Urban Drainage Design
Urban Drainage Design
Urban Drainage Design
FHWA-HIF-24-006
February 2024
i
Page Intentionally Left Blank
ii
HEC-22, 4th edition Table of Contents
Table of Contents
Technical Report Documentation Page ......................................................................................... i
Table of Contents......................................................................................................................... iii
List of Figures .............................................................................................................................. xi
List of Tables............................................................................................................................... xv
Acknowledgments ......................................................................................................................xvii
Notice ........................................................................................................................................ xviii
Non-Binding Contents ............................................................................................................... xviii
Quality Assurance Statement ................................................................................................... xviii
Glossary ..................................................................................................................................... xix
Abbreviations ............................................................................................................................ xxv
Symbols ................................................................................................................................... xxvii
Chapter 1 - Introduction ................................................................................................................ 1
1.1 Purpose and Scope ..................................................................................................... 1
1.2 Organization ................................................................................................................ 2
1.3 Target Audience .......................................................................................................... 3
1.4 Units in this Manual ..................................................................................................... 3
Chapter 2 - Federal Policy for Urban Storm Drainage .................................................................. 5
2.1 Federal Highways and Urban Drainage: National Overview ....................................... 5
2.2 FHWA Statutes and Regulations................................................................................. 5
2.2.1 FHWA Statutes ................................................................................................ 6
2.2.2 FHWA Regulations .......................................................................................... 8
2.3 Other Federal Agency Statutes and Regulations ...................................................... 10
2.3.1 Rivers and Harbors Act of 1899 [33 U.S.C. § 401 and § 403] ....................... 10
2.3.2 General Bridge Act of 1946 [33 U.S.C. §§ 525-533] ..................................... 10
2.3.3 Transportation Act of 1966 [Public Law 89-670] ............................................ 10
2.3.4 National Environmental Policy Act [42 U.S.C. § 4321 et seq.] ...................... 10
2.3.5 Clean Water Act [33 U.S.C. §§ 1251-1387] ................................................... 11
2.3.6 Endangered Species Act [16 U.S.C. §§ 1531-1544] ..................................... 11
2.3.7 National Historic Preservation Act [54 U.S.C. § 300101 et seq.] ................... 11
2.3.8 National Flood Insurance Act of 1968 [42 U.S.C. § 4001 et seq.] ................. 12
2.3.9 Wild and Scenic Rivers Act [16 U.S.C. § 1271 et seq.]. ................................ 12
2.3.10 Fish and Wildlife Coordination Act [16 U.S.C. §§ 661-666c] ......................... 12
iii
Table of Contents HEC-22, 4th edition
2.3.11 Migratory Bird Treaty Act [16 U.S.C. § 703 et seq.]. ..................................... 13
Chapter 3 - System Planning ...................................................................................................... 15
3.1 Design Objectives ..................................................................................................... 15
3.2 Minor versus Major Systems ..................................................................................... 15
3.3 Design Approach ....................................................................................................... 16
3.3.1 Data Collection .............................................................................................. 16
3.3.2 Agency Coordination ..................................................................................... 17
3.3.3 Concept Plan Development ........................................................................... 18
3.3.4 Hydrologic and Hydraulic (H&H) Design ....................................................... 18
3.3.5 Final Design................................................................................................... 18
3.4 Stormwater Drainage System Components .............................................................. 19
3.4.1 Collection ....................................................................................................... 19
3.4.2 Conveyance................................................................................................... 19
3.4.3 Discharge Controls ........................................................................................ 20
Chapter 4 - Urban Hydrologic Procedures .................................................................................. 21
4.1 Rainfall (Precipitation) ............................................................................................... 21
4.1.1 Uniform Rainfall Intensity ............................................................................... 21
4.1.2 Variable Rainfall Intensity (Hyetograph) ........................................................ 21
4.1.3 Synthetic Design Storm Events ..................................................................... 23
4.2 Peak Flow.................................................................................................................. 23
4.2.1 Statistical Analysis ......................................................................................... 23
4.2.2 Rational Method ............................................................................................ 23
4.2.2.1 Runoff Coefficient .............................................................................. 25
4.2.2.2 Rainfall Intensity ................................................................................ 27
4.2.2.3 Time of Concentration ....................................................................... 27
4.2.3 USGS Regression Equations ........................................................................ 31
4.2.3.1 Rural Equations ................................................................................. 31
4.2.3.2 Urban Equations ................................................................................ 32
4.3 Design Hydrographs.................................................................................................. 32
4.3.1 Unit Hydrograph Methods .............................................................................. 32
4.3.1.1 NRCS Dimensionless Unit Hydrograph ............................................. 33
4.3.1.2 Snyder Unit Hydrograph .................................................................... 35
4.3.2 USGS Nationwide Urban Hydrograph ........................................................... 36
4.3.3 Continuous Simulation ................................................................................... 36
iv
HEC-22, 4th edition Table of Contents
v
Table of Contents HEC-22, 4th edition
vi
HEC-22, 4th edition Table of Contents
vii
Table of Contents HEC-22, 4th edition
viii
HEC-22, 4th edition Table of Contents
ix
Table of Contents HEC-22, 4th edition
x
HEC-22, 4th edition List of Figures
List of Figures
Figure 3.1. Drainage design process overview. .......................................................................... 16
Figure 4.1. Example IDF curves. ................................................................................................ 22
Figure 4.2. Example mass rainfall curve and corresponding hyetograph. .................................. 22
Figure 4.3. Log-Pearson type III distribution analysis, Medina River, Texas. ............................. 24
Figure 4.4. Dimensionless curvilinear NRCS unit hydrograph and equivalent triangular
hydrograph. .............................................................................................................. 33
Figure 4.5. Snyder synthetic hydrograph definition. .................................................................... 35
Figure 5.1 Transition from normal crown to superelevated curve to the left. .............................. 44
Figure 5.2. Typical stormwater conveyance sections. ................................................................ 46
Figure 5.3. Relative effects of spread, cross slope, and longitudinal slope on gutter
capacity. ................................................................................................................... 57
Figure 6.1. Total energy in open channels. ................................................................................. 60
Figure 6.2. Specific energy diagram. .......................................................................................... 61
Figure 6.3. Channel geometries. ................................................................................................. 66
Figure 6.4. Shear stress distribution in channel bends. Source: HEC-15. .................................. 71
Figure 6.5. Flexible channel lining design process. Source: HEC-15. ........................................ 74
Figure 7.1. Storm drain inlet types. ............................................................................................. 82
Figure 7.2. P-1-7/8-4 grate (P-1-7/8 is this grate without transverse rods). ................................ 84
Figure 7.3. P-1-1/8 grate. ............................................................................................................ 85
Figure 7.4. Curved vane grate. ................................................................................................... 86
Figure 7.5. Tilt-bar grate: 45°- 60 (2.25 inch) and 45°- 85 (3.25 inch). ....................................... 87
Figure 7.6. Tilt-bar grate: 30°- 85 (3.25 inch). ............................................................................. 88
Figure 7.7. Reticuline grate. ........................................................................................................ 89
Figure 7.8. Splash-over velocity for grate inlets. ......................................................................... 93
Figure 7.9. Depressed curb-opening inlet. .................................................................................. 97
Figure 7.10. Slotted drain inlet at an intersection. ..................................................................... 100
Figure 7.11. Combination curb-opening with 45-degree tilt-bar grate inlet. .............................. 101
Figure 7.12. Sweeper combination inlet. ................................................................................... 101
Figure 7.13. Comparison of inlet interception capacity on grade. ............................................. 104
Figure 7.14. Comparison of inlet interception capacity, flow rate variable. ............................... 105
Figure 7.15. Profile and plan view grate definition sketch. ........................................................ 106
Figure 7.16. Curb-opening inlet definition sketch. ..................................................................... 109
Figure 7.17. Curb-opening inlet throat configurations. .............................................................. 111
xi
List of Figures HEC-22, 4th edition
xii
HEC-22, 4th edition List of Figures
xiii
List of Figures HEC-22, 4th edition
xiv
HEC-22, 4th edition List of Tables
List of Tables
Table 4.1. Runoff coefficients for the Rational Method (ASCE 1960). ........................................ 26
Table 4.2. Manning’s roughness coefficient (n) for overland sheet flow (FHWA 2002). ............. 28
Table 4.3. Intercept coefficients for velocity vs. slope relationship (FHWA 2002). ..................... 28
Table 4.4. Typical range of Manning’s coefficient (n) for channels and pipes. ........................... 29
Table 5.1. Example minimum design frequency and spread. ..................................................... 38
Table 5.2. Typical pavement cross slopes. ................................................................................. 41
Table 5.3. Manning’s n for street and pavement gutters (FHWA 1977). ..................................... 47
Table 6.1. Typical channel lining Manning’s roughness coefficients (FHWA 2005).................... 65
Table 6.2. Possible adverse channel outlet impacts and potential mitigation. ............................ 79
Table 7.1. Inlet grate types and specifications. ........................................................................... 83
Table 7.2. Average debris handling efficiencies of grates. ......................................................... 90
Table 7.3. Inlet ranking for bicycle and pedestrian safety. .......................................................... 90
Table 7.4. Interception and efficiency results for example. ......................................................... 95
Table 7.5. Grate opening ratios. ............................................................................................... 107
Table 8.1. Example access hole spacing criteria (AASHTO 2000). .......................................... 132
Table 9.1 Manning’s roughness coefficients for storm drain conduits. ..................................... 140
Table 9.2. Increase in capacity of alternate shapes based on a circular pipe with the same
height. .................................................................................................................... 141
Table 9.3. Typical values for Ke for gradual enlargement of pipes in open channel flow. ......... 146
Table 9.4. Head loss coefficients. ............................................................................................. 148
Table 9.5. Values for the coefficient, CB.................................................................................... 154
Table 9.6. Case conditions and downstream EGL estimates. .................................................. 164
Table 9.7. Flow conditions at the upstream end of a conduit. ................................................... 164
Table 9.8. Intensity-duration data for example. ......................................................................... 166
Table 9.9. Drainage area information for example. ................................................................... 166
Table 10.1. Coefficients for the NRCS detention volume method. ........................................... 188
Table 10.2. Stage-storage relationship. .................................................................................... 194
Table 10.3. Storm drain pipe stage-storage relationship. ......................................................... 197
Table 10.4. Derivation of stage-storage relationship for example irregular basin. .................... 200
Table 10.5. Computation of stage-active storage relationship for example basin..................... 201
Table 10.6. Stage-discharge orifice flow example. ................................................................... 207
Table 10.7. Broad-crested weir coefficient values (adapted from Brater and King 1976). ........ 211
Table 10.8. Stage-discharge relationship. ................................................................................ 214
xv
List of Tables HEC-22, 4th edition
xvi
HEC-22, 4th edition Acknowledgments
Acknowledgments
The cover image is a collage of photos starting from the top left and proceeding clockwise:
detention pond, combination inlets, storm drain outlet, and urban water quality inlet. Source:
Roger Kilgore.
Unless noted otherwise, the authors developed all photographs and graphics, and give
permission for their use in this document. The authors have designated images used from the
public domain by their source.
xvii
Quality Assurance Statement HEC-22, 4th edition
Notice
This document is disseminated under the sponsorship of the U.S. Department of Transportation
(USDOT) in the interest of information exchange. The U.S. Government assumes no liability for
the use of the information contained in this document. This manual does not constitute a standard,
specification, or policy.
The U.S. Government does not endorse products or manufacturers. Trademarks or
manufacturers’ names appear in this report only because they are considered essential to the
objective of the document. They are included for informational purposes only and are not intended
to reflect a preference, approval, or endorsement of any one product or entity.
Non-Binding Contents
The contents of this document do not have the force and effect of law and are not meant to bind
the public in any way. This document is intended only to provide clarity to the public regarding
existing requirements under the law or agency policies.
xviii
HEC-22, 4th edition Glossary
Glossary
Access Hole: A hole through which one can access an underground element
for repairs or inspections.
Bench: The elevated bottom of an access hole to help streamline flow
through the structure.
Bypass Flow: Flow which bypasses an inlet on grade and is carried in the
street or channel to the next inlet downgrade.
Check Storm: A lesser frequency event used to assess hazards at critical
locations.
Check Valve: Watertight valve used to prevent back flow.
Combination Inlet: Use of both a curb opening inlet and a grate inlet.
Convolution: The multiplication-translation-addition process used to route a
rainfall-excess hyetograph using the unit hydrograph as the
routing model.
Cover: Distance from the outside top of a culvert or storm drain to the
final grade of the ground surface.
Critical Depth: In hydraulic analysis, the depth when flow has a Froude
number of 1.0. The depth associated with the minimum total
energy to pass a given flow through a given cross section.
Critical Flow: The open-channel flow condition where the specific energy of
flow is at a minimum and the Froude number for the flow is
one.
Cross Slope: The rate of change of roadway elevation with respect to
distance perpendicular to the direction of travel. Also known
as transverse slope.
Crown: The inside top elevation of a conduit. Also called the soffit or
obvert.
Curb-opening Inlet: A discontinuity in the curb structure which is covered by a top
slab.
Detention Time: The time required for a drop water to pass through a detention
facility when the facility is filled to design capacity.
Direct Runoff: The total runoff hydrograph minus base flow.
Drainage Inlet: Receptor for surface water collected in ditches and gutters,
which serves as the mechanism whereby surface water enters
storm drains; refers to all types of inlets such as grate inlets,
curb inlets, slotted inlets, etc.
Emergency Spillway: Structure designed to allow controlled release of storm flows
more than the design discharge from a detention facility.
xix
Glossary HEC-22, 4th edition
Energy Grade Line (EGL): The energy state at a channel or conduit section would be the
sum of the pressure, velocity, and elevation heads. The
energy grade line describes a conceptual link of the energy
states between two (or more) channel or conduit locations.
The differences in total energy between these two locations
would be associated with energy losses. The slope of the
energy grade line is often referred to as the friction slope.
Equivalent Cross Slope: An imaginary straight cross slope having a conveyance
capacity equal that of the given compound cross slope.
Extended Detention Dry Pond: Depressed basin that temporarily stores a portion of the
stormwater runoff following a storm event and releases
stormwater over a longer period than detention ponds.
Flanking Inlet: Inlet placed on either side of a low point inlet. Flanking inlets
limit the spread of water onto the roadway if the low point inlet
becomes clogged or is exceeded in its capacity.
Flap Gate: A gate that restricts water from flowing back into the discharge
pipe and discourages entry into the outfall line.
Flow Line: The bottom elevation of an open channel or closed conduit.
Freeboard: The vertical distance from the water surface at the design
discharge to a pre-determined component of the roadway or
channel.
Grate Inlet: Parallel and/or transverse bars arranged to form an inlet
structure.
Gutter: Portion of the roadway structure used to intercept pavement
runoff and carry it along the roadway shoulder.
Hydraulic Grade Line (HGL): A line coinciding with the level of flowing water in an open
channel. In a closed conduit flowing under pressure, the HGL
is the level to which water would rise in a vertical tube at any
point along the pipe. It is equal to the energy grade line
elevation minus the velocity head.
Hydraulic Jump: Hydraulic phenomenon in open channel flow where
supercritical flow changes to sub-critical flow. This results in
an abrupt rise in the water surface elevation.
Hydraulic Radius: The cross-sectional flow area of a channel or conduit divided
by its wetted perimeter.
Hydrograph: A plot of flow versus time.
Hydroplaning: Separation of the vehicle tire from the roadway surface due to
a film of water on the roadway surface.
Hyetograph: A plot of the rainfall intensity (or depth) versus time.
Infiltration Basin: An excavated area which impounds stormwater flow and
gradually exfiltrates it through the basin floor.
xx
HEC-22, 4th edition Glossary
Infiltration Trench: Shallow excavation that has been backfilled with a coarse
stone media. The trench forms an underground reservoir
which collects runoff and exfiltrates it to the subsoil.
Inundation: Presence of water in excess of water film (sheet flow) including
ponding, overtopping, and concentrated flowing water.
Intensity-duration-frequency: A graphical, tabular, or mathematical relation between the
rainfall intensity, storm duration, and exceedance frequency.
Invert: The inside bottom elevation of a culvert, storm drain, or other
hydraulic structure.
Junction Boxes: Formed control structures used to join sections of storm
drains.
Longitudinal Slope (Grade): The rate of change of elevation with respect to distance in the
direction of travel or flow. The longitudinal grade may
represent the slope of a roadway along the profile grade line,
or along a designated offset, such as a gutter grade.
Major System: This system provides overland relief for stormwater flows
exceeding the capacity of the minor system and is composed
of pathways that are provided, knowingly or unknowingly, for
the runoff to flow to natural or constructed receiving channels
such as streams, creeks, or rivers.
Mass Rainfall Curve: The cumulative precipitation plotted over time.
Minor System: Portion of the storm drainage system that is normally designed
to carry runoff from the more frequent storm events. This
includes curbs, gutters, ditches, inlets, access holes, pipes
and other conduits, open channels, pumps, detention basins,
water quality control facilities, etc.
Open Channel Flow: Flow exposed to atmospheric pressure.
Open Channel: A natural or constructed structure that conveys water with the
top surface in contact with the atmosphere.
Orifice Flow: Flow of water through an opening driven by the water surface
on the upstream end that is above the top of the opening.
Permissible Shear Stress: The stress required to initiate movement of the channel bed or
shear stress lining material.
Pressure Flow: Flow not exposed to atmospheric pressure.
Profile Grade: The trace of a vertical plane intersecting a particular surface
of the road; usually along the longitudinal centerline of the
roadway at the top of finished pavement. Profile grade means
either elevation or gradient of such trace according to the
context.
Routing: The process of transposing an inflow hydrograph through a
structure or channel and determining the outflow hydrograph
from the structure or channel.
xxi
Glossary HEC-22, 4th edition
xxii
HEC-22, 4th edition Glossary
xxiii
Glossary HEC-22, 4th edition
xxiv
HEC-22, 4th edition Abbreviations
Abbreviations
AASHTO American Association of State Highway and Transportation Officials
ACPA American Concrete Pipe Association
AEP Annual Exceedance Probability
AISI American Iron and Steel Institute
AOP Aquatic Organism Passage
BFE Base Flood Elevation
BMP Best Management Practice
CAD Computer Aided Design
CFR Code of Federal Regulations
CU Customary Units (English)
CWA Clean Water Act
DEM Digital Elevation Model
DOT Department of Transportation
EO Executive Order from the Federal Register
FAHP Federal-Aid Highway Program
FDC Flow Duration Curve
FEMA Federal Emergency Management Agency
FHWA Federal Highway Administration
FIRM Flood Insurance Rate Map
FIS Flood Insurance Study
GIS Geographic Information System
H&H Hydrology and Hydraulics
HDG Highway Drainage Guidelines
HDS Hydraulic Design Series
HEC Hydraulic Engineering Circular
HWM High Water Mark
LiDAR Light Detection and Ranging
NASEM National Academies of Sciences, Engineering, and Medicine
NCHRP National Cooperative Highway Research Program
NED National Elevation Database
NEH National Engineering Handbook
NEPA National Environmental Policy Act
NFIP National Flood Insurance Program
xxv
Abbreviations HEC-22, 4th edition
xxvi
HEC-22, 4th edition Symbols
Symbols
a Gutter depression
A Drainage area
A Cross-sectional area of flow
A Minimum distance from back wall to trash rack
Ac Contributing drainage area
Aq Clear opening area of the grate
Ao, Ai Outlet and inlet storm drain cross-sectional areas
Ao Orifice area
Aw Area of flow in depressed gutter section
A’w Area of flow in a specified width of the depressed gutter
b Access hole or junction chamber diameter
b Width of spillway
B Maximum distance between a pump and the back wall
B Bottom width of channel
B Cross-sectional area of flow of basin
Co Orifice coefficient
CW Weir coefficient
CN Curve number
d Trench depth
di Depth at lip of curb opening
do Effective head on the center of the orifice throat
D Pump, orifice, or storm drain diameter
DHW Design high water elevation
Di Inflowing pipe diameter
Do Outlet pipe diameter
E Efficiency of an inlet
Ea Access hole energy level
Ei Energy head for access hole outlet pipe
Eai Initial access hole energy level
Eo Ratio of flow in a depressed gutter section to total gutter flow
E’o Ratio of flow in a portion of a depressed gutter section to total gutter flow
Et Total energy
EGLa Access hole energy grade line elevation
EGLi Energy grade line elevation at upstream end of a pipe run
EGLo Energy grade line elevation at downstream end of a pipe run
ΔE Total energy lost
Fr Froude number
g Gravitational acceleration
Gi Grade of roadway
xxvii
Symbols HEC-22, 4th edition
xxviii
HEC-22, 4th edition Symbols
xxix
Symbols HEC-22, 4th edition
Vc Critical velocity
Vd Channel velocity downstream of outlet
Vo Gutter velocity where splash-over first occurs
Vo Average storm drain outlet velocity
Vl Lateral velocity
Vr Inflow volume of runoff
Vs Storage volume estimate
V1 Velocity upstream of transition
V2 Velocity downstream of transition
W Width of gutter or width of basin at base
w Trench width
y Flow depth
yc Critical depth of flow in conduit
yn Normal depth of flow in conduit
Z Elevation above a given datum
z Horizontal distance for side slope of trapezoidal channel
α Angle
Δ Angle of curvature
Δd Water surface elevation difference in a channel bend
ΔS Change in storage
Δt Time interval
γ Unit weight of water
τ Average shear stress
τb Bend shear stress
τd Maximum shear stress
τp Permissible shear stress
θ Angle between the inflow and outflow pipes
θ Angle of v-notch
xxx
HEC-22, 4th edition Chapter 1 - Introduction
Chapter 1 - Introduction
This Fourth Edition of the Urban Drainage Design Manual provides technical information for
understanding, assessing, and addressing drainage design for transportation infrastructure. This
chapter describes the purpose and scope, organization, target audience, and units used in the
manual.
1
Chapter 1 - Introduction HEC-22, 4th edition
fair, just, and impartial treatment of all individuals, including individuals who belong to traditionally
underserved communities or populations (USDOT 2022).
Resilient and reliable design of storm drainage systems for transportation facilities is also
essential in addressing the significant and growing risk presented by climate change. (USDOT
2021). In the transportation context, this risk is many-faceted, including risks to the safety,
effectiveness, equity, and sustainability of the Nation’s transportation infrastructure and the
communities it serves. The USDOT recognizes that the United States has a “once-in-a-
generation” opportunity to address this risk, which is increasing over time (USDOT 2021; see also
Executive Order 14008 on Tackling the Climate Crisis at Home and Abroad, 86 FR 7619 (2021)).
Addressing the risk of climate change is also closely interlinked with advancing transportation
equity because of the disproportionate impacts of climate change on vulnerable populations,
including older adults, children, low-income communities, and communities of color. The USDOT
intends to lead the way in addressing the climate crisis.
The FHWA believes that this manual will be useful for aligning and integrating these concepts
and principles of sustainability within the context of the design of storm drainage systems
associated with transportation facilities.
1.2 Organization
This manual consists of 12 chapters, a glossary, list of acronyms, reference section, and
appendices. This chapter, Chapter 1, provides discussion of the purpose, background,
organization, and units.
Chapter 2 provides an overview of Federal policy as it relates to urban stormwater drainage
analysis and design. This context guides work in stormwater management through a series of
statutes and regulations.
Chapter 3 describes high-level concepts of system planning and outlines considerations for
successful design. These include data requirements, agency coordination, concept development,
and design.
Chapter 4 outlines hydrologic procedures for estimating rainfall and flow amounts that will drive
the type, size, and configuration of the drainage system. The chapter includes selection of a
design storm which establishes the overall capability of the drainage system to manage runoff.
Chapters 5, 6, and 7 describe detailed methods and information for designing the surface
collection components of a comprehensive stormwater drainage system—roadway pavement
drainage, roadside and median channels, and inlets, respectively. Each of these captures water
from the land surface to preserve safe roadway facilities.
Chapters 8 and 9 address the subsurface system of storm drain structures and conduits,
respectively. These components convey the collected stormwater to an offsite or discharge
location.
Chapter 10 describes the design of detention and retention facilities when needed to manage
stormwater quantity. These facilities can attenuate flood peaks and redistribute flood volumes.
Chapter 11 outlines the selection and design of stormwater quality best management practices
(BMPs). These tools assist designers in improving the water quality of discharges offsite or to
receiving waters to mitigate potential negative water quality impacts.
Chapter 12 addresses pump stations. Stormwater drainage systems primarily rely on gravity to
convey stormwater away from roadways safely. When this is not an option, stormwater pump
stations provide an alternative.
2
HEC-22, 4th edition Chapter 1 - Introduction
3
Chapter 1 - Introduction HEC-22, 4th edition
4
HEC-22, 4th edition Chapter 2 - Federal Policy for Urban Storm Drainage
5
Chapter 2 - Federal Policy for Urban Storm Drainage HEC-22, 4th edition
6
HEC-22, 4th edition Chapter 2 - Federal Policy for Urban Storm Drainage
• National goals and performance management measures [23 U.S.C. § 150]. Congress
has declared that it is “in the interest” of the United States to focus the Federal-aid highway
program on certain national transportation goals including Infrastructure Condition, or the
objective to “maintain … highway infrastructure in a state of good repair;” and System
Reliability, or the objective to “improve the efficiency of the surface transportation system.”
[23 U.S.C. § 150(b)].
• PROTECT Program [23 U.S.C. § 176]. The Promoting Resilient Operations for
Transformative, Efficient, and Cost-Saving Transportation (PROTECT) program allows
the FHWA to provide grants for resilience improvements through: (i) formula funding
distributed to States; (ii) competitive planning grants; and (iii) competitive resilience
improvement grants. [23 U.S.C. § 176(b)]. Eligible activities under the PROTECT program
include, among others, “resurfacing, restoration, rehabilitation, reconstruction,
replacement, improvement, or realignment of” certain existing surface transportation
facilities and “the incorporation of natural infrastructure.” [23 U.S.C. §§ 176(c)(1) and
176(d)(4)(A)(ii)(II)].
• Bridge Replacement, Rehabilitation, Preservation, Protection, and Construction
Program (or Bridge Formula Program) (Division J, title VIII, Highway Infrastructure
Program heading, paragraph (1)). The Bridge Formula Program provides funding to help
repair approximately 15,000 highway bridges. In addition to providing funds to states to
replace, rehabilitate, preserve, protect, and construct highway bridges, the Bridge Formula
Program has dedicated funding for Tribal transportation facility bridges as well as “off-
system” bridges, which are generally locally-owned facilities not on the federal-aid
highway system.
• Bridge Investment Program (23 U.S.C. § 124). The Bridge Investment Program provides
financial assistance for eligible projects with program goals to improve the safety,
efficiency, and reliability of the movement of people and freight over bridges; improve the
condition of bridges; and provide financial assistance that leverages and encourages non-
Federal contributions from sponsors and stakeholders involved in the planning, design,
and construction of eligible projects.
• National Culvert Removal, Replacement, and Restoration Grants Program (49
U.S.C. §§ 6703)]. The National Culvert Removal, Replacement, and Restoration Grant
program established an annual competitive grant program to award grants to eligible
entities for projects for the replacement, removal, and repair of culverts or weirs that would
meaningfully improve or restore fish passage for anadromous fish.
• Research and technology development and deployment [23 U.S.C. § 503]. In carrying
out certain highway and bridge infrastructure and research and development activities, the
FHWA must “study vulnerabilities of the transportation system to … extreme events and
methods to reduce those vulnerabilities.” [23 U.S.C. § 503(b)(3)(B)(viii)].
• Statutory Definition of “Resilience.” [23 U.S.C. § 101(a)(24)]. Section 11103 of the
Bipartisan Infrastructure Law (BIL), enacted as the Infrastructure Investment and Jobs Act,
Pub. L. 117-58 (Nov. 15, 2021), added a definition of “resilience,” which applies throughout
Title 23 of the U.S. Code. With respect to a project, “resilience” means a project with the
ability to anticipate, prepare for, and or adapt to changing conditions and or withstand,
respond to, and or recover rapidly from disruptions, including the ability: (A) to resist
hazards or withstand impacts from weather events and natural disasters, or reduce the
magnitude or duration of impacts of a disruptive weather event or natural disaster on a
project; and (B) to have the absorptive capacity, adaptive capacity, and recoverability to
decrease project vulnerability to weather events or other natural disasters. 23 U.S.C. §
101(a)(24). See also FHWA Order 5520 (FHWA 2014b).
7
Chapter 2 - Federal Policy for Urban Storm Drainage HEC-22, 4th edition
base (1-percent chance) floodplains. Section 650.111 sets forth requirements for location
hydraulic studies to identify the potential impact of the highway alternatives on the base floodplain;
these studies are commonly used during the National Environmental Policy Act (NEPA) process.
The regulations prohibit significant encroachments on base floodplains unless the FHWA
determines that such encroachment is the only practicable alternative. [23 CFR 650.113(a)]. This
finding must be included in the NEPA documents for a project and supported information including
the reasons for the finding and considered alternatives. [Id.]. The procedures also provide
minimum standards for Interstate Highways, set freeboard requirements to account for debris and
scour, and require highway encroachments to be consistent with certain established design flood
standards for hydraulic structures, including standards from FEMA and State and local
governments related to administration of the National Flood Insurance Program (NFIP). [23 CFR
650.115(a)]. Notably, the policies and procedures in this Subpart apply to encroachments in all
base floodplains, not just the floodplains regulated by the Federal Emergency Management
Agency (FEMA) in the NFIP. [23 CFR 650.107]. Additionally, the Subpart incorporates a
requirement for project-by-project risk assessments or analyses. [23 CFR 650.115(a)(1)]. Notable
sections include:
• Section 650.103 [Policy]. This section states that “it is the policy of the FHWA: (a) To
encourage a broad and unified effort to prevent uneconomic, hazardous or incompatible
use and development of the Nation’s flood plains, (b) To avoid longitudinal
encroachments, where practicable, (c) To avoid significant encroachments, where
practicable, (d) To minimize impacts of highway agency actions which adversely affect
base flood plains, (e) To restore and preserve the natural and beneficial flood-plain values
that are adversely impacted by highway agency actions, (f) To avoid support of
incompatible flood-plain development, (g) To be consistent with the intent of the Standards
and Criteria of the National Flood Insurance Program, where appropriate, and (h) To
incorporate “A Unified National Program for Floodplain Management” of the Water
Resources Council into FHWA procedures.” [23 CFR 650.103].
• Section 650.115 [Hydraulic Design Standards]. This regulation applies to all Federal-
aid projects, whether on the NHS or Non-NHS. Federal, State, local, and AASHTO
standards may not change or override the design standards set forth under § 650.115 —
although certain State and local standards must also be satisfied under the same section.
The section also requires development of a “Design Study” for each highway project
involving an encroachment on a floodplain. [23 CFR 650.115(a)].
• Section 650.117 [Content of Design Studies]. This regulation requires studies to contain
the “hydrologic and hydraulic data and design computations.” [23 CFR 650.117(b)]. As
both hydrologic and hydraulic factors and characteristics lead to scour formation, data and
computations applicable to scour should be provided as well. Project plans must show the
water surface elevations of the overtopping flood and base flood (i.e., 100-year flood) if
larger than the overtopping flood. [23 CFR 650.117(c)].
Executive Order 14030, Climate-Related Financial Risk, and Executive Order 13690,
Establishing a Federal Flood Risk Management Standard and a Process for Further
Soliciting and Considering Stakeholder Input (80 FR 6425). Project applicants should be
aware that DOT and FHWA, as of 2022, are in the process of developing guidance and
considering updates to floodplain requirements, including redefining the appropriate flood hazard
area to account for future climate conditions.
