts must be
taken away to restore the flexibility function.
3. Generator rotor
Page: 68
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
3.1 The generator rotor structure
The generator rotor structure sees drawing 3-1.
Page: 70
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 71
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 72
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
The end-windings are held tangentially by insulating wedges (11) arranged between the straight
parts of the coils.
Together the coils and wedges form a continuous structure.
The end-windings are held axially by insulating wedges (12) pressed between the coil connection
pieces (4). There are also insulating axial wedges against the end-winding on the shaft body side
(13) and on the centering ring side (14). The centering ring is held by the retaining ring (9) which is
shrunk onto the shaft body (1).
The axial wedging system completely immobilizes the end-windings.
The end-windings, the radial wedges, and the tangential wedges are held radially against centrifugal
forces by the retaining ring (6).
② Cooling of endwindings
See drawings3-6 and 3-7
The circulation of hydrogen in the rotor (1) is an axial- radial one. Cold gas flows in at each end of
the rotor underneath the retaining rings (2) in a tube (3) with partitions so as to separate gas inlets
and outlets.
The supplying of the longitudinal ducts (4) of the end windings is performed one turn after the other
through lateral inlets (5) which are themselves supplied via a part of the openings (6) inside the
cooling tube (3).
On the one hand, hot gas is dissipated through lateral ducts (7) which through the intermediary of the
gas outlet openings (8) inside the cooling tube (2)- communicate with the compartment (9). From
there, gas is dissipated through the slots (9) machined at the end of the rotor body; and on the other
hand it is directly dissipated in the first slits (4) of the rotor winding.
The tightness between the gas inlet and outlet openings is obtained by means of the wedging (10)
between turns.
The main fans generate the necessary overpressure for hydrogen circulation.
The cooling of end windings is thus performed by a cold gas circulation in a multitude of elementary
circuits in parallel.
3.1.3 Retaining rings & centering rings
See drawing 3-8
(1) Retaining rings
The retaining rings (2) are non-magnetic steel cylinders which hold the end-windings against the
effect of centrifugal force.
The characteristics of the steel are tested using specimen pieces taken from the forging during
manufacture, and also on the finished rings.
The endwinding and its wedging press against the retaining ring via an insulating cylinder (5).
The retaining rings are hot shrunk onto the shaft body tightly enough to avoid separation at runaway
speed.
Page: 73
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 74
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 75
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 76
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 77
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
They are held axially by bayonet-fitting locking rings (4) via which axial thermal expansion stresses
Page: 78
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
originating in the winding are transmitted to the rotor.
Page: 79
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
(1)Central shaft connection
The central shaft connection (1) is made of two D-shaped solid copper bars, separated by layer
insulation, and housed in the central shaft bore.
The shaft bore provides a means of linking the excitation unit and the generator without interfering
with the journal bearing, the shaft seals, or the axial fan.
The central shaft connection is insulated from the shaft by an insulating sheath (6).
The seal rings (10) is used for H2 seal at
(2)Radial connecting rods
Radial connecting rods are connected to two end of central shaft connection. The radial connecting
rods are copper rods screwed into the central shaft connections (1). The ones inside the frame are
connected with outer axial connections (3); the ones outside the frame are connected with two slip
rings (7). Radial connecting rods constitute the radial connection of excitation circuit.
The seal rings (10) are used to insure seal at radial connecting rods.
(3) Slip ring
Slip ring is made of high strength and wearable chromium alloy steel. Brushes contact slip ring by
sliding on it to conduct the current from static part to rotating part. Between slip ring and shaft there
is insulation sleeve.
3.1.6 Cooling of slip ring
When generator is running, electric loss and friction loss will occur on slip rings. These losses will
increase the temperature of slip rings.
Slip rings are cooled by air, to see drawing 3-11. Cold air enters the soundproof housing through
shutter (8) on the housing, then through the brush gear to cool the slip rings and brushes into the seat
box (7) driven by slip ring fan (3) through the ventilation opening on the seat box (7).
Slip ring fan (3) and fan cover (4) drive and lead the air in the ventilation system of slip ring.
Page: 80
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 81
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 82
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 83
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
3.2 Rotor removal and installation
3.2.1 Operations required for rotor removal
—Disconnecting of soundproof of brush gear
—Disconnecting of brush gear
—Disconnecting of fan cover of brush gear
—Disconnecting of small shaft at excitation end
—Disconnecting of seat box of brush gear
—Disconnecting of bolts of turbine end coupling
—Disassembly of rotor ground brush
—Disassembly of the field winding detection probe ( NOTE : the rotor winding detection probe
must be disassembled before assembling and disassembling the rotor)
—Disassembly of power angle probes (or speed probes at turbine end) and their support.
—Disconnecting of jacking and lube oil supply
—Disassembly of an inspection hatch
—Disassembly of outer oil deflectors
—Disassembly of bearing closings
—Disassembly of vibration detectors
—Disassembly of temperature detectors
—Disassembly of clamping collar
—Disassembly of upper half-journal bearing
—Disassembly of upper 1 /2 bearing
—Disassembly of inner oil deflectors
—Positioning of external support
—Disassembly of shaft seal rings
—Disassembly of lower 1/2 journal bearing
—Disassembly of pipework
—Disassembly of lower 1/2 bearing
Disassembly of fan nozzle ring
—Disassembly of blades
The above-mentioned work should be done at turbine end and excitation end simultaneously. It also
can be done respectively. As a result, the rotor should be put on the external support.
Page: 84
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 85
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
3.2.2 The work after rotor inserted
The works after the rotor has been on its position can be carried out as the contrary process that the
rotor is removal in chapter
After reassembly, the generator is in stage of start condition. Some inspection must be done .They
are: the stator sealing test, insulation check between bearing excitation end and earth, temperature
sensor element check, vibration probe check and the earth of three water manifold.
NOTE: The rotor should be handled carefully to avoid knocking it against the various components of
the stator.
Make sure that the insulation of the stator bars is not damaged during the operation.
The end windings and their wedging should never be used as a support or a walkway.
Instructions for wedging and slinging the rotor must be followed carefully.
The rotor must never be handled by or supported on the retaining rings. As soon as possible, it
should be protected against dust.
PRELIMINARY NOTE (see position 3-13 VII): it is imperative to position the rotor in a way that
the flange (331) is properly orientated in relation to the rack (324).
For this reason, place the flange (331) at the end (3H) of the shaft. The axis (332) will be horizontal.
POSITION I:
The rotor is supported by the external supports (3B) at the turbine end and (3C) at the excitation end.
POSITION II:
With the help of support jacks (3B) and (3C) raise the rotor to the maximum being sure that the
retaining ring (3E) does not come into contact with the magnetic core (3D) or the winding (3N).
Position the shim (316), the metal sheet (315) and the rotor shoe (302) on the magnetic core (3D).
ATTENTION: the rotor shoe (302) must not come into contact with the retaining ring (3E).
Turbine end
—Fix the handling extension (312) onto the support (3R) with the help of screws (313).
Page: 86
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Fix the upper half-collar (308) to the handling support (3R) with the help of the axis (3W) or a
shackle (3U).
—Sling as indicated and remove the upper half-collar (308) on the rotor journal (3A).
—Fix the shim (305) onto the upper half-collar (308) using screws (314) and do not block.
—Gently pivot the half-collar (308), shim (305) assembly around the rotor.
—Fix the lifting beam (3S) onto the pad (304) with the help of screws (310).
—Fix the pad (304) onto the handling support (3R) with the help of the axis (3W).
—Sling as indicated and remove the pad (304) from the shim (305).
—Fix the upper half-collar (308) onto the pad (304) with the help of screws (306) and do not block.
—Sling the pad (304) with the hoist (3P) and tool (3S).
—With the help of the hoist (3P), gently pivot the assembly around the rotor so that it can be
lowered.
—Remove the screws, (314) the shim (305), and wedge (3T).
Page: 87
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 88
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 89
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 90
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 91
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 92
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 93
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
3N Stator winding 3P Hoist
3R Handling support 3U Straight shackle
N Distance between K and shaft end on excitation end
L Position of the shim ref: 341 S Position of the shim ref: 340
3T Wedge 3S Lifting beam
3W Gudgeon pin Φ16 302 Rotor shoe
304 Rotor support 305 Shim
306 Screws M24×100 307 Tallow
308 Upper half collar 309 Rotor extension
310 Screws M14×40 311-1 Screws M30×130
311-2 Screws M20×150 311-3 Nut M20
312 Handling extension 313 Screws M20×50
314 Screws M16×25 315 Protective shim
316 Shim 317 Screws M24×50
318 Washer 24 320 Protective shim
321 Shim 322 Rotor shoe (similar with 302)
323 Jack support 324 Rack
326 Screws M42×4.5 327 Jack
329 Extensions 330 Screws M20×50
331 Flange 332 Should rod
333 Pin 340 Hollowed out hard wooden wedge
370 Sling
—Using handling support (3R) and equipment (312) sling half the collar with axis (3W) or shackle
(3U).
—Raise the assembly and support it against the cooler ring.
—Remove axis (3W) or shackle (3U). Release the handling support (3R).
—Block the screws (306) with a 540.m.N. tightening torque
POSITION IV:
Page: 94
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Assemble the extension (309) on the shaft (3A) using screws (311).
—Clean the protective shim (320).
—Place the shiny cardboard (321) which will possibly be stuck to the external surface of the sheet
(320).
—Lightly coat the internal surface of the sheet (320) with tallow (307).
—Sling the rotor as indicated.
—Raise the rotor and remove the rotor shoe (302), the sheet (315) and the shim (316).
—Introduce the protective shim (320) into the stator bore taking care not to damage the shiny
cardboard, in its final position, the sheet must even out the end of the -magnetic core (3D) at the
excitation end(3H).
—Side (3G), attach the sheet (320) to the end shield bearing (3H) using a small diameter cable, in
the aim
of avoiding the sheet being dragged along with the rotor as it's being removed.
—Introduce the rotor shoe (322) at the (3H) side and position it at the (3G) side.
ATTENTION: It could be necessary to slightly raise the rotor (3A) using the external support (3B) in
order to position the pad (322).
—The pad (322) must not touch the retaining ring (3E).
—Position the rotor shoes (302) at the (3H) side.
ATTENTION: the pad (302) must not touch the retaining ring (3E).
Page: 95
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Sling the rotor as indicated
—Slightly raise the rotor (3A) in order to eliminate the pressure on the pad (302).
—Position the dust protectors on the rotor.
—With the help of the jack (327), remove the rotor, coordinating the movements of the traveling
crane and the rotor.
ATTENTION: during the removal of the rotor:
—Make sure that the protective shim (320) remains immobile.
—Monitor the movement of the pad (322) to ensure a continuous movement.
—The support (304) must not touch the sheet (320) as long as it is outside the magnetic core (3D).
—Monitor the movement of the pad (302) and remove it as soon as the retaining ring (3E) is
removed from the end winding cones (3N).
—After a rotor movement corresponding to the travel of the rack, disassemble one of the extensions
(329) and carry out the removal of the rotor.
POSITION VII:
—When all the extensions have been disassembled and the rack (324) is at the end of its travel at the
support side (323), position the wedging (340) under the rotor (3A). Adjust the height of the
wedging as requested.
ATTENTION: the wedging (340) must not touch the retaining ring (3E).
—Remove the rotor from the wedging (340).
—Remove the pin (333) and axis (332).
—Remove the screws (317) (318), the jack (327) and the rack (324).
—Remove screws (326) and support (323) and adjusting shims.
—Remove the screws (330) and the flange (331).
POSITION VIII:
—Sling the rotor (3A) as indicated, placing the shims (341) between the rotor and the sling (370).
The sling is wrapped around the rotor to avoid it moving on the rotor during its handling.
—Slightly lift the rotor (3A) and remove the wedging (340).
—Remove the rotor making sure that the support (304) and the turbine end coupling do not hit the
various components of the stator.
POSITION IX:
—Remove the rotor from the wedging (340).
ATTENTION: the wedging (340) must not touch the retaining rings (3E).
—Protect the rotor as indicated in chapter 3.77.16.
—Remove the protective shim (320).
Page: 96
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
See the annexed drawings 3-12~3-17 (Note: Rotor winding detection probe is not assembled then)
—Clean the protective shim (320)
—Place the shiny cardboard (321) which may be glued on the external face the shim (320)
—Slightly coat the internal face of the shim (320) with tallow (307)
—Introduce the protective shim (320) in the stator core, making sure not to damage the shiny
cardboard. In the final position, the shim and the magnetic arc end are flush on excitation end (3H).
