Approach Ramp - Bridge-3
Approach Ramp - Bridge-3
Subject: Estimation
Detailed estimate
of MajorofBridge
Approaches road for Major Bridge Bridge - 3
Item
Description Unit No L B D Quantity Rate Amount
No.
1 Construction of embankment with
approved material obtained from
approved borrow areas complete with
all leads and lifts as per Technical
Specification Clause 305.
Approach ramp Cu.m. 1 Volume = 12639.7 12640
Straight Portion Cu.m. 1 Volume = 627.0 627
Total Quantity = 13267 200 2653333
2 Construction of Sub grade & earthen /
un paved shoulders satisfying the
requirements of minimum 10% CBR
value as indicated in the drawings and
specification with approved material
with all leads & lifts all complete as per
Technical Specification Clause No 305.
Subgrade layer
Approach ramp Cum 1 307.06 Area = 6.96 2137
Straight Portion Cum 2 50.00 Area = 6.96 696
Between pavement layers
Approach ramp Cum 2 307.06 Area = 0.8 491
Straight Portion Cum 4 50.00 Area = 0.8 160
Total Quantity = 3484 250 871007
3 Providing and laying coarse graded
granular sub-base (GSB) Grading-I
complete as per MoRT&H Technical
Specification Clause 401.
Approach ramp Cum 1 307.06 Area = 2.085 640
Straight Portion Cum 2 50.00 Area = 2.085 209
Total Quantity = 849 1400 1188208
4 Providing and laying wet mix macadam
(WMM) base complete as per MoRT&H
Technical Specification Clause 406.
Subject: Estimation
Detailed estimate
of MajorofBridge
Approaches road for Major Bridge Bridge - 3
Item
Description Unit No L B D Quantity Rate Amount
No.
Approach ramp Cum 1 307.06 7.50 0.04 92
Straight Portion Cum 2 50.00 7.50 0.04 30
Total Quantity = 122 6800 830402
7 Providing Grouted Revetment with
rough stone (HBG) of not less than 300
mm size grouted with 0.20 cum of CC
(1:4:8) including cost, seigniorage
charges and conveyance of materials to
site and including labour charges for
packing the stones for revetment etc.,
complete for finished item of work as
per MoRT&H specification 2504 ( 4th
revision ) for Embankment Revetment
& Toe walls (600x600mm)
a) For Embankment Revetment Cum 2 307.06 Area = 1.955 1201
b) For Toe walls along Embankment Cum 2 307.06 0.6 0.6 221
Total Quantity = 1422 1060 1506989
8 Providing and laying filter material with
Gravel underneath pitching in slopes
including cost, seigniorage charges and
conveyance of materials to site including
labour charges etc., complete for
finished item of work as per MoRT&H
Specification 2504 (4th Revision) for
Cum 2 307.06 Area = 0.9775 600
Embankment.
Total Quantity = 600 1390 834420
9 Construction of Earthen drain as per
drawing and Technical specifications
Cum 2 357.06 Area = 1.125 803
Total Quantity = 803 150 120508
10 Provision of Highmast Lightening as per
drawing and technical specifications
Cum 9 9
Total Quantity = 9 50000 450000