National Bridge Inspection Standards [23 CFR 650 Subpart C]. This regulation implements
requirements of 23 U.S.C. § 144. In addition to the inspection and inventory requirements, the
regulation specifically focuses on scour at bridges.
9
Chapter 2 - Federal Policy for Urban Storm Drainage HEC-22, 4th edition
Mitigation of Impacts to Wetlands and Natural Habitat [23 CFR Part 777]. This regulation
provides policy and procedures for the evaluation and mitigation of adverse environmental
impacts to wetlands and natural habitat resulting from Federal-aid funded projects.
2.3.1 Rivers and Harbors Act of 1899 [33 U.S.C. § 401 and § 403]
River and coastal highway engineering projects are subject to Section 9 [33 U.S.C. § 401] and
Section 10 [33 U.S.C. § 403] of the Rivers and Harbors Act of 1899. Section 9 of this Act restricts
the construction of any bridge, dam, dike, or causeway over or in U.S. navigable waterways.
Except for bridges and causeways under Section 9 [33 U.S.C. § 401], the U.S. Army Corps of
Engineers (USACE) is responsible for maintaining the standards set by and for issuing permits
under the Rivers and Harbors Act. Authority to administer Section 9, applying to bridges and
causeways, was redelegated to the U.S. Coast Guard under the provisions of the Department of
Transportation Act of 1966 (as discussed below).
environmental impact of” and “alternatives to” the proposed action.” [Id.] FHWA implements NEPA
according to the Council on Environmental Quality (CEQ) NEPA regulations at 40 CFR Part 1500
et seq. and the FHWA-FRA-FTA joint regulations at 23 CFR Part 771.
11
Chapter 2 - Federal Policy for Urban Storm Drainage HEC-22, 4th edition
Register of Historic Places [36 CFR 800.16(l)(1); see also 54 U.S.C. 300311 and 302102]. The
responsibilities of SHPOs are set forth at 54 U.S.C. § 302303.
In addition to Section 106, Section 4(f) of the U.S. Department of Transportation Act of 1966 [23
U.S.C. § 138 and 49 U.S.C. § 303] requires that the FHWA not approve the use of historic sites
for a project unless there is no prudent and feasible alternative and the project incorporates all
possible planning to minimize harm, or any impacts to historic sites are determined to be de
minimis. The FHWA’s regulations for implementation of Section 4(f) are found at 23 CFR Part
774.
2.3.8 National Flood Insurance Act of 1968 [42 U.S.C. § 4001 et seq.]
The National Flood Insurance Act of 1968 instituted the National Flood Insurance Program (NFIP)
to help indemnify and reduce impacts associated with floods. The NFIP adopted the area subject
to a 1 percent chance or greater of being flooded in any given year (also known as the 100-year
flood) as the standard, or base flood, for mapping floodplains. [See, e.g., 44 CFR 9.4]. The area
inundated by the 100-year flood determines the Special Flood Hazard Area (SFHA) on Flood
Insurance Rate Maps (FIRMs) developed by FEMA and used to determine flood insurance rates
for structures. [See, e.g., 44 CFR 59.1, which defines “area of special flood hazard”]. FEMA
implements the NFIP using its regulations found in Title 44 of the CFR.
The FHWA’s policies require projects to be consistent with the Standards and Criteria in the NFIP,
where appropriate. [23 CFR 650.115(a)(5)]. To assist State DOTs in complying with this policy,
the FHWA developed coordination procedures for Federal-aid highway projects with
encroachments in NFIP-regulated floodplains. FEMA agreed to these procedures by signing a
1982 Memorandum of Understanding with the FHWA.
2.3.9 Wild and Scenic Rivers Act [16 U.S.C. § 1271 et seq.].
This Act establishes a policy to preserve designated rivers “in free-flowing condition” and to
protect “their immediate environments … for the benefit and enjoyment of present and future
generations.” [16 U.S.C. § 1271]. Section 7(a) provides that “no department or agency of the
United States shall assist by loan, grant, license, or otherwise in the construction of any water
resources project that would have a direct and adverse effect on the values for which such river
was established.” [16 U.S.C. § 1278(a)]. A water resources project is “any dam, water conduit,
reservoir, powerhouse, transmission line, or other project works under the Federal Power Act ...
or other construction of developments which would affect the free-flowing characteristics of a Wild
and Scenic River or Study River.” [36 CFR 297.3]. “Federal assistance means any assistance by
an authorizing agency including, but not limited to, ... [a] license, permit, or other authorization
granted by the Corps of Engineers, Department of the Army, pursuant to the Rivers and Harbors
Act of 1899 and section 404 of the Clean Water Act (33 U.S.C. 1344).” [Id.]
12
HEC-22, 4th edition Chapter 2 - Federal Policy for Urban Storm Drainage
13
Chapter 2 - Federal Policy for Urban Storm Drainage HEC-22, 4th edition
14
HEC-22, 4th edition Chapter 3 - System Planning
15
Chapter 3 - System Planning HEC-22, 4th edition
in a general sense) the flow pathways and related depths and velocities of the major system under
less frequent or check storm conditions.
Typically, design effort focuses on components of the minor system. However, when infrastructure
owners and designers also consider the functioning of the major storm drainage system, they can
provide more resilient transportation infrastructure and associated drainage features when storms
exceeding the design magnitude for the minor system inevitably occur. This is especially relevant
today as the FHWA and others seek to ensure the transportation network is resilient and reliable
for all users despite the risk associated with a changing climate. (USDOT 2021).
16
HEC-22, 4th edition Chapter 3 - System Planning
• Soils maps: These identify soil types and hydrologic soil groups. They are available in
county soil surveys available online and from local U.S. Natural Resources Conservation
Service (NRCS) offices.
• Flood histories and high-water marks: These may be available from local offices of the
USGS, National Weather Service (NWS), Federal Emergency Management Agency
(FEMA), U.S. Army Corps of Engineers (USACE), local planning agencies, river
authorities, and drainage districts. Residents or Department of Transportation (DOT)
regional or district maintenance offices may also be able to provide this information.
• Descriptions of existing drainage facilities: These includes size, shape, material, invert
information, age, condition, etc. As-built information for existing drainage facilities may be
available from the local facility owner. If unavailable, the DOT can perform field surveys to
obtain this information.
• Design and performance data for existing drainage systems: These may be available from
the facility owner. If unavailable for the existing system, the designer can develop the
needed information to determine how the existing system will function under the new
loading.
• Utility plans and descriptions: These may be available from the utility owner. If unavailable,
the DOT can perform field surveys to determine critical design information.
• Existing right-of-way information: These may be available from the appropriate highway
agency ROW office or local tax maps.
• Federal, State, and local regulatory requirements: Typical regulatory authorities include
USACE, U.S. Environmental Protection Agency (USEPA), State environmental regulatory
agencies, and local governments. (Chapter 2 describes Federal statutes and regulations.)
17
Chapter 3 - System Planning HEC-22, 4th edition
describes final design documentation requirements, which can vary with project type and scope.
The AASHTO Drainage Manual (AASHTO 2014) provides a general description of design
documentation.
3.4.1 Collection
Collection components, including gutters, ditches, and inlets, concentrate water on the roadway
or bridge and move it away from the traveled way. Roadside and median ditches intercept runoff
and carry it to a storm drain or channel. Ditch design considers not only hydraulic capacity but
also safety for vehicles that may leave the roadway. If necessary, the design provides channel
linings to control erosion in ditches.
Gutters intercept pavement runoff and carry it along the roadway edge to an adequate storm drain
inlet. Designers install curbs in combination with gutters where runoff from the pavement surface
would erode fill slopes or where ROW requirements or topographic conditions will not permit the
development of roadside ditches. Urban settings typically use curbed pavement sections. Some
other areas use gutters without curbs.
Drainage inlets receive surface water collected in ditches and gutters and serve as the
mechanism for surface water to enter storm drains. Along the edge of the roadway, designers
size and locate storm drain inlets to limit the spread of surface water onto travel lanes. Inlets may
be grated, curbed, slotted, etc.
Roadway geometry and the ability to control the spread of water on the roadway surface
determine the location of drainage inlets. Generally, placing inlets at low points in the gutter grade,
intersections, crosswalks, cross-slope reversals, and on side streets prevents the water from
flowing onto the main road. Additionally, placing inlets up-gradient of bridges prevents drainage
onto bridge decks; placing inlets down-gradient of bridges prevents the flow of water from the
bridge onto the roadway surface. Chapter 7 discusses inlet design.
3.4.2 Conveyance
Upon reaching the main storm drainage system, storm drains connected by access holes or other
structures convey stormwater along and through the ROW to its discharge point. Storm drains
receive runoff from inlets and convey it to some point where it is discharged into a channel,
waterbody, or other piped system. Storm drains can be closed conduit or open channel; they
consist of one or more pipes or conveyance channels connecting two or more inlets.
Access holes, junction boxes, and inlets serve as access structures and alignment control points
in storm drainage systems. Access structure spacing and storm drain deflection are critical design
parameters related to these structures. Maintenance tasks often dictate spacing limits. In addition,
these structures are located at the intersections of two or more storm drains, when there is a
change in the pipe size, and at changes in alignment (horizontal or vertical). Chapter 9 describes
the design of storm drains.
19
Chapter 3 - System Planning HEC-22, 4th edition
Where gravity drainage is impossible or not economically justifiable, designers can use
stormwater pump stations. For example, stormwater pump stations may be the only alternative
for draining depressed roadway sections. Chapter 12 introduces the design of stormwater
pumping stations.
20
HEC-22, 4th edition Chapter 4 - Urban Hydrologic Procedures
21
Chapter 4 - Urban Hydrologic Procedures HEC-22, 4th edition
22
HEC-22, 4th edition Chapter 4 - Urban Hydrologic Procedures
CIA
Q= (4.1)
Ku
where:
Q = Flow, ft3/s (m3/s)
C = Dimensionless runoff coefficient
I = Rainfall intensity, in/h (mm/h)
A = Drainage area, ac (ha)
Ku = Unit conversion constant, 1.0 in CU (360 in SI)
23
Chapter 4 - Urban Hydrologic Procedures HEC-22, 4th edition
Figure 4.3. Log-Pearson type III distribution analysis, Medina River, Texas.
compensate for the reduced effect of infiltration and other hydrologic abstractions during less
frequent, higher intensity storms. The frequency-of-event correction factor is multiplied times the
runoff coefficient, C, to produce an adjusted runoff coefficient.
Because of the inherent assumptions, HDS-2 recommends application of the Rational Method to
drainage areas smaller than 200 ac (80 ha) and provides additional information on the Rational
Method (FHWA 2002).
Cx A x
C=∑ (4.2)
A total
where:
x = Subscript designating values for incremental areas with consistent land cover
25
Chapter 4 - Urban Hydrologic Procedures HEC-22, 4th edition
Table 4.1. Runoff coefficients for the Rational Method (ASCE 1960).
Land Use
Category Type of Drainage Area Runoff Coefficient, C*
Downtown areas 0.70 - 0.95
Business
Neighborhood areas 0.50 - 0.70
Single-family areas 0.30 - 0.50
Multi-units, detached 0.40 - 0.60
Residential Multi-units, attached 0.60 - 0.75
Suburban 0.25 - 0.40
Apartment dwelling areas 0.50 - 0.70
Light areas 0.50 - 0.80
Industrial
Heavy areas 0.60 - 0.90
Parks, cemeteries 0.10 - 0.25
Playgrounds 0.20 - 0.40
Open
Railroad yard areas 0.20 - 0.40
Unimproved areas 0.10 - 0.30
Sandy soil, flat, 2% 0.05 - 0.10
Sandy soil, average, 2 - 7% 0.10 - 0.15
Sandy soil, steep, 7% 0.15 - 0.20
Lawns
Heavy soil, flat, 2% 0.13 - 0.17
Heavy soil, average, 2 - 7% 0.18 - 0.22
Heavy soil, steep, 7% 0.25 - 0.35
Asphaltic 0.70 - 0.95
Streets Concrete 0.80 - 0.95
Brick 0.70 - 0.85
26
HEC-22, 4th edition Chapter 4 - Urban Hydrologic Procedures
0.8
K u nL
t t = 0.5 (4.3)
P2 S
where:
tt = Sheet flow travel time, min
n = Roughness coefficient
L = Flow length, ft (m)
P2 = 2-year, 24-hour rainfall depth, inches (mm)
S = Surface slope, ft/ft (m/m)
Ku = Unit conversion constant, 0.42 in CU (5.5 in SI)
Table 4.2 summarizes Manning’s roughness coefficients. Equation 4.3 is the modified version of
the sheet flow equation. An iterative version of the equation replaces rainfall depth with rainfall
intensity (FHWA 2002).
Shallow concentrated flow develops as sheet flow concentrates in rills and then gullies of
increasing proportions. Designers can estimate the velocity of such flow using a relationship
between velocity and slope, as described in HDS-2 (FHWA 2002) as follows:
V = K ukSp0.5 (4.4)
where:
V = Velocity, ft/s (m/s)
k = Intercept coefficient
Sp = Slope, percent
Ku = Unit conversion constant, 3.28 in CU (1.0 in SI)
27
Chapter 4 - Urban Hydrologic Procedures HEC-22, 4th edition
Table 4.2. Manning’s roughness coefficient (n) for overland sheet flow (FHWA 2002).
Surface Description n
Smooth asphalt 0.011
Smooth concrete 0.012
Ordinary concrete lining 0.013
Good wood 0.014
Brick with cement mortar 0.014
Vitrified clay 0.015
Cast iron 0.015
Corrugated metal pipe 0.024
Cement rubble surface 0.024
Fallow (no residue) 0.05
Cultivated soils: Residue cover # 20% 0.06
Cultivated soils: Residue cover > 20% 0.17
Cultivated soils: Range (natural) 0.13
Short grass prairie 0.15
Dense grasses 0.24
Bermuda grass 0.41
Woods: Light underbrush * 0.40
Woods: Dense underbrush * 0.80
*When selecting n, consider cover to a height of about 1 inch (30 mm).
This is only part of the plant cover that will obstruct sheet flow.
Table 4.3. Intercept coefficients for velocity vs. slope relationship (FHWA 2002).
28
HEC-22, 4th edition Chapter 4 - Urban Hydrologic Procedures
Open channel and pipe flow occurs when water further collects in gullies, channels, or pipes.
Such channels can be identified when they are shown on maps or are visible on aerial
photographs. Velocity calculations typically use cross-section geometry and roughness for all
channel reaches in the watershed. Designers commonly use Manning’s equation to estimate
average flow velocities in pipes and open channels as follows:
K u 2 3 12
V= R S (4.5)
n
where:
n = Roughness coefficient
V = Velocity, ft/s (m/s)
R = Hydraulic radius (measured as the flow area divided by the wetted perimeter), ft
(m)
S = Slope, ft/ft (m/m)
Ku = Unit conversion constant, 1.49 in CU (1 in SI)
Table 4.4 provides representative values of Manning’s roughness coefficient for channels and
pipes. For a circular pipe flowing full, the hydraulic radius equals one-fourth of the diameter.
Table 4.4. Typical range of Manning’s coefficient (n) for channels and pipes.
L
t= (4.6)
60V
29
Chapter 4 - Urban Hydrologic Procedures HEC-22, 4th edition
where:
t = Travel time for a given segment, min
L = Flow length for the given segment, ft (m)
V = Velocity for the given segment, ft/s (m/s)
30
HEC-22, 4th edition Chapter 4 - Urban Hydrologic Procedures
Step 2. Determine the total travel time by summing the individual travel times.
tc = tt1 + tt2 + tt3 = 47.1 + 3.7 + 1.4 = 52.2 min; use 52 min
Solution: The estimated time of concentration is 52 minutes.
31
Chapter 4 - Urban Hydrologic Procedures HEC-22, 4th edition
RQT = a A b Bc Cd (4.7)
where:
RQT = T-year rural peak flow, ft3/s (m3/s)
a = Regression constant
b, c, d = Regression coefficients
A, B, C = Basin or meteorological characteristics
The USGS, State highway, and other agencies conducted a series of studies to develop rural
equations for all States. These equations do not apply where dams and other hydrologic
modifications have a significant effect on peak flows. HDS-2 presents other limitations (FHWA
2002).
32
HEC-22, 4th edition Chapter 4 - Urban Hydrologic Procedures
1,000 mi2 (FHWA 2002). This section discusses the NRCS dimensionless unit hydrograph and
Snyder unit hydrograph methods.
Figure 4.4. Dimensionless curvilinear NRCS unit hydrograph and equivalent triangular
hydrograph.
33
Chapter 4 - Urban Hydrologic Procedures HEC-22, 4th edition
The area under a hydrograph equals the volume of direct runoff, QD, which is 1 inch (millimeter)
for a unit hydrograph. To calculate the peak flow:
K uK p AQD
qp = (4.8)
tp
where:
qp = Peak flow, ft3/s (m3/s)
A = Drainage area, mi2 (km2)
QD = Volume of direct runoff (= 1 for unit hydrograph), inch (mm)
tp = Time to peak, h
Kp = Peaking constant equal to 484, dimensionless
Ku = Unit conversion constant, 1 in CU (0.0043 in SI)
The peaking constant reflects a unit hydrograph with 3/8 of its area under the rising limb. For
mountainous watersheds, the fraction could be expected to be greater than 3/8, and therefore the
constant may be near 600. For flat, swampy areas, the constant may be on the order of 300.
Time to peak, tp, can be expressed in terms of time of concentration, tc, as follows:
2
tp = tc (4.9)
3
K uK p AQD
qp = (4.10)
tc
where:
Ku = Unit conversion constant, 1.5 in CU (0.00645 in SI)
34
HEC-22, 4th edition Chapter 4 - Urban Hydrologic Procedures
Solution: The key parameters for this application are a peak flow of 251 ft3/s (7.1 m3/s)
and a time to peak of 0.89 hours.
35
Chapter 4 - Urban Hydrologic Procedures HEC-22, 4th edition
Snyder initially applied this unit hydrograph for watersheds in the Appalachian highlands;
however, the general method has been successfully applied throughout the country. HDS-2
provides additional information and an example problem that describes the procedures for
computing the Snyder Synthetic Unit Hydrograph (FHWA 2002).
36
HEC-22, 4th edition Chapter 5 - Roadway Pavement Drainage
5.1 Spread
The width of pavement (outward from the face of curb) covered by water during rainfall is called
“spread.” Spread at any point on the roadway relates to the intensity and duration of rainfall.
Allowable spread represents the maximum width of pavement covered during the design storm.
Designers also evaluate spread associated with a larger (less frequent) storm.
37
Chapter 5 - Roadway Pavement Drainage HEC-22, 4th edition
upgrade the drainage design and reduce risks at moderate costs. In other instances, costs
may be very sensitive to the criteria selected for design.
Designers consider inconvenience, hazards, and nuisances to pedestrian, bicycle, and other
personal transport traffic. In some places, such as in commercial areas, this consideration may
assume major importance. Local design practice may also be a major consideration since it can
affect the feasibility of designing to higher standards, and it influences public perception of
acceptable practice.
Designers also consider the relative elevation of the highway and surrounding terrain where water
can be drained only through a storm drainage system, as in underpasses and depressed roadway
sections. They consider the potential for ponding to undesirable depths when selecting the
frequency and spread criteria and in checking the design against storm runoff events of lesser
frequency than the design event.
Selection of design criteria for intermediate types of facilities may be the most difficult. For
example, some arterials with relatively high traffic volumes and speeds may not have shoulders
which will convey the design runoff without encroaching on the traffic lanes. In these instances,
practitioners typically assess the relative risks and costs of various design spreads to select
appropriate design criteria. Table 5.1 provides example minimum design frequencies and spread
based on the type of highway and traffic speed.
Along with the situations covered in Table 5.1, for depressed sections and underpasses where
ponded water can be removed only through the storm drainage system, designers frequently
consider additional criteria including a 0.02 AEP event. The use of a more severe event, such as
a 0.01 AEP event to assess hazards at critical locations where water can pond to appreciable
depths is commonly referred to as a “check storm.”
Design Frequency
Road Classification Context (AEP) Design Spread
Interstate Varies 0.02 Shoulder
Design speed < 45 mph 0.1 Shoulder + 3 ft
Principal arterial
(divided or bi- Design speed > 45 mph 0.1 Shoulder
directional)
Sag vertical curve 0.02 Shoulder + 3 ft
Design speed < 45 mph 0.1 1/2 Driving Lane
Major or minor
Design speed > 45 mph 0.1 Shoulder
collector
Sag vertical curve 0.1 1/2 Driving Lane
Low ADT 0.2 1/2 Driving Lane
Local streets High ADT 0.1 1/2 Driving Lane
Sag Point 0.1 1/2 Driving Lane
Designers base selection of the frequency for the check storm on the same considerations used
to select the design storm, i.e., the consequences of spread exceeding that chosen for design
and the potential for ponding. Where no significant ponding can occur, check storms are typically
unnecessary. During the service life of a roadway, there is always a risk that a storm more severe
than the design and check storm will occur once or multiple times. When the consequences of
such events are potentially unacceptable, a designer may employ risk-based design concepts
(FHWA 2016). With risk-based design, the designer evaluates the consequences of design flow
exceedance and balances the number of occurrences of the consequences against cost and other
goals of society.
Each State and locality determine standards for the criteria for spread during the check event.
Examples of criteria for a check storm event include: 1) one lane open to traffic, and 2) one lane
free of water. In the first, water may partially of fully cover the lane but at a depth that drivers can
drive through at a reduced speed.
5.2.1 Hydroplaning
When a rolling vehicle tire meets a film of water on the roadway, it has the potential to lose contact
with the roadway, a condition known as hydroplaning. Ideally, the water is channeled through the
tire tread pattern and through the surface roughness of the pavement. Hydroplaning occurs when
the drainage capacity of the tire tread pattern and the pavement surface is insufficient to conduct
the water away, and the water begins to build up in front of the tire. As this wedge of water builds
up in front of the tire, the wedge produces a force that can lift the tire off the pavement surface.
This is considered as full dynamic hydroplaning and, since water offers no shear resistance, the
tire loses its ability to exert stopping or steering force on the vehicle. The driver has then lost
control of the vehicle. Hydroplaning can occur at speeds of 55 mph with a water depth of 0.08
inches (Anderson et al. 1995). However, depending on a variety of criteria, hydroplaning may
occur at lower speeds and depths.
39
Chapter 5 - Roadway Pavement Drainage HEC-22, 4th edition
Hydroplaning is a function of the water depth, roadway geometry, vehicle speed, tread depth, tire
inflation pressure, and pavement texture. The AASHTO Model Drainage Manual (AASHTO 2000)
provides methods of calculating when it can occur. In problem areas, hydroplaning hazard may
be reduced by:
• Designing the highway geometry to reduce the drainage path lengths of flow over the
pavement to prevent flow buildup.
• Increasing the pavement surface texture depth. Grooving of concrete pavement and the
use of asphalt-aggregate surface treatment (chip seal) are examples of surfaces that
inhibit hydroplaning. An increase of pavement surface texture will increase the drainage
capacity at the tire pavement interface.
• Using open graded asphaltic pavements. The open texture prevents the buildup of
hydrostatic pressure and the corresponding lifting force by allowing the water to be forced
out from under the tire.
• Adding drainage structures to capture water from the pavement to reduce the film of water
and reduce the hydroplaning potential.
NASEM (2021) provides an in-depth discussion of hydroplaning and the related variables.
K = L / (G2 - G1 ) (5.1)
where:
K = Vertical curve constant ft/percent (m/percent)
L = Horizontal length of curve, ft (m)
Gi = Grade of roadway, percent
40
HEC-22, 4th edition Chapter 5 - Roadway Pavement Drainage
41
Chapter 5 - Roadway Pavement Drainage HEC-22, 4th edition
42
HEC-22, 4th edition Chapter 5 - Roadway Pavement Drainage
• Water on bridge decks freezes before surface roadways leading to ice-covered bridges.
• Bridge deck drainage gutters may have lower capacity than roadway gutters because
cross slopes may be flatter.
• Parapet-type bridge rails can accumulate roadway debris.
• Scuppers and other deck drains generally have smaller open areas than many roadway
inlets and can be easily clogged by debris.
• Bridges lack auxiliary lanes or additional width beyond the travel lanes.
• Bridges over water may be subject to water quality restrictions limiting direct discharge to
the water body.
• Bridges crossing over land, including other roadways or bridges, may have to convey
water to a safe discharge location.
To address these difficulties in providing for deck drainage systems, designers focus on
intercepting and redirecting gutter flow from the roadway leading to a bridge before it reaches a
bridge whenever possible. For similar reasons, designers avoid zero longitudinal grades and sag
vertical curves on bridges. HEC-21 includes detailed coverage of bridge deck drainage systems
(FHWA 1993).
43
Chapter 5 - Roadway Pavement Drainage HEC-22, 4th edition
Figure 5.1 Transition from normal crown to superelevated curve to the left.
44
HEC-22, 4th edition Chapter 5 - Roadway Pavement Drainage
the pavement in that location. Designers seek to avoid conditions where water is directed across
the roadway from the outer side of the curve to the inner side.
The drainage designer also considers the relative changes in the roadway profile grade and the
gutter profile grade as these do not change at the same rates in a superelevation transition.
Relative to the roadway profile grade, the gutter profile grade may decrease, increase, or even
change direction. Depth of flow available at the curb may decrease and spread may increase
(depending on flow direction).
In superelevation transitions, the roadway design may rotate the roadway cross-section about the
centerline, inner edge, or outer edge. If rotated about the centerline or outer edge, the gutter
profile on the inner side of the curve may be depressed by the increase of cross slope past the
normal crown slope at full superelevation. Combining the increased drainage distance of a
superelevated section and a depressed gutter profile grade line can result in significant increase
in spread, and in depth of runoff on the inner side of curves. If the roadway is rotated about either
edge, the centerline profile grade line will show a “hump” or “dip” to reflect the transition and curve
that may affect drainage.
Because of the many possible situations for superelevation transitions and the importance of good
drainage for safe roadways, drainage and roadway geometry designers coordinate to minimize
problem areas created by superelevated curves and transitions. They consider the profile grade
line, both gutter grades, and the rotation of the roadway (centerline, inner edge, or outer edge) in
the superelevation transition to avoid flatter areas where water builds up and drains slowly from
the roadway and to avoid areas where water is directed from one side of the road to the other.
5.2.5.4 Roundabouts
Designers increasingly use circular “roundabout” intersections as a traffic management
technique. Roundabouts can present unique drainage situations. The profile grade lines of the
roadways converging or crossing at a roundabout are adjusted to intersect at a common elevation
at the center of the roundabout. Traffic turns to the right to enter the roundabout, curves to the left
while traveling in the roundabout, turns to the right to exit the roundabout. Traffic proceeds through
roundabouts at speeds lower than the approaching roadway sections. The lower speed facilitates
the “reversing” motion of entering, transiting, and leaving the roundabout.
Typically, the central island of a roundabout is elevated, and roadways approaching a roundabout
have a center crown with cross slopes of 0.02. The cross slope on the roundabout circle is an
adverse superelevation (sloping from the outside of the curve rather than the inside) throughout
(NASEM 2007, NASEM 2010). Researchers recommend that the central island be elevated in all
classifications of roundabouts (mini, single-lane, and multi-lane). If the central island is not
elevated, cross slope toward the central island will create ponding near the island, and drainage
structures will be needed to alleviate the ponding (NASEM 2010). Multi-lane roundabouts, like
other multi-lane features, exhibit wider pavement sections, and longer accumulation distances for
runoff, than do single-lane features.
The adverse cross slope within the roundabout directs water toward the outside of the
roundabout. Because the outer edge of the roadway within the roundabout has a larger
circumference than the inner edge, as water flows toward the outer edge of the roundabout the
increase of depth resulting from increasing pavement area is mitigated by the larger
circumference.
Among the intended purposes of roundabouts is to limit traffic speed; because of this, they are
inherently low-speed features. The tendency to limit speed also serves to mitigate hydroplaning,
even in cases where water ponds on the pavement in depths greater than would be desirable on
other roadway features.
45
Chapter 5 - Roadway Pavement Drainage HEC-22, 4th edition
Gutter design at the outer edge of the roundabout determines the spread conditions. The gutters
either direct water to inlets within the roundabout or to gutters on roadways connected to the
roundabout. Because roundabouts direct water to the periphery and slow traffic speeds,
roundabouts can reduce the potential for hydroplaning compared to other intersection
configurations.
46
HEC-22, 4th edition Chapter 5 - Roadway Pavement Drainage
where:
Ku = Unit conversion constant, 0.56 in CU (0.376 in SI)
n = Manning’s coefficient
Q = Flow rate, ft3/s (m3/s)
T = Width of flow (spread), ft (m)
Sx = Cross slope, ft/ft (m/m)
SL = Longitudinal grade, ft/ft (m/m)
Equation 5.2 neglects the resistance of the curb face since this resistance is negligible. Table 5.3
summarizes typical Manning’s coefficients for paved gutters. In terms of velocity, the relationship
is:
Designers often use spread on the pavement and flow depth at the curb as criteria for spacing
pavement drainage inlets. Equation 5.2 can be solved in terms of T to estimate a spread width
given a flow rate:
0.375
Qn
T = 1.67 0.5
(5.4)
K u S x SL
Table 5.3. Manning’s n for street and pavement gutters (FHWA 1977).
47
Chapter 5 - Roadway Pavement Drainage HEC-22, 4th edition
Q w = Q Eo (5.5)
Qs = Q (1-Eo ) (5.6)
48
HEC-22, 4th edition Chapter 5 - Roadway Pavement Drainage
where:
Q = Total gutter flow rate, ft3/s (m3/s)
Qw = Flow in the depressed section of the gutter, ft3/s (m3/s)
Qs = Flow in the gutter section above the depressed section, ft3/s (m3/s)
Eo = Ratio of flow in the depressed section (usually the width of a grate) to total gutter
flow
The ratio of flow in the depressed section to the total flow is:
1
Eo = (5.7)
Sw / Sx
1+ 2.67
Sw / Sx
1 + −1
( T / W ) − 1
where:
Sw = Cross slope in the depressed section, ft/ft (m/m)
As shown in Figure 5.2 (a.2) the depressed section cross slope is:
a
S=
w Sx + (5.8)
W
The following example demonstrates computing flow and spread in a composite gutter.
Example 5.2: Composite gutter flow.
Objective: Estimate: A) the flow in a composite gutter at a spread of 8.2 ft (2.5 m) and B)
the spread in the gutter at a flow of 4.2 ft3/s (0.12 m3/s).
Given: Gutter section illustrated in Figure 5.2 (a.2) with:
W = 2 ft (0.61 m)
SL = 0.01 ft/ft (m/m)
Sx = 0.02 ft/ft (m/m)
n = 0.016
a = 2 inches (51 mm) (gutter depression)
Step A1. Compute the cross slope of the depressed gutter, Sw, and the width of spread from the
junction of the gutter and the road to the limit of the spread, Ts.
Sw = a / W + Sx = [(2)/(12)]/(2) + (0.020) = 0.103 ft/ft
Ts = T - W = 8.2 - 2.0 = 6.2 ft
Step A2. Compute Qs from equation 5.2 using Ts.
Qs = (Ku/n) Sx1.67 SL0.5 Ts2.67 = (0.56/0.016) (0.02)1.67 (0.01)0.5 (6.2)2.67 = 0.66 ft3/s
Step A3. Determine the gutter flow, Q.