—By means of small diameter cables secure the shim (320) to the end shield bearing (3F) to prevent
it from being introduced together with the rotor.
Position IX
Give the rotor such an angular position that the flange (331) is correctly oriented versus the rack
(324) (see position in V). Therefore offer the flange (331) up to the shaft end (3H). The axis (332) is
then horizontal
Turbine end (3G)
—Assemble the support (304) onto the rotor (3A).
—Place the collar (308)
—Assemble the support (304) and the collar (30S) using the screws (306)
—Lock the screws (306) by 540 N.m
EXCITATION END (3H)
—Install the extension (309) on the shaft (3A) with the screws (311-1, 311-2, and 311-3)
—Sling the rotor as indicated, inserting the shim (341) between the rotor and the sling (370). The
sling will be given one locking turn around the rotor so as to avoid any displacement of the sung
during rotor handling.
—Check if the rotor body is horizontal by means of a level. Adjust the sling if necessary.
POSITION VIII
—Introduce the rotor into the stator bore, making sure that the support (304) or the coupling on
turbine end does not shock the various stator components. The rotor will enter the stator as deep as
allowed by the sling.
—Install the supporting wedge (340) under the rotor (3A) and adjust the height by wedging as
required.
WARNING: The support wedge (340) shall not rest on the retaining ring (3E).
—Lower the rotor down on the protective shim (320); making sure that the support (304) is resting
on the magnetic core (3D) and on the support wedge (340).
—Remove the sling.
POSITION VII
—Place the jack support (323)
—Align the rack axis (324) with the rotor axis (3A) approximatively with the adjusting shims as
required.
Page: 97
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Fix the jack support (323) by means of the screws (326)
—Fix the jack (327) fitted with the rack (324) on the support (323) using the screws (317) (318). Do
not lock.
—At the shaft end, fix the flange (331) with the screws (330).
—Align the rack and the rotor axes and lock the screws (317) (318).
—Connect the rack end (324) to the flange (331) using the shoulder rod (332) and the pin (333).
—Sling the rotor as indicated
—Sling the rotor as indicated
—Slightly lift the rotor (3A) and remove the support wedge (340)
—Remove the dust protections coating the rotor
WARNING: Make sure that all protection coatings have been removed before installation of the
rotor.
POSITION VI
—By means of the jack (327) introduce the rotor (3A), harmonizing rotor and crane displacements.
—As soon as the retaining ring (3E) is placed deep enough in the magnetic arc (3D), install the rotor
shoe (322) between the body and the protective shim (320).
—Once the rotor shoe (322) is completely introduced over the magnetic arc, lower the rotor (3A)
down to transfer its support onto the shoe (322) and therefore to withdraw the support (304).
WARING; During the rotor displacement, make sure that the shoe (322) is correctly drawn along.
Make sure that the protective shim (320) is not carried in.
—after a displacement of the rack length, insert an extension (329) between the extension (309) and
the flange (331) using the screws (330).
—Keep entering the shoe (302) until the retaining ring is drawn into the end-winding (3N).
—Go ahead until all the extensions (329) are installed.
NOTE: The natural sag of the rack increases with its length. Wedging may be necessary, in order to
ensure that the extension pieces do not buckle as a result of the compressive stress to which they are
subjected.
—The rotor will be pulled until the turbine coupling plate socket is at a distance of 5 to 10 mm from
the turbine plate.
POSITION V
—Lower the rotor down on the shoe (302)
—Remove the sling
—Withdraw the pin (333) and the shoulder rod (332)
—Withdraw the screws (330) and remove the extensions (329)
—Withdraw the screws (326) and remove the jack support (323) and the adjusting shims as required
with the jack (327) and the rack (324).
—Remove screws and bolts (317) (318), jack (327) and rack (324)
Page: 98
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Remove screws (326), jack support (323) and adjusting shims as needed
POSITION IV
—Install the external support as indicated in chapter 3.78.12 and remove the support of the shoe
(322).
—Sling the rotor as indicated.
—Remove the support of the shoe (302)
—Remove the shoes (302) and (322), the protective shim (320) making sure not to damage the shiny
cardboard.
—Position the shim (316) and the protective shim (315).
See situation II and III
—Position the shoe (302)
WARING: The shoe (302) must not rest against the retaining ring (3E).
—Place the rotor on the shoe (302)
—Remove the sling
EXCITATION END
—Withdraw the screws (311) and remove the extension (309)
TURBINE END POSITION Ⅲ
—Loosen the screws (306) so as to separate the lower shoe (5 mm).
—Slip the shim (305) between the lower half shoe and the rotor 3A.
—Fix the shim on the upper-half collar (308) by means of screws (314).
—Fix the tooling (3S) by means of screws (310) on the lower half shoe.
—By means of the handling support (3R) on to which the tooling is fixed (312), and using screws
(313) sling the half collar with the gudgeon pin (3W) or a shackle (3U).
—Slightly lift the assembly and pull it on to the rotor journal (3A).
—Position a wedge (3T) so as to allow rotation of shoe.
—Position hoist (3P)
—Sling the shoe (304) by means of hoist (3P) and tooling (3S).
—Using the hoist, gently rotate the assembly around the rotor (3A).
—After a rotation of the shoe of 180° sling the lower half shoe (304) by means of handling support,
tooling (3S) and gudgeon pin (3W).
—Remove the screws (306)
—Remove the lower half shoe (304)
—Carry out 180° rotation of upper half collar (308)
—Sling the upper half collar and remove it after having removed the screws (314) and after having
removed the sling (305) manually.
Page: 99
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
POSITION Ⅱ
—By means of jacks of supports (3B) and (3C) lift the rotor as high as possible, making sure that the
retaining ring (3E) does not touch the magnetic core (3D) or the windings (3N).
—Remove the rotor shoe (302), the protective shim (315) and the shim (316) and the rotor is now on
POSITION I
Page: 102
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
3.4 Disassembly and reassembly of couplings - unit shaft alignment
This chapter describes the uncoupling and coupling of the turbine and generator, and gives the
instructions necessary for the turbine-generator shaft alignment
The procedure for disassembling and reassembling the coupling bolts and the necessary tooling are
specified in the Turbine Manual.
— rotate the unit at rated speed none excited for several hours and take another measurement.
b. The rotor is out of the stator.
—drive low pressurized warm air, dry and oil-free air under the retaining rings, raising air
temperature gradually to 100°C. The temperature of the coppers must not exceed 80°C. Then
measure the insulation resistance.
If the insulation resistance remains below 1 megohm after drying, consult the manufacturer.
(2)Impedance measurement
Page: 105
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
The electrical connection between the rotor winding and the excitation busbar must be open.
The impedance of the rotor winding should be measured by applying an alternating current
(maximum 10 A).
Impedance may be deduced by taking a voltage reading and a current reading at the winding
terminals.
If the value is less than 0.9 times the initial value, the manufacturer should be informed.
(3)Measuring resistance
The electrical connection between the rotor winding and the excitation busbar must be open.
The resistance of the rotor winding may be measured at slip rings using a micro-ohmmeter or a
Thomson double bridge.
As the temperature of the rotor is uniform and known, compare with the resistance given in chapter
1.2.3.
A significant difference between the reading taken and the initial value indicates a fault in the
winding. Inform the manufacturer.
Page: 106
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 107
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
3.6 Fan
3.6.1 Disassembly of main fan blades
This operation requires a torque wrench capable of applying the tightening torque.
In addition to the usual precautions taken, the exact position of each blade at both turbine and
excitation ends must be marked carefully before disassembly so that each blade can be replaced in
exactly the same position, thus preventing possible unbalances developing during rotation.
Disassembly operations should be carried out as follows (see drawing 3-19):
—Mark position of each blade (401) for remounting
—Undo nut locks (402) which block the two screws fixing each blade
—Remove the two screws (403), the nut locks (402) and the corresponding blade (401)
—Arrange and store the blades after disassembly
NOTE:
—In order to reach the bottom blades, turn the rotor using the crane or a jack. This operation is
facilitated by switching on the jacking oil system, if available, or topping up the journal bearings
with oil.
—The same operations are performed at both the turbine and excitation ends
Page: 108
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 109
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
4. Generator end structures
Page: 110
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 111
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 112
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 113
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 114
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 115
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
4.1.3. Upper half-bearing
See drawing4-5
The upper-half-bearing is a steel fabricated structure obtained by welding a horizontal axis half-ring
(1) onto a shaft seal support (2).
The connection with the end shield bearing (4) is made by screws (5) securing a joint contact face
which carries a hydrogen tight joint device.
At the excitation end, the double insulation means that an intermediate ring (6) is needed between
the lower- half-bearing (1) and the end shield bearing (4), and that electric insulation is also
necessary (see chapter 5.3.4).
4.1.4 End shield bearing
See drawing 4-6 (turbine end shield bearing) and 4-7 (excitation end shield bearing)
The end shield bearing is a steel fabricated structure obtained by welding a horizontal axis cylinder
(2) onto a thick steel sheet disc or end shield (1). The assembly is made rigid by ribs (3).
It ensures the bearing support and the generator frame closing.
It is fixed by screws onto the frame (4) securing the joint contact face earning a hydrogen tight
device.
4.1.5 Clamping collar
See drawing 4-8.
The lower half bearing (1) carries a machined half ring serving as a lower support to the journal
bearing (3). This is covered by the clamping collar (4). The journal bearing contact with the
clamping collar and the lower half bearing (1) is on the spherical contact surface.
At each end of the collar (4), a flange of great thickness ensures its connection to the lower half
bearing (1) by screws.
After assembly, this collar exerts on the journal bearing (3) a clamping force sufficient to ensure
immobilization during unit operation.
4.1.6 Shaft seal
See drawing4-9
The hydrogen tightness of the machine is ensured principally by the shaft seals. They are made up of
a support or end shield (4) and the rings (7).
The hydrogen tightness is obtained by forced circulation of oil at the hydrogen end (1) and the air
end (2), thus separating the air and hydrogen casing.
The oil supply and treatment plant is described in the "Auxiliary" manual.
(1)End shield support of the shaft seal
The end shield support of the shaft seal is part of the bearing. At its base, it is made rigid by a thick,
horizontal steel sheet which makes up the contact surface with the half bearing, the assembly being
carried out by screws.
At its outer edge, the end shield support has a machined groove serving as housing for the tightness
rings and the oil supply.
Page: 116
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
(2) Shaft seal rings
Inside the support ring (4) are mounted two shaft seal rings (7). These rings are made of several
segments placed end-to-end to form rings. The rings are held together by two positioning springs (6).
Shaft seal oil is fed into the oil supply groove from where it flows between both rings and the
generator shaft (3) and then out on the hydrogen side (1) and the air side (2). The oil flow prevents
air from reaching the hydrogen and vice versa as long as the oil pressure is greater than the hydrogen
pressure.
Oil on the hydrogen side (1) is collected in the lower half-bearing from where it is drawn off towards
the oil unit.
Oil on the air side (2) is collected in the lower half- bearing from where it, along with the bearing
oil, is carried to the lube oil system.
Page: 117
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 118
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 119
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 120
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 121
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 122
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
4.1.8 Ventilation guides
See drawing 4-11
At each end of the generator are fixed partitions (1) which close off the stator end winding (2) from
the end shield (3). The space between the partition and the end shield acts duct (4) directing cool
hydrogen towards the axial fan (5).
This partition also serves as a ventilation guide around the outside of the axial fan.
The parts described above are of lightweight alloy. To facilitate assembly, they are in several pieces
that are pinned and screwed together to form a rigid whole which is fastened to the radial web (6) on
the stator frame end.
4.1.9 Axial alignment key
See drawing 4-12
The axial alignment key maintains the axial alignment of the generator after the stator axis and shaft
line have been properly positioned. It ensures axial alignment while the generator is operating.
An alignment key is located on both the turbine end and excitation end.
On the lower half bearing (1) are welded two rails forming a U-shaped female mating member (2).
Across from this part is a corresponding T-shaped male mating member (4) mounted on the
foundation block, which fits loosely between the two rails. The male member is positioned by means
of a key (5) and fastened by screws to the foundation block; after the stator and shaft line alignment
has been adjusted, two adjusting wedges are fitted into the spaces between the male and female
members. These wedges are held in by fastening screws (8).
Page: 123
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 124
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 125
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 126
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Assemble the support (302) with the end shield bearing (3C) using screws (310).
—Fix the shims (306) on the beam (305) using screws (311).
—Position screws (307).
—Raise the beam (305) using screws (307) position jacks (308) and wedges as required (309).
NOTE: The rotor should always be raised and lowered using jacks (308); the screws (307) only
serve as a mechanical stop.
