Process Control-Lecture 02
Process Control-Lecture 02
CE 560 / MT 580
Process control
Lecture 02
Process control activities & hierarchy
C. Botha (Mr.)
Contacts: Chemical Engineering Department
Email: [email protected]
Alt. Email: [email protected]
January, 2024
Ensure stability of a process cont’d…
o As an example, consider a
Heat/time P3
Continuous
x Stirred Tank Reactor
Qˊ2 A
(CSTR). B
Qˊˊ2
P2
o Heat released during the reaction
and temperature in the CSTR are
related by sigmoidal function P1
(curve A).
to Time T1 T2 Tˊ2 T3 Temperature
o P1, P2, P3 are the points at which heat generation in the reactor is completely
removed by the coolant.
o Since operating the reactor at any of these three states results in a steady state
reactor temperature. .
o This further increases the reactor temperature and the reaction rate which produces
more heat.
o Hence, increase in feed temperature takes reactor temperature away from steady
state P2.
o This is because the temperature at P1 may be too low resulting in low yields.
o And at P3, the temperature may be too high and unsafe for operation or may
damage the catalyst if present.
o Thus, the control objective for the CSTR would be to ensure stability of the unstable
mid-state P2.
Performance optimization of a process
o Optimum operation conditions for a plant or process are usually determined as part of
process design.
o During operation, such conditions may change frequently due to a number of factors:
Equipment availability,
o These factors can affect the optimum operating conditions thus necessitating
recalculation of such conditions.
Performance optimization of a process
o The new optimum conditions are then implemented as the new set points.
o Consider a continuous stirred batch reactor in which the following consecutive reaction
takes place.
Steam
Condensate
A B A
o The two reactions are assumed to be endothermic and having first-order kinetics.
o Heat required is supplied by steam flowing through the jacket around the reaction
vessel.
o Furthermore, B is the desired product and C is the unwanted waste.
o The economic objective for the batch reactor is to maximize profit ∅ over the time
period 𝒕𝑹 equal to the reaction or processing time.
𝑡𝑅
𝑅𝑒𝑣𝑒𝑛𝑢𝑒 𝑓𝑟𝑜𝑚 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐶𝑜𝑠𝑡 𝑜𝑓 𝑝𝑢𝑟𝑐ℎ𝑎𝑠𝑖𝑛𝑔
∅=න − − 𝑑𝑡 (2.1)
𝑠𝑎𝑙𝑒 𝑜𝑓 𝐵 𝑠𝑡𝑒𝑎𝑚 𝑟𝑒𝑎𝑔𝑒𝑛𝑡 𝐴
0
o The only variable that can be varied freely to maximize profit is the steam flow-rate Q.
Performance optimization of a process cont’d…
o Steam flow-rate can be varied with time and this in turn can affect reaction mixture
temperature.
o The temperature affects the reaction rates for the desired and undesired reactions.
o Therefore, the optimization problem is to determine how best steam flow-rate 𝑄(𝑡)
should vary to maximize profit ∅.
1) Keep steam flow-rate at the highest possible value for the entire duration 𝒕𝑹 of the
process.
For this option, temperature of reacting mixture will assume the highest possible
value.
Performance optimization of a process cont’d…
During the initial stage, concentration of reagent A is high, hence, product B yield
will likewise be high.
But the cost of steam will also be high thus profit will not be maximum.
2) Keep steam flow-rate at its lowest value possible for the entire duration of the reaction.
o Fig. 2.3 illustrates how in general the steam Fig.2.3 Optimal steam flow-rate profile for
profit maximization in a batch reactor
flow-rate may vary to maximize profit from the
batch process.
Performance optimization of a process cont’d…
o The exact profile which steam flow must follow requires solution of the optimization
problem described.
o Solution can be in terms of the best temperature profile which reaction mixture
temperature must follow.
o The control strategy will compute the best steam flow rate at every point during the
reaction time.
o It will then adjust the control valve in the steam line so that the steam flow
corresponds the best value as determined.
o Above discussion indicates that steam flow-rate is used to optimize the economic
performance.
Safety
o Safe operation of all industrial processes is required for the well-being of workers
on the plant, surrounding communities and for continued economic contribution.
For plant operation, one of the most important goals is to ensure that plant
activities (operations) have less risks associated with them.
A control system is required to achieve such an objective with its set point in
this case based on the limit.
Safety cont’d…
I.e., set point is close to the limit if the variability in the controlled variable is low and
well below the limit if variability is high.
o This ensures that the temperature is within the prescribed operating range.
o Exceeding the recommended temperature range may result in unsafe operation or other
undesirable effects i.e., matte-slag phases may fail to separate properly.
o Also as a safe practice, reaction mixtures must never be allowed to form explosive
mixtures.