T / W = 8.2 / 2 = 4.10
Sw / Sx = 0.103 / 0.020 = 5.15
49
Chapter 5 - Roadway Pavement Drainage HEC-22, 4th edition
50
HEC-22, 4th edition Chapter 5 - Roadway Pavement Drainage
T / W = 5.55
T = 2.0 (5.55) = 11.1 ft
Ts = 11.1 - 2.0 = 9.1 ft
Qs = 1.85 ft3/s
Qs assumed = Qs computed. Computations completed.
Solution: A) The estimated discharge of the gutter for the given spread is 2.3 ft3/s (0.065
m3/s). B) The estimated spread of the composite gutter for the given discharge
is 11.1 ft (3.38 m).
5.3.3.1 V-Sections
Equation 5.2 can be used to compute the flow in a shallow V-shaped section by estimating the
cross slope, Sx, using the following equation:
S x1 S x2
Sx = (5.9)
S x1 + S x2
Step 1. Calculate Sx using equation 5.8 assuming all flow is contained entirely in the V-shaped
gutter section determined by Sx1 and Sx2.
Sx = Sx1 Sx2 / (Sx1 + Sx2) = (0.25) (0.04) / (0.25 + 0.04) = 0.0345 ft/ft
51
Chapter 5 - Roadway Pavement Drainage HEC-22, 4th edition
Step 2. Using equation 5.4, find the hypothetical spread, T’, assuming all flow contained entirely
in the V-shaped gutter.
T’ = [(Q n)/(Ku Sx1.67 SL0.5)]0.375 = [(1.77)(0.016)/{(0.56)(0.0345)1.67(0.01)0.5}]0.375 = 6.4 ft
Step 3. Determine if T’ is within Sx1 and Sx2.
dB = TBC Sx2 = (2) (0.04) = 0.08 ft
TAB = dB / Sx1 = (0.08) / (0.25) = 0.32 ft
TAC = TAB + TBC = 0.32 + 2.0 = 2.32 ft
2.32 ft < T’ therefore, spread falls outside V-shaped gutter section. An iterative solution
technique is used to solve for the section spread, T, as illustrated in the following steps.
Step 4. Solve for the depth at point C, yc, and compute an initial estimate of the spread along
TBD.
yC = dB – TBC (Sx2)
From the geometry of the triangle formed by the gutter, an initial estimate for dB is determined
as:
(dB /0.25) + (dB /0.04) = 6.4 ft
dB = 0.22 ft
yc = 0.22 - (2.0) (0.04) = 0.14 ft
Ts = yc / Sx3 = 0.14/ 0.02 = 7 ft
TBD = Ts+ TBC = 7 + 2 = 9 ft
Step 5. With TBD, develop a weighted slope for Sx2 and Sx3.
2.0 ft at Sx2 (0.04) and 7.0 ft at Sx3 (0.02)
[(2.0) (0.04) + (7.0) (0.02)] / 0.90 = 0.024 ft/ft
Use this slope along with SX1, find Sx using equation 5.9:
Sx = (Sx1 Sx2) / (Sx1 + Sx2) = [(0.25) (0.024)] / (0.25 + 0.024) = 0.022 ft/ft
Step 6. Using equation 5.2, compute the gutter spread using the composite cross slope, Sx.
T = [(Q n)/(Ku Sx 1.67 SL 0.5)] 0.375 = [(1.77)(0.016)/{(0.56)(0.022)1.67(0.01)0.5}]0.375 = 8.5 ft
This 8.5 ft is lower than the assumed value of 9.0 ft.
Therefore, assume TBD = 8.3 ft and repeat step 5 and step 6.
Step 5 (repeated). 2.0 ft at Sx2 (0.04) and 6.3 ft at Sx3 (0.02).
[(2.0) (0.04) + (6.3) (0.02)] / 8.30 = 0.0248
Use this slope along with Sx1, find Sx using equation 5.6:
Sx = [(0.25) (0.0248)] / (0.25 + 0.0248) = 0.0226 ft/ft
Step 6 (repeated). Using equation 5.2 compute the spread.
T = [(Q n)/(Ku Sx1.67 SL0.5)]0.375 = [(1.77)(0.016)/{(0.56)(0.0226)1.67(0.01)0.5}]0.375 = 8.31 ft
Solution: This value of T is close to the assumed value, therefore, OK.
52
HEC-22, 4th edition Chapter 5 - Roadway Pavement Drainage
The following example illustrates analysis of a V-shaped median gutter resulting from a roadway
with an inverted crown section.
Example 5.4: V-shaped median shallow swale.
Objective: Find A) spread for the design flow of 24.7 ft3/s (0.70 m3/s) and B) compute the
flow for a spread of 23.0 ft (7.0 m).
Given: V-shaped gutter as illustrated in Figure 5.2 (b.2) with:
TAB = 3.28 ft (1 m)
TBC = 3.28 ft (1 m)
SL = 0.01 ft/ft (m/m)
n = 0.016
Sx1 = 0.25 ft/ft (m/m)
Sx2 = 0.25 ft/ft (m/m)
Sx3 = 0.04 ft/ft (m/m)
Step A1. Assume spread remains within middle “V” (A to C) and compute Sx.
Sx = (Sx1 Sx2 ) / (Sx1 + Sx2 ) = (0.25) (0.25) / (0.25 + 0.25) = 0.125 ft/ft
Step A2. Compute the spread from equation 5.4.
T = [(Q n)/(Ku Sx1.67 SL0.5)]0.375 = [(24.7)(0.016)/{(0.56) (0.125)1.67 (0.01)0.5}]0.375 = 7.65 ft
Since “T” is outside Sx1 and Sx2 an iterative approach is used to compute the spread.
Step A3. Treat one-half of the median gutter as a composite section and solve for T’ equal to
one-half of the total spread.
Q’ for T’ = ½ Q = 0.5 (24.7) = 12.4 ft3/s
Step A4. Try Q’s = 1.8 ft3/s.
Q’w = Q’ - Q’s =12.4 - 1.8 = 10.6 ft3/s
Step A5. Using equation 5.5, determine the W/T’ ratio.
E’o = Q’w/Q’ = 10.6/12.4 = 0.85
Sw / Sx = Sx2 / Sx3 = 0.25 / 0.04 = 6.25
W/T’ = 0.33 from trial-and-error
Step A6. Compute spread based on assumed Q’s.
T’ = W / (W/T’) = 3.28 / 0.33 = 9.94 ft
Step A7. Compute Ts based on assumed Q’s.
Ts = T’ - W = 9.94 - 3.28 = 6.66 ft
Step A8. Use equation 5.2 to determine Q’s for Ts.
Q’s = (Ku/n) Sx31.67 SL0.5 Ts2.67 = (0.56/0.016) (0.04)1.67 (0.01)0.5 (6.66)2.67 = = 2.56 ft3/s
Step A9. Check computed Q’s with assumed Q’s.
Q’s assumed = 1.8 < 2.56 = Q’s computed
Therefore, try a new assumed Q’s and repeat steps 4 through 9.
53
Chapter 5 - Roadway Pavement Drainage HEC-22, 4th edition
d
( )
0.488
= K u ( Qn ) / D2.67 SL0.5 (5.10)
D
where:
d = Depth of flow in circular gutter, ft (m)
D = Diameter of circular gutter, ft (m)
Ku = Unit conversion constant, 0.972 in CU (1.179 in SI)
54
HEC-22, 4th edition Chapter 5 - Roadway Pavement Drainage
The width of circular gutter section Tw is represented by the chord of the arc which can be
computed using:
TW = 2 ( r 2 - ( r - d) )0.5
2
(5.11)
where:
Tw = Width of circular gutter section, ft (m)
r = Radius of circular gutter, ft (m)
1.67
S x1 K1 Q1 Q1
= = (5.12)
S x2 K 2 Q2 Q2
Similar transformations can be performed to evaluate the effects of changing longitudinal slope
and width of spread on gutter capacity resulting in:
0.5
SL1 Q1
= (5.13)
SL2 Q2
2.67
T1 Q1
= (5.14)
T2 Q2
Figure 5.3 illustrates that the effects of cross slope are also relatively significant. At a cross slope
of 4 percent, a gutter has 10 times the capacity of a gutter of 1 percent cross slope. A gutter at 4
percent cross slope has 3.2 times the capacity of a gutter at 2 percent cross slope. Designers
generally have little latitude to vary longitudinal slope to increase gutter capacity but slope
changes, which change gutter capacity, are frequent.
( ) (
Va = K u K G T22.67 - T12.67 / T22 - T12 ) (5.15)
where:
Va = Average velocity in the gutter section between T1 and T2 locations, ft/s (m/s)
T1 = Upstream spread, ft (m)
T2 = Downstream spread, ft (m)
KG = Gutter geometry parameter
Ku = Unit conversion constant, 0.84 in CU (0.564 in SI)
K G = ( SL0.5 S0.67
X ) / n (5.16)
56
HEC-22, 4th edition Chapter 5 - Roadway Pavement Drainage
Figure 5.3. Relative effects of spread, cross slope, and longitudinal slope on gutter capacity.
57
Chapter 5 - Roadway Pavement Drainage HEC-22, 4th edition
58
HEC-22, 4th edition Chapter 6 - Roadside and Median Channels
59
Chapter 6 - Roadside and Median Channels HEC-22, 4th edition
6.1.1 Energy
Conservation of energy is a basic principle in open channel flow. As shown in Figure 6.1, the total
energy (or head) at a given location in an open channel is expressed as the sum of the potential
energy (channel bottom elevation plus depth) and kinetic energy (velocity head). (Pressure head
is zero in open channel flow and, therefore, excluded from consideration.) The total energy at any
cross-section along the channel can be approximated as:
V2
Et = Z + y + (6.1)
2g
where:
Et = Total energy, ft (m)
Z = Elevation of the channel bottom above a given datum, ft (m)
y = Flow depth, ft (m)
V = Mean velocity, ft/s (m/s)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
Figure 6.1 depicts a channel schematic highlighting two cross-section locations. Balancing energy
between cross-section 1 and a downstream cross-section 2, the energy equation becomes:
V12 V2
Z1 + y1 + = Z2 + y 2 + 2 + hL (6.2)
2g 2g
60
HEC-22, 4th edition Chapter 6 - Roadside and Median Channels
where:
hL = Energy (head) lost between section 1 and 2 to friction and turbulence, ft (m)
The energy equation states that the total energy head at an upstream cross-section is equal to
the total energy head at a downstream cross-section plus the energy head loss between the two
sections.
V2
E=y+ (6.3)
2g
For a given discharge and channel roughness, the specific energy changes with channel slope.
At mild slopes, flow moves through a channel relatively slowly and with greater depths. As slope
increases, velocity increases and depth decreases. Figure 6.2 illustrates the change in specific
energy relative to the depth for three different flow rates, q1, q2, and q3. The figure reveals that
for each of the curves there is a depth at which the specific energy is a minimum.
Critical flow occurs when the specific energy is at its minimum for a given flow and the
corresponding depth is the critical depth. Figure 6.2 shows that at critical flow, the critical depth
is two-thirds of the specific energy. The velocity head is the remaining one-third.
61
Chapter 6 - Roadside and Median Channels HEC-22, 4th edition
Subcritical flow occurs when the depth is greater than critical depth and supercritical flow occurs
when the depth is less than critical depth. Hydraulic engineers use the Froude number to identify
critical, subcritical, or supercritical flow conditions in a channel. The Froude number is calculated
for rectangular channels using the following equation:
V
Fr = (6.4)
gy
where:
V = Mean velocity of flow, ft/s (m/s)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
y = Flow depth, ft (m)
When the Froude number is less than one, the flow is classified as subcritical. Depth is greater
than critical depth, the velocity is slower than critical velocity, and small water surface
disturbances travel both upstream and downstream. Downstream conditions control the flow rate.
The control may be a structure or obstruction in the channel, or the control may be the channel
roughness. Subcritical flow generally occurs on mild slopes.
When the Froude number is greater than one, the flow is classified as supercritical. Depth is less
than critical depth, the velocity is faster than critical velocity, and small water surface disturbances
cannot move upstream and are swept downstream. Upstream conditions control the flow rate.
Supercritical flow occurs only very rarely in natural channels but is common in constructed
channels on relatively steep slopes.
When the Froude number is equal to one, the flow is critical. When the Froude number is close
to one, small changes in the flow rate, channel geometry, or channel slope can initiate a change
in flow regime. A change from subcritical flow to supercritical flow results in higher velocities than
anticipated and a change from supercritical to subcritical flow results in higher depths than
anticipated. Considering these changes and any resulting impacts on flow depth or channel
stability will help engineers design roadside and median channels that serve their intended
function.
When the Froude number is greater than one (flow is supercritical) and a change in channel
condition, such as an obstacle or a reduction in channel slope, occurs, flow may transition abruptly
from supercritical to subcritical in a hydraulic jump. A hydraulic jump results in a rapid increase
in depth and reduction in velocity. In making this transition, the jump can dissipate a significant
portion of the flow energy.
The turbulence of a hydraulic jump may threaten the stability of a roadside or median channel.
Exposing an unprotected channel boundary material, e.g., soil, to the turbulence of a hydraulic
jump may result in undesirable scour and erosion of the boundary, altering the channel shape
and resulting in long-term or recurrent channel maintenance problems. In addition, as the flow
varies over time (e.g., from the beginning of a runoff event to its peak and recession), the location
of a jump along the channel can vary significantly as the Froude number varies with flow.
62
HEC-22, 4th edition Chapter 6 - Roadside and Median Channels
For these reasons, designers typically avoid hydraulic jump conditions in roadside and median
channels. The designer may consider the potential for a hydraulic jump in cases where the Froude
number is greater than one or where the slope of the channel bottom changes abruptly from steep
to mild. If hydraulic jumps cannot be avoided, accounting for their likely presence allows the
designer to apply measures, such as protective linings, that create a more sustainable design.
63
Chapter 6 - Roadside and Median Channels HEC-22, 4th edition
Ku
Q= A R 2/3 S1/2
o
(6.5)
n
where:
Ku = Unit conversion constant, 1.486 in CU (1.0 in SI)
Q = Discharge rate, ft/s3 (m/s3)
A = Cross-sectional flow area, ft2 (m2)
R = Hydraulic radius, ft (m)
So = Energy grade line slope, ft/ft (m/m)
n = Manning’s roughness coefficient
V2 T
∆d = (6.6)
g Rc
64
HEC-22, 4th edition Chapter 6 - Roadside and Median Channels
where:
Δd = Difference in water surface elevation between the inner and outer banks of the
channel in the bend, ft (m)
V = Average velocity, ft/s (m/s)
T = Surface width of the channel, ft (m)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
Rc = Radius to the centerline of the channel, ft (m)
Table 6.1. Typical channel lining Manning’s roughness coefficients (FHWA 2005).
Lining Manning’s n Manning’s n Manning’s n
Category Lining Type Minimum Typical Maximum
Concrete 0.015 0.013 0.011
Grouted Riprap 0.040 0.030 0.028
Rigid Stone Masonry 0.042 0.032 0.030
Soil Element 0.025 0.022 0.020
Asphalt 0.018 0.016 0.016
Bare Soil 0.025 0.020 0.016
Unlined
Rock Cut 0.045 0.035 0.025
Open-weave textile 0.028 0.025 0.022
RECP Erosion control blanket 0.045 0.035 0.028
Turf reinforcement mat 0.036 0.030 0.024
Equation 6.6 is valid for subcritical flow conditions. The elevation of the water surface at the outer
channel bank will be ∆d/2 higher than the centerline water surface elevation and the elevation of
the water surface at the inner channel bank will be ∆d/2 lower than the centerline water surface
elevation.
Under supercritical flow conditions, the water surface is not influenced by conditions or geometry
downstream, including bends in the channel. Bends intended to change the direction of
supercritical flow may result in potentially undesirable hydraulic conditions such as standing
waves oblique to the direction of flow, oblique hydraulic jumps, and directional jets. If supercritical
flow conditions approaching a bend are unavoidable, the designer can consider introducing a
controlled hydraulic jump to induce subcritical conditions prior to changing direction (Chow 1959).
To avoid unstable side slopes, designers specify channel side slopes for roadside and median
channels that do not exceed the angle of repose of either the soil or lining material, or both.
Designers compute cross-section area, wetted perimeter, and flow top width for triangular (B = 0)
and trapezoidal channels using:
A = Bd + zd2 (6.7)
T = B + 2dz (6.9)
where:
A = Cross-sectional area of the channel, ft2 (m2)
P = Wetted perimeter of the channel, ft (m)
T = Surface width of the channel, ft (m)
66
HEC-22, 4th edition Chapter 6 - Roadside and Median Channels
Channels immediately adjacent to the roadway may be influenced by roadside safety needs or
features such as traffic barriers. For example, geometric design criteria frequently specify channel
side slopes that are traversable by errant vehicles (1V:3H or flatter with additional considerations)
(FHWA 2005). In areas where roadside safety may be of concern, the Roadside Design Guide
also allows for flatter channel side slopes, considering the functional classification of the roadway
and traffic volume (AASHTO 2011). Design of roadside and median channels, the highway
geometric and pavement design, and the design of appurtenances (e.g., signing, signals,
illumination, and the accommodation of utilities) work together to ensure proper balancing of
function, safety, utility, and drainage needs.
Example 6.1: Application of Manning’s equation
Objective: Estimate channel capacity and velocity for a channel lined with a turf
reinforcement mat with an n value of 0.03.
Given: A trapezoidal channel (as shown in Figure 6.3) with the following characteristics:
So = 0.01 ft/ft (m/m)
B = 2.6 ft (0.8 m)
z = 3
d = 1.6 ft (0.5 m)
67
Chapter 6 - Roadside and Median Channels HEC-22, 4th edition
Solution: The maximum flow for the channel is 55.7 ft3/s (1.58 m3/s) with an average
velocity of 4.7 ft/s (1.4 m/s).
6.2.4 Freeboard
Freeboard is the vertical distance from the water surface at the design discharge to a pre-
determined component of the roadway or channel. In a permanent roadside or median channel,
a designer may use the bottom of the pavement structure base course as the relevant roadway
component for defining freeboard. The need for freeboard depends on the consequences of
overflows escaping the channel. At a minimum, appropriate freeboard prevents debris, waves,
superelevation changes, or fluctuations in water surface from overflowing the sides. However, to
accommodate the large variations in flow caused by shocks, standing waves, splashing, and
surging in a steep channel, the designer can consider a freeboard height equal to the total energy
depth. For temporary channels, freeboard is optional.
τ = R
γ S (6.10)
where:
τ = Average shear stress, lb/ft2 (N/m2)
γ = Unit weight of water, 62.4 lb/ft3 at 60° F (9.81 kN/m3 at 15° C)
68
HEC-22, 4th edition Chapter 6 - Roadside and Median Channels
The maximum shear stress for a straight channel occurs where flow is deepest (on the channel
bed) (Chow 1959). It is computed using maximum depth instead of hydraulic radius:
τ d = d
γ S (6.11)
where:
τd = Maximum shear stress, lb/ft2 (N/m2)
d = Maximum depth of flow, ft (m)
Because shear stress is related to depth of flow and flow is shallower at the channel edges than
in the middle of the channel, shear stress is not uniformly distributed along the wetted perimeter
of a channel. The maximum shear on the side of a channel is estimated by the following (FHWA
2005):
τs = K1τd (6.12)
where:
τs = Side shear stress on the channel, lb/ft2 (N/m2)
K1 = Ratio of channel side to bottom shear stress
τd = Shear stress in the channel at maximum depth, lb/ft2 (N/m2)
The value K1 depends on the size and shape of the channel. For triangular channels with rounded
bottoms, there is no sharp discontinuity along the wetted perimeter. Therefore, computation of
shear stress at any point on the side slope is related to the depth at that point using equation
6.11.
The work of Anderson et al. (1970) led to the development of estimates for K1 in trapezoidal and
triangular channels (FHWA 2005):
K1 = 0.77 z 1.5
≤
K1 = 0.066 z + 0.67 1.5 < z < 5 (6.13)
K1 = 1.0 5 z
≤
The z value is the horizontal dimension 1:z (V:H) of side slope. Side slopes steeper than 1:3 (V:H)
are at greater risk for failure because of the potential for erosion of the side slopes.
For noncohesive linings such as gravel or riprap the resisting ability of the lining is reduced
because the material has the potential to roll or slide out of place. While the reduced shear stress
on the channel sides might suggest increased stability in that region of the channel, this may be
diminished by the steepness of side slope. For example, when designing a trapezoidal channel
lined with gravel or riprap having side slopes steeper than 1:3 the appropriate rock size for the
side slopes is estimated as:
K1
D50, sides = D
50, bottom (6.14)
K2
69
Chapter 6 - Roadside and Median Channels HEC-22, 4th edition
where:
D50 = Riprap or bed material median size, ft (m)
K1 = Ratio of shear stresses on the sides and bottom of a trapezoidal channel
K2 = Ratio of tractive force on the sides and bottom of a trapezoidal channel
K2 is a function of the side slope angle and the stone angle of repose and is determined from
equation 6.15. HEC-15 (FHWA 2005) provides the angle of repose for gravels and riprap of
different types.
( ) (
K 2 = 1 - sin2Θ / sin2Φ ) (6.15)
where:
Θ = Angle of side slope
Φ = Angle of repose for the channel lining material
Flow around bends also creates secondary currents which impose higher shear stresses on the
channel sides and bottom compared to straight reaches. Areas of high shear stress in bends are
illustrated in Figure 6.4.
The maximum shear stress in a bend is a function of the ratio of channel curvature to the top
(water surface) width. This ratio increases as the bend becomes sharper and the maximum shear
stress in the bend increases. The bend shear stress can be computed using the following
relationship:
τb = K b τd (6.16)
where:
τb = Bend shear stress, lb/ft2 (N/m2)
Kb = Ratio of channel bend to bottom shear stress
τd = Maximum channel shear stress, lb/ft2 (N/m2)
Kb can be determined from the following equation from Young et al. (1996) adapted from Lane
(1955):
K b = 2.00 Rc /T 2
≤
K b = 2.38 - 0.206 (Rc / T ) + 0.0073 (Rc / T )
2
2 < Rc /T < 10 (6.17)
K b = 1.05 ≤ c /T
10 R
where:
Kb = Ratio of channel bend to bottom shear stress
Rc = Radius to the centerline of the channel, ft (m)
T = Top (water surface) width of channel, ft (m)
70
HEC-22, 4th edition Chapter 6 - Roadside and Median Channels
The increased shear stress produced by the bend persists downstream of the bend a distance Lp,
as shown in Figure 6.4. This distance can be computed using the following relationship:
Lp = (K u R7/6 ) / nb (6.18)
where:
Lp = Length of protection (length of increased shear stress due to the bend)
downstream of the curve point of tangency, ft (m)
nb = Manning’s n in the channel bend
R = Hydraulic radius, ft (m)
Ku = Unit conversion constant, 0.604 in CU (0.736 in SI)
provide higher capacity and greater erosion resistance. In some cases, rigid linings may be the
only feasible alternative.
Flexible linings can be either long-term, transitional, or temporary. Designers use long-term
flexible linings where the channel needs protection against erosion for the life of the channel.
Long-term lining materials include cobbles, rock riprap, wire-enclosed riprap, gabion mattresses,
vegetation, and turf reinforcement. State DOTs often choose established vegetation as the
primary long-term channel management strategy; vegetation may be planned or incidental but
will frequently occur eventually.
Designers use transitional flexible linings to provide erosion protection until long-term protection,
usually vegetation, can be established. They use temporary channel linings without vegetation to
line channels that might be part of a construction site erosion and sediment management strategy,
or some other short-term channel situation. State DOT staff can select turf reinforcement either
as a transitional approach or as part of a long-term strategy of providing additional structure to
the soil/vegetation matrix.
Typical turf reinforcement materials include gravel/soil mixes and turf reinforcement mats (TRMs).
A TRM is usually a non-degradable rolled erosion control product (RECP) processed into a three-
dimensional matrix. A TRM is stiffer, thicker, and denser than an erosion control blanket, which is
typically a degradable product composed of an engineered distribution of natural or polymer fibers
bound together to form a continuous mat. Open-weave textiles (OWT) are a degradable RECP
composed of natural or polymer yarns more loosely woven into a matrix. RECPs are laid in the
channel and secured with staples or stakes.
Construction of rigid concrete linings involves considerable effort, costly materials, and
specialized construction equipment. As a result, the cost of rigid linings is typically higher than
flexible linings. Rigid lining such as concrete paving or grouted riprap is susceptible to failure from
undermining, particularly when placed on constructed or disturbed material such as
embankments. It can also be subject to structural instability from overtopping, freeze-thaw cycles,
swelling, and excessive soil pore water pressure. Thermal stress causes ubiquitous cracking of
concrete. Over time, water invasion and erosion of the supporting soil through cracks often results
in concealed void spaces under the concrete. These concealed void spaces present the danger
of sudden and unexpected collapse during runoff events or under the load of errant vehicles.
72
HEC-22, 4th edition Chapter 6 - Roadside and Median Channels
Prefabricated modular linings, such as interlocking concrete paving blocks, can be an alternative
if shipping distances are not excessive, however these often involve labor-intensive placement.
Modular linings are classified as flexible as they can withstand some movement and erosion
underneath the lining before failing.
In general, when selecting a lining, the designer considers the cost of the lining that affords
satisfactory protection as the baseline for comparison, but will also evaluate constructability,
aesthetics, and long-term service. In some regions, State DOTs often use vegetation alone or in
combination with other types of linings. Thus, a channel might be lined with vegetation on flatter
slopes and with more erosion resistant material on steeper slopes. In cross-section, the channel
might be lined with a resistant material within the depth necessary to carry frequent flows and
lined with vegetation above that depth for protection from less frequent flows.
τp SF
≥ τd (6.19)
where:
τp = Permissible shear stress for the channel lining, lb/ft2 (N/m2)
SF = Safety factor
Flexible linings reduce the shear stress acting directly on the underlying soil surface. Therefore,
the erodibility of the underlying soil is a key factor in the performance of flexible linings. Erodibility
of noncohesive (granular) soils (plasticity index less than 10) primarily relates to particle size and
specific gravity, while in cohesive (clay or clay-bound) soils it largely corresponds with the
cohesion and density of the soil. Vegetative and RECP lining performance relates to how well
they protect the underlying soil from shear stress, therefore, the protection offered by these lining
types depends on soil type. Figure 6.5 summarizes the basic procedure for designing a flexible
lining.
73
Chapter 6 - Roadside and Median Channels HEC-22, 4th edition
74
HEC-22, 4th edition Chapter 6 - Roadside and Median Channels
0.4
Q
di+1=di (6.20)
Qi
where:
di+1 = Next estimate of depth for computing the implied discharge, ft (m)
di = Previous estimate of depth for computing the implied discharge, ft (m)
Q = Design discharge, ft3/s (m3/s)
Qi = Implied discharge based on the previous estimate of depth, di, ft3/s (m3/s)
75
Chapter 6 - Roadside and Median Channels HEC-22, 4th edition
The channel reach consists of a straight section and a 90-degree bend with a centerline radius
of 20.0 ft (6.1 m). The design discharge is 28 ft3/s (0.79 m3/s). Assume a vegetated lining with
a Manning’s n value of 0.030. Maximum depth in the channel is 1.3 ft based on the desired
freeboard and channel dimensions.
Step 1. Select design hydrology and channel geometry.
The design hydrology (28 ft3/s) and trapezoidal channel geometry were given above.
Step 2. Select trial lining type.
Assume a vegetative lining with a Manning’s n value of 0.030 as given.
Step 3. Estimate the depth of flow.
Channel geometry and freeboard limit the maximum depth of flow to 1.3 ft. Assume an initial
depth of 1 ft to estimate the implied discharge.
Step 4. Estimate implied discharge.
A = Bd + zd2 = (3.0) (1.0) + (3) (1.0)2 = 6.0 ft2
P = B + 2d(z2+1)0.5 = (3.0) + (2) (1.0) (32+1)0.5 = 9.3 ft
R = A/P = 6.0/9.3 = 0.64 ft
Q = (Ku/n) A R(2/3) So(1/2) = (1.486/0.030) (6.0) (0.64)(2/3) (0.01)(1/2) = 22.1 ft3/s
76
HEC-22, 4th edition Chapter 6 - Roadside and Median Channels
77
Chapter 6 - Roadside and Median Channels HEC-22, 4th edition
• Prepare existing and proposed plan and profile of the proposed channels. Include any
constraints on design such as highway and road locations, culverts, and utilities.
• Collect any available site data such as soil types and topographic information.
Step 2. Obtain typical cross-section information.
Establish preliminary cross-section geometric parameters and controlling physical features
considering the following:
• Roadway width, auxiliary lanes, shoulders, pedestrian facilities (e.g., sidewalks), and other
roadway features when present.
• Adequate channel depth to drain the subbase and minimize freeze-thaw.
• Channel side slopes based on geometric design criteria including safety, economics, soil,
aesthetics, and access.
Step 3. Select initial channel slope.
Plot initial slopes on the plan and profile. Note that highway grades often control slopes on
roadside channels. Use the following guides when establishing initial channel slopes:
• Provide a channel slope with sufficient elevation drop to minimize ponding and sediment
accumulation.
• Where possible, avoid features which may influence or restrict slope, such as utility (e.g.,
electricity and gas) structures.
Step 4. Check flow capacities and adjust sections.
Evaluate the hydraulic capacity of the channel and confirm that it meets the hydraulic design
criteria using the techniques in Section 6.2. The following activities may be appropriate:
• Compute the design discharge at the downstream end of each channel segment (see
Chapter 4).
• Set preliminary values for channel size, roughness, and slope as discussed in Section 6.2
based on long-term conditions and maintenance considerations.
• Determine the maximum allowable depth of channel including freeboard.
• Estimate the flow depth using the design discharge and channel characteristics.
• If the capacity is not adequate, consider possibilities for increasing capacity including:
• Increasing bottom width.
• Flattening channel side slopes.
• Steepening channel slope.
• Providing smoother channel lining.
• Intercepting some flow before it reaches the channel.
• Installing drop inlets and a parallel storm drainpipe beneath the channel to supplement
channel capacity.
Step 5. Select channel protection.
Follow the procedure outlined in Section 6.3 to complete final design of channels that will involve
a lining for stability.
78
HEC-22, 4th edition Chapter 6 - Roadside and Median Channels
Table 6.2. Possible adverse channel outlet impacts and potential mitigation.
79
Chapter 6 - Roadside and Median Channels HEC-22, 4th edition
80
HEC-22, 4th edition Chapter 7 - Inlet Design
81
Chapter 7 - Inlet Design HEC-22, 4th edition
as the gutter grade steepens. Consequently, curb-opening inlets are most effective in sags and
on grades less than 3 percent.
Combination inlets consist of both a curb-opening inlet and a grate inlet placed in a side-by-side
configuration, but the curb opening may extend upstream of the grate. Combination inlets provide
the advantages of both curb-opening and grate inlets and perform as a high-capacity inlet. When
the curb opening extends upstream of the grate in a “sweeper” configuration, the curb-opening
inlet acts as a trash interceptor during the initial phases of a storm. Used in a sag configuration,
the sweeper inlet can have a curb opening on both ends of the grate.
Slotted inlets consist of a pipe cut along the longitudinal axis with bars perpendicular to the
opening to maintain the slotted opening. Slotted inlets can be used in areas where it is desirable
to intercept sheet flow before it crosses onto a section of roadway. Their principal advantage is
that they can intercept flow over a wide section. However, the susceptibility of slotted inlets to
clogging from sediments and debris makes them ill-suited for use in environments where
significant sediment or debris loads may be present. Slotted inlets on a longitudinal slope exhibit
the same hydraulic capacity as curb openings when debris is not a factor. Slotted drains may also
be combined with grates.