—When the rotor (3A) is to be lowered, it should be slightly raised using jacks (308). Reset the
screws (307) and lower the rotor.
—When the rotor is to be raised, raise it with the jacks (308), and then fit the screws (307) on the
support
(301) or (302).
(2) Disassembly of the rotor external support
In the event where the rotor is in its stator, be sure that the rotor is in contact with its journal bearing.
The jacks (308) are not raised. The external support can therefore be disassembled.
A. Turbine end
—Remove the jacks (308) and the wedging (309)
—Lower the beam (303) and removing the screws (307)
—Remove the screws (307) and (311)
—Remove the shims (304)
—Remove the screws (310), the support (301), and the beam (303).
B.Excitation end
—Remove the jacks (308) and the wedging (309)
—Lower the beam (305) removing the screws (307)
—Remove the screws (307) and (311)
—Remove the shims (306)
—Remove the screws (310), the support (302), and the beam (305).
4.2.2 Removal of the journal bearings at the turbine and excitation ends.
(1)Removal of the journal bearing
See drawing 4-14~4-18
①. Removal of the clamping collar
—Identify the clamping collar (401) reference.
—Remove the screws (402).
PHASE I:
—Fasten the support (303) to the support (302) using the screws (316).
—Sling the handling support (302).
Page: 127
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Fasten the support (302) onto the collar (3K) using screws (317)
—Vertically raise the collar (3K) in order to loosen the stop pieces (404).
—Remove the clamping collar (3K.) and place it on a wooden wedging.
—Remove the plates (405) remaining on the lower 1/2 bearing.
—Remove the screws (317) and the support(303).
② Removal of the upper 1/2 journal bearing
See drawing 4-18
—Identify the lower and upper 1/2 bearing references
—Open the locks (402)
—Remove the screws (401)
PHASE II :
—Fit the lifting beam (317) onto the upper 1/2 journal bearing (3L) using screws (313).
—Fasten the support (315) to the support (302) using screws (316).
—Sling the handling support (302)
—Fasten the support (302) onto the lifting beam (312) using the cotter pin (314)
—Fit the washer (304) and immobilize the axle (314) using the pin (305)
—Vertically raise the 1/2 journal bearing (3L) in order to remove the centering bushes (403)
—Remove the 1/2 journal bearing and place it on a wooden wedging.
—Remove the pin (305) then the axle (314) and remove the support (302).
—Remove the screws (313) and the lifting beam (312)
③ Removal of the lower 1/2 journal bearing
—Remove the centering bushes (403)
—Remove the jacking oil circuit copper pipe in front of the journal bearing,
—Vertically raise the rotor. The maximum elevation will be 0.2 mm.
Page: 128
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 129
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 130
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 131
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Parts list for drawing 4-14, 4-15, 4-16 removal of the journal bearing
3A lower 1/2 bearing 3B upper 1/2 bearing
3C end shield bearing 3D shaft
3E generator frame 3F lower /12 journal bearing
3G sling 3H lifting ring
3J shackle 3K clamping collar
3L upper 1/2 journal bearing 302 handling support
303 support 304 washer
305 pin 312 lifting beam
313 screw 314 shoulder pin
315 support 316 screw
317 screw 322 guide plate
323 screw 324 handling flange
325 screw 326 requested wedging
327 requested wedging
328 handling flange
Page: 132
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 133
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 134
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
PHASE III:
—Fit the guiding plates (322) onto the side of the lower 1/2 bearing (3F) and fix them using the
screws (323).
—As indicated, fit the handling flange (324) or (328) on the 1/2 journal bearing (3F) using the
screws (325).
—Fit the lifting ring (3H) onto the end of the handling flange (324) or (328).
—Pass the sling (3G) under the rotor and fix it to the ring (3H) using the shackle (3J)
—Grease the journal (3D).
PHASE IV:
—Gently pivot the 1/2 journal bearing on the journal making sure to place a wedging (327) on the
contact surface.
—When the 1/2 journal bearing is in contact with the wedging (327), continue to rise in such a way
that the wedging (326) can be introduced.
—Place the 1/2 journal bearing on the wedging (326)
—Remove the sling (3G).
—From this moment, the lower 1/2 journal bearing is in a position similar to that of the upper 1/2
journal bearing.
—The removal of the lower 1/2 journal bearing is carried out in the same way as the upper 1/2
journal bearing.
(2) Installing the journal bearings on turbine end and excitation end
see drawing 4-14~-18
① Installation of the lower 1/2 journal bearing
—The rotor is secured by the outer support and fitted by 0.2 mm versus its normal position
—Check the cleanness of the lower 1/2 journal bearing (3F)
—Clean then lubricate the spherical seat of the 1/2 bearing ring (3A)
PHASE IV:
—Mount the guiding plates (322) on the outer side of the 1/2 journal bearing (3F) and lock them by
means of the screws (323).
—Mount the handling flange (324) or (328) on the 1/2 journal bearing (3F) as indicated and fix it by
means of the screw (325).
—Fit the lifting ring (3H) at the end of the handling flange (324) or (328).
—Mount the lifting beam (312) on the 1/2 journal bearing (3F) by means of the screws (313).
—Mount the support (315) on the support (302) by means of the screws (316)
—Sling the handling support (302).
—Hook the handling support (302) on the lifting beam (312) by means of the shoulder axis (314).
—Fit the o-ring (304) and lock the shoulder axis (314) with the pin (305).
Page: 135
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Install the wedges (326) and (327) and place the 1/2 journal bearing (3F) resting on these wedges.
WARNING: from now make sure that the oil flow openings of the journal bearing and the lower 1/2
bearing are facing each other when the journal bearing will be installed.
—Remove the pin (305), then the shoulder axis (314) and loose the handling support (302).
—Sling as indicated by hooking the sling (3G) to the lifting ring (3H) by means of the shackle (3J).
—Once this performed lift the 1/2 journal bearing and remove the wedging (326).
PHASE III:
—Lower the 1/2 journal bearing on the journal ,slightly turn it up to its normal position, the
wedging (327) having been removed.
WARNING: during the 1/2 journal bearing rotation, make sure that the sling moves freely.
—Remove the sling (3G).
—Remove the screws (313) and the lifting beam (312).
—Remove the screw (325) and the handling flange (324).
—Remove the screws (323) and the guiding plates (322).
—Adjust the parallelism journal bearing/journal according to drawing 4-19 and 4-20 by lateral
action on the lower 1/2 journal bearing.
—Place the rotor into its 1/2 journal bearing.
—Check the horizontal clearance between journal and journal bearing according to drawing 4-19
and 4-20
—Install the centering rings (403).
—Check that the oil supply openings of the lower 1/2 journal bearing and of the lower bearing is
facing each other.
—Install the jacking oil circuit flexible hoses.
② Installation of the upper 1/2 journal bearing
—Check the cleanness of the upper 1/2 journal bearing (3L).
—Mount the lifting beam (312) by means of the screws (313).
—Identify the existing marks.
PHASE II:
—Mount the support (315) on the support (302) by means of the screws (316)
—Sling the handling support (302).
—Hook the handling support (302) on the lifting beam (312) with the shoulder axis (314).
—Fit the o-ring (304) and lock the shoulder axis (314) with the pin (305).
—Lower the upper 1/2 journal bearing (3L) on the lower one (3F).
—Remove the pin (305) then the shoulder axis (314) and remove the handling support (302).
—Remove the screws (313) and the lifting beam (312).
Page: 136
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 137
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 138
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Check the clearances between journal bearing and journal according to drawing 4-19 and 4-20.
—The clearances checked on machine internal and external ends must not vary by more than 0.05
mm.
—Unless the parallelism between journal bearing and journal must be readjusted.
—Install and lock the screws (401) fitted with the o-rings (402) with a torque of 620 N.m.
③ Installation of the clamping collar
—Check the cleanness of the contact surfaces of the clamping collar and the upper 1/2 journal
bearing.
—Identify the existing marks.
—Install the upper 1/2 oil deflectors.
PHASE I:
—Mount the support (303) on the support (302) by means of the screws (316)
—Sling the handling support (302).
—Hook the handling support (302) on the clamping collar (3K) with the screws (317).
—Install the screws and the o-ring (402) and (403) on the clamping collar (3K), see drawing 4-17.
—Install the clamping collar (3K.) on the upper 1/2 journal bearing, after having located the
centering locking screw (404) into its housing.
—Remove the screws (317) and remove the handling support (302).
—Tightening the screws (402) with a torque of 1130 N.m.
(3)Maintenance operations for elliptical journal bearings
After arriving at the power plant, the recheck of the journal see appendix A.
A visual inspection of the white metal (babbit) should not reveal any scratches, blisters, pining or
signs of heating.
Scratches on the white metal are caused by impurities in the lubricating oil, which should be filtered
(see Turbine Manual).
If the scratches are more than 0.5 mm deep, and particularly if they lead to or cross the jacking
pocket or the lateral grooves, the journal bearing must be reconditioned.
Smaller scratches may be removed by surface scraping.
Blisters on the white metal are indications of localized non-adherence.
The journal bearing should be reconditioned if:
—There is a blister on the lower half journal bearing
—The surface area of the largest blister on an upper half journal bearing is greater than 5 % of the
total surface area of the upper half journal bearing
—The total surface area of the blisters on the upper half journal bearing is greater than 5 % of the
surface area of the upper half journal bearing
Although pitted white metal does not damage the journal bearing, it shows that the bearing assembly
is incorrectly insulated or that the shaft is not properly grounded.
Page: 139
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Pitting occurs on the corresponding journal.
Remove pitting by surface scraping.
If the white metal shows signs of heating, this may be due to the malfunctioning of the lubricating or
jacking system.
Check the jacking oil circuit (see below).
The journal bearing should be reconditioned if there are geometric faults in the bearing support
surface. In other cases, signs of heating can be removed by surface scraping.
Ultra-sonic testing may be used to check that the white metal adheres to the shell properly. The
attached table gives the acceptance criteria used by BSTG.
The spherical contact surfaces of the journal bearings and spherical seats should not show any signs
of seize or local contact. Remove any faults by scraping.
If the journal bearing has been changed, check contact between journal bearing and spherical seat.
The total contact surfaces area should be greater than 80% in the range of 90%.
The jacking oil circuit should be disassembled. It should be re-assembled before the journal bearing
is remounted in the generator. Check if the spring is in good condition.
The cylindrical contact surfaces of the spherical seats and clamping collars must not show any signs
of seizing or local contact. Any faults should be removed by scraping.
Type of journal bearing Maximum single area of non- Maximum sum of areas of non-
adherence adherence
Page: 140
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Disassemble the screws (403) or (430), the washers (406) or (431)
—Assemble the handling support (420), the tooling (317) on the bearing with the screws (315) (316)
(see drawing 4-22) —slightly lift the bearing to separate the shaft seal rings
—Move the bearing by means of the parting screws (433) or (408). Shift the 1/2 bearing by
slackening the hoist (3P) as soon as sufficient space is provided so as to avoid the rotor shoulder.
—Lower the bearings (4A) down on a wooden wedge
—Clean all the contact surfaces of the upper 1/2 bearings and protect them if necessary.
(2) Disassembly of the lower 1/2 bearings
See drawings 4-21~4-29.
—Coat the rotor supporting portions with plenty of tallow
—Assemble the dummy 1/2 journal bearing (306) or (307) between the rotor and the bearing.
—Assemble the dummy 1/2 journal bearing (322) or (323) by means of the collar (302), the spacers
(304), washers (305) and the screws (3E)
—Disassemble the fixing screws and auxiliary of the lower 1/2 bearings
—Separate the bearing by means of the screws
—Remove the parting screws
—Introduce a thin sling into the hole (3F) and fix the 1/2 bearing by a lifting lug and a shackle
screwed at the 1/2 bearing section, slightly stretch
—Fix a ring (3L) on the end shield bearing (3B), fix a hoist to this ring and to the lower 1/2 bearing,
slightly stretch
—By means of the crane and the hoist turn the bearing by 180°
—Secure the 1/2 bearing in this position by screwing both pins (334) into the end shield bearing,
passing them through the fastening holes
—Remove the sling and the hoist
—Sling the 1/2 bearing using the handling support (320) and the tooling (314), while following the
instructions on the support, slightly stretch
—Disassemble both pins (334)
—Disassemble the dummy 1/2 journal bearings
—Take the screws (3E) out and remove the collar (302), the dummy 1/2 journal bearings (322) or
(323) and (306) (307)
—Shift the 1/2 bearing by slackening the hoist (3P) as soon as sufficient space is provided so as to
avoid the rotor shoulder
—Lower the bearings (4A) down on a wooden wedge
—Clean all the contact surfaces of the lower 1/2 bearings (4A) (4B) (4C) and protect them if
necessary.