Product specification
o Industrial plants are designed to produce a desired amount and quality of the
products.
Control mechanisms are required to ensure that the required tonnage and grade
of the concentrate are achieved.
o Also, a plant may be required to produce 2 million tonnes ethylene per day with
about 99% purity.
To ensure that such a production level (2 million TPD) and purity are sustained,
a control system is required.
Environmental regulations
o Various government and environmental protection agencies (i.e., ZEMA) may specify
that the temperature, concentration of chemicals and flow-rates of effluents from
industrial processes be within certain limits.
E.g., there are regulations in place on the amount of SO2 emissions from a plant.
Similarly, the quality of water discharged into natural water bodies is also
regulated.
Such as regulations on the maximum permissible temperature for discharged into
aquatic environments.
To ensure that such regulations are adhered to, some form of control may be
used.
o Also, concentrations of toxic chemical species in effluents must also be within
allowable limits.
Operational/Equipment constraints
o Different types of equipment used for various purposes on the plant have
constraints inherent to their operations.
o For instance, pumps must maintain a certain net positive suction head (NPSH).
o This can lead to loss of valuable chemicals and may cause slippery surfaces that
maybe dangerous for plant personnel.
o Likewise, a reactor may have a designed upper temperature and must be operated near
that temperature.
o Excessive temperatures above the design temperature may cause catalyst degradation
and undesired side reactions.
Operational/Equipment constraints cont’d…
o Furthermore, product size from milling circuits should be maintained within a required
size range.
o I.e., ore particle size must be within a certain desired size range for effective leaching
and floatation to take place.
o Also, mill circulating load in gridding/milling circuits must be maintained within a certain
flow-rate to avoid overloading of the mills, pumps and hydrocyclones.
o This may lead to energy over-consumption, premature wear of the mills and damage to
pumps.
Economics
o Plant operation must satisfy the market conditions, that is, availability of the raw
materials and demand for the final products.
o The plant must also be as economical as possible in its utilization of raw materials,
energy, capital and human labour.
o Higher levels contain desirable but optional activities, typically required for efficient
operation.
o Measurement and actuation activities are indispensable and as such are always
required.
o Layers contain equipment groups and/or human actions designed to ensure safety.
o They are typically organised in the order of activation when there is a plant incident.
o The innermost layer contains the process design providing the first level of
protection.
o Two layers containing basis process control systems (BPCS) may follow.
o The BPCS i.e., emergency switch button or kill switch are coupled with alarms or
critical alarms and operator supervision.
o Safety instrumented systems (SIS) and/or emergency shutdown (ESD) systems are
in the next layer.
Hierarchy of process control activities cont’d…
o SIS formerly known as safety interlock system automatically takes corrective action
when BPCS layers fail to handle an emergency.
o The outer layers contains physical protection systems i.e., pressure relief devices,
o Includes control functions designed to keep key process variables at or near their set
points.
o Multiloop: contains many loops and manipulated variable in each loop is adjusted
based on single controlled variable in that loop.
That is, model depicting how the manipulated variables affect controlled variables.
Upper limit is based on pump and valve characteristics while lower limit may be
determined by safety considerations.
o Thus, operating a process close to the limit becomes an important control objective.
o Though set point cannot be the actual limit itself since a disturbance can easily force
the controlled variable beyond the limit.
Hierarchy of process control activities cont’d…
I.e., if controlled variable varies significantly, set point should be well below the
limit.
And if variability is less then set point can be set close to the constraint limit.
o That is, for control involving significant interactions and inequality constraints.
o Level 3b activities may be considered once lower level activities are achieved.
Hierarchy of process control activities cont’d…
o Involves determining new optimum operating conditions in real time i.e., as operation
is on going.
o Since optimum conditions can change from design optimum conditions due to some
factors as pointed out.
o RTO calculations are based on steady state models of the plant and economic data
such as costs for products and raw materials.
o Data analysis can also be performed during RTO to ensure process model is
accurate for the current conditions.
o Data reconciliation can then be used i.e., real-time data is reconciled with model data.
o This improves model accuracy so that steady state mass and energy balances are
satisfied.
o RTO is not always required in most industrial processes but can be profitable.
o Planning and scheduling activities for entire plant occupy the highest level.
o I.e., such control activities are typically performed after all the other activities.
Hierarchy of process control activities cont’d…
o Production rates for products and intermediates are planned and coordinated for
continuous process.
o Typically based on, equipment constraints, storage capacity, sales projections and
operation of other plants.
o For batch and semibatch, production control becomes batch scheduling problem.
o Level 1, 2 and 3a activities are always required while level 3b – 5 are optional but
can be beneficial.
Hierarchy of process control activities cont’d…
o It also depend on company priorities for limited resources i.e., human and financial
resources.
o Transfer of information from one level to the next is required as part of coordination.