82
HEC-22, 4th edition Chapter 7 - Inlet Design
Barriers and barrier walls used during construction temporarily separate vehicles from
construction activities. Where pavement runoff flows toward the barriers, drainage designers
provide for capture and diversion of this runoff from the traveled way. Typically, these barriers
include pre-located rectangular openings to allow water to pass beneath the barriers. Although,
these openings create a hydraulic configuration analogous to a curb and gutter, they are different
in important ways:
• The openings in each barrier are generally prefabricated and not customized based on
the drainage needs.
• The openings are located at regular, closely spaced intervals in a series of barriers that
are not selected by the drainage designer.
• The barriers are often located close to the traveled way potentially reducing or eliminating
flow in a gutter.
For drainage under temporary barriers, the drainage design estimates the contributing flow to,
and interception capacity of, the barrier openings to assess water depth and spread to maintain
safe vehicle use of the roadway. In addition to adapting the tools in this manual for curb inlets,
drainage designers can use tools developed by researchers focused specifically on barrier wall
drainage, e.g., Kranc et al. (2005).
83
Chapter 7 - Inlet Design HEC-22, 4th edition
Figure 7.2. P-1-7/8-4 grate (P-1-7/8 is this grate without transverse rods).
84
HEC-22, 4th edition Chapter 7 - Inlet Design
85
Chapter 7 - Inlet Design HEC-22, 4th edition
86
HEC-22, 4th edition Chapter 7 - Inlet Design
Figure 7.5. Tilt-bar grate: 45°- 60 (2.25 inch) and 45°- 85 (3.25 inch).
87
Chapter 7 - Inlet Design HEC-22, 4th edition
88
HEC-22, 4th edition Chapter 7 - Inlet Design
89
Chapter 7 - Inlet Design HEC-22, 4th edition
In addition, areas where pedestrians using various mobility assistance devices may be found, the
Americans with Disabilities Act (ADA) has resulted in grates designated as ADA-compliant.
Generally, ADA-compliant grates include smaller openings than non-compliant grates reducing
their flow interception efficiency under some conditions. Like other grates, interception efficiency
is grate specific. Lottes and Bojanowski (2015) compared the efficiency of a curved vane grate
and an ADA-compliant grate with the same dimensions and confirmed a reduction in interception
efficiency. However, the magnitude of reductions varies with the design.
90
HEC-22, 4th edition Chapter 7 - Inlet Design
Qi
E= (7.1)
Q
where:
E = Inlet efficiency
Q = Total gutter flow, ft3/s (m3/s)
Qi = Intercepted flow, ft3/s (m3/s)
Qb =Q - Qi (7.2)
where:
Qb = Bypass flow, ft3/s (m3/s)
The interception capacity of all inlet configurations increases with increasing flow rates, and inlet
efficiency generally decreases with increasing flow rates. Gutter flow characteristics also affect
inlet interception capacity. The depth of water next to the curb is the major factor in the interception
capacity of both grate inlets and curb-opening inlets. The interception capacity of a grate inlet
depends on the amount of water flowing over the grate, the size and configuration of the grate,
and the velocity of flow in the gutter.
Interception capacity of a curb-opening inlet largely depends on flow depth at the curb and curb-
opening length. Local gutter depression at a curb-opening or a continuously depressed gutter
increase depth at the curb, interception capacity, and efficiency. Top slab supports placed flush
with the curb line can substantially reduce the interception capacity of curb openings. Tests have
shown that such supports reduce the effectiveness of openings downstream of the support by as
much as 50 percent and, if debris is caught at the support, interception by the downstream portion
of the opening may be reduced to near zero. However, Schalla (2016) and Muhammad (2018)
concluded that, in the absence of debris, flush slab supports did not reduce interception. Where
feasible, recessing intermediate top slab supports several inches from the curb line and rounding
their shape reduces loss of interception capacity.
Slotted inlets function in essentially the same manner as curb-opening inlets, i.e., as weirs with
flow entering from the side. Interception capacity depends on flow depth and inlet length.
Efficiency depends on flow depth, inlet length, and total gutter flow.
The interception capacity of an equal length combination inlet consisting of a grate placed
alongside a curb opening on a grade does not differ materially from that of a grate only.
Interception capacity and efficiency depend on the same factors which affect grate capacity and
efficiency. A combination inlet consisting of a curb-opening inlet placed upstream of a grate inlet
(a sweeper configuration) has a capacity equal to that of the curb-opening length upstream of the
grate plus that of the grate. However, capacity of the grate lowers because of the reduced spread
and depth of flow over the grate resulting from the interception by the curb opening. This inlet
91
Chapter 7 - Inlet Design HEC-22, 4th edition
configuration has the added advantage of intercepting debris that might otherwise clog the grate
and deflect water away from the inlet.
The following sections present methods for estimating interception capacity of inlets on grade.
For locally depressed inlets, the quantity of flow reaching the inlet depends on the upstream gutter
section geometry and not the locally depressed section geometry.
Qw
= 1- (1-W/T )
2.67
Eo = (7.3)
Q
where:
Eo = Frontal flow ratio
Q = Total gutter flow, ft3/s (m3/s)
Qw = Frontal flow in width W, ft3/s (m3/s)
W = Width of depressed gutter or grate, ft (m)
T = Total spread of water, ft (m)
1 − ( Qw / Q ) =
Qs / Q = 1 − Eo (7.4)
When the velocity approaching the grate is less than the splash-over velocity, the grate will
intercept essentially all frontal flow. Conversely, when the gutter flow velocity exceeds the splash-
over velocity for the grate, only part of the flow will be intercepted. The ratio of frontal flow
intercepted to total frontal flow, Rf, is expressed as:
1 − K u ( V − Vo )
Rf = (7.5)
where:
Ku = Unit conversion constant, 0.09 in CU (0.295 in SI)
V = Velocity of flow in the gutter, ft/s (m/s)
Vo = Gutter velocity where splash-over first occurs, ft/s (m/s)
Figure 7.8 provides the splash-over velocity for several grate types for equation 7.5. The
approaching gutter flow velocity is computed from the gutter equation (equation 5.3). If the splash-
92
HEC-22, 4th edition Chapter 7 - Inlet Design
over velocity is greater than the gutter flow velocity, Rf is 1.0 because capture efficiency cannot
exceed 100 percent.
The inlet also intercepts part of the flow along the side of the grate. The ratio of side flow
intercepted to total side flow, Rs, or side flow interception efficiency, depends on the pavement
cross slope, the grate length, and the flow velocity:
(
Rs = 1 / 1+(K u V1.8 ) / (S x L2.3 ) ) (7.6)
93
Chapter 7 - Inlet Design HEC-22, 4th edition
where:
Ku = Unit conversion constant, 0.15 in CU (0.0828 in SI)
Equation 7.6 underestimates side flow interception where the velocity is low, and the spread only
slightly exceeds the grate width. Error due to this deficiency is small.
The total efficiency of a grate inlet, E, is expressed as:
E = R f Eo + Rs (1 − Eo ) (7.7)
The first term on the right side of the equation is the ratio of intercepted frontal flow to total gutter
flow, and the second term is the ratio of intercepted side flow to total side flow. The second term
is insignificant with high velocities and short grates.
Frontal flow to total gutter flow ratio, Eo, for grate inlets in composite gutter sections assumes
frontal flow width equal equals the depressed gutter section width which also equals the grate
width. If the grate width is less than W, the frontal flow ratio, Eo, is modified to evaluate grate
efficiency. As an approximation, the adjusted frontal flow ratio assumes that average velocity in
the gutter is applicable to the entire gutter width. Then, the adjusted frontal flow ratio, E’o, is
calculated by multiplying Eo by a flow area ratio. The area ratio is the gutter flow area in a width
equal to the grate width divided by the total flow area in the depressed gutter section and is applied
as follows:
E 'o = Eo ( A ′w / A w ) (7.8)
where:
E’o = Adjusted frontal flow area ratio for grates in composite cross-sections
A’w = Gutter flow area in a width equal to the grate width, ft2 (m2)
Aw = Flow area in the depressed gutter width, ft2 (m2)
Equation 7.9 describes the interception capacity of a grate inlet on grade as the efficiency of the
grate multiplied by the total gutter flow. The adjusted frontal ratio, E’o is substituted for Eo when
the grate width is less than the gutter width.
Qi =E Q =Q R f Eo + Rs (1 − Eo ) (7.9)
95
Chapter 7 - Inlet Design HEC-22, 4th edition
Solution: Table 7.4 summarizes the interception capacities. The P-1-7/8 parallel bar grate
intercepts 48 percent of the total flow compared with 42 percent for the
reticuline grate. Increasing the length of the grates would not be cost-effective,
because the increase in side flow interception is small.
where:
LT = Curb-opening length required to intercept 100 percent of the gutter flow, ft (m)
Ku = Unit conversion constant, 0.6 in CU (0.817 in SI)
SL = Longitudinal slope, ft/ft (m/m)
Q = Gutter flow, ft3/s (m3/s)
For depressed curb-opening inlets, as shown in Figure 7.9, or curb openings in depressed gutter
sections an equivalent cross slope, Se, replaces Sx in equation 7.10. Se is:
S=
e S x + S w' E0 (7.11)
where:
S’w = Cross slope of the gutter measured from the pavement cross slope, Sx, ft/ft
(m/m)
Eo = Frontal flow ratio for the depressed section determined by the gutter
configuration upstream of the inlet
Sw’ is computed as a/W or equivalently, Sw – Sx, where Sw is shown in Figure 7.9. Using the
equivalent cross slope, Se, equation 7.10 becomes:
96
HEC-22, 4th edition Chapter 7 - Inlet Design
0.6
L T = K u Q0.42 SL0.3 1/ ( n Se ) (7.12)
Increasing the cross slope or the equivalent cross slope reduces the required curb-opening length
for 100 percent interception. The equivalent cross slope can be increased by use of a continuously
depressed gutter section or a locally depressed gutter section.
The efficiency of curb-opening inlets shorter than the length required for total interception is
applicable for either uniform cross slopes or composite cross slopes and is expressed as:
1.8
L
E =1 − 1 − (7.13)
LT
where:
L = Curb-opening length, ft (m)
97
Chapter 7 - Inlet Design HEC-22, 4th edition
Step A1. Determine the length of curb opening required for total interception of gutter flow
without gutter depression.
Using equation 7.10:
LT = Ku Q0.42 SL0.3 (1/(n Sx))0.6 = 0.6 (1.77)0.42(0.01)0.3(1/[(0.016)(0.02)])0.6 = 23.9 ft
Step A2. Compute the curb-opening efficiency without gutter depression.
Using equation 7.13:
L / LT = 9.84 / 23.9 = 0.41
E = 1 – (1 – L / LT)1.8 = 1 – (1 – 0.41)1.8 = 0.61
Step A3. Compute the interception capacity without gutter depression.
Qi = E Q = (0.61) (1.77) = 1.08 ft3/s
Step B1. Determine the W/T ratio for the depressed gutter.
Determine spread, T (see example 5.2(B))
Assume Qs = 0.64 ft3/s
Qw = Q – Qs = 1.77 – 0.64 = 1.13 ft3/s
Eo = Qw / Q = 1.13 / 1.77 = 0.64
Sw = Sx + a/W = 0.02 + (0.083/2.0) = 0.062
Sw/Sx = 0.062 / 0.02 = 3.1
Use equation 5.7 to determine that W/T = 0.24
Then, T = W / (W/T) = 2.0 / 0.24 = 8.3 ft
Ts = T – W = 8.3 – 2.0 = 6.3 ft
Use the gutter flow equation (equation 5.2) to obtain Qs.
Qs = (Ku/n) Sx1.67 SL0.5 Ts2.67 = {(0.56) / (0.016)} (0.02)1.67(0.01)0.5 (6.3)2.67 = 0.69 ft3/s
Since this is close to the assumed Qs no further iterations are necessary.
Step B2. Determine efficiency of curb opening with the depressed gutter section.
Using equation 7.11:
Se = Sx + S’w Eo = Sx + (a/W)Eo = 0.02 + [(0.083)/(2.0)](0.64) = 0.047
Using equation 7.12:
LT = KU Q0.42 SL0.3 [1/(n Se)]0.6 = (0.6) (1.77)0.42 (0.01)0.3 [1/((0.016)(0.047))]0.6 = 14.3 ft
Using equation 7.13:
L/LT = 9.84/14.3 = 0.69
E = 1 – (1 – L/LT)1.8 = 1 – (1 – 0.69)1.8 = 0.88
Step B3. Compute curb-opening interception.
Using equation 7.1:
Qi = Q E = (1.77) (0.88) = 1.56 ft3/s
98
HEC-22, 4th edition Chapter 7 - Inlet Design
Solution: A) the interception of the curb inlet without the depressed gutter is 1.08 ft3/s
(0.031 m3/s). B) the interception of the same inlet with a depressed gutter is
1.55 ft3/s (0.044 m3/s), an increase of approximately 40 percent under these
conditions.
The following example illustrates computation of the required curb-opening length to intercept 100
percent of the flow given the gutter flow.
Example 7.3: Curb-opening length on grade.
Objective: Find the minimum length of a locally depressed curb-opening inlet required to
intercept 100 percent of the gutter flow.
Given: A curb-opening inlet in the following situation:
SL = 0.01 ft/ft (m/m)
Sx = 0.02 ft/ft (m/m)
n = 0.016
Q = 2.26 ft3/s (0.064 m3/s)
T = 8.2 ft (2.5 m)
Step 1. Compute the composite cross slope for the locally depressed section.
Using equation 7.11:
S’w = a/W = (2/12) / 2 = 0.0833
Se = Sx + S’w Eo = 0.02 + (0.0833) (0.7) = 0.078
Step 2. Compute the length of curb-opening inlet required for 100 percent interception.
Using equation 7.12:
LT = KU Q0.42 SL0.3 (1 / n Se)0.6 = (0.60)(2.26)0.42(0.01)0.3 [1/ {(0.016) (0.078)}]0.6 = 11.7 ft
Solution: For the given conditions, the curb-opening length for 100 percent interception is
11.7 ft (3.56 m).
99
Chapter 7 - Inlet Design HEC-22, 4th edition
equation 7.10. Similarly, FHWA concluded that equation 7.13 also applies to slotted inlets and
can be used to obtain the inlet efficiency for a given inlet length.
For overland flow, FHWA research indicates that 1-, 1.75-, and 2.5-inch-wide slotted drain inlets
can capture 100 percent of the approaching flow up to 0.025 ft3/s/ft for water depths ranging from
0.38 to 0.56 inches on slopes ranging from 0.005 to 0.09 ft/ft. During tests at a system capacity
of 0.040 ft3/s/ft, a small amount of splash-over occurred.
100
HEC-22, 4th edition Chapter 7 - Inlet Design
101
Chapter 7 - Inlet Design HEC-22, 4th edition
Step 1. Compute the portion of the curb opening contributing to the interception capacity of the
combination inlet.
L = 9.84 – 2.0 = 7.84 ft
Step 2. Determine the frontal flow ratio for the depressed portion of the gutter.
Determine spread, T (see example 5.2(B))
Assume Qs = 0.64 ft3/s
Qw = Q – Qs = 1.77 – 0.64 = 1.13 ft3/s
Eo = Qw / Q = 1.13 / 1.77 = 0.64
Step 3. Determine the efficiency of the curb opening with the depressed gutter section.
Using equation 7.11:
Se = Sx + S’w Eo = Sx + (a/W)Eo = 0.02 + [(0.083)/(2.0)](0.64) = 0.047
Using equation 7.12:
LT = KU Q0.42 SL0.3 [1/(n Se)]0.6 = (0.6) (1.77)0.42 (0.01)0.3 [1/((0.016)(0.047))]0.6 = 14.3 ft
L / LT = 7.84 / 14.3 = 0.55
Using equation7.13:
E = 1 – (1 – L / LT)1.8 = 1 – (1 – 0.55)1.8 = 0.76
Qic = E Q = (0.76)(1.77) = 1.35 ft3/s
Step 4. Compute the flow approaching the grate.
Qg = Q – Qic = 1.77 – 1.35 = 0.42 ft3/s
Step 5. Estimate the side flow approaching the grate.
Determine spread, T (see example 5.2(B))
Assume Qs = 0.01 ft3/s
Qw = Q – Qs = 0.42 – 0.01 = 0.41 ft3/s
Eo = Qw / Q = 0.41/0.42 = 0.97
102
HEC-22, 4th edition Chapter 7 - Inlet Design
such as increasing cross slope, gutter depression, or local inlet depression, increase interception.
The effect of depression on curb-opening inlets is illustrated by comparing undepressed curb
openings (curves 9 and 10) with depressed curb openings of the same length (curves 11 and 12).
The depressed curb openings capture significantly higher flows for these conditions.
Figure 7.13 also illustrates that interception for grate inlets can increase with increasing
longitudinal slope until the splash-over velocity is reached. The grates represented by curves
other than 1 and 1A show an increase in interception for an increase in slope because the flow
spread is narrowing. However, at greater slopes, they experience a decrease in interception as
the splash-over velocity for the grate is reached and flow begins to jump over the grate. The P-1-
7/8 grates (curves 1 and 1A) show an increase in interception at the longitudinal slopes shown
because the velocity in the gutter has not reached their splash-over velocity. Based on these
performance characteristics curves, parallel bar grates and the curved vane grate are relatively
efficient at higher velocities and the reticuline grate is least efficient. At low velocities, the grates
perform equally well. However, some of the grates such as the reticuline grate are more
susceptible to clogging by debris than the parallel bar grate.
Figure 7.13 demonstrates that inlet length increases interception. The 4 ft grate (curve A)
intercepts more flow than the 2 ft grate (curve 1A). However, under these conditions, the doubling
of length increases interception modestly. Wider grates could increase interception because side
flow, not frontal flow, is escaping these grates. The figure reveals greater benefits of lengthening
curb opening and slotted inlets under these conditions. Interception increases significantly for the
10 ft curb-opening inlets (curves 9 and 11) compared with the 5 ft counterparts (curves 10 and
12).
Over a range of gutter flow rates, Figure 7.14 compares the same inlet types holding longitudinal
slope at 6 percent, cross slope at 3 percent, and Manning’s n at 0.016. It shows, for example, that
at a 6 percent slope, splash-over begins at about 0.7 ft3/s on a reticuline grate. It also illustrates
104
HEC-22, 4th edition Chapter 7 - Inlet Design
that with increased discharge, the interception capacity of all inlets increases, and inlet efficiency
decreases.
The performance characteristics shown in Figure 7.13 and Figure 7.14 neglect the effects of
debris and clogging on inlets. Section 7.1.3 discusses clogging.
105
Chapter 7 - Inlet Design HEC-22, 4th edition
Qi = Cw 2g P d1.5 (7.14)
where:
Qi = Intercepted flow, ft3/s (m3/s)
Cw = Weir coefficient (typically equal to 0.37)
P = Perimeter of the grate disregarding the side against the curb, ft (m)
d = Average depth across the grate, ft (m)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
Figure 7.15 describes the computation of average depth across a grate. The figure also describes
the grate width, W, and the grate length, L. The perimeter for estimating weir flow is L + 2W.
When operating under orifice flow conditions, designers estimate interception capacity as:
Qi = C o A g ( 2 g d )
0.5
(7.15)
where:
Qi = Intercepted flow ft3/s (m3/s)
Co = Orifice coefficient usually taken as 0.67
Ag = Clear opening area of the grate, ft2 (m2)
d = Average depth across the grate, ft (m)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
106
HEC-22, 4th edition Chapter 7 - Inlet Design
The clear area of opening of a grate equals the total area (length times width) times an opening
ratio. Burgi (1978b) tested three grate styles for the FHWA and showed that for flat bar grates,
such as the P-1-7/8-4 and P-1-1/8 grates, the clear opening equals the total area of the grate less
the area occupied by longitudinal and lateral bars. The curved vane grate performed about 10
percent better than a grate with a net opening equal to the total area less the area of the bars
projected on a horizontal plane. That is, the projected area of the bars in a curved vane grate is
68 percent of the total area of the grate leaving a net opening of 32 percent, however the grate
performed as a grate with a net opening of 35 percent. Tilt-bar grates were not tested, but
extrapolation of the testing results indicates a net opening area of 34 percent for the 30-degree
tilt-bar and zero for the 45-degree tilt-bar grate. However, the 45-degree tilt-bar grate has greater
than zero capacity. The tilt-bar angle and curved vanes enhance interception on grade. However,
because of the low opening ratio, tilt-bar and curved vane grates perform poorly in sump locations
under orifice flow conditions. Table 7.5 summarizes grate opening ratios.
107
Chapter 7 - Inlet Design HEC-22, 4th edition
Step 1. Determine the required grate perimeter without clogging for weir flow.
Depth at curb:
d2 = T Sx = (9.84) (0.05) = 0.49 ft
Average depth over grate:
d = d2 – (W/2) SW = 0.49 – (2.0/2) (0.05) = 0.44 ft
Using equation 7.14:
P = Qi / (Cw (2g)0.5 d1.5) = (6.71)/[(0.37) (64.4)0.5 (0.44)1.5] = 7.66 ft
Step 2. Determine the required grate perimeter with clogging for weir flow.
Assuming 50 percent clogging from the curb:
Peffective = 7.66 = L +(0.5) 2W = L + 0.5 (2) (2.0)
Solving for L = 5.66 ft
Select a double 2 ft by 3 ft grate.
Peffective = (0.5) (2) (2.0) + (6) = 8 ft
Step 3. Check depth of flow at curb for weir flow.
Using equation 7.14:
d = [Q/(Cw (2g)0.5 P)]0.67 [6.71/((0.37 (64.4)0.5 (8.0)]0.67 = 0.43 ft
Therefore, grate size meets spread requirements with clogging.
Step 4. Determine the required grate opening area without clogging for orifice flow.
Using equation 7.15:
Ag = Qi / [Co (2gd)0.5)] = (6.71)/[(0.67)(2(32.2)(0.44)0.5] = 2.15 ft2
Step 5. Determine the required grate opening area with clogging for orifice flow.
Assuming 50 percent clogging from the curb:
Ag effective = 2.15 = (L) (W) (opening ratio) (clogging) = L (2.0) (0.8) (0.5)
Solving for L = 2.67 ft
Select a single grate 2 ft by 3 ft.
Ag effective = (0.5) (2.0) (3.0) = 3 ft2
Step 6. Check depth of flow at curb for orifice flow.
Using equation 7.15:
d = [Qi/(CoAg)]2/(2g) = [6.71 / ((0.67) (3.0))]2/(2(32.16)) = 0.17 ft
Because this depth for orifice flow is less than the depth computed using the weir equation
(step 3), the weir equation is used for design and the orifice equation is disregarded.
108
HEC-22, 4th edition Chapter 7 - Inlet Design
Solution: A double 2 ft by 3 ft (0.61 m by 0.91 m) grate 50 percent clogged from the curb
is adequate to intercept the design storm flow and meet the design spread.
However, the tendency of grate inlets to clog completely warrants consideration
of a combination inlet or curb-opening inlet in a sag where ponding can occur,
and flanking inlets in long flat vertical curves.
Qi = Cw 2g L d1.5 (7.16)
where:
Cw = Weir coefficient (typically equal to 0.37)
L = Length of curb opening, ft (m)
d = Depth at curb, ft (m)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
For non-depressed inlets with a uniform gutter, the curb inlet operates as a weir for depths up to
the curb-opening height, h. The weir location for a curb-opening inlet that is not depressed is at
the lip of the curb opening and its length is equal to that of the inlet, as shown in Figure 7.16.
At a given flow rate, the effective water depth at the curb can be increased by using a continuously
depressed gutter, a locally depressed curb opening, or by increasing cross slope, thus decreasing
the width of spread at the inlet.
The weir location for a depressed curb-opening inlet is at the edge of the gutter, and the effective
weir length depends on the width of the depressed gutter and the length of the curb opening. The
interception capacity of a locally depressed curb-opening inlet operating as a weir is:
109
Chapter 7 - Inlet Design HEC-22, 4th edition
where:
Cw = Weir coefficient (typically equal to 0.29)
L = Length of curb opening, ft (m)
W = Lateral width of depression, ft (m)
d = Depth at the curb measured from the pavement cross-slope (Sx), ft (m)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
The weir coefficient for a curb-opening inlet is less than in equation 7.16 primarily because
experimental tests did not include depth measurements taken at the weir and drawdown occurs
between the point where measurements were made and the weir. The weir equation applies to
depths at the curb. For weir flow at a depressed curb inlet, the depth at the curb for equation 7.17
must be less than the curb-opening height:
di ≤ h = d + a (7.18)
where:
di = Depth at the curb with local depression, ft (m)
h = Curb-opening height, ft (m)
d = Depth at the curb measured from the pavement cross-slope (Sx), ft (m)
a = Depth of depression, ft (m)
Although laboratory experiments for FHWA did not include curb-opening inlets with a continuously
depressed gutter, the FHWA expects that the effective weir length described in equation 7.17
would be equaled or exceeded with a continuously depressed gutter. Therefore, equation 7.17
provides conservative estimates of the interception capacity in this situation.
For curb-opening lengths greater than 12 ft, equation 7.16 for non-depressed inlet produces
intercepted flows which exceed the values for depressed inlets computed using equation 7.17.
Since depressed inlets will perform at least as well as non-depressed inlets of the same length,
equation 7.16 is most accurate for all curb-opening inlets longer than 12 ft.
Curb-opening inlets operate as orifices at depths greater than approximately 1.4 times the
opening height. The interception capacity for depressed and undepressed curb-opening inlets
can be computed as:
Qi = Co A o ( 2 gdo )
0.5
(7.19)
where:
Co = Orifice coefficient, usually taken as 0.67
do = Effective head on the center of the orifice throat, ft (m)
Ao = Clear area of opening, ft2 (m2)
The effective head on the center of the orifice throat, d0, and the clear opening area, A0, are
computed based on the curb-opening configuration. Figure 7.17 illustrates a horizontal throat, an
inclined throat, and a vertical throat. The clear opening area is the length of the curb-opening inlet
times the height of the curb-opening inlet as represented in the figure. A limited throat width could
reduce the capacity of the curb-opening inlet by causing the inlet to go into orifice flow at depths
less than the height of the opening. Equation 7.19 applies to other configurations when the
designer appropriately selects the effective head and clear opening area.
110
HEC-22, 4th edition Chapter 7 - Inlet Design
111
Chapter 7 - Inlet Design HEC-22, 4th edition
h = 0.43 ft (0.13 m)
T = 8.2 ft (2.5 m)
Qi = Cw 2g L d1.5 (7.20)
where:
Cw = Weir coefficient
L = Length of slot, ft (m)
d = Depth at curb measured from the normal cross slope, m (ft)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
112
HEC-22, 4th edition Chapter 7 - Inlet Design
The weir coefficient for a slotted inlet varies with flow depth and slot length, but a typical value is
approximately 0.31.
The interception capacity of a slotted inlet operating as an orifice can be computed as:
Qi = Co L W ( 2 gd)
0.5
(7.21)
where:
W = Width of slot, ft (m)
Co = Orifice coefficient (typically equal to 0.8)
L = Length of slot, ft (m)
d = Depth of water at slot, ft (m)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
For depths in the transition between weir flow and orifice flow, designers compute interception
capacity using both the weir and orifice equations and use the lowest interception capacity (most
conservative) for design. Similarly, when estimating ponding depth from a given flow rate,
designers use both equations and use the highest depth for design.
Example 7.7: Slotted inlet in a sag.
Objective: Find the slotted inlet length to limit maximum depth at the inlet to 3.6 inches
assuming no clogging.
Given: A slotted inlet located along a curb:
W = 1.75 in (44.5 mm)
Q = 4.9 ft3/s (0.14 m3/s)
113
Chapter 7 - Inlet Design HEC-22, 4th edition
When the ponded depths are sufficiently high so that both the grate and the curb opening are
operating in orifice flow, the capacity of the combination inlet equals the sum of the two operating
independently using the orifice equations described in Section 7.3.1 and Section 7.3.2,
respectively. Under these conditions, a trial-and-error solution best finds the depth that satisfies
both orifice equations and totals to the design flow. In the transition between weir and orifice flow,
trial-and-error solutions are also used to find the depth associated with a given design flow.
Example 7.8: Combination inlet in a sag.
Objective: Find the depth at the curb and spread for a clog-free combination inlet and a
combination inlet with the grate 100 percent clogged.
Given: A combination inlet in a sag location with the following characteristics:
Q = 5.3 ft3/s (0.15 m3/s)
Sx = 0.03 ft/ft (m/m)
Curb-opening inlet:
L = 4 ft (1.22 m)
h = 3.9 inches (100 mm)
114
HEC-22, 4th edition Chapter 7 - Inlet Design
115
Chapter 7 - Inlet Design HEC-22, 4th edition
is rectangular in shape. In this case, the designer assumes the time of concentration is the same
for all inlets.
The following procedure and example illustrate the inlet spacing design process. Designers can
implement calculations in a spreadsheet or use automated drainage design software to achieve
the same goals. Regardless of the tools used, documentation of the process and results facilitates
independent review and future revisions if conditions or criteria change.
Step 1. Plan the design sequencing.
In this first step, the designer begins the documentation process and plans the design sequencing.
This step generally includes the following activities:
• Confirm the design criteria including the design frequency, allowable spread, and
maximum inlet spacing.
• Mark plans with the location of inlets which are necessary to satisfy geometric controls
such as the locations described in Section 7.4.1.
• Identify a high point to begin, at one end of the job, if possible, and progress toward the
low point. Then begin at the next high point and work backward toward the same low point.
• Select a trial drainage area and inlet location below the high point and outline the area on
the plan. Depending on the drainage area width, an initial trial might be approximately 300
to 500 ft long. Include any area that may drain over the curb and onto the roadway.
However, where practical, drainage from large areas behind the curb should be
intercepted before reaching the roadway or gutter.
Step 2. Calculate the gutter discharge.
In step 2, the designer estimates the drainage area to the trial inlet location and the design flow
in the gutter approaching the inlet. This step generally includes the following activities:
• Describe the locations of the proposed inlets by number and station.
• Compute the drainage area to the inlet.
• Determine the runoff coefficient, C, the time of concentration, tc, and rainfall intensity for
the inlet using the procedures from Chapter 4. Note the minimum time of concentration
applicable to the project.
• Calculate the design flow in the gutter using the Rational Method or other appropriate
method from Chapter 4.
Step 3. Estimate spread.
In step 3, the designer uses the gutter characteristics and the design flow to estimate the gutter
spread as the flow approaches the inlet. This step generally includes the following activities:
• From the roadway profile, determine the gutter longitudinal slope, SL, at the inlet,
considering any superelevation.
• From the cross-section, determine the cross slope, Sx, and the grate gutter width, W.
• Determine the total gutter flow approaching the inlet. The total flow is the flow computed
in step 2 plus any bypass flow from the inlet up-gradient. For the most up-gradient inlet in
a series, there is no bypass flow.
• Determine the spread, T, and depth at the curb using methods described in Chapter 5.
• Compare the spread with the allowable spread. Compare the depth at the curb with the
actual curb height. If the calculated spread is near the allowable spread and the depth at
116
HEC-22, 4th edition Chapter 7 - Inlet Design
the curb is less than the actual curb height, continue to step 4. Otherwise, move the inlet
to expand or decrease the drainage area to increase or decrease the spread, respectively.
The drainage area can be expanded by increasing the length to the inlet and it can be
decreased by decreasing the distance to the inlet. Then, repeat step 2 and step 3 until
appropriate values are obtained.
Step 4. Select inlet and compute interception.