(3)Reassembly of bearing
See drawings 4-21~4-29.
Page: 141
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
① Fit the lower half bearings
Fit the gaskets to the end shield on turbine end and to the intermediate ring on excitation end.
—Install the shaft seal rings. For this assembly refer to document chapter 4.2.4
—Install the half dummy journal bearing (322) or (323) in the bottom of end shield bearing fitted
with its collar (302).
—Carefully grease the rotor supporting surface.
Phase Ⅰ:
—Sling the lower half bearing by means of the handling support (320) and the tooling (314) and
(321) in accordance with the indications on the support.
—Shift the lower half bearing while slackening the hoist (3P). See drawing 4-21 and 4-22.
Phase Ⅱ:
—After having inserted the half bearing in the end shield, level the assembly back with the hoist
(3P).
—Slightly lift the assembly using the crane so that the copper insert (318) or (319) can be placed
between the oil seal supporting surface and the journal and install the half dummy journal bearing
(306) or (307) between the rotor and the half bearing.
—Lower the crane down until the half bearing is resting on the journal bearing.
—Secure the assembly in this position by means of the two pins (334) screwed through the end
shield bearing (3B) fixation holes.
—Remove all the handling tooling.
—Assemble the dummy journal bearing (322) or (323) by means of the collar (302) positioned in the
end shield with the screws (3E), washers (305) and shuns (304).
Phase Ⅲ:
—Fit a small sling in the hole (3F) and hang up the half bearing by means of a lifting ring and a
shackle screwed at the half bearing section; slightly tighten.
—Fix a ring (3L) on the end shield bearing (3B). Attach a hoist to this ring and to the lower half
bears. Slightly tighten.
—Remove both pins (334).
—To aid the rotation of the half bearing, slightly tighten the hoist and simultaneously slacken the
crane.
—Continue in this way until the assembly has rotated 180". The lower half bearing is in low
position.
② Transfer and fastening of the 1/2 bearing
—Lubricate the rotor on the movement surface.
—Install threaded rods (331) and two pin (334) through the bearing fixing holes, so that they are
diametrically opposed and screwed into the end shield.
Page: 142
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 143
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 144
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
3A frame 3B end shied bearing
3E collar fixing screws 3F vibration sensor holes
3I upper half bearing 3J lower half bearing (excitation end)
3L ring 3N shackle
3P hoist 302 handling collar
304 spacers 305 washer
306 dummy journal bearing φ450(excitation end)
307 upper dummy journal bearingφ420(turbine end)
310 screw 311 spring washer
312 screws 313 spring washer
314 handling tooling lower half bearing 315 screw
316 washer 317 handling tooling upper half bearing
318 copper sheet 319 copper sheet
320 handling support 321 dummy journal bearingφ450(excitation end)
322 upper dummy journal bearingφ420(turbine end) 330 tallow
331 threaded rod 332 nut
333 washer 334 pin
335 guide
Page: 145
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 146
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 147
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
4A end shied bearing 4B frame
4C intermediate seal ring 4D contact surface of intermediate seal ring
421 screw 422 position pin
423 washer 424 nut
425 locking nut 426 screw
427 washer 435 collar
436 screw 437 spring washer
438 rubber sealing strip 439 collar
440 screw 441 washer
442 gun 443 plug
444 hole for shackle 446 bended tube
447 non return valve 448 rubber pad
449 rubber pad 450 bended tube
451 screw 452 locking washer
322 round washer
Page: 148
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 149
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 150
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 151
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 152
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 153
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 154
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Gradually tighten each nut so that the whole bearing can be transferred on to the rotor.
—Proceed in this way until the lower 1/2 bearing is in its final position.
—Install several bearing fixing screws with their fittings.
—Remove threaded rods, washers and nuts.
—Remove the lower and upper handling journal bearings and half collar.
—Remove the protective copper shim.
—Fit all the 1/2 bearing fixing screws and block them at 350 N.m.
③ Fit upper half bearings
—Position the shaft seal rings
To perform this assembly it is necessary to refer to document chapter 4.2.4
④ Assembly of the upper half bearings
See drawings 4-21~4-29.
PHASE I :
—Sling the upper half bearing by means of the handling support (320) and the tooling (317).
—Shift the upper half bearing while slackening the hoist (3P).
—Coat the contact surfaces with tight seal.
PHASE II:
—After having re-inserted the half bearing into the end shield, level the assembly back with the
hoist.
—Position the upper half bearing on the lower half bearing
—Fit the adjusted bolts (407) or (432), the washers (406) or (431) and the nuts (404) or (429) on the
joint contact surface.
—Remove the handling tooling.
—Fit the screws (403) or (430) and the washers (406) or (431)
—Clamp the screws of the joint contact surface (403) or (430)
—Fit all fixing screws of the upper 1/2 bearing and block the screws to 350 N.m.
Page: 156
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 157
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
4.2.5 Reassembly 、assembly and maintenance of the oil deflectors
(1) Disassembly of oil deflectors and bearing closings
① Disassembly of outer oil deflectors
See drawing 4-32
AT THE CONTACT SURFACE:
—remove the adjusted bolts (450)
—remove the screws (446) and (444)
—Remove the screws (441) from the upper half oil deflector (4D)
—Separate the upper 1/2 oil deflector (4D)
—Remove the upper 1/2 oil deflector (4D) and put it on a wooden wedging
—Un-tighten the screws (441) of the lower 1/2 oil deflector (4E)
—While holding the lower 1/2 oil deflector, separate it in such a way that the positioning pins (443)
can be removed
—Remove the screws (441)
—Remove the lower 1/2 oil deflector (4E) and place it on a wooden wedging
—If need be, protect every contact surface
② Disassembly of bearing closings
See drawings 4-33 and 4-34.
At the contact surface:
—remove the adjusted bolts (466)
—remove the screws (464)
—Attach two lifting rings (303) fitted with their washers (304) to the holes of the upper 1/2 closing
(3A)
—Sling the upper 1/2 closing by means of shackles as indicated and slightly tension
—Unscrew all the screws (461) from the upper 1/2 closing (4K)
—Separate the upper 1/2 closing (4K) so that the positioning pins may be removed (463)
—Remove the upper 1/2 closing and place it on a wooden wedging
—Fit two lifting rings (303), themselves fitted with washers (304), into the lower 1/2 bearing holes
(3B)
—Sling the lower 1/2 closing (3B) by means of shackles (302) as indicated and slightly tension
—Unscrew all the screws (461) of the lower 1/2 closing
—Separate the lower 1/2 closing (4L)
—Remove the lower 1/2 closing and put it on a wooden wedging
Page: 158
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 159
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 160
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 161
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 162
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Clean all contact surfaces of the end shield bearing (4M) and of the 1/2 bearing closings (4K) and
(4L)
—If need be, protect all contact surfaces
③ Disassembly of the inner oil deflectors
See drawings 4-35
—Remove the screws (423) from the upper 1/2 oil deflector
—Remove the upper 1/2 bearing (4A) following chapter 4.2.3
AT THE CONTACT SURFACE:
—remove the screws (425)
—remove the adjusted bolts (428)
—Remove the upper 1/2 oil deflector and place it on a wooden wedging
—Un-tighten the screws (423) of the lower 1/2 oil deflector
—Separate the lower 1/2 oil deflector and hold it
—Remove the screws (423) and rotate the 1/2 oil deflector into top position
—Remove the lower 1/2 oil deflector and place it on a wooden wedging
—Remove the seal (431)
—Clean ail contact surfaces of the bearing (4A) and (4B) and of the oil deflectors
—If need be, protect all the contact surfaces
(2) Reassembly of the oil deflectors and bearing closings
① Reassembly of the inner oil deflectors
See drawing 4-35、4-36
—Check that the contact surfaces are clean
—Glue the gasket (431) on the lower half oil deflector with glue (432)
—Coat the contact faces with sealing pulp
—Position the lower half oil deflector (4D) on the rotor (4C) and rotate it to the bottom position
—Fit the screws (423) and the washers (424) without blocking them
—Glue the gasket (431) on the upper half oil deflector (433) with glue (432)
—Apply sealing glue on the gasket (431)
—Assemble the upper half bearing in accordance with chapter 4.2.3.
—Fit the fixing screws (434/435) of the upper half oil deflector on to the upper half bearing
—Block all the screws (434) at a torque of 70 N.m
② Reassembly of the bearing closings
See drawing 4-33、4-34
Page: 163
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 164
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 165
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
TURBINE END
—Check that the contact surfaces of the upper half closing (4K), the lower half closing (4L) and the
end bearing are clean
—Coat all the mounting with sealing pulp
—Install the lower half closing (4L) temporarily on a wooden block under the rotor
—Place two lifting rings (303) fitted with washers (304) into the holes of the lower half closing (3B)
—Sling the lower half closing (3B) with the shackles (302) as indicated and put it into position
WARNING: Make sure that the sling never touches the rotor
—Fit the screws (461) and the washers (462) but do not block them
—Remove the sling, the lifting rings (305) and washers (304)
—Place two lifting rings (303) fitted with washers (304) into the holes of the upper half closing (3A)
—Sling the upper half closing (3A) with the shackles (305) as indicated and put it into position
ON THE JOINT CONTACT FACE:
—Fit the screws (464), the washers (462) and the nuts (465) but do not block them
—Fit the adjusted bolts (466), the washers (462) and the nuts (465) and block them at a torque of
104N.m
—Remove the sling, the lifting rings (303) and washers (304)
—Tighten the screws (464) at a torque of 186 N.m
—Fit the screws (461) and the washers (462) but do not block them
—Fit the metal pins which are provided with the tooling
—Tighten all the screws (461) at a torque of 70 N.m
—Dismantle the metal pins and replace them with insulating pins (463)
EXCITATION END
The installation of bearing closings excitation end is carried out in the same way as turbine end. But
there exist insulation parts such as (474), (475), (476) along with the bolt tightening between bearing
closings and end shield bearing. Be careful during installation. Check the insulation condition
between bearing closings and end shield bearing after installation. If there exist short circuit, try to
eliminate it.
Page: 167
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 168
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Carry out same operations for lower 1/2 fan nozzle ring.
(2)Reassembly of the fan nozzle rings
The reassembly of a fan nozzle ring requires the following to be carried out:
—Make sure contact surfaces are clean.
—Position the lower 1/2 fan nozzle ring and hold it by means of some screws (413) fitted with their
washers (414).
—Fit the pins (409).
Carry out same operations for the upper 1/2 fan nozzle ring.
—Fit the screws (403) fitted with their nuts (404) and locks (405). Do not block.
—Fit the bolts (406) fitted with their nuts (407) and locks (408). Do not block.
—Tighten fixing screws (413) to 40 N.m, (403) to 300 N.m, and (406) to 500 N.m.
—Check clearance j=1.5mm (theoretic value) between blades (4A) and fan nozzle ring (4B).
—If clearance j is not correct, remove pins (409). Untighten screws (413) and re-center fan nozzle
ring.
—Fit locks (410) onto pins (409).
—Fit nuts (411), washers (415) onto pins (409). Do not block.
—Fit and block screws (412).
—Fold back locks (410), (405) and (408).
—Fit retaining screws (413) fitted with their washers (414).
—Tighten remaining screws (413) to 40 N.m.
Page: 170
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 171
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Carry out same operation for compensators (408) and (426)
—Clean contact surfaces on lower 1/2 bearing (4A) and on end shield (4B)
—If need be, protect all the contact surfaces.
② Excitation end
See drawing 4-41.
—Remove screws (457) and (464) from pipework (456).
—Disconnect pipework (456)
—Remove pipework (456) and place it on a wooden block
—Carry out same operations for pipeworks (440) and (485)
—Remove screws (468) from compensator (467)
—Separate compensator (467)
—Remove compensator and place it on a wooden block
—Carry out same operations for compensator (453) and (484)
—Clean the contact surfaces on the lower 1/2 bearing (4A) and on the end shield (4B)
—If need be, protect all the contact surfaces
(2)Assembly of bearing oil inlet and outlet pipework
①Assembly at the turbine end
For this assembly, see drawing4-40
—Firstly it's necessary to give the contact surfaces of the 1 /2 bearing (4A) and the end shield
bearing (4B) a good clean.
—Position the seal (419) and the compensator (417).
—Position the screws (418) with their washers (413) and do not block.
—Do the same with the compensator (426) to be assembled with the seal (428) the screws (427) and
the washers (422) and with the compensator (408) to be assembled with the seal (410), the screws
(409) and the washers (403).
—Position the seal (414) on the compensator (417) and position the pipework.
—Place the washers (413) the screws (415) the nuts (416) and do not block.
—Position the second seal (414) on the 1/2 bearing (4A).
—Position the washers (413) and the screws (412) and do not block.
—Check that the seals (414) and (419) are correctly positioned as well as the correct alignment of
the compensator flanges and the pipework.
—After checking and any readjustment necessary, block the screws (412) and (418) to 58 N.m. and
the screws (415) at 155 N.m.
Page: 172
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 173
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 174
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 175
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 176
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
—Do the same with the pipework (420) and (401) to be fitted with the relevant assembly
components (compensators, seal pads screws, nuts, washers etc.)
② Assembly at the excitation end
Page: 177
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
For this assembly, see drawing 4-41
—Firstly, the contact surfaces of the lower 1/2 bearing (4A) and on the end shield bearing (4B)
must be cleaned.
—Position the real (469) and the compensator (467).
—Position the screws (468) with their washers (462) and do not block.
—Do the same with the compensator (484) to be assembled with the seal (483), the screws washers
(473) as well as for the compensator (453) to be assembled with the seal (455) the screws (454)
and the washers (445).
—Take two seals (461) and an insulating ring (460). Place the insulating ring between the two seals
and position everything on the compensator flanges (467) receiving the pipework (456).
—position the pipeworks (456), the laminated tubes (465), the washers (463), the washers (462),
the screws (464) and the nuts (466).Do not block the assembly.
—Take the other seals (461) and insulating rings (460) and position then between the lower 1/2
bearing (4A) flange and the pipework (456).Position the laminated tubes (458), the laminated
washers (459), the washers (463), the washers (462) and the screws (457). Do not block the
assembly.
(463) the washers (462) and the screws (457). Do not block this assembly.
—Check that the seals and the insulating ring seals are correctly positioned and than flakes and the
pipework are correctly aligned. After checking and necessary readjustment block the screws
(457) and (468) to 58 N.m. and this screws (464) to 155 N.m.
—Do the same for the pipework (485) and (440), compensator (484) and (453), fitted with their
respective assembly components and their seals with insulating ring
NOTE:
The screws fitted in the lower 1/2 bearing or in the end shield will be tightened to 58 N.m.
The screws fitted with a nut will be tightened to 155 N.m
Page: 178
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
5. Generator detection and protection
5.1 Stator detection and protection
5.1.1 Temperature sensors for magnetic core, copper shield
(1)Thermocouples of magnetic core and copper shield
Thermocouples work as a temperature detecting component for magnetic core and copper shield.
The thermocouple is a device wherein the ends of two varies of different metals are soldered
together to form what is called a hot junction. When the hot junction is exposed to a heat source, a
potential difference is generated whose magnitude is proportional to the temperature of the source.
With the exception of the hot junction itself, the wires are insulated along their whole length from
each other and from the generator ground. The hot junction is insulated from the generator ground.
The index of thermocouples is K.
The following table gives the correspondence between the temperature and the potential difference
generated in different thermocouple.
T (℃) 0 10 20 30 40 50 60
E.M.F.(mV) 0 0.397 0.798 1.203 1.611 2.022 2.436
The drawing 5-1 shows how the thermocouple is connected to the measuring device.
The thermocouple is thus protected by both the resistance (6) and the neon spark-gap (7).
As induction may produce a.c potential in the thermocouples, in order to ensure accurate temperature
measurement, the alternating (50Hz) parasitic component of the signal is filtered out by a filter
located within the measuring apparatus.
Each of the thermocouples in the generator can be put out of operation, in which case they are
connected on standby as shown in drawing 5-2.
⑵ Thermocouples of magnetic core
The highest temperature of magnetic core occurs at core end. The temperature detecting points of
Page: 179
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
magnetic core are located at the predicted positions of highest temperature at either turbine end or
excitation end. Thermocouple is stuck onto the core end lamination. The core ends are fitted with 12
thermocouples, 2 for each phase at both turbine end and excitation end.
For magnetic core, the serial number of thermocouple at turbine end are 40 ~45, the serial number
of thermocouple at excitation end are 50~55, lead terminals are connected to electrical connectors
respectively, see drawing 5-6“lead-out of temperature detecting components”, and attached
documents”330MW generator temperature sensors layout instruction” .
The temperature indicated by these thermocouples must be below 100 °C, and must on no account
exceed 130°C。
(3) Thermocouples of copper shield
Copper shield works in order to avoid the stator endwinding overheat which is caused by magnetic
leakage from generator end structure. But at the same time copper shield may have overheat effect
because of eddy current by magnetic leakage. The strongest effect point which is caused by magnetic
leakage from generator end structure is located at internal circle of copper shield; the position of the
strongest effect is also the position of the highest temperature. The copper shields are fitted with 6 on
the turbine end and the excitation end, 3 for each end; equal-space distributed alone the
circumference.
The serial numbers of temperature detecting points of copper shield at turbine end are 37 ~39, the
serial numbers of temperature detecting points of copper shield at excitation end are 138 ~140, its
lead terminal is connected to electrical connectors respectively, see drawing 5-6“lead-out of
temperature detecting components” and attached documents“330MW generator temperature sensors
layout instruction”.
The temperature indicated by these thermocouples must be below 115 °C, and must on no account
exceed 150°C。
Temperature detecting components are located at inside of inter-bar spacer which is between the top
bar and bottom bar inside stator slots.
There are 36 double-thermocouples for detecting temperature of stator winding, 1 for each slot. The
serial numbers are 1 ~ 36. The lead terminals of these 36 temperature detecting components are
connected to electrical connectors respectively; see drawing 5-6“lead-out of temperature detecting
components” and attached documents “330MW generator temperature sensors layout instruction”.
The temperature indicated by these thermocouples must be below 90 °C, and must on no account
exceed 120°C。
Stator winding is cooled by deionized water. After the heat of stator winding is taken away by
deionized water, temperature of deionized water will increase, the amount of increasing heat is
proportional to the heat situation of stator winding, therefore, by measuring temperature of deionized
water at outlet, the heat situation of stator winding can be estimated.
Page: 180
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
The platinum resistance detectors for measuring temperature are of endface type. The detectors are
installed in the small joints (for detecting temperature) which are welded on the water joints on water
manifold for the insulated connection hose.
In the small joint, the detector is pressed against the inside bottom of the small joint by a spring
tightly. The endface of detector contact bottom of small joint very well, so the temperature difference
between them is very small, that is ,the temperature of detector is consider as that of outlet water
flowing through the water joint.
At excitation end (water outlet end), there is an insulated connection hose connected between water
manifold and every top or bottom stator bar. There is a water-outlet temperature detecting point for
each top or bottom stator bar. The serial numbers of water-outlet temperature detecting point at
bottom bar are 60~95, the serial numbers of water-outlet temperature detecting point at top bar are
96~131. The lead terminals are connected to electrical connectors respectively,
See drawing 5-6“lead-out of temperature detecting components” and attached documents“330MW
generator temperature sensors layout instruction”.
The temperature indicated by these platinum resistances must not exceed 85°C。In normal operation,
the temperature is no more than 65°C.
5.1.4 Temperature instrumentation of circular phase connections
The H.V connections, including the circular phase connections, like the stator bars, are water-cooled.
These connections are made of copper tube. As for the water circuit itself, the phase connections is
in series with H.V. intermediate connections and terminals, the cold water passing first through the
terminal from bottom to top, then into H.V. intermediate connections, then into the phase connection
and returning into the outlet manifold.(Please refer to the drawing 1-2).
There is total 6 water outlet of phase connections at excitation end. The phase connection and
terminal circuits are fitted with a total of 6 the platinum resistance detectors, i.e. 1 on each hydraulic
fitting leading into the water outlet manifold. The warm water temperature is therefore monitored at
the point where the Teflon hose meets the water outlet manifold.
The serial number of 6 temperature detecting points for outlet water of terminal leads are 132 ~137,
their lead terminals are connected to electrical connectors respectively, see drawing 5-6“lead-out of
temperature detecting components” and attached documents“330MW generator temperature sensors
layout instruction”.
The temperature indicated by these thermocouples is below 65°C during normal operation, and must
on no account exceed 85°C.
5.1.5 Temperature instrumentation of hydrogen
The platinum resistance for measuring temperature of hydrogen is exposed to hydrogen, so rigid
external jacket is necessary to protect the resistance. Drawing 5-5 shows the structure and
installation situation of platinum resistance.
This wiring method of platinum resistance is same as the wiring method of imbedded platinum
resistance. See drawing 5-3 and 5-4.
Page: 181
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 182
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 183
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 184
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 185
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
(2) Temperature detection for hydrogen
Hydrogen is the coolant for rotor winding, stator core & stator end structures. The hydrogen is
circled in the generator under the action of the fans. During the circulation, hot hydrogen is cooled in
the coolers. The hydrogen cooler is located at the junction between hot hydrogen and cold hydrogen
inside the generator.
Inside generator, monitoring of cold hydrogen must run simultaneously with monitoring of hot
hydrogen. The temperature of hot hydrogen can show the heat situation of the parts which are cooled
by cold hydrogen, the temperature of cold hydrogen can show working situation of hydrogen
coolers. Generator has 2 cooling chamber, each chamber has 1 (2 groups) hydrogen cooler (see
2.1.3). 2 platinum resistances for measuring temperature of hot hydrogen and 2 platinum resistances
for measuring temperature of cold hydrogen are located at hydrogen inlet and outlet of 2 cooling
chambers respectively. The serial numbers of 8 temperature detecting components of platinum
resistance for measuring hydrogen temperature are 46 ~ 49 and 56 ~ 59, their lead terminals are
connected to the electrical connectors respectively, see drawing 5-6“lead-out of temperature
detecting components” and attached documents“330MW generator temperature sensors layout
instruction”.
Under condition of normal operation, the temperature of cold hydrogen indicated by these platinum
resistances should be blow 48°C, and that of cold hydrogen should not exceed 69 °C.
5.1.6 Leading-out of stator temperature instrumentation
Stator temperature instrumentations are lead out to outside of generator via the electrical connectors.
The electrical connector is an electric connecting component between inside and outside of
temperature detecting component machine. Because inside of generator is filled with high-pressure
hydrogen, the electrical connectors must have of hydrogen seal function in order to prevent
hydrogen leakage; there is a hydrogen seal structure at the position of installation.
Generator has 10 electrical connectors; each electrical connector has 68 contact points. To find the
corresponding components to each electrical connector contact, see attached documents“330MW
generator temperature sensors layout instruction”.
ATTENTION: there are ground contact points on electrical connectors, these contact points are
connected with external shield of components inside generator, in fact these ground contact points do
not contact with ground directly, and additional circuit is needed between the ground contact points
and ground.
Special bracket support which is provided by manufacturer must be used during installation, see
diagram 5-7.
Page: 186
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 187
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 188
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 189
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
For safety of human and machine, the generator stator must be grounded credibly.
This is achieved by providing an electrical connection between the frame and the manifolds at
turbine end and excitation end including the U shape manifold beneath the terminal box during the
generator is in operation.
There are 2 rectangular ground bosses welded to the bottom of the frame. These 2 pillars are
grounded during generator installation; this structure makes the electric connection between frame
and ground and completes the process of stator ground.
The outer surface of these bosses is machined, so as to obtain a clean contact surface for electrical
connection. This is to guarantee stator ground works well.
The hot junction (2) of thermocouple is located at head of rigid protective sheath (1). The head of
protective sheath and detected parts (journal bearing babbait alloy for this generator) are getting in
touch or close to each other. The hot junction (2) is isolated from protective sheath (1) via insulation
cover (3). With the exception of the hot junction itself, the wires are insulated along their whole
length each other and from the generator ground. Fit the sensors on the support (5) (i.e. the outer
frame of the journal bearing for this generator) by nut-spring equipment (4), and leading-out wires
will be fitted on appropriate position of the generator frame (i.e. end shield bearing for this
generator) via wire connection socket (6).
Drawing 5-10 shows the structure of temperature detection of journal bearing at either turbine end or
excitation end. Thermocouple (401) is fixed on external surface of journal bearing (4C). The lead
wire is fixed up to the position below end cover by wire clips (402) and bolts (403). Lead wire is
connected to socket (408); the socket is fixed on flange (404) by bolts (411), washers (412) and seal
pads (405). Lead wire socket is also connected to measuring device.
Under condition of normal operation, the temperature indicated by these thermocouples must be
blow 105 °C, and must on no account exceed 120°C.