The designer selects an inlet type and size and then computes the interception and bypass. This
step generally includes the following activities:
• Select the inlet type (grate, curb-opening, or combination) and dimensions.
• If using a grate or combination inlet, calculate W/T to initiate the computation of frontal
versus side flow.
• Calculate the flow intercepted by the inlet, Qi, using the tools in Section 7.2.
• Determine the bypass flow, Qb.
Step 5. Repeat process for the next inlet.
The designer repeats steps 2 through 4 for each subsequent inlet down-gradient until the low
point is reached. For long stretches at a constant gradient, a uniform spacing between inlets of a
single type and size is desirable.
For inlet spacing in areas with changing grades, the spacing will vary as the grade changes. If the
grade becomes flatter, inlets may be spaced at closer intervals because the spread will exceed
the allowable. Conversely, for an increase in slope, the inlet spacing will become longer because
of increased capacity in the gutter sections. Additionally, individual transportation agencies may
have limitations for spacing due to maintenance constraints.
Example 7.9: Inlet spacing on continuous grades.
Objective: Find the maximum design inlet spacing for a 2 ft by 3 ft (0.61 m by 0.91 m) P-1-
7/8-4 grate.
Given: The storm drainage system illustrated in Figure 7.18 with:
n = 0.016
Sx = 0.04 ft/ft (m/m)
SL = 0.03 ft/ft (m/m)
W = 2.0 ft (0.61 m)
h = 0.5 ft (0.15 m)) (curb height)
Design criteria:
Allowable spread = 6.6 ft (2.0 m)
Design storm = 0.1 AEP (10-year) event
Minimum time of concentration = 5 minutes
Maximum inlet spacing (for maintenance reasons) = 360 ft (110 m)
117
Chapter 7 - Inlet Design HEC-22, 4th edition
118
HEC-22, 4th edition Chapter 7 - Inlet Design
Estimate runoff coefficient, time of concentration, and rainfall intensity using the Rational
Method (Chapter 4).
Runoff coefficient, C = 0.73
Time of concentration, tc, = 1.7 min (use 5 min minimum)
Rainfall intensity from IDF curve: i = 7.1 in/h
Flow from the Rational Method:
Q = CIA/Ku = (0.73)(7.1)(0.35)/(1) = 1.81 ft3/s
Total flow to inlet # 41: Q = 0.93 + 1.81 = 2.74 ft3/s
T = 5.6 ft (T < T allowable)
d = (5.6) (0.4) = 0.22 ft (d < curb height)
Select P-1-7/8-4 grate 2 ft wide by 3 ft long.
Qi = 2.05 ft3/s
Qb = Q– Qi = 2.74– 2.05 = 0.69 ft3/s
Solution: For the conditions, the inlet spacing on this continuous grade is limited by the
maintenance limitation of 360 ft (110 m). The spread and depth are less than
the allowable spread and curb height.
Designers locate and size flanking inlets to receive the design flow when the primary inlet at the
bottom of the sag is clogged without exceeding the allowable spread. If the flanking inlets are the
same dimension as the primary inlet, they will each intercept one-half the design flow when they
are located so that the depth of ponding at the flanking inlets is 63 percent of the depth of ponding
at the low point. When flanking inlets differ from the primary inlet, the designer estimates ponding
120
HEC-22, 4th edition Chapter 7 - Inlet Design
depths based on inlet performance to determine the capacity of the flanking inlet at the desired
depths (AASHTO 2014).
The spacing required for the allowable depth at the curb in a vertical sag curve is:
X = ( 74 dK )
0.5
(7.22)
where:
X = Maximum distance from bottom of sag to flanking inlet, ft (m)
d = Depth of water over inlet in bottom of sag, ft (m)
K = Vertical curve constant, ft/percent (m/percent)
=K L / ( G2 − G1 ) (7.23)
where:
L = Horizontal length of the vertical curve, ft (m)
G1, G2 = Approach grades, percent
The AASHTO policy on geometrics specifies maximum K values for various design speeds and
a maximum 167 ft/percent (50 m/percent) considering drainage (AASHTO 2018). [See 23 CFR
625.3(b) and 625.4(a)].
Example 7.10: Flanking inlet spacing.
Objective: Determine the location of flanking inlets to function in relief of the inlet at the low
point.
Given: A sag vertical curve at an underpass on a 4-lane divided highway. The allowable
spread criterion is to stay within the shoulder width of 9.84 ft (3.0 m).
G1 = -2.5 percent
G2 = +2.5 percent
L = 500 ft (150 m)
Sx = 0.02 ft/ft (m/m)
121
Chapter 7 - Inlet Design HEC-22, 4th edition
122
HEC-22, 4th edition Chapter 7 - Inlet Design
Designers balance drainage requirements, safety, clogging potential, and erosion potential.
Where practical, continuous cross drainage structures across the median reduce clogging and
erosion potential compared with non-continuous cross drainage. Because ditches tend to erode
at drop inlets, paving around the inlets helps to prevent erosion and may increase the interception
capacity of the inlet marginally by acceleration of the flow.
At times, designers use culverts to collect stormwater from medians. These generally need more
water depth to intercept median flow than drop inlets. No test results are available on which to
base design procedures for estimating the effects of placing grates on culvert inlets, but little effect
is expected.
The interception capacity of drop inlets in median ditches on continuous grades depends on the
approach depth and velocity, as well as the inlet dimensions and type. Chapter 6 discusses flow
in median and roadside ditches and describes Manning’s equation for open channels:
where:
Q = Discharge rate, ft3/s (m3/s)
Ku = Unit conversion constant, 1.49 in CU (1.0 in SI)
n = Hydraulic resistance variable
A = Cross-sectional area of flow, ft2 (m2)
R = Hydraulic radius (flow area/wetted perimeter), ft, (m)
SL = Bed slope, ft/ft (m/m)
Interception capacity is based on the ratio of frontal flow to total flow in the median ditch. For a
trapezoidal channel, the frontal flow ratio is:
Eo W / ( B + d z )
= (7.25)
where:
Eo = Ratio of frontal to total flow
W = Inlet width, ft (m)
B = Bottom width of the trapezoidal channel, ft (m)
d = Flow depth in the channel, ft (m)
z = Channel side slope (1:z)
Placement of small berms down-gradient of drop inlets, as shown in Figure 7.20, increases
interception by impeding bypass flow. If not overtopped, the berm provides for complete
interception of the approach flow. In many cases, the berms are small (less than 6 inches high)
and have traffic-safe slopes. Berm height for complete interception on continuous grades or the
depth of ponding in sag vertical curves depends on the maximum ponding depth estimated for
weir flow in a sag (equation 7.14) or orifice flow in a sag (equation 7.15). In contrast to weir flow
at a grate against a curb, the effective perimeter of a grate in an open channel with a berm is 2(L
+ W) since one side of the grate is not adjacent to a curb and flow is captured from both sides.
See Section 7.3.1 for computing ponding depth in a sag.
Inlet interception for median and ditch inlets on grade depends on the capture of frontal and side
flow as described in Section 7.2.1 for grate inlets at a curb. For a ditch bottom that is approximately
equal to the inlet width, the ditch side slope is used to estimate side flow capture. For a ditch
bottom wider than the inlet width, the side slope is effectively zero. In this case, a low side slope,
123
Chapter 7 - Inlet Design HEC-22, 4th edition
such as 1 percent, is used to estimate side flow capture. Experience indicates that both
assumptions are conservative.
To avoid overtopping the berm because of the momentum of the water, designers add freeboard
to the berm height. The height of freeboard varies with the situation; 0.5 ft is often a good starting
point.
Example 7.11: Median ditch inlet.
Objective: Find the intercepted and bypassed flows at a 2 ft by 2 ft (0.61 m by 0.91 m)
median ditch inlet with a P-1-7/8 parallel bar grate. Determine the berm height
needed to provide 100 percent interception.
Given: A median ditch with the following characteristics:
B = 2.0 ft (0.61 m)
n = 0.03
z = 6
SL = 0.03 ft/ft (0.03 m/m)
Q = 9.9 ft3/s (0.28 m3/s)
124
HEC-22, 4th edition Chapter 7 - Inlet Design
Note: When the ditch is wider than the inlet, Sx is zero at the edge of the inlet in the bottom of
the median ditch. A flat slope, such as Sx = 0.01, can be used in the equation.
Step 5. Compute total efficiency.
E = Eo Rf + Rs (1 – Eo) = (0.40)(1.0) + (0.315)(1 - 0.40) = 0.59
Step 6. Compute interception and bypass flow.
Qi = E Q = (0.59)(9.9) = 5.8 ft3/s
Qb = Q - Qi = (9.9) - (5.8) = 4.1 ft3/s
Step 7. Estimate the height of a downstream berm for 100 percent interception.
Assuming the depth results in weir flow, calculate the perimeter, and use equation 7.14:
P = 2 (L+W) = 2 (2.0+ 2.0) = 8.0 ft
d = [Qi / (Cw P)]0.67 = [(9.9) / {(3.0)(8.0)}]0.67 = 0.55 ft
Solution: A P-1-7/8 inlet intercepts about 59 percent of the design flow for the given
conditions. To capture 100 percent of the flow, the anticipated ponding depth is
0.55 ft (0.17 m). The berm will be that height plus freeboard to prevent the
momentum of flow overtopping the berm.
125
Chapter 7 - Inlet Design HEC-22, 4th edition
Section 7.2.1 provides tools and approaches for designing embankment inlets on grade.
However, to prevent erosion caused by bypass flow, embankment inlets may necessitate higher
or near total interception efficiencies than many typical applications can achieve. Grate inlets
intercept little more than the flow conveyed by the gutter width occupied by the grate. Options to
increase interception include:
• Combination inlets with the length of curb opening upstream of the grate (sweeper
configuration) sufficient to reduce spread in the gutter to the width of the grate.
• Depressed curb openings.
• Extra width grate inlets with the width based on the design spread.
• Slotted inlets with a length based on the design spread.
126
HEC-22, 4th edition Chapter 8 - Storm Drain Structures
8.1.2 Location
Chapter 7 describes inlet spacing based on where they are needed to capture surface flow. Below
ground, designers locate inlet structures at the upstream end and at intermediate points along a
storm drain line. Designers generally use an iterative process to locate inlet structures to produce
an economical and hydraulically effective system.
127
Chapter 8 - Storm Drain Structures HEC-22, 4th edition
128
HEC-22, 4th edition Chapter 8 - Storm Drain Structures
In some cases, a smaller access shaft aligns concentrically with the bottom chamber. Figure 8.2a
displays a constant diameter bottom chamber up to a conical section a short distance below the
top. In other design configurations, the access shaft and bottom chamber align to provide a
vertical series of steps for easier access. Figure 8.2b illustrates a practice that uses an eccentric
cone for the access shaft.
Figure 8.2c shows an option that maintains the bottom chamber diameter to a height sufficient for
adequate working space. This design tapers to 3 ft for the access shaft. The frame rests on the
broad base of the access shaft. Because of the inward leaning angle of the steps in the access
shaft, designers typically limit these configurations to bottom chambers 3 ft in diameter or less.
Figure 8.2d illustrates a design that minimizes the access shaft height and features a removable
flat precast concrete slab that facilitates addressing more extensive maintenance needs.
Designers prefer these tangent alignments for access holes with bottom chamber diameters 4 ft
or greater.
The size of the bottom chamber limits the size of storm drain conduits that can connect to it. For
larger storm drain conduits that are not readily accommodated by typical access hole structure
configurations, designers could choose a vertical riser connected to the storm drain pipe with a
“tee” unit as illustrated in Figure 8.3.
The configurations in Figure 8.2 represent variations of channels and benching at the bottom of
the access hole. Many access holes do not include benching, which designers refer to as a “no
benching” configuration. Flow channels provide a smooth, continuous path for the flow, reducing
turbulence and, therefore, energy losses in the access hole. The bench elevates the bottom of
the access hole on either side of the flow channel further increasing the hydraulic efficiency of the
access hole. Because of the added cost associated with benching, designers use it when the HGL
is relatively flat and there is no appreciable head available. Chapter 9 discusses energy losses
and benching in greater detail.
Access hole frames and covers provide adequate strength to support superimposed loads,
provide a fit between cover and frame, facilitate opening while providing resistance to
unauthorized opening (especially from children), and prevent blowouts. To differentiate storm
drain access holes from other underground utility access such as for sanitary sewers and
communication conduits, good practice includes the words “STORM DRAIN” or equivalent cast
into the top surface of the covers. Blowouts may occur during a flood event when the HGL in the
access hole rises above the ground surface with sufficient pressure to move the cover from its
normal position on the frame. To prevent blowouts, designers can provide openings to release
surcharged flow or secure the cover in the frame with bolts or another type of locking mechanism.
Designers most commonly use pre-cast concrete and cast-in-place concrete when selecting
materials for access holes. In most areas, the availability and competitive cost of pre-cast
concrete access holes make them popular. They may include cast-in-place steps at the desired
locations and special transition sections to reduce the diameter of the access hole at the top to
accommodate the frame and cover. The transition sections are usually eccentric with one side
vertical to accommodate access steps.
129
Chapter 8 - Storm Drain Structures HEC-22, 4th edition
130
HEC-22, 4th edition Chapter 8 - Storm Drain Structures
131
Chapter 8 - Storm Drain Structures HEC-22, 4th edition
In addition, designers locate access holes at intermediate points along straight runs of storm drain
in accordance with applicable spacing criteria. Table 8.1 shows example spacing criteria, but
designers use the criteria from the jurisdiction within which they are working.
8.4.1 Transitions
In storm drainage systems, transitions from one pipe size to another typically occur in access
holes or junction chambers. Where maintenance access is not needed, designers use transitions
to avoid obstructions, to join different pipe sizes, and to join different conduit shapes. Figure 8.4
illustrates a transition where a rectangular pipe transition is used to avoid an obstruction. Figure
8.3 illustrates use of a transition upstream of tee type access holes.
Because abrupt transitions increase turbulence and energy loss, designers provide smooth,
gradual transitions to minimize head losses whenever feasible. For example, when the flow
velocity is less than 20 ft/s, designers typically use a 5:1 to 10:1 transition ratio for both expansion
and contraction in the straight wall configuration shown in Figure 8.4a. For higher velocities, more
gradual transition ratios of 10:1 to 20:1 reduce energy losses further.
132
HEC-22, 4th edition Chapter 8 - Storm Drain Structures
133
Chapter 8 - Storm Drain Structures HEC-22, 4th edition
barrels; however, the American Association of State Highway and Transportation Officials
(AASHTO)suggests a minimum of two barrels (AASHTO 2014). Multiple barrels allow one barrel
to operate for lower flows with additional barrels becoming active with higher flows. Regardless
of the number of barrels, the lowered section of the inverted siphon does not drain by gravity when
the flow stops, and the designer may wish to consider means for draining this section after each
storm.
Designers can avoid sediment deposits in the lowered section by designing for sufficiently high
velocities over a range of flows to flush any deposits. Designers can also facilitate flushing of
sediment deposits by limiting the slope of the rising portion of the lowered section to a maximum
of 15 percent or jurisdictionally specified value. Designers may include a sump in the inlet
chamber to collect sediment prior to entering the siphon.
To minimize energy losses, debris capture, and sedimentation, designers avoid sharp bends and
maintain a constant conduit section throughout the lowered section. Because inverted siphons
are generally not maintenance free, designers plan for cleaning and maintenance.
from entering the storm drain system. When rainstorms and high receiving water levels occur
simultaneously, the dominant hydrostatic force, combined with the weight of the flap gate,
determines whether the flap gate opens or closes. To avoid storm drain backups, the designer
considers the probability and consequences of the situation where the receiving water hydrostatic
force dominates and restricts discharge during a rainstorm.
Sediment, organic materials, and trash can impair the functioning of outlet conduits with flap gates
by reducing the conveyance of the conduit. The reduction of flow velocity behind a closed or
partially open flap gate may also cause sediment deposition in the storm drain near the outlet.
Organic materials and trash from the storm drain system or the receiving waters can collect
between the flap and seat preventing full closure of the flap gate. In addition, where a flap gate is
mounted on a pipe projecting into a stream, the designer considers how to protect the conduit
and flap gate from damage by woody material or ice during high flows. Flap gate installations
depend on regular inspection and removal of accumulated sediment, organic materials, and trash
to serve their intended function.
135
Chapter 8 - Storm Drain Structures HEC-22, 4th edition
136
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
137
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
rising and falling of discharge, flow in the conduit will go from zero, through open channel
conditions, to pressure flow, then back through open channel conditions. In actual performance,
only parts of a system may operate in pressure flow at any given time.
For decades, highway agencies have considered the relative merits of using open channel or
pressure flow to control design. For a given flow rate, open channel flow designs involve larger
conduit sizes than do pressure flow designs. While the materials may cost more for storm
drainage systems based on open channel flow, this approach provides a margin of safety by
adding capacity in the conduit to accommodate larger discharges than the design discharge.
Designers often want to include this margin of safety given the inexact nature of runoff estimation
methods and the technical and financial difficulty of replacing existing storm drains. When
designers add the costs of excavation, trench protection, pipe bedding, trench backfill,
compaction, and other associated storm drain construction expenses, they typically find only
minor cost savings from using the smaller conduit allowed by design for pressure flow. The most
expensive decision designers make regarding storm drains is choosing to install them at all.
Having made that decision, designers will wish to maximize associated benefits.
However, some situations may call for pressure flow design. For example, designers may choose
to use an existing system that only accommodates the increased flow rates when placed under
pressure flow. In such instances, the designer may make a hydraulic and economic analysis of a
storm drain using both design methods before final selection.
Most ordinary conditions call for sizing storm drains based on open channel flow at or less than
flow full. Designing for full flow is a conservative assumption since the peak flow capacity actually
occurs at 93 percent of the full flow depth of a circular pipe. When using pressure flow, designers
will want to ensure the joints can withstand the pressure to avoid exfiltration. However, the
pressures encountered are usually moderate.
K 2.67 0.5
Q= Q D So (9.2)
n
where:
V = Mean velocity, ft/s (m/s)
Q = Rate of flow, ft3/s (m3/s)
KV = Unit conversion constant, 0.59 in CU (0.397 in SI)
KQ = Unit conversion constant, 0.46 in CU (0.312 in SI)
n = Manning’s roughness coefficient
D = Storm drain diameter, ft (m)
So = Slope of the energy grade line, ft/ft (m/m)
Table 9.1 provides representative values of the Manning’s roughness coefficient for various storm
drain materials. Figure 9.1 illustrates storm drain conduit capacity sensitivity to the parameters in
138
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
Manning’s equation. For example, doubling the diameter of a circular storm drain conduit
increases its capacity by a factor of 6.35; doubling the slope increases capacity by a factor of 1.4;
but doubling the roughness reduces pipe capacity by 50 percent.
139
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
Roughness or
Type of Culvert Corrugation Manning’s n *
Concrete Pipe Smooth 0.010-0.011
Concrete Boxes Smooth 0.012-0.015
Spiral Rip Metal Pipe Smooth 0.012-0.013
2-2/3 by 1/2 inch
(annular) 0.022-0.027
The shape of a storm drain conduit also influences its capacity. Designers most commonly use
circular storm drain conduits; using an alternate shape sometimes increases capacity. Table 9.2
lists the increase in capacity obtained by using alternate conduit shapes with the same height as
the original circular shape but with a different cross-sectional area. Although these alternate
shapes generally cost more than circular shapes, specific project area conditions sometimes
warrant their use. For example, limited headroom (vertical clearance) may warrant use of elliptical,
pipe-arch, and box shapes. Standard practice orients elliptical and box shapes with the longer
dimension horizontal. In case of limited horizontal clearance, orienting elliptical pipe vertically may
enhance performance over circular pipe.
Some shapes are not available from suppliers in all locations. Designers may wish to consult
industry suppliers in their State before specifying a particular shape to ensure its availability for
their project. Commonly, either pipe-arch or elliptical shapes are available, but not both.
140
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
Table 9.2. Increase in capacity of alternate shapes based on a circular pipe with the same
height.
Area Conveyance
Shape (Percent Increase) (Percent Increase)
Circular -- --
Oval 63 87
Arch 57 78
Box (B = D) 27 27
141
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
142
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
downstream direction relative to the receiving stream. This will reduce turbulence and the
potential for excessive erosion. If designers cannot orient the outfall structure in a downstream
direction, they will want to consider the potential for outlet scour. For example, where a storm
drain outfall discharges perpendicular to the direction of flow of the receiving channel, erosion
may occur on the opposite channel bank. If erosion potential exists, designers may consider a
channel bank lining of riprap or other suitable material on the bank. Alternatively, they could use
an energy dissipator structure at the storm drain outlet.
hf = S f L (9.3)
where:
hf = Friction loss, ft (m)
Sf = Friction slope, ft/ft (m/m)
L = Length of pipe, ft (m)
The friction slope is also the slope of the hydraulic gradient for a particular pipe run. Assuming
steady uniform flow (see Section 9.1.1), the friction slope is the same as the pipe slope for partially
full flow. Pipe friction loss for full flow in a circular pipe is:
2
hf Qn
Sf =
= 2.67
(9.4)
L K QD
where:
KQ = Unit conversion constant, 0.46 in CU (0.312 in SI)
V2 V2
=H0 1.0 o − d (9.5)
2g 2g
where:
Vo = Average outlet velocity
Vd = Channel velocity downstream of outlet in the direction of the pipe flow
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
144
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
Note that when Vd = 0, as in a reservoir, the exit loss equals one velocity head. For part full flow
where the pipe outlets in a channel with water moving in the same direction as the outlet water,
consider the exit loss as virtually zero.
V2
=Hb 0.0033( ∆ ) (9.6)
2g
where:
∆ = Angle of bend, degrees
Designers can express energy losses in expansions or contractions in open channel flow in terms
of the kinetic energy at the two ends:
V 22 V 12
=He K e − (9.7)
2g 2g
where:
Ke = Expansion coefficient
V1 = Velocity upstream of transition, ft/s (m/s)
V2 = Velocity downstream of transition, ft/s (m/s)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
145
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
V2 V2
=Hc K c 2 − 1 (9.8)
2g 2g
where:
Kc = Contraction coefficient
V1 = Velocity upstream of transition, ft/s (m/s)
V2 = Velocity downstream of transition, ft/s (m/s)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
Table 9.3. Typical values for Ke for gradual enlargement of pipes in open channel flow.
Angle of Cone
D2/D1 10° 20° 45° 60° 90° 120° 180°
1.5 0.17 0.40 1.06 1.21 1.14 1.07 1.00
3 0.17 0.40 .86 1.02 1.06 1.04 1.00
where:
Hj = Junction loss, ft (m)
Qo = Outlet flow, ft3/s (m3/s)
Qi = Inlet flow, ft3/s (m3/s)
Ql = Lateral flow, ft3/s (m3/s)
146
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
9.1.6.6 Approximate Method for Inlet and Access Hole Energy Loss
Estimating inlet and access hole energy losses at the junction between inflow and outflow pipes
presents more complexity than estimating junction losses. The Approximate Method is the
simplest and appropriate only for preliminary design estimates. The method recognizes that initial
layout of a storm drain system begins at its upstream end. The designer estimates sizes and
establishes preliminary elevations as the design progresses downstream. The Approximate
Method estimates losses across an access hole by multiplying the velocity head of the outflow
pipe by a coefficient:
Vo2
Hah = K ah (9.10)
2g
147
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
where:
Hah = Head loss across an access hole, ft (m)
Kah = Head loss coefficient
Vo = Outlet pipe velocity, ft/s (m/s)
Table 9.4 presents applicable coefficients (Kah) and Figure 9.5 describes the angle of connection
for the coefficients. With the estimated head loss, the designer estimates the initial pipe crown
drop across an access hole (or inlet) structure to offset energy losses at the structure. The
designer then uses the crown drop to establish the appropriate pipe invert elevations.
However, access hole and inlet energy losses are more complex than a simple proportional
relationship to outlet velocity head and interior angle. Therefore, this represents a preliminary
estimate only and does not apply to EGL calculations.
148
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
• Limited representation of very different hydraulic conditions within access holes when
using or developing a single coefficient multiplied by an outlet velocity head.
• Difficulties producing reasonable results on some surcharged systems and systems with
supercritical flows leaving the access hole.
• Under-prediction of calculated versus observed access hole flow depths.
• Dependence on relatively complex iterative methods.
• Development of problematic solutions in some situations resulting from limitations in these
methods.
To address these issues, the FHWA developed a more comprehensive method for estimating
losses in access holes and inlets. The resulting approach classifies access holes and their
hydraulic conditions in a manner analogous to inlet control and full flow for culverts (Kilgore 2005,
Kilgore 2006, Kerenyi et al. 2006). The method then applies equations in appropriate forms for
the given classification. In addition to avoiding the limitations described above, this method has
the following benefits:
• Uses hydraulically sound fundamentals for key computations (inlet control and full flow
analogies) as a foundation for extrapolating the method beyond laboratory data.
• Incorporates an approach to handling surcharged systems with the full flow component of
the method.
• Avoids problems associated with supercritical flows in outlet pipe by using a culvert inlet
control analogy.
• Provides equivalent or better performance in predicting access hole water depth and
inflow EGL on the extensive FHWA laboratory dataset.
• Presents a direct (non-iterative), simple, and manually verifiable computational procedure.
The method includes three fundamental activities (with terms described in Figure 9.6):
• Determines an initial access hole energy level (Eai) based on inlet control (weir and orifice)
or outlet control (partially full and full flow) equations.
• Adjusts the initial access hole energy level based on benching, inflow angle(s), and
plunging flows to compute the final calculated energy level (Ea).
• Calculates the exit loss from each inflow pipe and estimating the energy grade line (EGLo),
which will then be used to continue calculations upstream.
149
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
150
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
Seeking to obtain values for other elements of total outflow pipe energy head (Ei), such as outflow
pipe depth (potential head) and pressure head, may exacerbate this issue. Consider Ei as the
sum of the potential, pressure, and velocity head components:
P V2
Ei =+
y + (9.11)
γ 2g
where:
Ei = Outflow pipe energy head, ft (m)
y = Outflow pipe depth (potential head), ft (m)
(P / γ) = Outflow pipe pressure head, ft (m)
(V2 / 2g) = Outflow pipe velocity head, ft (m)
Solving for equation 9.11 may cause a problem for certain conditions (e.g., where P cannot be
assumed to equal atmospheric pressure). Designers can also determine Ei by subtracting the
outflow pipe invert elevation (Zi) from the outflow pipe energy grade line (EGLi) (both known
values) at that location:
Ei EGLi − Zi
= (9.12)
Knowing Ei serves as a check on the method. In circumstances with very low flow, the
computations may result in access hole energy levels less than the outflow pipe energy head. In
such cases, the designer sets the access energy level equal to the outflow pipe energy head.
To determine the initial estimate of the access hole energy level, the designer takes the maximum
of the three values:
where:
Eaio = Estimated access hole energy level for outlet control (full and partially full flow),
ft (m)
Eais = Estimated access hole energy level for inlet control (submerged), ft (m)
Eaiu = Estimated access hole energy level for inlet control (unsubmerged), ft (m)
In the outlet control condition, the downstream storm drain system limits discharge out of the
access hole such that the outflow pipe either flows full or partially full in subcritical flow. The initial
structure energy level (Eaio) estimate is:
Eaio= Ei + Hi (9.14)
where:
Hi = Entrance loss assuming outlet control, calculated using equation 9.16, ft (m)
V2
Hi = K i (9.15)
2g
where:
Ki = Entrance loss coefficient = 0.2 (Kerenyi et al. 2006)
151
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
As described earlier, using the concept of outflow pipe energy head (Ei) and equation 9.13 allows
the designer to estimate energy level directly without considering the water surface within the
access hole. Defining a one-dimensional velocity head in a location with highly turbulent multi-
directional flow presents a challenge.
Inlet control calculations employ a dimensionless ratio (the discharge intensity) adapted from the
analysis of culverts. The discharge intensity (DI) parameter, or the ratio of discharge to pipe
dimensions, describes the discharge intensity:
Q
DI = (9.16)
A(gDo )0.5
where:
A = Area of outflow pipe, ft2 (m2)
Do = Diameter of outflow pipe, ft (m)
The submerged inlet control condition uses an orifice analogy to estimate the energy level
(Eais). Researchers derived the equation using data with discharge intensities less than or equal
to 1.6 resulting in:
Laboratory analyses (Kilgore 2005, Kilgore 2006) revealed that unsubmerged inlet control
conditions involve DIs in a 0.0 to 0.5 range (though the equation is not limited to this range). The
unsubmerged inlet control condition uses a weir analogy to estimate the energy level (Eaiu):
Ea = Eai + HB + Hθ + HP (9.19)
where:
HB = Additional energy loss for benching (floor configuration), ft (m)
Hθ = Additional energy loss for angled inflows other than 180 degrees, ft (m)
HP = Additional energy loss for plunging flows, ft (m)
Ea represents the level of the EGL in the access hole. However, if calculations result in an Ea less
than the outflow pipe energy head (Ei), then set Ea equal to Ei.
152
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
Designers may also wish to know the water depth in the access hole (ya). A conservative approach
would use Ea as ya for design purposes.
Benching tends to direct flow through the access hole, resulting in a reduction in energy losses.
Figure 9.7 illustrates some typical bench configurations. Generally, from Figure 9.7 (a) to (e), the
energy losses tend to decrease.
For access hole benching, the additional benching energy loss is:
HB CB (Eai − Ei )
= (9.20)
where:
CB = Energy loss coefficient for benching.
Table 9.5 summarizes benching coefficients. A negative value indicates water depth will be
reduced rather than increased.
153
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
Floor
Configuration Bench Submerged * Bench Unsubmerged *
Flat (level) -0.05 -0.05
Depressed 0.0 0.0
Half Benched -0.05 -0.85
Full Benched -0.25 -0.93
Improved -0.60 -0.98
*A bench submerged condition has the properties of (Eai/Do)>2.5 and
bench unsubmerged condition has the properties of (Eai/Do)<1.0. Use
linear interpolation between the two values for intermediate values.
Address the effect of skewed inflows entering the structure by considering momentum vectors.
To maintain simplicity, the contribution of all inflows contributing to structure and with a hydraulic
connection (i.e., not plunging) resolves into a single flow weighted angle (θw):
Σ(Q j θ j )
θw = (9.21)
ΣQ j
where:
QJ = Contributing flow from inflow pipe, ft3/s (m3/s)
θJ = Angle measured from the outlet pipe (180 degrees is a straight pipe)
Figure 9.8 illustrates the orientation of the pipe inflow angle measurement. The angle for each of
the non-plunging inflow pipes references to the outlet pipe, so that the angle is not greater than
180 degrees. A straight pipe angle is 180 degrees. The summation only includes non-plunging
flows as indicated by the subscript j. If all flows are plunging, set θw to 180 degrees.
Then, calculate an angled inflow coefficient (Cθ) as follows:
ΣQ j θ
Cθ = 4.5 cos w (9.22)
Q0 2
where:
Qo = Flow in outflow pipe, ft3/s (m3/s)
The angled inflow coefficient approaches zero as θw approaches 180 degrees and as the relative
inflow approaches zero. The additional angle inflow energy loss is:
Hθ Cθ (Eai − Ei )
= (9.23)
Plunging inflow describes inflow (pipe or inlet) where the invert of the pipe (zk) is greater than
the estimated structure water depth (approximated by Eai). The value of zk represents the
difference between the access hole invert elevation and the inflow pipe invert elevation.
154
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
The method determines a relative plunge height (hk) for a plunging pipe (denoted by the subscript
k) as:
(zk − Eai )
hk = (9.24)
Do
This relative plunge height allows determination of the plunging flow coefficient (CP):
Σ(Qk hk )
CP = (9.25)
Qo
155
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
As the proportion of plunging flows approaches zero, CP also approaches zero. Equations 9.24
and 9.25 only apply to conditions where zk < 10Do. If zk > 10Do set it to 10Do.
The additional plunging inflow energy loss is given by:
HP CP (Eai − Ei )
= (9.26)
The method allows determination of the incremental benching (HB), inflow angle (Hθ), and
plunging energy (HP) terms. However, incremental losses can be small, possibly even small
enough to be “lost in the rounding.” Alternatively, compute Ha by algebraically rearranging the
benching, inflow angle, and plunging equations to yield:
Note that the value of Ha should always be positive. If the calculation yields a negative value, the
designer sets Ha equal to zero. The revised access hole energy level is:
E=
a Eai + Ha (9.28)
If the computed estimate of Ea is less than the outlet pipe energy (Ei), use the higher of the two
values for Ea.
Knowing the access hole energy level (Ea) and assuming the access hole invert (za) has the same
elevation as the outflow pipe invert (zi) allows determination of the access hole energy grade line
(EGLa):
EGL=
a Ea + Z a (9.29)
The potentially highly turbulent nature of flow within the access hole makes determination of water
depth problematic. However, designers can reasonably use EGLa as a comparison elevation to
check for potential surcharging of the system. Research has shown the difficulty of determining
velocity head within the access hole, even in controlled laboratory conditions (Kerenyi et al. 2006).
EGL=
o Ea + Ho (9.30)
where:
EGLo = Inflow pipe energy head, ft (m)
Ea = Revised access hole energy grade line, ft (m)
Ho = Inflow pipe exit loss, ft (m)
The subscript “o” is used for the inlet pipe because the equation represents losses at the outlet
end of the inlet pipe. Calculate exit loss in the traditional manner using the inflow pipe velocity
head since a condition of supercritical flow is not a concern on the inflow pipe. The equation is:
156
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
V2
Ho = K o (9.31)
2g
where:
Ko = Exit loss coefficient = 0.4, dimensionless (Kerenyi et al. 2006)
Water discharging from plunging inflow pipes freely falls into the access hole. For plunging
pipes, take the inflow pipe energy grade line (EGLo) as the energy grade line calculated from the
inflow pipe hydraulics. In this case, EGLo does not depend on access hole water depth and losses.
Determining the EGL for the outlet of a pipe has already been described in Section 9.1.5.
For both the non-plunging and plunging cases, use the resulting EGL to continue computations
upstream to the next access hole. At each access hole, repeat the three-step procedure of
estimating: 1) entrance losses from entering the outlet pipe; 2) additional benching, angled inflow,
and plunging losses within the access hole, and 3) exit losses leaving the inlet pipe and entering
the access hole.
157
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
Maximum high water describes the allowable elevation of the water surface (HGL) during the
design storm at any given point within a storm drain system including inlets, access holes, or other
connections to the ground surface. Before initiating hydraulic evaluation, designers establish the
maximum high water at any point to avoid impairment of the intended function of these locations
and surface flooding.
158
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
For the second calculation, the designer estimates the portion of the area relevant to the shorter
time of concentration using:
t c1
Ac = A (9.32)
tc 2
where:
Ac = Part of the larger primary area that will contribute to the discharge during the
time of concentration associated with the smaller, less pervious area, ac (ha)
A = Area of the larger primary area, ac (ha)
tc1 = Time of concentration of the smaller, less pervious, area, min
tc2 = Time of concentration associated with the larger primary area as is used in the
first calculation, min
The second calculation uses the weighted C value that results from combining C values of the
smaller less pervious tributary area and the area Ac.
where:
Ku = Unit conversion constant, 2.87 in CU (6.35 in SI)
D = Diameter, ft (m)
159
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
9.2.5 Maintenance
Design, construction, and maintenance closely relate to each other. Storm drain maintenance
represents a critical consideration during both design and construction. Common maintenance
160
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
problems associated with storm drains include debris accumulation, sedimentation, erosion,
scour, piping, roadway and embankment settlement, and conduit structural damage.
Debris and sediment frequently accumulate in storm drains, particularly during construction.
Designs for a minimum full flow velocity as discussed in Section 9.2.3 reduce the likelihood of
sedimentation. Providing access hole spacing in accordance with the criteria presented in Chapter
8 ensures adequate access for cleaning.
DOTs also frequently report the maintenance issue of scour at storm drain outlets. Riprap aprons
or energy dissipators at storm drain outlets can minimize scour.
Following appropriate design and installation specifications avoids piping, roadway and
embankment settlement, and conduit structural failure. These problems, when they occur, usually
relate to poor construction. Tight specifications along with thorough construction inspections can
help reduce these problems.
Even in a properly designed and constructed storm drainage system, proper functioning depends
on a comprehensive program for storm drain maintenance. Regular inspections detail long-term
changes and will indicate appropriate maintenance to ensure safe and continued operation of the
system. An appropriate maintenance program includes both periodic inspections and
supplemental inspections following storm events. Since storm drains exist almost entirely
underground, inspection of the system is more difficult than surface facilities. The Culvert
Inspection Manual (FHWA 1986) provides information for inspecting storm drains or culverts.
161
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
162
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
EGL computations begin at the outfall and are worked upstream taking each junction into
consideration. Many storm drain systems are designed to function in a subcritical flow regime. In
subcritical flow, pipe and access hole losses are summed to determine the upstream EGL levels.
If supercritical flow occurs, pipe and access losses are not carried upstream. When a storm drain
section is identified as being supercritical, the designer advances to the next upstream pipe
section to determine its flow regime. This process continues until the storm drain system returns
to a subcritical flow regime. The steps continue from the preliminary design in Section 9.3 with
step 4.
Step 4. Determine the tailwater elevation at the storm drain outfall.
The designer estimates the water surface elevation at the discharge point of the storm drain
system. This may be at a larger body of water such as a pond, lake, or tidally influenced receiving
point. In these cases, the receiving water is assumed to have no velocity. The tailwater elevation
may also be determined by a stream or the critical depth in the discharge pipe if the receiving
elevation is lower than the pipe invert elevation. Estimating the tailwater elevation may involve
coincident flow calculations, tidal condition assumptions, reservoir/detention pond routing
assumptions, or other, unrelated calculations.
Estimate critical depth in the conduit for the design discharge and calculate the elevation of critical
depth at the outfall. If the water surface elevation in the receiving water is below that elevation,
critical depth will dominate outfall conditions. If it is above critical depth, the receiving water will
exert some influence on the energy state at the outfall.
163
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
From the initial elevation and the corresponding area of flow and discharge, compute the total
energy at the outfall. The HGL elevation is the initial elevation, the EGL is that, plus the energy
head.
Step 5. Estimate the HGL and EGL at the downstream end of the next pipe.
Beginning with the outfall pipe, estimate the HGL and EGL at the downstream end of the pipe,
but just inside the pipe. The designer determines this from the tailwater elevation, physical pipe
characteristics and design flow. This step is repeated for each pipe in the storm drain system. For
subsequent pipes the designer uses the energy state in the downstream structure as the tailwater
condition.
The designer estimates the EGL at the downstream end based on one of the conditions
comparing the pipe with the downstream EGL shown in Table 9.6. All cases apply for mildly sloped
pipes. Cases A and E also apply to steep pipes. For the outfall pipe discharging to a receiving
water, the tailwater elevation is substituted for EGLa.
Step 6. Estimate the HGL and EGL at the upstream end of the outfall pipe.
Compute the elevation of the HGL at the upstream end of the conduit run (next structure
upstream). The HGL is the depth of flow in the conduit plus change in elevation of the conduit
(slope times length).
Table 9.7 summarizes potential flow conditions within the conduit that determine calculation of
the upstream pipe end EGL and HGL. For conditions A, B, and C, the HGL and EGL are computed
using pipe friction and minor losses. For condition D, the designer computes the velocity head at
normal depth. Added to the HGL elevation, that is the EGL elevation at the upper end of the
conduit.
C BOCi +yn ≥ HGLi > BOCi +yc Subcritical partial flow conditions
D BOCi +yc ≥ HGLi Supercritical partial flow conditions
164
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
165
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
Step 1. Prepare a working plan for the layout and profile of the storm drain system.
Figure 9.10 illustrates the proposed system layout including location of storm drains, access
holes, and other structures. All structures have been numbered for reference.
Step 2. Determine the hydrologic parameters for each inlet.
Table 9.9 provides the drainage area information to compute the inlet design flows. Use the
Rational Method to compute inlet design flows.
166
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
167
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
168
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
V = 8.7 ft/s
Travel time = 0.6 min, use 1 min
Estimate crown drop using equation 9.10, loss coefficient from Table 9.4 equal to 0.5 for an
inlet – straight run:
Hah = (Kah)(V2 / 2g) = (0.5)(8.72 / 64.4) = 0.6 ft
Calculate the upstream invert:
Zu/s = 354.67 – 0.6 = 354.07 ft
Calculate the downstream invert:
Zd/s = Zu/s – (S0)( L) = 354.07 – (0.03)(328) = 344.23 ft
Step 3c. Size and locate the next pipe (pipe 42 – 43).
Estimate the design flow for pipe connecting structures 42 and 43 considering all upstream
contributing areas. From Table 9.9:
A = 0.64 + 0.35 + 0.32 = 1.31 ac
C = 0.73
Inlet time of concentration = 2 min
System time of concentration = 3 + 1 + 1 = 5 min (use minimum time of 5 min)
From Table 9.8:
I = 7.1 in/h
Q = CIA = (0.73)(7.1)(1.31) = 6.75 ft3/s
D = 1.96 ft = use 2.0 ft
V = 2.6 ft/s
Travel time = 0.09 min, use 0 min
Estimate crown drop using equation 9.10, loss coefficient from Table 9.4 equal to 1.5 for inlet –
90° angle:
Hah = (Kah)(V2 / 2g) = (1.5)(2.62 / 64.4) = 0.16 ft
Calculate the upstream invert:
Zu/s = 344.23 – 0.16 = 344.07 ft
Calculate the downstream invert:
Zd/s = Zu/s – (S0)(L) = 344.07 – (0.001)(14) = 344.06 ft
Step 3d. Size and locate the next pipe (pipe 43-44).
Q = 6.75 ft3/s (no additional CA accumulated and no addition to the system time of
concentration)
D = 1.27 ft = use 2.0 ft (to prevent possible clogging, do not reduce conduit size)
V = 6.1 ft/s
Travel time = 0.15 min, use 0 min
Hah = (Kah)(V2 / 2g) = (1.5)(6.12 / 64.4) = 0.87 ft
170
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
Since this is the downstream most pipe, set the downstream invert:
Zd/s =330.71 ft (outfall elevation for the pipe)
Calculate the upstream invert:
Zu/s = Zd/s + (S0)(L) = 330.71 + (0.01)(55.8) = 331.27 ft
This invert results in a crown drop = 344.06 – 331.27 = 12.79 ft (which is greater than 0.87 ft)
Figure 9.11 summarizes the preliminary pipe lengths, diameters, and inverts for the example.
Step 4. Determine the tailwater elevation at the storm drain outfall.
For the EGL and HGL computations, start at the downstream end at the outfall (structure 44).
Computations proceed in the upstream direction. From Figure 9.11:
HGLTW = downstream pool water surface elevation = 333.5 ft
EGLTW = 333.5 ft (assume no velocity head in the pool)
Step 5. Estimate the HGL and EGL at the downstream end of pipe 43-44 (the outfall pipe).
BOCo = 330.71 ft
TOCo = 330.71 + 2.0 ft = 332.71 ft
Determine the applicable case from Table 9.6:
Is the downstream end of the pipe submerged (EGLTW > TOCo)?
333.5 ft > 332.71 ft is true. Pipe is submerged (case A). Use full pipe flow.
Estimate the energy loss exiting the outfall pipe:
V = Q / A = 6.75 ft3/s / 3.14 ft2 (area of a 2 ft diameter circle) = 2.15 ft/s
V2 / 2g = (2.152) (64.4) =0.07 ft
Exit loss for an outfall:
Ho = (1.0)V2/2g = (1.0) (0.07) = 0.07 ft
EGLo = TW + Ho = 333.5 ft + 0.07 ft = 333.57 ft
HGLo = EGLo – V2/2g = 333.57 ft – 0.07 ft = 335.50 ft
Step 6. Estimate the HGL and EGL at the upstream end of pipe 43-44.
At structure 43 for the pipe from structure 43 to 44 (pipe 43-44):
Pipe length, L = 55.8 ft
BOCi = 331.27 ft
TOCi = BOCi + D = 331.27 ft + 2.0 ft = 333.27 ft
Sf = [(Qn)/(KQD2.67)]2 = [(6.75)(0.013)/(0.46)(2.0)2.67] 2 = 0.00090 ft/ft
Hf = Sf L = (0.00090) (55.8) = 0.05 ft
No other losses in conduit: Hb, Hc, He, Hj = 0.0
EGLi = EGLo + pipe loss = 333.57 ft + 0.05 ft = 333.62 ft
HGLi = EGLi - V2/2g = 333.62 ft - 0.07 ft = 333.55 ft
Ei = EGLi – BOCi = 333.62 ft – 331.27 ft = 2.35 ft
171
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
Determine the flow condition at the upstream end of the outflow pipe from Table 9.7:
HGLi (333.55 ft) > TOCi (333.27 ft), therefore, pipe is flowing full (surcharge) (condition A), and
losses are carried upstream as computed.
Step 7. Calculate EGL and HGL at structure 43.
Eai = max(Eaio, Eais, Eaiu)
Compute Eaio using equations 9.14 and 9.15:
Hi = (Ko)(Vo2/2g) = (0.2)(0.07) = 0.014 ft
Eaio = Ei + Hi = 2.35 ft + 0.014 ft = 2.364 ft
Discharge intensity for outflow pipe (pipe 43-44):
DI = Q / [A(Dg)0.5] = 6.75 / [((π/4)(2.0)2)((2.0)(32.2))0.5] = 0.268
Compute Eais using equation 9.17:
Eais = (1.0)(DI) 2 (D) = (0.268) 2 (2.0) = 0.14 ft
Compute Eaiu using equation 9.18:
Eaiu = (1.6)(DI) 0.67 (D) = 1.6(0.268) 0.67 (2.0) = 1.32 ft
Select maximum (to two decimal places): Eai = 2.36 ft
Compute Ea:
For benching:
CB = -0.05, Eai / D < 1, therefore, assume flat bench, unsubmerged access hole
For angled inflow:
Cθ = 0.0 because the flow is plunging and θw = 180 even though there is a 45-degree bend
For plunging flow:
zk = 334.06 ft - 331.27 ft = 12.79 ft
hk = (zk - Eai ) / Do = (12.79 – 2.29)/(2.0) = 5.25
Cp = (Σ(Qk hk))/Qo = ((6.75)(5.25))/(6.75) = 5.25 (only one inflow)
Check to ensure net energy. Is Eai > Ei ? Since 2.36 > 2.35 OK
Ha = (Eai - Ei)(CB + Cθ + CP) = (2.36 – 2.35)(-0.05 + 0.0 + 5.25) = 0.05 ft (greater than 0)
Ea = Eai + Ha = 2.36 ft + 0.05 ft = 2.41 ft
EGLa = Ea + BOCi = 2.41 ft + 331.27 ft = 333.68 ft
Ground elevation = 347.76 ft. Since 347.76 ft > 333.68 ft HGL is OK
Step 8. Repeat steps 5, 6, and 7 for all pipes and structures in the storm drain system.
Continue upstream with all pipes entering the structure analyzed in the previous step. In this
example, only one pipe enters structure 43. Go to step 5 for this pipe.
Step 5 (for next pipe). Estimate the HGL and EGL at the downstream end of pipe 42-43.
One pipe enters structure 43 from structure 42 (pipe 42-43):
D = 2.0 ft
172
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
Q = 6.75 ft3/s
L = 14.1 ft
BOCo = 344.06 ft
TOCo = BOCo + D = 344.06 ft + 2.0 ft = 346.06 ft
Determine the applicable case from Table 9.6:
Is the downstream end of the pipe submerged (EGLa > TOCo)?
EGLa (333.68 ft) > TOCo (346.06 ft) is not true. Pipe outlet is not submerged (case A).
Is the pipe plunging (EGLa < BOCo)?
EGLa (333.68 ft) < BOCo (344.06 ft) is true. Pipe is not plunging (case E)
V = 2.6 ft/s (part full flow)
Q/Qf = 6.75 / 7.12 = 0.95
yn = 1.56 ft
V2/2g = (2.6)2/(2)(32.2)= 0.10 ft
yc = 0.80 ft
Ho = 0.0
EGLo = (BOCo + yn) + V2/2g = 344.06 ft + 1.56 ft + 0.10 ft = 345.72 ft
HGLo = EGLo – V2/2g = 345.72 – 0.10 = 345.62 ft
Step 6. Estimate the HGL and EGL at the upstream end of pipe 42-43.
BOCi = 344.07 ft
TOCi = BOCi + D = 344.07 ft + 2.0 ft = 346.07 ft
Pipe not full, so Sf = pipe slope. However, recall that the D/S conduit invert was dropped 2-3
inches, changing the original design slope.
Sf = (344.07 - 344.06) / 14.1 = 0.0007 ft/ft
Hf = Sf L = (0.0007)(14.1) = 0.01 ft
No other losses in conduit: Hb, Hc, He, Hj = 0
Total pipe loss = 0.01 ft
EGLi = EGLo + total pipe loss = 345.72 ft + 0.01 ft = 345.73 ft
HGLi = EGLi - V2/2g = 345.73 ft - 0.10 ft = 345.63 ft
Ei = EGLi - BOCi = 345.73 ft - 344.07ft = 1.66 ft
Determine the flow condition at the upstream end of the outflow pipe from Table 9.7:
HGLi (345.63 ft) < TOCi (346.07 ft), therefore not full flow (surcharged) (condition A).
yn = 1.56 ft
yc = 0.8 ft
BOCi +yn (344.07+1.56 = 345.63 ft) ≥ HGLi (345.63 ft) > BOCi +yc (344.07+0.8 = 344.87 ft),
therefore subcritical partial flow conditions (condition C). Therefore, losses are carried
upstream as computed.
173
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
174
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
EGLa (345.81 ft) > TOCo (345.73 ft) is true. Pipe outlet is submerged (case A).
With submerged outlet: V = Q/A = 5.1/[(π/4)(1.5)2] = 2.9 ft/s
V2/2g = (2.9)2/(2)(32.2) = 0.13 ft
Ho = (0.4)V2/2g = 0.05 ft
EGLo = EGLa + Ho = 345.81 ft + 0.05 ft = 345.86 ft
HGLo = EGLo – V2/2g = 345.86 ft – 0.13 ft = 345.73 ft
Step 6. Estimate the HGL and EGL at the upstream end of pipe 41-42.
BOCi = 354.07 ft
TOCi = BOCi + D = 354.07 ft + 1.5 ft = 355.57 ft
Sf = [(Qn)/(KQD2.67)]2 = [(5.1)(0.013)/(0.46)(1.5)2.67]2 = 0.0024 ft/ft
Hf = Sf L = (0.0024) (328.0) = 0.78 ft
No other conduit losses: Hb, Hc, He, Hj = 0.0
Total pipe loss = 0.78 ft
EGLi = EGLo + pipe loss = 345.86 ft + 0.78 ft = 346.64 ft
HGLi = EGLi - V2/2g = 346.64 ft - 0.13 ft = 346.51 ft
Determine the flow condition at the upstream end of the outflow pipe from Table 9.7:
HGLi (346.51 ft) < TOCi (355.57 ft), therefore, pipe is not flowing full (surcharge) (condition A).
Estimate yn and yc:
Q/Qf = 5.1 / 18.1 = 0.28
V/Vf = 0.86
V = (0.86)(10.3) = 8.86 ft/s
yn / D = 0.37
yn = (0.37) (1.5) = 0.56 ft
V2/2g = (8.86)2/(2)(32.2) = 1.22 ft
yc = 0.87 ft
BOCi +yc (354.07 + 0.87 = 354.94 ft) ≥ HGLi (346.51 ft), therefore, supercritical partial flow
conditions (condition D). Pipe losses not carried upstream. Recompute HGLi and EGLi.
HGLi = yn + BOCi = 0.56 ft + 354.07 ft = 354.63 ft
EGLi = HGLi + V2/2g = 354.63 ft + 1.22 ft = 355.85 ft
In this conduit, the flow is in a supercritical regime. Given that the D/S portion of the conduit is
nearly submerged by the access hole, there would likely be a hydraulic jump somewhere
within the barrel. Important observations are that the energy should not decrease when
moving up the conduit and assumptions of full flow could yield erroneous results.
Step 7. Calculate EGL and HGL at structure 41.
Eai = max(Eaio, Eais, Eaiu)
Since condition D was identified in the previous step, Eaio = 0.00 ft
175
Chapter 9 - Storm Drain Conduits HEC-22, 4th edition
176
HEC-22, 4th edition Chapter 9 - Storm Drain Conduits
178
HEC-22, 4th edition Chapter 10 - Detention and Retention
179
Chapter 10 - Detention and Retention HEC-22, 4th edition
180
HEC-22, 4th edition Chapter 10 - Detention and Retention
at or near the time of the mainstem peak. With multiple detention facilities in a watershed,
designers will consider the effects of detention on hydrograph timing downstream to avoid
creating flooding problems.
10.1.3 Safety
Detention designers promote safe facilities by preventing public trespass, providing emergency
escape aids, and eliminating other hazards. Preventing public trespass recognizes that children
and adults may be attracted to the site, regardless of whether the site is intended for their use.
For example, the designer may use fences to enclose ponds to limit access. Ideally, designers
locate detention basins away from busy streets and intersections.
Designers consider inflow and outflow structures with safety in mind. For example, removable,
hydraulically efficient grates and bars may cover the ends of inlet and outlet pipes, particularly if
they connect with an underground storm drain system or otherwise present a safety hazard. Safer
design of outflow structures would also limit flow velocities at points where people could be drawn
into the discharge stream.
Where a detention basin incorporates active recreation areas, designers use mild bottom slopes
along the periphery of the basin. Persons who enter a detention pond or basin while stormwater
is being discharged may be at risk. The force of the currents may push a person into an outflow
structure or may hold a victim under the water where a bottom discharge is used. Urban
Stormwater Management (APWA 1981) discusses several design precautions intended to
improve safety.
10.1.4 Maintenance
Stormwater management facilities depend on proper maintenance to function as intended over
time. Depending on the facility type and location, appropriate periodic maintenance may include:
• Scheduled inspections may occur for the first few months after construction and on an
annual basis thereafter. In addition, inspections during and after major storm events
181
Chapter 10 - Detention and Retention HEC-22, 4th edition
ensure that the inlet and outlet structures continue functioning by either identifying damage
or clogging or confirming that none has occurred. They also can identify erosion on
embankment side slopes and evidence of soil piping that can degrade the facility.
• Mowing at least twice a year discourages woody growth and controls weeds.
• Sediment, debris, and litter control at least twice a year maintains functionality and
reduces clogging potential. In particular, removing accumulated sediment, debris, and
trash around outlet structures prevents clogging of the control device.
• Standing water or soggy conditions within the lower stage of a storage facility can create
nuisance conditions such as odors, insects, and weeds. Nuisance control, such as
providing allowance for positive drainage during design, minimizes these problems.
• Inlet and outlet devices, and standpipe or riser structures deteriorate with time,
necessitating structural repairs and replacement. The actual life of a structural
component will depend on individual site-specific factors, such as soil conditions.
• The system releases excess stormwater expeditiously to ensure that the entire storage
volume is available for subsequent storms and to minimize hazards. A dry pond, which is
a facility with no permanent pool, may need a paved low flow channel to ensure complete
removal of water and to aid in nuisance control.
• The facility typically satisfies Federal (see Chapter 2) and State statutes and recognizes
local ordinances.
• Provides access for maintenance.
• Avoids being an “attractive nuisance,” which may involve fencing and signage.
Figure 10.3 shows a schematic of the cross-section of a detention basin with a single-stage riser.
A pool forms behind the retaining structure. The hydrograph of the post-development flood runoff
enters the pool at the upper end of the detention basin. Water can be discharged from the pool
through a pipe that passes through or around the detention structure. The size of the pipe can
serve to limit the outflow rate, thus forming a permanent pool, with the permanent pool elevation
changing only through evaporation and infiltration losses.
Detention
Dry weather pool elevation basin
discharge
Dead storage
Riser pipe
Outlet pipe
Using a permanent pool has several advantages, including water quality control, aesthetic
considerations, and wildlife habitat improvement. A permanent pool also increases the total
storage volume, involving both a larger retaining structure and a larger commitment of land, both
of which increase project cost.
Figure 10.3 does not show several other elements of detention basin design. The designer may
determine that the riser inlet should be fitted with both an antivortex device and a trash rack. The
antivortex device prevents the formation of a vortex, thus maintaining the hydraulic efficiency of
the outlet structure. The trash rack prevents high velocity flows from sucking trash (and people)
into the riser.
All detention basins should have an emergency spillway to pass runoff from very large flood
events, so the retaining structure is not overtopped and washed out. The elevation of the bottom
of the emergency spillway, which will pass high flows around the retaining structure, is above the
elevation of the riser outlet, but below the top of the retaining structure. Designers call the zone
between the detention or surcharge storage zone.
Various methods exist for the planning and design of stormwater detention facilities. Design
involves the simultaneous sizing of the storage volume characteristics and the riser/outlet
characteristics. Some stormwater management (SWM) methods (“planning methods”) only apply
to estimating the volume of storage that would meet the intent of the SWM policies. Designers
183
Chapter 10 - Detention and Retention HEC-22, 4th edition
use other planning methods to determine the characteristics of the outlet facility. Ultimately, the
designer selects the final design using a method that simultaneously estimates the volume of
storage and the characteristics of the outlet facility.
The simultaneous solution is important because there is a wide array of feasible solutions for any
one site and set of design conditions. When designers separately determine storage volume and
outlet facility characteristics, they may produce an ineffective, and possibly incorrect, design. In
summary, planning methods provide less accuracy and involve less effort than design methods.
184
HEC-22, 4th edition Chapter 10 - Detention and Retention
storage. Because each method provides preliminary estimates only, the designer may apply
several of the methods and use engineering judgment to select an initial storage estimate.
Q s = Q a - Qb (10.1)
where:
Qs = Storage needed, inch (mm)
Qa = Runoff depth for post-development watershed condition, inch (mm)
Qb = Runoff depth for pre-development watershed condition, inch (mm)
Designers often refer to the variable Q as a volume even though it has the dimension of a depth.
It represents the volume of water at the computed depth spread uniformly over the entire
watershed. The designer computes the volume of storage, Vs, by multiplying Qs by:
VS =αAQS (10.2)
where:
α = Unit conversion constant, 3,630 in CU (10 in SI)
A = Drainage area, ac (ha)
The designer can compute the runoff depths Qa and Qb of equation 10.1 using any one of several
methods. For the Natural Resources Conservation Service (NRCS) method, apply the NRCS
runoff equation (SCS 1986) using the post-development and pre-development curve numbers
(CNs). Using the Rational Method to estimate peak flows, the runoff depths, Q, is:
qp t c
Q=α (10.3)
A
where:
qp = peak flow, ft3/s (m3/s)
α = Unit conversion constant, 0.0165 in CU (6.0 in SI)
A = Drainage area, ac (ha)
tc = Time of concentration, min
Solve equation 10.3 for both the pre- and post-development conditions by using the appropriate
values of qp and tc. Then compute the runoff depth difference by entering the values into equation
10.1, ultimately using it to compute the volume of storage with equation 10.2.
Example 10.1: Storage estimate for a detention pond.
Objective: Estimate the storage needed for a detention pond using the loss-of-natural-
storage method.
Given: An existing watershed under development with the following characteristics:
A = 5.7 ac (2.3 ha)
C = 0.2 and 0.45 (existing and developed conditions, respectively)
185
Chapter 10 - Detention and Retention HEC-22, 4th edition
Step 1. Calculate the peak flows for the existing and developed conditions.
qpb = (1/ α) Cb ib A = (0.2)(3.1)(5.7) = 3.5 ft3/s
qpa = (1/ α) Ca ia A = (0.45)(4.0)(5.7) = 10.3 ft3/s
Step 2. Estimate the runoff depths.
Using equation 10.3:
Qb = α[(qpb tc)/A] = (1/60.5)[3.5(18)/5.7] = 0.18 inches
Qa = α[(qpa tc)/A] = (1/60.5)[10.3(11)/5.7] = 0.33 inches
Step 3. Compute the depth and volume of storage.
Using equation 10.1:
QS = Qa – Qb = 0.33 – 0.18 = 0.15 inches
Using equation 10.2:
VS = α AQS = 3630 (5.7) (0.15) = 3,100 ft3
Solution: The detention pond needs 3,100 ft3 (88 m3) of storage.
Figure 10.4. Estimating storage using the actual inflow/estimated release of hydrograph method.
186
HEC-22, 4th edition Chapter 10 - Detention and Retention
where:
Vs = Storage volume estimate, ft3 (m3)
qi = Peak inflow rate into the basin, ft3/s (m3/s)
qo = Peak outflow rate out of the basin, ft3/s (m3/s)
ti = Duration of basin inflow, s
The duration of basin inflow equals two times the time of concentration. The triangular hydrograph
procedure, originally described by Boyd (1981), compares favorably with more complete design
procedures involving reservoir routing.
The coefficients CO, C1, C2, and C3 are a function of the NRCS rainfall distribution and are provided
in Table 10.1.
Rainfall Distribution C0 C1 C2 C3
I or IA 0.660 -1.76 1.96 -0.730
II or III 0.682 -1.43 1.64 -0.804
VS =αRS Qa A (10.6)
where:
α = Unit conversion constant, 3,630 in CU (10 in SI)
Qa = Post-development depth of runoff, inches (mm)
A = Drainage area, ac (ha)
Step 2. Calculate storage using the Rational Method Triangular Hydrograph method.
The inflow rate into the detention basin (qi) is 31.1 ft3/s. The peak flow rate out of the basin (qo)
is set to be = 19.4 ft3/s.
Using equation 10.4, compute the initial storage volume as:
Vs = 0.5 ti (qi - qo) = (0.5)(1.43 h x (60 min/h)(60 s/min))(31.1 - 19.4) = 30,116 ft3
Step 3. Determine storage using the NRCS TR-55 Method. Calculate Rq.
As previously noted, the inflow discharge is 31.1 ft3/s, and the outflow discharge is set to be
19.4 ft3/s by local ordinance.
The ratio of basin inflow to basin outflow is:
qo / qi = Rq = 19.4 / 31.1 = 0.62
189
Chapter 10 - Detention and Retention HEC-22, 4th edition
R S = Q s / Q a = C 0 + C 1 R q + C 2R q2 + C 3R q3
= 0.682 + (-1.43)(0.62) + (1.64)( 0.62)2 + (-0.804) (0.62)3 = 0.23
Step 5. Calculate the preliminary estimated storage volume (Vs) using the NRCS TR-55 Method
and equation 10.6.
Vs = α Rs Qa A = (3630) (0.23) (0.43) (43.4) = 15,600 ft3
Solution: The hydrograph and triangular hydrograph methods result in the most
consistent and conservative estimates, whereas the NRCS TR-55 method is
less conservative.