The operation situation of journal bearing can be estimated by measuring temperature of outlet oil of
bearing. The detailed method is in relevant turbine generator instruction.
Under condition of normal operation, the allowable temperature of outlet oil of bearing must be
65°C, and must on no account exceed 70°C.
5.2.3 Temperature instrumentation of restraining bearing
Page: 190
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Thermal couple is used to measuring temperature of restraining bearing. The thermal couple is in a
rigid sheath, and it has its own connector. The couple is inserted from one side of the bearing
pedestal to the position under the Babbitt of bearing, to see drawing 5-11. The couple is fastened on
the pedestal with its own bolt, nut and seal gasket. The terminals on the connector are for user to
connect the couple to the measuring instrument.
The oil temperature is also need to be measured at outlet of restraining bearing with a thermal
resistance. The oil outlet flange is at the pedestal side. The type of the resistance is WZP-231, Pt100.
The resistance is also in a protection sheath and with connector. The resistance is inserted from the
flange into pipe in which the oil flows back. The oil outlet can be measured directly. Same as the
couple, the Pt 100 resistance is provided with its own fastening device (bolt and nut) and seal gasket
with which it is mounted on the oil outlet flange. The resistance shall be connected to measuring
instrument from the terminals of connector.
In normal operation condition, the temperature of bearing shall not exceed 80℃, and the oil
temperature at outlet shall not be higher than 65℃.
5.3 Rotor detection and protection
5.3.1 Shaft vibration measurement
The shaft vibrations measurement will completed through two sensors which are vertical from each
other .see drawing 5-12.
Vibration sensors (3) is located on external surface of journal bearing (2).Through a hole in the
journal, it’s probe reaches to the position close to surface of the shaft (1). The signals obtained from
the sensors is transmitted to the device (9) via wires (4), and then connected to the control device of
measurement. Lead wires (4) are fixed by clamps (5), screws (6) and washers (7).
Shaft vibration sensors, lead wires and device are matched and will be supplied by turbine generator
contractor, detailed instruction is in separate specific manuals for turbine.
When generator is in condition of normal operation, magnitude of shaft vibration (peak-peak) should
be less than 0.08mm
5.3.2 Detection of interturn short circuit in rotor winding
(1) Special detector monitored detection of inter-turn short circuit in rotor winding (see drawing 5-
13)
The detector (1) can be introduced into the hydrogen-filled generator to the position close to the
shaft (2) surface by an air lock (3) which gives access to a hole provided in the frame. The probe is
installed inside an air lock (4), which is insulated from hydrogen. There are special windings on the
top end of the probe. The rotor fields can induce potentials in these windings. We can observe these
potentials through an oscillograph and judge the shape of the signal, then we can find out that
whether there is short-circuit fault in the inter-turn insulation in rotor winding.
(2) Disassembly and assembly of the probe (see drawing 5-14)
Remove the screw (405) and open the cover (403). Take care not to tension the connection wiring
between the connectors (402) and detector (401) when removing the cover403).
Page: 192
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 193
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 194
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 195
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 196
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 197
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 198
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 199
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
The test can be performed on a generator which is not connected to the grid. It is easy to achieve this
configuration, but on the other hand it is difficult to detect a minor fault, such as a single short-
circuit between two turns.
The test can also be performed on a generator on load. In this case, considerable modulations of the
signal occur due to the generator load angle.
It is recommended that this test be performed on a short-circuit generator. In this way the accuracy of
the measurement is improved and the distortions of the voltage signal observed during a test in open
circuit are eliminated.
Page: 200
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
c. Plot the different values (as shown) on a graph and mark the polar and inter polar axes. For each
pole, values (XD) and (XG) must be the same.
d. Take the mean of the values measurement per coil for each pole. Compare the poles.
Any dissymmetry in the results indicates an inter-turn insulation defect.
NOTE: Results of an on-load test are analyzed as described above, but the generator load angle has
to be taken into account.
④ Localizing the short-circuit
If possible a fault should be localized by recording a signal identifying the position of the rotor
relative to the detector at the same time as the detector voltage signal. Since the position of the rotor
“blip” relative to the rotor axes is known, the fault can be localized easily.
Brush (409) and brush holder (401) are fitted onto a support plate (4A) which is bolted onto the oil
deflector. Link the joint (419) to twin brushes (418) with brush wires. A conductive braid connects
the boss to ground (see drawing 5-17). The cabling is protected by a thermoshrinking sheath and
fixed by wire clip (405).Wire clip (405) is fitted onto the outer oil deflector or welded on the frame.
A spring presses the brush down onto the shaft, the pressure exerted being constant throughout the
period of wear (so avoiding the need for pressure adjustment). See drawing 5-16.
There is insulation between the pedestal of restraining bearing and the seat box of brush gear. The
screws are insulated too from pedestal by insulation tube and gasket. There are insulation tubes and
gaskets between inlet and outlet flanges and tubes.
Page: 202
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 203
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Parts list for drawing 5-15 recording and analyzing of the voltage due to the leakage flux from
the rotor slots
3A pole A 3B Pole B
3D polar axis 3E interpolar axis
3F damper slot peaks
xD peak-peak voltage corresponding to 1/2 to coil x
(right hand part of coil x, pole A)
xG peak-peak voltage corresponding to 1/2 to coil x
(left hand part of coil x, pole A)
Note:
This diagram represents a rotor with 7 coils per pole and 3 dampers in the centre of the pole.
Page: 204
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 205
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 206
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 207
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Page: 208
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
6 Generator installation
The full description of generator installation is not included in this section; this section just describes
Page: 209
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
some cases during the installation of generator.
⑵ Before the installation of generator, installation staff must familiar with the relevant drawings and
technical documents, staffs must count the amount of all parts and accessories and establish
reasonable and feasible technical and safety policy according to relevant standard and installation
regulation of large turbine generator.
⑶ Some components of generator must be subjected to special tests during installation of generator,
some of components need to be tested before installation. The details of special tests are not included
in this instruction.
⑷ All measurements, inspections and tests during installation of generator must have detailed
records, the copy of these records must be provided to workshop.
(5) During the installation of generator, every person who entering the generator must wear gumshoe
Brush and special uniform (no metal attachments). Metal and other dirt are not permitted to take into
generator, keep clear inside the generator at all time.
⑶End shield bearing and winding cover-H2 fan nozzle ring installation.
See section 6.5.
⑸ Rotor installation
See relevant parts and drawings of chapter 1-section 3.2:
5EG.487.079S rotor installation
5EG.487.069S rotor installation
5EG.487.047S rotor installation
5EG.487.048S rotor installation
5EG.487.049S rotor installation
The relevant parts and drawings about rotor overhung support are in section 4.2.1:
5EG.487.080S rotor external support assembly
Note: Before rotor being installed, the small shaft should be dismounted from rotor in order to
Page: 210
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
install the tools. When small shaft is being assembled, measure the turn-off at the journal of small
shaft, and turn-off should not exceed 0.04 mm. After dismounting installation tools, reassembly the
small shaft.
⑹ Lower half bearing installation
See relevant parts and drawings of section 4.2.2:
5EG.264.142S journal bearing φ450 (turbine end)
5EG.264.143S journal bearing φ420 (excitation end)
5EG.048.023S journal bearing handling
5EG.048.024S journal bearing handling
5EG.048.025S journal bearing collar handling
⑺ Gas guide ring and blade installation
Gas guide ring installation, see the relevant parts and drawings of section 4.2.6:
5EG.013.213S Winding cover-H2 fan nozzle ring general layout
Blade installation, see the relevant parts and drawings of section 3.6.2:
5EG.217.528S Blade mounting
Check whether the gap between gas guide ring and blades is satisfactory to requirement after blade
installation.
⑻inner deflector installation
See the relevant parts and drawings of section 4.2.5:
5EG.012.432S covers assembly (excitation end and turbine end)
⑿detectors installation
This procedure needs to install the following detecting components:
①Journal bearing temperature detecting component –See the relevant parts and drawings of section
5.2.2:
F5000063S journal bearing thermocouple testing
②Shaft vibration detecting component - See the relevant parts and drawings of section 5.3.1:
5EG.421.204S bearing vibration instrumentation
③Bearing insulation measurement - See the relevant parts and drawings of section 5.3.4:
5EG.421.448S bearing insulation testing
④Grounding brush assembly - See section 5.3.3.
5EG.125.221S Grounding brush assembly
⒀ Hydrogen cooler installation
See the relevant parts and drawings of section 2.4.2
Page: 211
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
5EG.487.030S generator cooler handling
0EG.340.534S turbine generator cooler installation
⒆ Hollow copper intermediate connections, H.V. terminal bushings and current transformers
installation
See section 6.7
─ Documents preparation
0EG.340.223S generator installation layout
5EG.020.688S foundation plate assembly
0EG.314.061S stator leveling and rotor alignment
─ Installation process
⑴ Do high intensity block technical experiment, determine the ingredient and facture. The high
intensity blocks is not allowed to shrinkage or expand after solidification, the resist-intensity of
block is at least 60MPa.
Page: 212
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
⑵ According to the requirement of foundation plate assembly diagram, make sure the height mark
(150mm lower than the finished surface in this case) of base surface which at the place of high
intensity block. Carefully roughen the foundation concrete and remove all loose particles.
⑶ According to the requirement of generator installation layout, check whether the steel tubes to be
embedded are in the correct position to foundation bolts, also check whether the perpendicularity is
satisfactory to the requirement of assembly drawing.
⑷ According to the requirement of foundation plate assembly, place sub sole leveling plates to the
positions of item.3,.4,.5,.6, 7, 11 and 12 which are indicated in assembly diagram.
⑹ Replace the subsole leveling plates to the positions, according to diagram, install expansion bolts
No.25, nuts No.26 and washer No.27, but do not tight any components.
⑺ Install adjusting bolts No. 24 on every subsole leveling plate, and adjust the height of plates by
adjusting bolts according to the requirement of stator leveling and rotor alignment (0EG.314.061S).
⑻ Lock the bolts No.26 on every subsole leveling plate, and then check the height of every
foundation plate again.
⑼ Place model box at the place where is required to make high intensity blocks, and then cast high
intensity blocks.
⑽ Remove nuts No.26 and washer No.27, trim away the extra parts of expansion bolts No.25 which
is higher than subsole leveling plate. Meanwhile, the adjusting bolts (No.24) should not protrude
subsole leveling plate; trim the protrusion part if the extra part exists.
⑾Place each sole plate (No.2, No.9). According to drawing “generator installation layout”, check
the following items:
Check transverse and longitudinal position of each foundation plate;
Check the levelness and parallelism of side foundation plates;
Check the contact condition between foundation plate and accessorial sole plates;
Positive gradient of sole plate and centering condition of embedded steel pipe for anchor bolt are
need to be inspected according to the requirement of generator installation diagram. Adjust in time if
any requirement is not achieved.
⑿ According to the requirement of generator installation drawing, check whether the foundation
bolts for foundation plate (No.14) and embedded steel tubes are in the correct position, also check
whether the perpendicularity is satisfactory to the requirement of drawing.
⒀ Check whether the height of plate surface No.32 is correct and clean it up according to the
requirement of foundation plate assembly diagram.
⒁ Place plate of No.32 to specified position according to generator installation drawing, and then
check its height and levelness, place packing piece of No.28, 29 and 30.
⒂ Place plate No.14, inspect its transversal position, longitudinal position, height and levelness. The
error between height and levelness can be adjusted by adjusting packing piece No. 28, 29 and 30.
Page: 213
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
⒃ Install 4 anchor bolts for installing plate No.14 (including Bolt No.31, plate No.23 and nuts
No.20). Adjust height of bolts in order to make nuts No.20 at t he upper position and stud (No.31))
end is lower than upper surface of plate No.14.
⒅ Apart from the anchor bolts which are for plate No.14 is installed in this process, other anchor
bolts which include anchor bolts for stator and anchor bolts for seat box for brush gear are installed
loosely (not tightened) after positioning of stator and seat box, these anchor bolts are tightened
according to the requirement of foundation plate assembly diagram after the adjustment of generator
position finished.
⑴ Check the seal condition of joints of stator according to drawing 5EG.311.236S. Inspect if there is
any defects on stator which is caused during transport or storage.
⑵ Lifting the terminal box and lower it down to the generator pit.
⑶ Install 4 stator lifting trunnions according to the requirement of the drawing” handling trunnion
general layout” 5EG.472.018S, the side of lifting trunnion with plain surface should face down,
tighten the bolts between lifting trunnion and frame by a torque of 1200N*m.
The lifting trunnion should be removed before the operation of generator.