V = LWD (10.7)
D2
V = 0.5W (10.8)
S
where:
V = Volume at a specific depth, ft3 (m3)
D = Depth of ponding for that shape, ft (m)
W = Width of basin at base, ft (m)
L = Length of basin at base, ft (m)
S = Slope of basin, ft/ft (m/m)
190
HEC-22, 4th edition Chapter 10 - Detention and Retention
191
Chapter 10 - Detention and Retention HEC-22, 4th edition
A special case, rarely permitted by site, occurs with a horizontal rectangular bottom area and
vertical sides. In this case, the storage simply equals the bottom area (i.e., length times width)
multiplied by the depth of storage. If the relationship is plotted in a Cartesian axis system with
storage as the ordinate and stage as the abscissa, the stage-storage relationship will be a straight
line with a slope equal to the surface area of the storage facility.
A variation on the rectangular basin occurs where the bottom of the storage facility is a rectangle
(L x W), the longitudinal cross- section is a trapezoid, and the ends are vertical. In this case, the
stage-storage relationship is given by:
L
V= h + (L W )h
2
(10.9)
tan θ
where:
θ = Angle of side slopes
h = Height above bottom of basin, ft (m)
Graphing equation 10.9 results in a stage-storage relationship with the shape of a second-order
polynomial with a zero intercept and a shape that depends on the values of L, W, and θ.
Example 10.3: Storage estimate of rectangular basin.
Objective: Estimate the maximum volume of a rectangular basin.
Given: Consider a rectangular basin:
L = 656 ft (200 m)
W = 328 ft (100 m)
Z = 2
Step 1. Apply equation 10.7, which becomes:
S = 2L h2 + (L W ) h
4
V
= LWD + (L + W ) ZD2 + Z 2 D3 (10.10)
3
where:
V = Volume at a specific depth, ft3 (m3)
D = Depth of ponding or basin, ft (m)
192
HEC-22, 4th edition Chapter 10 - Detention and Retention
Estimate the trial dimensions of a basin by rearranging the equation for volume in terms of basin
length:
4rV
0.5
− ZD ( r + 1) + ( ZD ) ( r + 1) – 5.33 ( ZD ) r +
2 2 2
D
L= (10.11)
2r
193
Chapter 10 - Detention and Retention HEC-22, 4th edition
Figure 10.10 provides a definition sketch for a generalized prism in a pipe or other shape of
conduit. To provide for sediment transport through the conduit, designers place the conduit on a
slope. The prismoidal formula provides an estimate of storage volume based on estimates of
cross-sectional areas at three locations:
L
V = ( A1 + 4M + A 2 ) (10.12)
6
194
HEC-22, 4th edition Chapter 10 - Detention and Retention
where:
V = Volume of storage, ft3 (m3)
L = Length of section, ft (m)
A1 = Cross-sectional area of flow at base, ft2 (m2)
A2 = Cross-sectional area of flow at top, ft2 (m2)
M = Cross-sectional area of flow at midsection, ft2 (m2)
For a circular conduit, as illustrated in Figure 10.11, an exact storage volume results from when
d ≤ 2r:
H (0.667a3 ± cB)
V= (10.13)
r±c
0.5
a = ( 2r – d) d (10.14)
c =d–r (10.15)
a
α = 2 sin−1 (10.16)
r
where:
V = Volume of storage, ft3 (m3)
B = Cross-sectional end area at depth d, ft2 (m2)
H = Wetted pipe length, ft (m)
r = Pipe radius, ft (m)
195
Chapter 10 - Detention and Retention HEC-22, 4th edition
To assist in the determination of the cross-sectional area of B, the area of the associated circular
segment is:
r2
As =
(α − sin α ) (10.17)
2
where:
As = Segment area, ft2 (m2)
d a c H alpha B V
(ft) (ft) (ft) (ft) (rad) (ft2) (ft3)
197
Chapter 10 - Detention and Retention HEC-22, 4th edition
(A + A 2 )
V1,2 = 1 d (10.18)
2
where:
V1,2 = Storage volume between elevations 1 and 2, ft3 (m3)
A1 = Horizontal area at elevation 1, ft2 (m2)
A2 = Horizontal area at elevation 2, ft2 (m2)
d = Change in elevation between points 1 and 2, ft (m)
Generally, the average-end area formula approximates irregular basin storage volume well when
calculating volumes with small changes in elevation between respective elevations or when the
basin width or length is changing but not both.
The conic section formula approximates irregular basin storage volume more accurately when
both length and width of a basin are changing as shown in Figure 10.12. The conic approximation
is:
A1 + ( A1A 2 )0.5 + A 2
V = d (10.19)
3
where:
V = Volume of frustum of a pyramid, ft3 (m3)
A1 = Surface area at elevation 1, ft2 (m2)
A2 = Surface area at elevation 2, ft2 (m2)
d = Change in elevation between points 1 and 2, ft (m)
198
HEC-22, 4th edition Chapter 10 - Detention and Retention
286
285
284
283
282
281
280
279
279
284
Section
5 + 20
Figure 10.13. Topographic map for deriving stage-storage relationship at site of structure
(section 5+20).
199
Chapter 10 - Detention and Retention HEC-22, 4th edition
10
8
Depth
6
0
0 10 20 30 40 50 60 70
Cumulative storage(*10³)
Figure 10.14. Stage-storage relationship.
Total Area
within
Contour Contour Change in
Elevation Elevation Average Contour Storage Cumulative
(ft) (ft2) Area (ft2) Interval (ft) Depth (ft) (ft2) Storage (ft3)
278 0 0 0
245 1 245
279 490 1 245
1,115 1 1,115
280 1,740 2 1,360
3,015 1 3,015
281 4,290 3 4,375
5,585 1 5,585
282 6,880 4 9,960
8,600 1 8,600
283 10,320 5 18,560
11,575 1 11,575
284 12,830 6 30,135
14,165 1 14,165
285 15,500 7 44,300
17,685 1 17,685
286 19,870 8 61,985
Many storage facilities include a permanent pool. In such cases, the elevation of the weir or the
bottom of the orifice is set above the elevation of the bottom of the pond. Storage below the outlet
elevation is called dead storage. Storage above the outlet elevation is called active storage. Total
storage equals the sum of the active and dead storages.
200
HEC-22, 4th edition Chapter 10 - Detention and Retention
Solution: If the outlet facility has a minimum elevation of 0.5 ft (0.15 m), all storage below
this elevation is dead storage. The active storage is 0.0 at an elevation of 0.5 ft
(0.15 m). The active storage above 0.5 ft (0.15 m) equals the difference
between the total storage and the dead storage. The stage (column 1) versus
active storage (column 7) would be used when designing a storage facility.
201
Chapter 10 - Detention and Retention HEC-22, 4th edition
202
HEC-22, 4th edition Chapter 10 - Detention and Retention
Ke = 0.5
Step 1. Evaluate the pipe for inlet and outlet control.
Using the same discharges from example 10.2, the maximum predeveloped discharge from
the watershed is 19.4 ft3/s (0.55 m3/s). Since the discharge pipe can function under inlet or
outlet control, the pipe size will be evaluated for both conditions. The larger pipe size will be
selected for the final design.
Step 2. Size the pipe for inlet control.
Using HDS-5 (FHWA 2012a) yields the relationship between head on the pipe and the
resulting discharge for inlet control. The analysis shows the pipe diameter that will carry the
flow under the specified conditions is 30 inches.
Step 3. Size the pipe for outlet control.
Using HDS-5 (FHWA 2012a) yields the relationship between head on the pipe and discharge
for barrel (outlet) control. The analysis shows the pipe diameter that will carry the flow under
the specified conditions is 27 inches.
Solution: For the design, select pipe diameter equal to 30 inches (750 mm).
10.3.3.2 Orifices
Figure 10.15 shows a schematic of a tank with a hole of area in its bottom. Assuming all losses
can be neglected, write Bernoulli’s equation between a point on the surface of the pool (point 1)
and a point in the cross-section of the orifice (point 2):
P1 V12 P V2
+ + z1 = 2 + 2 + z 2 (10.20)
γ 2g γ 2g
where:
P = Pressure, lb/ft2 (N/m2 or Pa)
V = Velocity, ft/s (m/s)
γ = Specific weight, lb/ft3 (N/m3)
z = Height above datum, ft (m)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
Z1
V2
2 Z2
Datum
Figure 10.15. Schematic diagram of flow through an orifice.
203
Chapter 10 - Detention and Retention HEC-22, 4th edition
This can be simplified by assuming: 1) the pressure at both points is atmospheric, therefore p1 =
p2; 2) the surface area of the pool A1 is very large relative to the area of the orifice A2, so from the
continuity equation V1 is essentially zero; and 3) z1 - z2 = h. Equation 10.20 becomes:
V22
h= (10.21)
2g
Q AV
= = A 2gh (10.22)
Equation 10.22 assumes ideal conditions with zero energy losses and atmospheric pressure
across the opening of the orifice. It is actually atmospheric at a point below the orifice, where the
cross-sectional area of the discharging water is slightly smaller than the area of the orifice. To
account for these conditions, the orifice flow equation introduces a discharge coefficient:
Q = Co A o ( 2gho ) (10.23)
where:
Q = Orifice flow rate, ft3/s (m3/s)
Co = Discharge coefficient
Ao = Area of orifice, ft2 (m2)
ho = Effective head on the orifice measured from the centroid of the opening, ft (m)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
Values of Co range from 0.5 to 1.0, with a value of 0.6 commonly used, for square-edged, uniform
orifice entrance conditions. For ragged edged orifices, such as those resulting from the use of an
acetylene torch to cut orifice openings in corrugated pipe, use a value of 0.4.
If the orifice is not horizontal, the depth, h, is usually measured from the center of area of the
orifice.
If the orifice discharges as a free outfall, i.e.,
unsubmerged, then measure the effective
Orifice or Culvert
head from the centerline of the orifice to the
upstream water surface elevation. For a Pipes smaller than 1 ft (0.3 m) in
submerged orifice discharge, the effective diameter may be analyzed as a
head equals the difference in elevation of submerged orifice when ho/D is greater
the upstream and downstream water than 1.5. Headwater and tailwater effects
surfaces. Figure 10.16 shows this latter influence pipes greater than 1 ft (0.3 m) in
condition of a submerged discharge. diameter, which function as discharge
pipes, not just as an orifice; analysis
Designers use orifice plates on riser
accordingly incorporates this design
structures to control outflow from a detention
consideration.
pond. As shown in Figure 10.17, orifice
plates consist of multiple openings.
Compute flow through multiple orifices by
summing the flow through individual orifices. For multiple orifices of the same size and under the
influence of the same effective head, multiplying the discharge for a single orifice by the number
of openings yields the total flow.
204
HEC-22, 4th edition Chapter 10 - Detention and Retention
205
Chapter 10 - Detention and Retention HEC-22, 4th edition
Using equation 10.23 with D = 0.49 ft yields the following relationship between the effective
head on the orifice (ho) and the resulting discharge:
ho = Depth - D/2
206
HEC-22, 4th edition Chapter 10 - Detention and Retention
10.3.3.3 Weirs
The following sections provide relationships for sharp-crested, broad-crested, V-notch, and
proportional weirs.
Vc
Fr = 1= (10.24)
(gy c )0.5
1
q2 3
yc = u (10.25)
g
Vc2 3
Ec =y c + = yc (10.26)
2g 2
where:
Fr = Froude number
Vc = Critical velocity, ft/s (m/s)
yc = Critical depth, ft (m/s)
qu = Discharge rate per unit width, ft2/s (m2/s)
Ec = Minimum specific energy, ft (m)
207
Chapter 10 - Detention and Retention HEC-22, 4th edition
V12 V22
2g 2g
EGL
Qo h1 h2
Datum
(Z1 = Z2 = 0)
Assuming hydrostatic pressure at sections 1 and 2, then Pi/γ = hi. Thus, Bernoulli’s equation is:
V12 V2
h1 + + z1 =h2 + 2 + z 2 (10.27)
2g 2g
By setting the datum at the top of the weir, z1 = z2 = 0, assuming that the velocity head at section
1 is much smaller than the velocity head at section 2, and recalling that the flow passes through
critical depth as it passes over the weir, then V2 = VC and h2 = yC, reducing equation 10.27 to:
Vc2
h1
= + yc (10.28)
2g
yc 3y c 2
h
= + y=
c or y=
c h (10.29)
2 2 3
2 0.5 8g 0.5 3 2 3
( )
0.5
=qu gy
= 3
g =
c h = h
2
2gh
2
(10.30)
3 27 27
208
HEC-22, 4th edition Chapter 10 - Detention and Retention
2 1.5
Q= 2g h L (10.31)
27
where:
Q = Discharge over a horizontal weir, ft3/s (m3/s)
h = Head (depth) of approach flow above the weir, ft (m)
L = Weir length, ft (m)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2).
Submergence affects sharp-crested weirs when the tailwater rises above the weir crest elevation,
as shown in Figure 10.20. These effects reduce discharge over the weir. The discharge equation
for a submerged sharp-crested weir is (Brater and King 1976):
0.385
h 1.5
Qs = Q 1– 2 (10.34)
h1
where:
Qs = Submerged flow, ft3/s (m3/s)
Q = Unsubmerged weir flow, ft3/s (m3/s)
209
Chapter 10 - Detention and Retention HEC-22, 4th edition
θ
Q = Cw 2g tan h2.5 (10.35)
2
where:
Q = Discharge, ft3/s (m3/s)
Θ = Angle of v-notch, degrees
h = Head on apex of v-notch, ft (m)
Cw = Weir coefficient for a v-notch weir (typically equal to 0.31)
210
HEC-22, 4th edition Chapter 10 - Detention and Retention
Table 10.7. Broad-crested weir coefficient values (adapted from Brater and King 1976).
211
Chapter 10 - Detention and Retention HEC-22, 4th edition
x y
0.5
a
Q = Cw 2g a0.5 b h – (10.37)
3
where:
Q = Discharge, m3/s (ft3/s)
h = Head above horizontal sill, ft (m)
Cw = Weir coefficient for a proportional weir (typically equal to 0.62)
212
HEC-22, 4th edition Chapter 10 - Detention and Retention
213
Chapter 10 - Detention and Retention HEC-22, 4th edition
214
HEC-22, 4th edition Chapter 10 - Detention and Retention
Figure 10.24. Profile and cross-section of excavated earth spillway. Source: USDA-NRCS
(2021).
215
Chapter 10 - Detention and Retention HEC-22, 4th edition
Figure 10.25. Single-stage riser characteristics for (a) weir flow and (b) orifice flow.
V=
t Vd + Vs (10.38)
1 Qpb
Ao =
C 2g 0.5 (10.39)
d E − E − Ho
1 o
2
where:
Ao = Orifice opening area, ft2 (m2)
Qpb = Discharge through the orifice (pre-development), ft3/s (m3/s)
E1 = Water surface elevation upstream of the orifice, ft (m)
Eo = Elevation of the bottom of the orifice, ft (m)
g = Gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
Ho/2 adjusts for head being measured from the center of the orifice.
For a rectangular orifice, compute the width of the orifice opening Wo:
Ao
Wo = (10.40)
Ho
1 Qpb
Lw = (10.41)
2gC (E − E )1.5
w 1 0
217
Chapter 10 - Detention and Retention HEC-22, 4th edition
If the selected size is not available, specify the next available larger size. Place the entrance
invert at an elevation of 96.1 ft (29.3 m). The designer selects the culvert inlet so that the
culvert headwater, i.e., the depth of water inside the riser, does not rise above the lowest riser
opening for the design conditions, where possible. The designer also adjusts the culvert invert
to be compatible with site conditions.
Step 2. Develop Stage-storage curve.
Section 10.3.2 gives details on constructing a stage-storage relationship. For this example,
Table 10.9 gives the stage-storage relationship at the site of the detention structure. Based on
the permanent pool elevation, interpolate the dead storage from the stage-storage curve to be
13,400 ft3.
Step 3. Estimate total storage.
Compute the active storage using one of the methods presented in Section 10.3.1, estimating it
at 23,700 ft3. The total storage equals the sum of the active and dead storages, 37,100 ft3.
Step 4. Find the maximum stage.
Find the elevation corresponding to the total storage by interpolating the stage-storage curve,
which is 101.4 ft.
Step 5. Compute orifice flow.
The orifice invert was established at an elevation of 98.8 ft to create the permanent pool.
Assuming an initial orifice height of 0.5 ft, compute the area of the orifice in the riser with equation
10.39 to create an outflow of 2.8 ft3/s at the assumed stage in the pond:
Ao = {1 / [0.6 (2*32.2)0.5]} {2.8 / [101.4 – 98.8 – (0.5 / 2)]0.5} = 0.379 ft2
Wo = Ao / D = 0.379 / 0.5 = 0.76 ft
Solution: One possible orifice is 0.5 ft by 0.76 ft. If the calculated dimensions are not
practical construction sizes, conduct an iterative trial process with practical
dimensions resulting in the same performance until finding suitable dimensions.
It is not usually appropriate to select the next larger available dimensions
because this will allow excessive discharge through the orifice. Using storage
routing, check the design before finalizing. The diameter of the riser (if it is also
circular) usually equals 2 to 3 times the diameter of the outlet culvert.
218
HEC-22, 4th edition Chapter 10 - Detention and Retention
219
Chapter 10 - Detention and Retention HEC-22, 4th edition
V=
t2 Vd + Vs2 (10.42)
220
HEC-22, 4th edition Chapter 10 - Detention and Retention
221
Chapter 10 - Detention and Retention HEC-22, 4th edition
222
HEC-22, 4th edition Chapter 10 - Detention and Retention
223
Chapter 10 - Detention and Retention HEC-22, 4th edition
Step 4. Estimate the runoff (or inflow) less evaporation and infiltration losses.
Assuming no basin outflow and no change in storage, the runoff (or inflow) less evaporation
and infiltration losses is:
Net Budget = 5,445,000 – 381,150 – 6,359,760 = -1,295,910 ft3
Since the average annual losses exceed the average annual rainfall, the proposed facility will
not function as a wet pond with a permanent pool. If the facility needs to function with a
permanent pool, accomplish that by reducing the pool size.
Step 5. Revise the pool surface area.
Pool surface and bottom areas equal 2.0 ac and 1.0 ac, respectively.
Step 6. Recompute the evaporation and infiltration.
Evaporation = (2.92 inches) (2.0 ac) (43560 ft2/ac) = 254,100 ft3
Infiltration = (0.01) (24) (365) (1.0) (43560/12) = 3,179,880 ft3
Step 7. Estimate revised runoff less evaporation and infiltration losses.
Net Budget = 5,495,000 – 254,100 – 3,179,880 = 2,011,020 ft3
Solution: The revised facility appears able to function as a wet pond with a permanent
pool. However, these calculations use average precipitation, evaporation, and
losses. During years of low rainfall, the pool may not persist.
225
Chapter 10 - Detention and Retention HEC-22, 4th edition
ΔS l + l O + O2
= 1 2 − 1 (10.45)
Δt 2 2
where:
ΔS = Change in storage, ft3 (m3)
Δt = Time interval, min
l = Inflow, ft3 (m3)
O = Outflow, ft3 (m3)
Subscripts 1 and 2 refer to the beginning and end of the time interval, respectively. Figure 10.29
illustrates the routing process graphically with the inflow hydrograph as the input to the routing
and the outflow hydrograph as the result of the routing. HDS-2 (FHWA 2002) provides a more
detailed description of storage routing.
226
HEC-22, 4th edition Chapter 10 - Detention and Retention
Figure 10.30. Inflow and routed outflow hydrographs for detention basin example.
228
HEC-22, 4th edition Chapter 10 - Detention and Retention
229
Chapter 10 - Detention and Retention HEC-22, 4th edition
Figure 10.31. Stage-discharge curves for detention basin example with weir lengths of 1.6 and
2.0 ft.
230
HEC-22, 4th edition Chapter 11 - Urban Stormwater Quality
231
Chapter 11 - Urban Stormwater Quality HEC-22, 4th edition
In addition to Malhotra and Normann (1994) and Schueler (1987), researchers have created
additional resources addressing BMP selection, performance, and evaluation of alternatives:
• Stormwater Best Management Practices in an Ultra-Urban Setting: Selection and
Monitoring (FHWA 2000).
• State of the Practice in Data Collection and Performance Measurement (FHWA 2014a).
• Stochastic Empirical Loading and Dilution Model (SELDM) for evaluating the adverse
effects of runoff from highway projects (Granato 2013).
L=cRCA (11.1)
where:
L = Average annual loading, lb (chemical constituents) or billion colonies (bacteria)
c = Unit conversion factor, 0.226 (chemical) or 103 (bacteria)
R = Annual runoff (inch)
C = Pollutant concentration (mg/l) for chemical constituents
= Bacteria concentration (1,000/ml) for bacteria
A = Area (ac)
The FHWA developed a computer model that characterizes stormwater runoff pollutant loads
from highways and predicts impacts to receiving water, specifically lakes and streams. The four-
volume FHWA report Pollutant Loadings and Impacts from Highway Stormwater Runoff (Driscoll
1990) contains more detail on the estimating procedures.
More recently, the FHWA, in cooperation with the U.S. Geological Survey (USGS), developed the
highway runoff database (HRDB) (FHWA 2009) and the SELDM to estimate and simulate
stormflow volumes, concentrations, and loads of highway and urban runoff constituents (Granato
2013, USGS 2020). HRDB and SELDM provide data, tools, and techniques to help transform
complex scientific data into meaningful information about the risk of adverse effects of runoff on
receiving waters, the potential need for mitigation measures, and the potential effectiveness of
such management measures for reducing these risks (Granato 2013, Granato 2014, Granato and
Jones 2019).
Several other stormwater management software applications and tools can generate pollutant
loads and the fate and transport of the pollutants:
• Stormwater Management Model (SWMM) (USEPA 2020).
• Storage, Treatment, Overflow, Runoff Model (STORM) (USACE 1977).
• Hydrologic Simulation Program, Fortran (HSPF) (USEPA 2002).
• Spreadsheet Tool for Estimating Pollutant Loads (STEPL) (USEPA 2018).
232
HEC-22, 4th edition Chapter 11 - Urban Stormwater Quality
233
Chapter 11 - Urban Stormwater Quality HEC-22, 4th edition
234
HEC-22, 4th edition Chapter 11 - Urban Stormwater Quality
Wet ponds represent an effective water quality BMP. If properly sized and maintained, wet ponds
can achieve a high removal rate of sediment, biological oxygen demand, organic nutrients, and
trace metals. Biological processes within the pond also remove soluble nutrients (nitrate and
ortho-phosphorus) that contribute to nutrient enrichment (eutrophication). Wet ponds are most
cost-effective in larger, more intensively developed sites. Positive impacts of wet ponds can
include creation of local wildlife habitat; higher property values; recreation; and landscape
amenities. Negative impacts can include possible upstream and downstream habitat degradation;
downstream sediment imbalance; potential safety hazards; occasional nuisance problems (e.g.,
odor, algae, and debris); and the eventual need for costly sediment removal.
235
Chapter 11 - Urban Stormwater Quality HEC-22, 4th edition
WQ
= V Q=
A (R V P)A (11.2)
236
HEC-22, 4th edition Chapter 11 - Urban Stormwater Quality
where:
WQv = Water quality volume
Q = Depth of runoff, inch (mm)
RV = Volumetric runoff coefficient
P = Rainfall depth, inch (mm)
A = Drainage area, ac (ha)
While water quality exfiltration systems do not typically satisfy stormwater storage goals, they may
result in smaller, less costly facilities downstream. The smaller size and area requirements of
water quality exfiltration systems allows considerable flexibility in their placement within a
development site, an important factor for “tight” sites. Additionally, if for some reason the water
quality trench fails, a downstream stormwater management facility may still adequately control
stormwater.
237
Chapter 11 - Urban Stormwater Quality HEC-22, 4th edition
Infiltration basins present a feasible option where soils are permeable, and where the water table
and bedrock are situated well below the soil surface. They have similar construction costs and
maintenance requirements to those for conventional dry ponds. Experience to date indicates that
infiltration basins have one of the highest failure rates of any BMP from plugging of the permeable
soils, emphasizing the importance of regular inspection for standing water.
Advantages of infiltration basins include:
• Preserving the natural water balance of the site.
• Serving larger developments.
• Usefulness as sediment basins during the construction phase.
• Reasonable cost-effectiveness in comparison with other BMPs.
Disadvantages of infiltration basins include:
• High rate of failure due to unsuitable soils.
• Need for frequent maintenance.
• Frequent nuisance problems (e.g., odors, mosquitoes, soggy ground).
238
HEC-22, 4th edition Chapter 11 - Urban Stormwater Quality
239
Chapter 11 - Urban Stormwater Quality HEC-22, 4th edition
240
HEC-22, 4th edition Chapter 11 - Urban Stormwater Quality
• Bioretention area (rain garden): Retains, infiltrates, and filters runoff and pollutants using
a shallow surface depression usually planted with native vegetation. See Figure 11.7.
• Bioretention swales: Also referred to as bioswales or vegetated swales, consist of typically
parabolic or trapezoidal depressions that use bioretention soil media and vegetation to
promote infiltration, water retention, and sedimentation and pollutant removal. See Figure
11.8.
• Stormwater curb extensions: Also called stormwater bump outs, extend the curb into the
roadway to reduce traffic speed and capture stormwater runoff from roadways and
sidewalks.
• Stormwater planters: Consist of narrow, flat-bottomed landscape areas, typically of
rectangular shape with vertical walls.
• Stormwater tree systems (i.e., pits and trenches): Intercept and capture stormwater using
a tree or shrub, bioretention soil media, and a gravel reservoir.
• Infiltration trenches: Excavated linear areas filled with layers of stone and sand wrapped
in geotextile fabric. See Figure 11.9.
• Subsurface infiltration and detention practices: Underground storage that holds runoff and
allows infiltration.
• Permeable pavements: Includes porous asphalt (pavement) and pavers that allow runoff
to infiltrate through void space instead of becoming surface runoff. See Figure 11.10.
Figure 11.7. Green infrastructure practice: bioretention (rain garden). Source: Roger Kilgore.
241
Chapter 11 - Urban Stormwater Quality HEC-22, 4th edition
242
HEC-22, 4th edition Chapter 11 - Urban Stormwater Quality
Table 11.1 summarizes the relative effectiveness (based on pollutant removal efficiencies) of
properly maintained green infrastructure practices for various water quality constituents that
roadway runoff typically produces in high concentrations.
243
Chapter 11 - Urban Stormwater Quality HEC-22, 4th edition
Table 11.1. Pollutant removal efficiencies of green infrastructure practices (USEPA 2021).
biological uptakes as runoff flows over and through vegetation. Removal of pollutants by a
biofiltration swale depends on the time that water remains in the swale, or the hydraulic residence
time, and the extent of its contact with vegetation and soil surfaces. The Washington State
Department of Transportation Highway Runoff Manual contains information on biofiltration swales
(WSDOT 2019).
Figure 11.11. Schematic of grassed swale level spreader and check dam.
development. A creatively landscaped filter strip can become a valuable community amenity,
providing wildlife habitat, screening, and stream protection. Engineers also commonly use grass
filter strips to protect surface infiltration trenches from clogging by sediment.
Filter strips do not provide storage or infiltration to effectively reduce peak flows. Typically, filter
strips make up one part of an integrated stormwater management system. Thus, the strips can
lower runoff velocity (and, consequently, the watershed time of concentration), slightly reduce
both runoff volume and watershed imperviousness, and contribute to groundwater recharge. Filter
strips also provide important benefits of preserving the riparian zone and stabilizing streambanks.
246
HEC-22, 4th edition Chapter 11 - Urban Stormwater Quality
by a trash rack connects this chamber to the oil separation chamber. The oil separation chamber
also maintains a permanent pool of water. An inverted elbow connects the separation chamber
to the third chamber.
Advantages of water quality inlets include compatibility with the storm drain network, easy to
access, able to pretreat runoff before it enters infiltration BMPs, and unobtrusive. Disadvantages
include their limited stormwater and pollutant removal capabilities, frequent cleaning (which
cannot always be assured), the possible difficulties in disposing of accumulated sediments, and
cost.
Other water quality ultra-urban applications, include filter inserts, hydrodynamic devices, and
simple sumps. Bag or basket type filter inserts have small openings to allow low flows to seep
through and larger flows to overflow without causing backwater to the inlet. Hydrodynamic devices
typically include baffles, vortex mechanisms, or other settling components, or a combination of
these elements. These devices separate sediment and pollutants from stormwater and commonly
are inserted between inlets and storm drain pipes. Sumps placed at the bottom of access holes
and below the storm drain pipe flow lines allow sediment and debris to deposit while releasing
stormwater through weep holes.
247
Chapter 11 - Urban Stormwater Quality HEC-22, 4th edition
248
HEC-22, 4th edition Chapter 12 - Pump Stations
249
Chapter 12 - Pump Stations HEC-22, 4th edition
relatively easily. Submersible pumps come in many sizes and have many applications. Rail
systems are available which allow removal of pumps without entering the wet well.
Dry-pit stations consist of two separate elements: a storage box or wet well and a dry well.
Stormwater arrives in the wet well, which is connected to the dry well by a horizontal suction pipe.
The dry well contains the stormwater pumps. Designers often use radial flow pumps in this
configuration. Either motors mounted in the dry well or drive shafts with overhead motors may
provide power.
Since dry-pit stations cost more than wet-pit stations, designers most often use wet-pit stations.
The hazards associated with pumping stormwater usually do not warrant the added expense of
dry-pit stations, and available space within the highway right-of-way may be a limiting factor.
However, dry-pit stations offer some advantages, including ease of access for repair and
maintenance, the protection of equipment from fire and explosion, and adaptability for storage
volume.
For both wet-pit and dry-pit stations, the station depth influences the cost and functionality of the
pump station. Engineers minimize station depth with designs that use only the depth that will allow
pump submergence and hydraulically necessary clearance below the inlet invert. HEC-24 (FHWA
2001) provides additional information on station types.
forms of radial flow pumps handle debris quite well. A single vane, open configured impeller
handles debris best because it provides the least interference with the passage of debris through
the pump. The debris handling capability decreases the number of vanes, since the size of the
openings decreases.
Mixed flow pumps represent a physical
transition from axial flow to radial flow and
have some attributes of each. Unlike with an Getting the Right Pump
axial flow pump, inside a mixed flow pump, The procurement process in some
the water flow direction changes from along jurisdictions may not allow the designer
the impeller’s axis of rotation to some angle to specify a particular brand, type, or
away from that axis. But, unlike in a radial style of pump or pump motor for
flow pump, the change in direction is not reasons of fairness and competition.
perpendicular to the axis of rotation. As in a The designer of a pump station may find
radial flow pump, the impeller “flings” the it necessary to specify certain aspects
water outward and adds energy, but the of pump performance within acceptable
pump case then redirects the water back ranges, allowing contractors bidding on
along the axis of rotation. projects to select equipment within that
Very often, mixed flow pumps are multi- range, with the agency retaining the
stage. This design stacks together several right of approval of shop drawings after
impellers inside of several cases and drives bidding and award of a contract and
them by a common shaft. Water passes before purchase of the equipment. For
through the impellers progressively, with such reasons, the final configuration
each stage imparting more energy to the and equipment of a pump station may
water. The impellers of a mixed flow pump differ from the initial design.
can be designed to shed and pass debris
better than an axial flow pump. Mixed flow
pumps work best for intermediate head and discharge applications. Because they are easily
configurable for multiple stages, and because of the physical configuration of mixed flow pumps,
most submersible pumps are of this type.
All pumps can use motors or engines housed overhead or in a dry well, or submersible motors
located in a wet well. Submersible pumps frequently provide the advantages of simplified design,
construction, and maintenance and, therefore, lower associated cost. Designers rarely use
anything other than a constant speed, single suction pump.