⑷ Carry the stator onto the required position of sole plate according to the requirement of generator
installation layout.
⑸ Place 4 jacks below the 4 generator lifting trunnions according to the requirement of stator and
terminal box positioning drawing 5EG.671.876S.
⑹ Lift stator by jacks, and place packing piece No.17 below the feet of stator frame according to
foundation plate assembly drawing, each foot needs 5mm. of packing pieces.
⑺ Set down stator. Install studs No.1, 8 and relative connecting components according to foundation
plate assembly drawing: nuts (No.15), washers (No.16), plates (No. 18) and nuts (No.19). Fasten
nuts gently (incompletely)
Tighten up the nuts completely after the adjustment of barb bolts at position of stator.
⑻ Install 4 lifting pulleys under frame according to the requirement of stator and terminal box
position drawing 5EG.671.876S, each lifting pulley has load capacity of 2t.
Page: 214
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
⑼ Lift the terminal box to the installation position by lifting pulley.
⑽ Fix the terminal box onto the frame by using bolts (No.1) and washers (No.2) according to the
requirement of terminal box assembly drawing 5EG.307.579S.
⑾ Tighten the connecting bolts between terminal box and frame by using torque of 1000N*m.
⑿ Weld the contact surface between frame and terminal box in order to prevent hydrogen leakage.
All the process is according to the requirement of generator site installation drawing 5EG.034.415S.
Note:Terminal box installation: see appendix E。
6.5 End shield bearing and winding cover-H2 fan nozzle ring installation
─ Documents preparation
5EG.013.213S Winding cover-H2 fan nozzle ring general layout
5EG.012.425S End shield bearing assembly at turbine end
5EG.012.421S End shield bearing assembly at excitation end
─ Installation process:
⑴ When generator is taken from manufacturing workshop, the internal end covers (includes winding
cover and H2 fan nozzle rings) are installed inside generator stator. After the stator is in position, the
H2 fan nozzle rings should be removed in order to install rotor. The upper H2 fan nozzle rings
should be taken away and stored after disassembly and the lower ones should be placed temporarily
lower place inside generator. The lower ones are reinstalled after installation of rotor.
⑵ Inspect whether the internal end cover inside stator is in final and good condition according to
winding cover-H2 fan nozzle ring general layout 5EG.013.213S.
⑶Install end shield bearing at turbine end according to the requirement of end cover assembly at
turbine end drawing 5EG.012.425S. From this diagram, the end shield bearing at turbine end
consists of end shield bearing; lower half bearing, clamping collar, upper half bearing and so on. In
this working process, only end shield bearing (i.e. No.1 in drawing) and its relative parts are
installed, such as end shield bearing machining at turbine end, connection components and seal
components with frame, including 78 bolts No.44, 2 position pin No.45, 2 nuts No.13, 2 washers
No.14 and 50, injecting glue.
⑷ Install end shield bearing at excitation end according to the requirement of end shield bearing
assembly at excitation end 5EG.012.421S. From this diagram, the end cover at excitation end
consists of end shield bearing; lower half bearing, clamping collar, upper half bearing, and
intermediate ring and so on. In this working process, only end shield bearing (i.e. No.1 in drawing )
and its relative parts are installed, such as end shield bearing machining at excitation end, connection
components and seal components with frame, including 78 bolts (No.14), 2 position pins (No.6) , 2
nuts (No.4) , 2 washers( No.5) 2 washers (No. 7), injecting glue.
⑸ Install intermediate ring NO.18 and its connection components and seal components with end
shield bearing, such as bolts (No.43 ), backing ring No. 39, 38 and 40, 41, laminated tube No.42 and
seal rubber tape. If the intermediate ring is installed on the end shield bearing when the generator is
shipped from manufacturing workshop, it is needed to inspect the condition of assembly and
insulation.
NOTE: Seal between end shield bearing and frame, to see:
Appendix E: High terminal connection installation inside terminal box
Page: 215
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Appendix F Hydrogen cooling turbine generator—gas-tight components installation regulation in
site
Adjust the position of conducting rings according to the position of slip rings. When installing
brushes, make sure the brushes near generator are 14 mm away from the end of slip ring in axial
direction, and the ones on the other side are 2 mm away from end of slip ring in axial direction( to
see the drawing). So, the brushes will be in the central portion of slip ring when generator is in
operation because of the expansion of the rotor shaft. It is required to grind the brushes before
starting the generator to rated speed so that they can contact slip ring well.
6.6.4 Restraining bearing installation
⑴ Restraining bearing is at the end of the whole generator shafting. The position of its pedestal
shall be adjusted and aligned together with the main journal bearing of turbine and generator in the
mean time the expansion and lift in the bearing of the shafting shall be taken in to account.
⑵ According to restraining bearing assembly drawing, place the lower half pedestal( No.3 ) on the
seat box, adjusting the shims between pedestal and seat box (No.34,35,36,37 ) to locate the central
line of the pedestal. Fix the pedestal on seat box with screws (No.30), insulation washers (No.31),
and insulation tube (No.32).
Note: The restraining bearing is an insulated one; the insulation part of above pieces must not be
Page: 216
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
damaged during being installed.
⑶ Install lower half and upper half bearing(No.5), check the clearance.
⑷ Fasten the screws ( No.4) to fix the bearing, then install bearing cover(the upper part of
pedestal) and fix the cover and pedestal together.
⑸ Ream the hole for insulated pin(No.40), then install the pin.
⑹ Install the other parts according to the drawing. Install the oil pipes.
6.6.5 Soundproof housing installation
⑴ Position the soundproof housing according brush gear assembly drawing. Make sure that the
clearance between shaft and wind deflector which is mounted at inner side (near generator) of
soundproof housing evenly.
⑵ According to diagram C in soundproof housing drawing, mark the position of 11-Ф14 holes.
⑶ Take away the soundproof housing, drill 11--Ф14holes, install the expansion bolts(No.15).
⑷ Position the soundproof housing again and fix it on the foundation with expansion bolts.
⑸ According to soundproof housing drawing, mount the doors and their attachments.
⑹ Fix the wind deflector.
NOTE: the high voltage bushing installation see appendix F “Hydrogen cooling turbine
generator—gas-tight components installation regulation in site”
⑴ Preparation
.Tools for installation
.Use lifter to lift up the high voltage bushing until the studs, washers and nuts can be assembly to
the bushing
.The movement of high voltage bushing can be adjusted by hands; the movement adjustment also
can be made by the tools which are fixed on the locking device. The adjustment is stopped until the
high voltage bushing reaches the final position.
.Lift the high voltage bushing up to its position and tighten nuts.
.Guarantee the position of washers is correct.
.Fix high voltage bushing by bolts
.Use corresponding bolts to fix the whole high voltage bushing.
.Lock high voltage bushing tightly.
① Preparation:
.Clean flange holes, studs and nuts carefully by solution
.Before installation, locking nuts should be installed on the stud which fix current transformer.
.Install stud with torque of 89Nm
.Lay on propylene polymer to thread.
.Put stud go through fixing flange, and use nut to lock it tightly.
.Inspect the contact surface of bushing end flange and the surface of silver plating on thread which
contact with high voltage bushing.
.Install and adjust the relative position between bushing end flange and high voltage bushing. Link
two half bushing end flanges together by using bolts.
Page: 218
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
⑷ The installation of insulated water hose which is between high voltage bushing and manifold.
NOTE:
The detailed installation process, to see:
Appendix E: High terminal connection installation inside terminal box
Some tests must be made before operation of generator, do water pressure test and air tight test to the
whole winding water system, after these tests, do water flow rate test, insulation resistance detection,
DC withstand-voltage test, DC leakage test and AC withstand-voltage test. Do ventilation test before
installation of rotor, do AC impedance measurement after installation of rotor. Hydrogen leakage test
is made at the final stage.
Page: 219
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
7 Generator operations
This section describes some questions during the operation of generator. The detailed operation rules
will be written by the user itself.
Before starting the unit, verify that all faults on each system have been cleared.
Before starting the unit, the auxiliary systems must be put in service in following order:
Hydrogen control system cannot be in operation until the sealing oil control systems have been in
complete service.
During starting the hydrogen control system, replace the air with carbon dioxide (CO 2), and then
replace the carbon dioxide (CO2) with hydrogen.
The process of starting the hydrogen control system is described in the specific manual of hydrogen
control system.
This system can be only in service after the generator has been filled with compressive-hydrogen,
besides that all parts of cooling water system must experience all kinds of special tests.
ATTENTION: close the water outlet valve before starting the water pump, and then open the
valve gently in order to avoid damage from impact of high-pressure water to stator winding and
pipelines.
The process of starting the stator cooling water system is described in specific manual of stator
cooling water system.
The excitation breaker is automatically open when the turbine generator unit is tripped.
ATTENTION: In any case the excitation system cannot be in service, if the generator speed is
being decreasing or at standstill.
FIRST CASE: the duration of the stop is short, and there is not any intervention to do in the
generator, the stator is maintained in hydrogen at the normal pressure.
SECOND CASE: the duration of the stop is short, but the stator has to be visited, the hydrogen
is drained, replaced by CO2 and then by air.
THIRD CASE: for the conservation in the other cases of stop, see the manual section 2.3 and
section 3.3
Generally, if the duration of the stop is long, the generator stator should be filled with hydrogen,
pressure higher than atmospheric pressure or be filled with dry air, pressure higher than the
atmospheric pressure (the minimum pressure is 0.1MPa). This is the best conservation.
If the stator is still on H2 pressure and the duration of the stop is short, the system has to be kept in
normal operation. This is the best conservation. If the duration of the stop is long, the unit should
be shut down. The system must be put out of service.
ATTENTION: Never stop this system when the field breaker is closed.
Page: 221
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
⑴ Excitation and regulation system
The setting values of the excitation system are not permitted to change during operation of the
unit. The operation point is the only factor which is permitted to change according to the
dispatcher’s requirement during the operation of unit, i.e. change the setting values of the
generator voltage. The detailed description is included in specific manual of excitation system.
The detailed descriptions see the specific manual of stator cooling water control system .
Page: 222
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
(1) The temperature of any stator winding is higher than 90℃
(2) The temperature of any stator winding water-outlet is higher than 80℃
(3) The standard deviation of each bar is higher than 5 ℃ in case of the standard deviation of top
bar and bottom bar is calculated separately.
Treatment after alarm: firstly, analyze the cause that makes high temperature of stator winding.
Take specific measures to eliminate the defects, such as reduce the generator load or eliminate the
fault in the pipeline of deionized water. If the temperature is too high as a result of the certain
hollow copper strands are blocked, monitor the temperature to avoid reaching the upper limit level
of temperature, and solve the problem when the unit is shut down.
If the measure after alarm is void, the temperature of stator winding increases continuatively, trip
should be made immediately when the temperature of any component of stator winding
Page: 223
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
interlamination reaches 120 ℃ or the temperature of outlet water of stator winding interlamination
reaches 85 ℃.
The possible cause that makes the temperature of hot hydrogen high may be:
1 generator over-load;
2 cold hydrogen temperature is too high;
3 hydrogen flowrate is not high enough as a result of gas circuit fault;
4 over leakage of hydrogen;
5 over low-pressure of hydrogen
Treatment after alarm: find out the exact cause, and then take specific measures to eliminate the
defects. If the hot hydrogen temperature maintains high, reduce the generator load to maintain the
hot hydrogen temperature below 60 ℃ and solve the problem when the unit is shut down.
If the hot hydrogen temperature is proper, abnormal condition of coolers operation is the main
cause to make the cold hydrogen temperature too high.
Treatment after alarm: find out the exact cause, and then take specific measures to eliminate the
defects.
7.4.4 Stator core end structure and copper shield temperature alarm and treatment
Alarm should be activated immediately if either temperature of stator core end is higher than 120
℃ or copper shield temperature is higher than 150 ℃.
It is usually caused by generator over-load or drop of cooling efficiency of the cooler. The causes
and treatment for cooling efficiency drop of the cooler see section 7.4.2 and 7.4.3.
If only the end structure temperature rises while the copper shield temperature rises, it is usually
caused by the generator end flux leakage. Check and find out whether the generator operates within
the range of the drawing 1-5 and 1-6. Reduce the reactive power of leading phase operation to make
the temperature of stator core end and flux shield maintain within proper range.
The trip should be made immediately if the stator core end temperature reaches
130 ℃.
If the magnitude of shaft vibration still increases, trip should be made immediately when the
magnitude of vibration reaches 0.24mm.
Page: 225
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
8 Outlet oil temperature of sensors in ℃ ≤ 65 > 70 > 80
journal bearings
9 Restraining bearing Temp. ℃ ≤ 90 > 100 > 120
sensor
10 Outlet oil temperature of sensor in ℃ ≤ 65 > 70 > 80
restraining bearing
11 Shaft vibration detector mm ≤ 0.08 > 0.12 > 0.24
The rated values of above protection items shall be made by user according to the generator
technical data given in section 1. We recommend some protection values as following:
The protection requirements of the auxiliary systems are described in the specific manual.
Page: 227
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Appendix A: Visual examination and dye penetrate examination of journal bearing
2 Technical requirement
No cracks on surface
No fault is permitted at lower bearing carrying zone
Faults on other zones:
a. The unit quantity of indication whose diameter is less than 0.5mm and depth is less than
0.5mm, should be less than 3 per cm 2. This position whose unit quantity of fault is equal to 3
per cm2 should be less than one every 200 cm2.
b. The number of faults whose diameter is less than 1mm, depth is less than 1/3 of bearing
Babbitt alloy layer depth at the place of the fault and depth is less than 1mm is not more than
1 for every 200 cm2. If two faults occur at the same surface, the distance between centers of
faults should be more than 10mm.
b. The situation for the indication whose diameter is less than 0.5 mm and depth is less than
0.5mm, and the unit quantity of indications is equal to 3 per cm 2, may occur at most once for
every 200 cm2.
c. The number of the indications whose distance in between is more than 10mm, diameter is
Page: 228
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
between 0.5mm and 1mm, depth is less than 1/3 of tungsten layer depth of the place of the
fault and depth is less than 1mm, is at most 1 within every 200 cm2.
NOTE: Lower load zone of journal bearing is the area whose range is 90 degrees as the center is
perpendicular center line of lower bearing as centering line.
Page: 229
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Appendix B Hydrogen cooled turbine generator sealing glue usage
1.1 Long-time operation immersed in hydrogen, the sealing glue has good gas-tightness.
3.1 The glue SWG-1 is used in seal groove, plain surface beside seal groove is coated with glue
SWG-2.SWG-2 is used on flange surface, joint surface and other plain surface.
3.2 Carefully inspecting before installation, make sure seal groove and seal plane are tidy. No burrs,
oil dirt and rust are allowed to exist. No dust, oil dirt, scales and so on exist at installation site.
3.3.1 Plane seal: before assembly, lay on SWG-2 sealing glue uniformly to seal plane.
ATTENTION:
A. Inspect and clean the bush dust or other dirt on the glue layer
B. place the seal plane in horizontal level
C. Wait for a moment after gluing, and then assembly when glue stops flowing.
A. Lay on SWG-2 sealing glue at the beginning on the seal surface beside groove
B. Do the procedures of 3.3.1 for assembly
C. Injecting SWG-1 sealing glue into first hole, and using screw to block up the first hole
when the glue neighbor holes is discharging, then injecting sealing glue into second
hole, do the same procedure until the last hole is blocked up.
4 Maintenance
During the generator operation, injecting glue if any gas leakage from end shields bearing happens.
5 Overhauls
5.1 General inspection about situation of integrity, make sure no dirt exists after open of seal groove
and plane seal
Page: 230
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
5.2 Remove the film of sealing glue and clean seal surface
5.3 Cover sealing glue and seal surface with thin film
Page: 231
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Appendix C Storage condition of insulation material for installation
Storage of standard insulating tape and insulating material for generator site installation is included
in this section.
1. General requirements: insulating material should be stored in dry and clean warehouse. The
insulating material should be kept away from fire, heating device and sun light.
2. Storage condition: in original pack and start from the date of manufacturing
ATTENTION: if the temperature of storage for mica products is blow 10 ℃, the products should be
placed under specific temperature range (10-35 ℃) for at least 24 hours before use.
Storage period of single group is 2 year if the product is in original pack and at room temperature of
20 ℃.
Using up the mixing glue within 1 hour after mixing 2 single group
4. Epoxy glue
Storage period under room temperature is 6 mouths if the product is stored in dry and ventilated
warehouse
Storage period of single unit is 1 year if the product is in original pack and at room temperature of 20
℃.
Using up the mixing glue within 1 hour after mixing 2 single group
Page: 232
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Appendix D Calculation of perpendicular distance between arc and chord for centering by
steel wire
Using steel wire for centering, the numerical value of perpendicular distance between arc and chord
of steel wire should be corrected during measuring. The formula is as following:
mW——suspension mass, kg
x——distance from steel wire fixing point to point of perpendicular distance between arc and chord
to be measured, m
2L——distance between two fixing points of steel wires, m
Page: 233
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Appendix E High terminal connection installation inside terminal box
Page: 234
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
2、 Weld the rib according to the position and size in drawing 5EG.175.1673S.
3、 Weld rib ( No.7 in drawing 5EG.175.1673S) with the fixed ribbed slab ( No.5 in drawing
5EG.175.1673S ) on water manifold according to the position and size in drawing
5EG.175.1672S, pay attention to position of water-inlet of manifold. This procedure can be
completed before terminal box installation according to actual situation.
4、 Assembly other parts according to requirement of drawing 5EG.175.1673S, carry out
chemical acid cleaning and liquid leak check to pipe component according to actual situation
of installation in site, the detailed requirement is from technical drawings. Clean insulation
parts before installation in order to guarantee its insulation capability.
5、 Install the water manifold and terminal box according to drawing
5EG.175.1673S、5EG.175.1672S, clean insulation parts before installation in order to
guarantee insulation capability. Then inspect and measure the insulation and the flange (No.4
in drawing 5EG.175.1673S) should be connected with ground during measuring.
6、 Install pipe component No. 5 according to drawing 5EG.175.1672S, sealing is required to the
connection between pipe component No.5 and high-voltage bushing. underlay the PTFE
plate No.11, tighten pipe component No.5 according to the drawing requirement, enwrap
insulation tape No.3 and coat solvent-free glue No.4 according to position in section A-A
and section B-B.
7、 Install insulating tube No.1 according to drawing 5EG.175.1672S, clean carefully the foreign
mater at each joint before installation.
8、 Connect the water manifold with ground according to drawing 5EG.516.058S; carry out test
to inspect the ground condition.
Page: 235
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
4、 Confirm the position relationship between 6 intermediate connections (8EG.512.227S~
8EG.512.232S) and stator connecting lead according to the marks and the drawing
5EG.512.442S (high-voltage terminal connection).
5、 Clean all electric joint surface, free-of water ethanol or propketone may be used for cleaning,
do not use hard staff to clean in order to avoid the damage on silver plating conducting
surface.
6、 Pre-assembly connecting bushing No.9 and No.16 and intermediate connections No.1—6
according to drawing 5EG.512.442S (high-voltage terminal connection), confirm the position
relationship.
7、 Inspect the sealing ring No. 17 and No.20, then install sealing ring No.17 and No.20
according to the position in drawing 5EG.512.442S; inspect and install sealing ring No.10
according to drawing 5EG.512.428S (high-voltage bushing assembly).
8、 Install connecting bushing No. 9 and 16 and intermediate connections No. 1—6, and use
corresponding components to fasten with equal torque. No foreign mater is permitted to enter
into transient connections, connection bushing and high-voltage bushing during installation;
careful inspection must be carried out before installation.
9、 Carry out hydraulic pressure and gas-tighten test and check leakage condition to each joint,
continue the next procedure if the leak check is satisfactory.
10、 Enwrap ployimide film No.25 on connection bushing, the connection bushing should be
connected well with upper and lower transient connections and high-voltage bushing.
11、 Clean terminal insulation box No.23, No.26 with free-of-water alcohol or propketone, coat
solvent-free glue onto internal surface of insulation box and airing.
12、 Pre-install terminal insulation box No. 23,26, adjust vertical position of insulation box in
order to guarantee the length of transient connections, stator terminal lead, and high-voltage
bushing are equal inside insulation box. Mark out the position on the intermediate
connections and stator terminal leads where the upper and lower end of the insulation box is
corresponding to.
13、 If the length of any insulation part inside insulation box is shorter than 30mm, Semi-wrap the
mica strip No.38 for 4-6 layers to ensure the length over 30mm.The mica strip should
cooperate well with original insulation.
14、 Install terminal insulation box No.23, 26 and tighten it up, adjust the box to make a uniform
gap with connection bushing, use epoxy mica clay or solvent-free-glue flexible felt to fill the
big gap, solidification under room temperature in order to prevent injecting glue leakage.
Page: 236
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
15、 Mix the injecting glue of insulation box of No.24 by specific ratio, carry out solidification
test to injecting glue.
16、 Inject glue by special injecting tool, observe the condition of glue drop and fill new glue until
the glue surface which has been hardened is at same level with top of insulation box.
17、 After glue solidified completely (about 16—24 hours), infrared light may be used to make
glue to solidify quicker and the temperature is not allowed to be too high. Clean external
surface of insulation box.
18、 Insulation test: 24kV DC voltage is exerted to stator winding; the test is satisfactory if the
potential on surface of insulation box is less than 2kV.
19、 Install plate No.14 and clamping plate No.15, No.33 according to drawing 5EG.512.442S
(high-voltage terminal connection). Insert immersed solvent-free-glue flexible felt No.29 into
junction between insulation contact part and each plate.
20、 Install insulation tube No.7 and No.8, insulation tube No. 37 and clamping plate No.31, 30
according to drawing 5EG.512.442S (high-voltage terminal connection). Insert immersed
solvent-free-glue flexible felt No.32 into junction between insulation contact part and each
plate.
21、 According to drawing 5EG.106.205S (terminal connection fixing at upper of terminal box),
connect and fix fixing joint No.2 with angle support No.1, then connect and fix clamping
plate No.5 with No.2 by using shaft collar No.4, insert immersed epoxy-glue flexible felt into
the gap between clamping plate No.5 and insulation box contact part, insert immersed epoxy-
glue flexible felt between shaft collar and clamping plate No.5. The tightening torque to nut
No.13 and 10 is 80Nm.Fix the laminated board No.9 by epoxy glue according to section A-
A.
22、 Clean inside of terminal box.
23、 According to drawing 5EG.311.183S (inspection hatch assembly), install seal ring No.11
after clean seal groove, install man-hole cover plate.
Page: 237
Beijing BEIZHONG Steam Turbine Generator Co.Ltd.
File no:Q96M SYE
Appendix F Supplement for Inspection and Test Item of the Generator
1 Stator
1.1 After the generator stator has reached the power plant, do visual inspection, and measure the
insulation resistance between winding and ground, phase and phase.
1.2 Before installing the intermediate connections and the high voltage terminals do hydraulic test,
water flow test and air tightness of water circuit inside the stator according to JB/T6228. The water
pressure is same as the acceptance test water pressure. Air tightness test also can be done according
to ALSTOM standard IBF R28268. After finishing assembly, do hydraulic test, water flow test and
air tightness on stator with intermediate connections and the high voltage terminals together. After
this, mount the insulation covers and inject insulation glue into it. Before inserting the rotor, do
insulation resistance test, DC voltage withstand e test and AC voltage withstand test on stator
winding. When tests being do, temperature sensors shall be grounded to prevent from being
damaged.
1.3 After some fault impact (such as short-circuit close to the generator, generator grounding fault,
faulty synchronizing and so on.) occur on the generator, thorough examine should be done on stator
and rotor. Abnormally high currents and torques may be occurred as result of a short-circuit close to
the generator in service, or of clearance and reclosure of a more distant fault, or of faulty
synchronizing. It is prudent to examine the generator thoroughly, with particular attention to the
stator windings. Any loosening of supports or packings should be made good before returning the
generator to service, to avoid the possibility of consequential damage being caused by vibration. It
may also be desirable to check for possible deformation of the coupling bolts, couplings and shafts.
2 Rotor
2.1 After the generator rotor has reached the power plant, visual inspection should be done
immediately and insulation resistance of the rotor winding must be measured immediately. If the
block condition of the ventilation hole on rotor is damaged, do ventilation test of the gas ventilation
cooling system of rotor, and compare the result with the records made by manufacturer.
2.2 Before inserting the rotor, do gas tightness test (according to IBF R28262) for the central shaft
connection and connection bar copper, ventilation test of the gas ventilation on rotor according to
standard B5680-2004 supplied by manufacturer, insulation resistance test and AC voltage withstand
test.
2.3 After rotor being inserted into stator, AC impedance test should be measured to judge if there
exists interturn short circuit. If doubt, it also can be judge by short-circuit test with the detector
assembled on the generator. And the priority should be given to the later.
3. After finishing the whole generator installation, start the hydrogen, oil and water system, and then
do hydrogen leakage test on the whole generator.
Page: 238