251
Chapter 12 - Pump Stations HEC-22, 4th edition
of discharge as shown in Figure 12.1. Since changes in head influence pump performance,
designers calculate the head required as accurately as possible including all “minor losses”
attributed to valves and bends. Designers can minimize these various head losses by carefully
selecting discharge line size and other components such as check valves and gate valves.
Designers select the discharge pipe size by considering the manufactured pump outlet size, either
matching the outlet size or, to reduce the loss in the line, by using a pipe larger than the outlet.
Generally, this approach allows the designer to identify a reasonable compromise in balancing
cost but would involve inclusion of an expansion loss in the calculations.
The static head represents the vertical lift required of the pump station, that is, the difference
between the head at the pump station outlet and inlet. It varies depending on the water levels in
the storage at the inlet and may also vary if the outlet water surface elevations fluctuate.
The total head required of the pump station combines static head, friction head, velocity head,
and minor losses (through fittings, values, pipe expansions, pipe contractions, etc.). This quantity
is called total dynamic head (TDH). It is dynamic because, except for static head, TDH increases
with flow. Designers compute TDH as:
TDH = Hs + Hf + Hv + Hl (12.1)
where:
TDH = Total dynamic head, ft (m)
Hs = Static head, ft (m)
Hf = Friction head (loss), ft (m)
Hv = Velocity head, ft (m)
Hl = Losses through fittings, valves, etc., ft (m)
Figure 12.1 displays a system curve which determines the energy required to pump any flow
through the discharge system. It is especially critical for the analysis of a discharge system with
a force main. When overlaid with pump performance curves (provided by the manufacturer), it will
yield the pump operating range.
252
HEC-22, 4th edition Chapter 12 - Pump Stations
253
Chapter 12 - Pump Stations HEC-22, 4th edition
Using pumps of equal size and type has the benefit of enabling all pumps to be freely alternated
into service thereby distributing the load between pumps more evenly. Providing an automatic
alternation system for each pump station allows this approach. This system would automatically
rotate the lead and lag pump after each pump cycle so that each pump in turn would become the
lead pump. This equalizes wear and reduces needed cycling storage. It also simplifies scheduling
maintenance and allows pump parts to be interchangeable. Providing hour and start meters aids
in scheduling needed maintenance.
254
HEC-22, 4th edition Chapter 12 - Pump Stations
The location or setting of sensors inside of the wet well or storage box controls the starting and
stopping of pump motors. Their function is critical because pump motors or engines must not start
more frequently than an allowable number of times per hour (i.e., the minimum cycle time) to
avoid damage. Designers can prolong motor life by providing sufficient storage volume between
the pump start and stop elevations to achieve the minimum cycle time requirement.
12.2.2 Power
Designers choose from several types of power for a pump station. Most commonly, they choose
electric motors, which involve the least maintenance and oversight. In some cases, designers
choose fuel-driven (gasoline, diesel, or natural gas) engines. When selecting fuel-driven engines,
considerations include reliable storage with minimal chance of leakage of liquid fuels and fuel
perishability. Fuel-driven engines involve periodic maintenance but must start and run reliably
without human oversight. Designers select the type of power that best meets the needs of the
project based on an estimate of future energy considerations and overall station reliability.
Developing a comparative cost analysis of alternatives helps make this decision. However, when
readily available, electric power usually costs the least while being the most reliable choice.
Getting input from the maintenance engineer will aid the designer in the selection process. The
designer will also benefit from remembering that the same conditions necessitating the pump
station—rainstorms—are also the conditions under which electric systems may experience
service outages.
Because of the tendency for outages to occur during storms, designers generally consider
provisions for backup power. However, if they deem the consequences of failure acceptable, they
may choose not to provide backup power. Generally, designers make the decision to provide
backup power on economics, serviceability, and safety. For electric motors, two independent
electrical feeds from the electric utility with an automatic transfer switch may provide sufficient
reliability and affordability when backup power is required.
For extensive depressed freeway systems involving several electric motor-driven stations, mobile
generators represent another potential source of backup power. Maintenance staff can store a
trailer mounted generator at any one of the pump stations, moving the generator to the affected
station in case of power outage.
255
Chapter 12 - Pump Stations HEC-22, 4th edition
256
HEC-22, 4th edition Chapter 12 - Pump Stations
monitoring office, or maintenance office, allowing the central control unit to initiate corrective
actions immediately in case of malfunction. This approach allows effective monitoring of such
functions as power, pump operations, unauthorized entry, explosive fumes, and high water levels.
A regular schedule of maintenance conducted by trained, experienced personnel help assure the
proper pump station functioning.
The ease of acquisition of information from remote locations allowed by ITS and modern
communications presents opportunities not available in the past. Designers may consider
including electronic weather monitoring equipment such as temperature and rainfall
measurements at pump stations, along with electronic records of operation (start/stop times,
water level in wet wells, inflow, and outflow data) over several years or the lifespan of a pump
station. Such data can prove invaluable in improving future design, maintenance, and operation
of pump stations, as well as in providing real-time data for active traffic management via ITS,
active maintenance management, and emergency incident management. Pump stations provide
a logical setting for such data collection and transmission equipment.
Since major storm events occur infrequently, the DOT can develop a comprehensive, preventive
maintenance, inspection, and recertification program for maintaining and testing the equipment
so that it will function properly when needed. Inclusion of instruments such as hour meters and
number-of-starts meters on each pump will help schedule maintenance. Soliciting input from
maintenance forces will allow designers to improve each new generation of stations.
Periodically testing equipment, instrumentation, and auxiliary features (hatches, doors, etc.) will
help ensure proper operation and condition. DOTs will also wish to schedule relatively frequent
inspection of the facility for vandalism, deterioration, weather damage, vehicular damage, and
unauthorized entry or occupation. In some areas, vegetation, roots, insects, or other creatures
can create entry or maintenance problems. Fire ants, in particular, can damage electronic
components. Bats, raccoons, skunks, snakes, and other animals can create disease or safety
hazards and damage components.
Safety First
For the safety of operation and maintenance, designers review all elements of the pump
station. Ladders, stairwells, and other access points facilitate use by maintenance
personnel. Designers also ensure adequate space for the operation and maintenance of
all equipment, paying particular attention to guarding moving components such as drive
shafts and providing proper and reliable lighting. In some cases, air testing equipment
can be available so maintenance personnel can check for clean air before entering.
Proper ventilation is essential.
Pump stations will likely be classified as a confined space resulting in appropriate access
requirements and safety equipment. Designers ensure pump stations are secure from
entry by unauthorized persons, providing as few windows as possible.
257
Chapter 12 - Pump Stations HEC-22, 4th edition
12.3.1 Location
Practical considerations usually allow
designers to locate pump stations near the
low point in the highway drainage system Consider Construction Experience
they serve. An adjacent frontage road or Construction methods impact the cost of
overpass can often provide easy access to the pump station. The more a pump
the station. If possible, locating the station station operates, the smaller the fraction
and access road on high ground will allow the construction cost is of life-cycle cost.
access if the highway becomes flooded. Soil With a stormwater pump station, which
borings made during the selection of the site operates only when needed (during wet
will reveal the allowable bearing capacity of weather) operating costs may be
the soil and identify any potential problems. insignificant compared to construction
Considering architectural and landscaping costs. One construction option includes
issues in the location phase of the design caisson construction, in which the
process will allow aboveground stations to station is usually circular, and
blend into the surrounding community or fit construction is open-pit construction.
with the theme of past and future projects. Soil conditions are important in
Foregrounding aesthetic, decorative, and selecting the most cost-effective
community-relevant aspects of highway alternative.
projects has become commonplace in Feedback from construction personnel
recent decades, and pump stations can fit on any problems encountered can
into such schemes. Relevant pump station improve future designs. “As-built”
location and design considerations include: drawings document any changes.
• Providing architecturally pleasing Personnel knowledgeable and
modern pump stations with a experienced with such equipment
minimal cost increase. conduct construction inspections of
pump stations.
• Using screening walls to hide
exterior equipment and break up the
lines of the building.
• Adding landscaping and plantings to improve the overall appearance of the site.
• Determining if it is necessary or desirable to place the station entirely underground.
• Accommodating maintenance requirements by providing unobtrusive parking and work
areas adjacent to the station without encouraging their use by the public.
258
HEC-22, 4th edition Chapter 12 - Pump Stations
12.3.2 Hydrology
For traffic safety and to avoid flood hazards, engineers usually design pump stations serving
major controlled-access thoroughfares and arterial streets to accommodate a 0.02 AEP event
(AASHTO 2014). To determine the extent of flooding and the associated risk, designers also
validate the drainage system performance for the 0.01 AEP event. Keeping the drainage area
contributing to the station small reduces the size of the pumping station and minimizes negative
impacts if the pumping station malfunctions. For the same reasons, designers anticipate future
development that could contribute to increases in flow to the pumping station.
Consider the feasibility of providing storage, in addition to that which exists in the wet well, at all
pump station sites. For most highway pump stations, the high discharges associated with the
inflow hydrograph occur over a relatively short time window. Additional storage, above or below
ground, may greatly reduce the peak pumping rate. Designers can use an economic analysis to
estimate the optimum combination of storage and pumping capacity. However, once constructed,
adding pumping capacity typically involves many additional costs compared to relatively low-cost
storage volume. Chapter 10 describes procedures for storage routing.
259
Chapter 12 - Pump Stations HEC-22, 4th edition
cost/benefit. This allows comparisons of life-cycle costs and sensitivity to uncertainties of both
physical and financial constraints.
During a stormwater event, pump station operations generally include the following series of
events:
1. As stormwater flows to the pump station, the wet well or storage box stores the water, and
the water level rises to an elevation which activates the first pump.
2. If the inflow rate exceeds the pump rate, the water level will continue to rise until it causes
the second pump to start. If not, the water level will diminish until the pump stops.
3. This process continues sequentially for each pump until either the inflow rate subsides, or
enough pumps operate to equal or exceed the inflow.
4. After the pumping rate exceeds the inflow rate, the stage in the station recedes until
reaching the pump stop elevations (sequentially), eventually stopping all pumps.
5. If inflow continues at a rate lower than the output of one pump, the water level will again
rise in the wet well until a pump starts.
6. The static condition after the end of an event has a water level somewhere between the
lowest elevation for NPSH and the first pump start elevation.
Evaluation of the relationship between pump station storage and pumping rate involves
developing an inflow mass curve and routing the mass curve through the pump station. The
following sections outline these elements of the design.
12.4.1 Storage
Storage attenuates the incoming flow and reduces the demands on pump station operation. Using
the inflow hydrograph and pump-system curves, designers can try various levels of pump capacity
to determine the corresponding required total storage. Designers estimate the required storage
volume by comparing the inflow hydrograph to the controlling pump discharge rate. Stormwater
management limitations, the capacity of the receiving system, desirable pump size, or available
storage may set this controlling pump discharge rate.
Figure 12.2 depicts an inflow hydrograph and an assumed peak pumping rate. Since the inflow
hydrograph peak is greater than the pumping rate, the needed storage volume is the shaded area
above the last pump turn-on point. Allowing more of the design storm to collect in a storage facility
enables use of a smaller pump station, with anticipated cost benefits.
The location of most highway related pump stations near either short underpasses or long
depressed sections, often makes aboveground storage impracticable. Designers ensure that
water originating outside of the depressed areas does not enter the depressed areas to avoid
pumping additional water. Enlarging the collection system or constructing underground storage
represent the simplest forms of storage for such depressed situations. State DOTs typically
construct these under the roadway area or in the median, so they rarely involve additional right-
of-way.
260
HEC-22, 4th edition Chapter 12 - Pump Stations
261
Chapter 12 - Pump Stations HEC-22, 4th edition
262
HEC-22, 4th edition Chapter 12 - Pump Stations
Using this information, designers develop a mass curve routing diagram as shown in Figure 12.6.
The letters in the figure note the following sequence of events:
1. The first pump starts at point A and pump at a rate represented by the slope of the line
between A and B.
2. At point B, the storage empties and the pump turns off.
3. At point C the start volume has accumulated again, and the lead pump turns on.
4. At Point D the storage has filled to the elevation where the second pump turns on. Since
this depicts a two-pump system, both pumps will operate along the pump curve from D to
E.
5. Point E represents the elevation where the second pump turns off. At point F, the storage
has been emptied and the lead pump turns off.
The vertical lines on Figure 12.6 represent the total volume stored at any given time, such as
when a pump starts or stops. The maximum vertical distance between the inflow mass curve and
263
Chapter 12 - Pump Stations HEC-22, 4th edition
the pump discharge curve represents the amount of storage needed for that set of conditions.
The pump start elevations tie directly to the storage volume at that elevation. The designer tries
different start elevations iteratively to find a set of start elevations that minimizes the storage
needed.
Designers can use a spreadsheet to perform the calculations. With reasonably short time steps,
they can try many different combinations of start/stop elevations. They can try different pump
performance curves the same way. HEC-24 provides a detailed example of stormwater pump
station design and describes additional design, operations, and maintenance aspects.
264
HEC-22, 4th edition Chapter 12 - Pump Stations
265
Chapter 12 - Pump Stations HEC-22, 4th edition
266
HEC-22, 4th edition Literature Cited
Literature Cited
AASHTO 2000. Model Drainage Manual, American Association of State Highway and
Transportation Officials, Washington, DC.
AASHTO 2007. Highway Drainage Guidelines, 4th Edition, Washington, DC.
AASHTO 2011. Roadside Design Guide, 4th Edition, Washington DC.
AASHTO 2014. Drainage Manual, 1st Edition, American Association of State Highway and
Transportation Officials, Washington, DC.
AASHTO 2018. A Policy on Geometric Design of Highways and Streets, 7th Edition, Washington,
DC.
ACPA 1978. Concrete Pipe Design Manual, American Concrete Pipe Association, Washington,
DC.
AISI 1983. Handbook of Steel Drainage and Highway Construction Products, American Iron and
Steel Institute, Washington, DC.
Anderson, A.G., S.P. Amreek, and J.T. Davenport 1970. “Tentative Design Procedure for Riprap
Lined Channels.” NCHRP Report No. 108, Highway Research Board, National Academy of
Sciences, Washington, DC.
Anderson, D.A., J.R. Reed, R.S. Huebner, J.J. Henry, W.P. Kilareski, and J.C. Warner 1995.
Improved Surface Drainage of Pavements, NCHRP Project I-29, Pennsylvania
Transportation Institute, Pennsylvania State University, Federal Highway Administration,
Washington, DC.
APWA 1981. Urban Stormwater Management, Special Report No. 49, American Public Works
Association Research Foundation and the Institute for Water Resources, Washington, DC.
ASCE 1960. Design Manual for Storm Drainage, American Society of Civil Engineers, New York,
NY.
ASCE 1992. Design and Construction of Urban Stormwater Management Systems, ASCE
Manuals and Reports of Engineering Practice No. 77, WEF Manual of Practice FD-20,
American Society of Civil Engineers, New York, NY.
Bauer, W.J. and D.C. Woo 1964. Hydraulic Design of Depressed Curb-Opening Inlets, Highway
Research Record No. 58, Highway Research Board, Washington, DC.
Boyd, M.J. 1981. Preliminary Design Procedures for Detention Basins, Proceedings, Second
International Conference on Urban Storm Drainage, Urbana, IL.
Brater, E.F. and H.W. King 1976. Handbook of Hydraulics, 6th ed., McGraw Hill Book Company,
New York, NY.
Burgi, P.H. 1978a. Bicycle-Safe Grate Inlets Study, Volume 2 - Hydraulic Characteristics of Three
Selected Grate Inlets on Continuous Grades, FHWA-RD-78-4, Federal Highway
Administration (May).
Burgi, P.H. 1978b. Bicycle-Safe Grate Inlets Study, Volume 3 - Hydraulic Characteristics of Three
Selected Grate Inlets in a Sump Condition, FHWA-RD-78-70, Federal Highway
Administration (September).
267
Literature Cited HEC-22, 4th edition
Burgi, P.H. and D.E. Gober 1977. Bicycle-Safe Grate Inlets Study, Volume 1 - Hydraulic and
Safety Characteristics of Selected Grate Inlets on Continuous Grades, FHWA-RD-77-24,
Federal Highway Administration (June).
Chang, F.M. and R.T. Kilgore 1989. Calculation of Head Loss Coefficients for Junction Manholes,
unpublished research report prepared for the Federal Highway Administration.
Chang, F.M., R.T. Kilgore, D.C. Woo, M.P. Mistichelli 1994. Energy Losses through Junction
Manholes, “Volume I: Research Report and Design Guide,” FHWA-RD-94-080, Federal
Highway Administration, McLean, VA.
Chow, V.T. 1959. Open-Channel Hydraulics, McGraw Hill, New York, 1959.
City of Alexandria, VA 1992. Alexandria Supplement to the Northern Virginia BMP Handbook,
Department of Transportation and Environmental Protection, Alexandria, VA.
Driscoll, E.D. 1990. Pollutants Loadings and Impacts from Highway Stormwater Runoff; Volume
II, FHWA-RD-88-007, Federal Highway Administration, Washington, DC. (April).
England, J.F., Jr., T.A. Cohn, B.A. Faber, J.R. Stedinger, W.O. Thomas, Jr., A.G. Veilleux, J.E.
Kiang, and R.R. Mason, Jr. 2019. Guidelines for Determining Flood Flow Frequency—
Bulletin 17C (ver. 1.1): U.S. Geological Survey Techniques and Methods, book 4, chap. B5,
148 p.
FHWA 1977 (reprint). Design Charts for Open-Channel Flow, Hydraulic Design Series 3 (HDS-
3), U.S. Department of Transportation, Washington, DC.
FHWA 1979. Underground Disposal of Stormwater Runoff, Design Guidelines Manual FHWA-TS-
80-218, Federal Highway Administration, Washington, DC.
FHWA 1984. Drainage of Highway Pavements, Hydraulic Engineering Circular No. 12 (HEC-12),
FHWA-TS-84-202.
FHWA 1986. Culvert Inspection Manual, Final Report FHWA-IP-86-2, Federal Highway
Administration, Washington, DC.
FHWA 1993. Design of Bridge Deck Drainage, Hydraulic Engineering Circular No. 21 (HEC-21),
FHWA-SA-92-010.
FHWA 2000. “Stormwater Best Management Practices in an Ultra-Urban Setting: Selection and
Monitoring” Federal Highway Administration, Washington, DC.
FHWA 2001. Highway Stormwater Pump Station Design, Hydraulic Engineering Circular No. 24
(HEC-24), FHWA-NHI-10-007.
FHWA 2002. Highway Hydrology, Second Edition, Hydraulic Design Series No. 2 (HDS-2),
FHWA-NHI-02-001.
FHWA 2005. Design of Roadside Channels with Flexible Linings, Hydraulic Engineering Circular
No. 15 (HEC-15), Third Edition, FHWA-NHI-05-114, Federal Highway Administration,
Washington, DC.
FHWA 2006a. Hydraulic Design of Energy Dissipators for Culverts and Channels, Hydraulic
Engineering Circular No. 14, FHWA-NHI-06-086, Federal Highway Administration,
Washington, DC.
FHWA 2006b. Geotechnical Aspects of Pavements, U.S. Department of Transportation
Publication No. FHWA NHI-05-037, May.
FHWA 2008. Introduction to Highway Hydraulics, Hydraulic Design Series No. 4 (HDS-4), Fourth
Edition, FHWA-NHI-08-090, Federal Highway Administration, Washington, DC.
268
HEC-22, 4th edition Literature Cited
FHWA 2009. Highway-Runoff Database (HRDB Version 1.0)--A Data Warehouse and
Preprocessor for the Stochastic Empirical Loading and Dilution Model, U.S. Department of
Transportation, Federal Highway Administration, FHWA-HEP-09-004, 57 p.
FHWA 2012a. Hydraulic Design of Highway Culverts, Third Edition, Hydraulic Design Series No.
5 (HDS-5), FHWA-HIF-12-026.
FHWA 2012b. Hydraulic Design of Safe Bridges, Third Edition, Hydraulic Design Series No. 7
(HDS-7), FHWA-HIF-12-018.
FHWA 2014a. Determining the State of the Practice in Data Collection and Performance
Measurement of Stormwater Best Management Practices, FHWA-HEP-16-021.
FHWA 2014b. “FHWA Order 5520: Transportation System Preparedness and Resilience to
Climate Change and Extreme Weather Events,” Federal Highway Administration,
Washington, DC.
FHWA 2015. FHWA Environmental Justice Reference Guide, Federal Highway Administration,
Washington, DC, available online:
http://www.ncfrpc.org/mtpo/FullPackets/MTPO/2021/ej_guide_fhwahep15035.pdf.
FHWA 2016. Highways in the River Environment — Floodplains, Extreme Events, Risk, and
Resilience, Hydraulic Engineering Circular No. 17 (HEC-17), 2nd Edition, FHWA-HIF-16-
018, National Highway Institute, Federal Highway Administration, Arlington, VA.
FHWA 2022a. Technical Note: Curb-Opening Inlet Interception on Grade, Federal Highway
Administration, FHWA-HRT-22-061.
FHWA 2022b. Highway Hydrology: Evolving Methods, Tools, and Data, Hydraulic Engineering
Circular No. 19 (HEC-19), FHWA-HIF-22-XXX, National Highway Institute, Federal
Highway Administration, Arlington, VA.
FHWA 2022c. “Sustainable Highways Initiative, Overview” (website), Federal Highway
Administration, Washington, DC, available online:
https://www.sustainablehighways.dot.gov/overview.aspx#quest1, last accessed June 1,
2022.
FHWA 2022d, “FHWA State Asset Management Plan Under BIL,” May 5, 2022, Federal Highway
Administration, Washington, DC.
Gallaway, B.M., D.L. Ivey, G. Hayes, W.B. Ledbetter, R.M. Olson, D.L. Woods, and R.F. Schiller,
Jr. 1979. Pavement and Geometric Design Criteria for Minimizing Hydroplaning, Texas
Transportation Institute, Texas A&M University, Federal Highway Administration, Report
No. FHWA-RD-79-30, A Technical Summary.
Galli, F.J. 1990. The Peat Sand Filter: An Innovative BMP for Controlling Urban Stormwater,
Anacostia Restoration Team, Washington, DC.
Granato, G.E. 2013. “Stochastic Empirical Loading and Dilution Model (SELDM) Version 1.0.0,”
U.S. Geological Survey Techniques and Methods, book 4, chap. C3.
Granato, G.E. 2014. Statistics for Stochastic Modeling of Volume Reduction, Hydrograph
Extension, and Water-quality Treatment by Structural Stormwater Runoff Best Management
Practices (BMPs), U.S. Geological Survey Scientific Investigations Report 2014–5037.
Granato, G.E. and S.C. Jones 2019. “Simulating Runoff Quality with the Highway-Runoff
Database and the Stochastic Empirical Loading and Dilution Model,” Transportation
Research Record, Journal of the Transportation Research Board, 2673(1), 136-142.
269
Literature Cited HEC-22, 4th edition
Harvey, J. and D.R. Smith 2018. Final Report: Permeable Pavement Road Map Workshop and
Proposed Road Map for Permeable Pavement, Research Report: UCPRC-RR-2018-01,
University of California Pavement Research Center, Davis and Berkeley, CA.
Hydraulic Institute n.d. “Hydraulic Institute Standards for Vertical Turbine Pumps,” Cleveland, OH.
IUCN 2020. Global Standard for Nature-based Solutions. A User-Friendly Framework for the
Verification, Design and Scaling Up of NbS, First edition, International Union for
Conservation of Nature, Gland, Switzerland.
Izzard, C.F. 1946. “Hydraulics of Runoff from Developed Surfaces,” Proc. Highway Research
Board, 26, 29-150, Highway Research Board, Washington, DC.
Kerenyi, K., J.S. Jones, and S. Stein 2006. Junction Loss Experiments: Laboratory Report,
FHWA-HRT-07-036, July.
Kilgore, R.T. 2005. “A Proposed Storm Drain Energy Loss Methodology for Access Holes,”
presented at the Transportation Research Board 84th Annual Meeting, Washington, DC,
January 9-13.
Kilgore, R.T. 2006. A Proposed Storm Drain Energy Loss methodology for Access Holes,
unpublished report to FHWA, January.
Kranc, S.C., C.J. Cromwell, C,J. Rabens, N. Collier, and B. Fast 2005. Experimental Investigation
and Analysis of Flow Under Barrier Walls, prepared for the Florida Department of
Transportation, FL/DOT/RMC/BC-353-27.
Lane, E. 1955. “Design of Stable Channels,” Transactions ASCE, 120.
Lottes, S.A. and C. Bojanowski 2015. Hydraulic Capacity of an ADA Compliant Street Drain Grate,
Transportation Research and Analysis Computing Center, Energy Systems Division,
Argonne National Laboratory, ANL/ESD-15/25.
Malhotra, V.P. and J.M. Normann 1994. Best Management Practices Computer Model, SDN
Water Resources.
Muhammad, M.A. 2018. Interception Capacity of Curb Opening Inlets, dissertation in partial
fulfillment of the requirements for a Doctor of Philosophy, University of Texas at Austin.
NASEM 2006. Evaluation of Best Management Practices for Highway Runoff Control, National
Academies of Sciences, Engineering, and Medicine, The National Academies Press,
Washington, DC.
NASEM 2007. Roundabouts in the United States, NCHRP Report 572, National Academies of
Sciences, Engineering, and Medicine, The National Academies Press, Washington, DC.
NASEM 2010. Roundabouts: An Informational Guide, Second Edition, NCHRP Report 672,
National Academies of Sciences, Engineering, and Medicine, The National Academies
Press, Washington, DC.
NASEM 2012. Guidelines for Evaluating and Selecting Modifications to Existing Roadway
Drainage Infrastructure to Improve Water Quality in Ultra-Urban Areas, National Academies
of Sciences, Engineering, and Medicine, The National Academies Press, Washington, DC.
NASEM 2014. Long-Term Performance and Life-Cycle Costs of Stormwater Best Management
Practices, National Academies of Sciences, Engineering, and Medicine, The National
Academies Press, Washington, DC.
NASEM 2017. A Watershed Approach to Mitigating Stormwater Impacts, National Academies of
Sciences, Engineering, and Medicine, The National Academies Press, Washington, DC.
270
HEC-22, 4th edition Literature Cited
NASEM 2019. Stormwater Infiltration in the Highway Environment: Guidance Manual, National
Academies of Sciences, Engineering, and Medicine, The National Academies Press,
Washington, DC.
NASEM 2021. Guidance to Predict and Mitigate Dynamic Hydroplaning on Roadways, National
Academies of Sciences, Engineering, and Medicine, The National Academies Press,
Washington DC.
NRCS 2010. “Time of Concentration,” National Engineering Handbook, Part 630 Hydrology,
Chapter 15.
PennDOT 1994. Standards for Roadway Construction, Publication No. 72, Pennsylvania
Department of Transportation, Harrisburg, PA (March).
Pugh, C.A. 1980. Bicycle-Safe Grate Inlets Study, Volume 4 - Hydraulic Characteristics of Slotted
Drain Inlets, FHWA-RD-79-106, Federal Highway Administration (February).
Ragan, R.M. 1971. A Nomograph Based on Kinematic Wave Theory for Determining Time of
Concentration for Overland Flow, Report Number 44, Civil Engineering Department,
University of Maryland at College Park.
Reis, K.G., 2007. The National Streamflow Statistics Program: A Computer Program for
Estimating Streamflow Statistics for Ungaged Sites, Chapter 6, Book 4, Hydrologic Analysis
and Interpretation, Section A, Statistical Analysis, U.S. Geological Survey.
Sandvik, A. 1985. “Proportional Weirs for Stormwater Pond Outlets,” Civil Engineering, American
Society of Civil Engineers, New York, NY.
Sauer, V.B., W.O. Thomas, Jr., V.A. Stricker, and K.V. Wilson 1983. Flood Characteristics of
Urban Watersheds in the United States, prepared in cooperation with U.S. Department of
Transportation, Federal Highway Administration, U.S. Geological Survey Water-Supply
Paper 2207.
Schalla, F.E. 2016. “Effects of Flush Slab Supports on the Hydraulic Performance of Curb Inlets
and an Analysis of Design Equations,” thesis in partial fulfillment of the requirements for a
Master of Science in Engineering, University of Texas at Austin.
Schueler, T.R. 1987. Controlling Urban Runoff: A Practical Manual for Planning and Designing
Urban BMPs, Metropolitan Council of Governments, Washington, DC.
SCS 1986. Urban Hydrology for Small Watersheds, Technical Release No. 55, Soil Conservation
Service, U.S. Department of Agriculture.
Strecker, E.W., J.M. Kersnar, E.D. Driscoll, and R.R. Horner 1992. The Use of Wetlands for
Controlling Stormwater Pollution, Woodward-Clyde Consultants for the Terrene Institute,
Washington, DC (April).
TxDOT 2019. Hydraulic Design Manual, Texas Department of Transportation.
UDFCD 2001. Urban Storm Drainage Criteria Manual, Volume 1, Urban Drainage and Flood
Control District, Denver, CO.
USACE 1977. STORM Storage Treatment Overflow Runoff Model, User’s CPD-7, U.S. Army
Corps of Engineers, Hydrologic Engineering Center (HEC), Davis, CA.
USDA-NRCS 2021. Title 210, National Engineering Handbook, Part 650 Engineering Field
Handbook, Chapter 11, Ponds and Reservoirs, U.S. Department of Agriculture, Natural
Resources Conservation Service, Washington, DC.
USDOT 2021. “Climate Action Plan: Revitalizing Efforts to Bolster Adaptation and Increase
Resilience, U.S. Department of Transportation, Washington, DC.
271
Literature Cited HEC-22, 4th edition
USDOT 2022. Equity Action Plan, U.S. Department of Transportation, Washington, DC, available
online: https://www.transportation.gov/sites/dot.gov/files/2022-04/Equity_Action_Plan.pdf.
USEPA 2002. User’s Manual for Hydrological Simulation Program - Fortran (HSPF), EPA/600/9-
80/015. U.S. Environmental Protection Agency, Washington, DC.
USEPA 2018. Spreadsheet Tool for the Estimation of Pollutant Load (STEPL), Version 4.4. U.S.
Environmental Protection Agency, Washington, DC.
USEPA 2020. Storm Water Management Model (SWMM), U.S. Environmental Protection Agency,
Washington, DC.
USEPA 2021. Green Streets Handbook, EPA 841-B-18-001, U.S. Environmental Protection
Agency, Washington, DC.
USGS 2020. SELDM: Stochastic Empirical Loading and Dilution Model - Project page:
https://www.usgs.gov/SELDM/.
Woodward, D.E. 1983. “Hydraulic Design of a Two-Stage Risers by a Shortcut Method,”
Engineering Technical Note No. 28, Soil Conservation Service, Bromall, PA.
WSDOT 2019. Highway Runoff Manual. Washington State Department of Transportation,
Olympia, WA.
Young, G.K., D.R. Pearson, S.M. Stein, J.S. Krolak, and A.T. Atayee 1996. HYDRAIN - Integrated
Drainage Design Computer System: Version 6.0 - Volume VI: HYCHL, FHWA-SA-96-064,
June.
272
HEC-22, 4th edition Appendix A - Units
Appendix A - Units
273
Appendix A - Units HEC-22, 4th edition
274
HEC-22, 4th edition Appendix B – Spread-Discharge for Parabolic Sections
y = ax - bx 2 (B.1)
where:
a = 2H/B
b = H/B2
H = Crown height, ft (m)
B = Half width, ft (m)
Figure B.1 shows the relationships between a, b, crown height, H, and half width, B.
To determine total gutter flow, divide the cross-section into segments of equal width and compute
the discharge for each segment by Manning’s equation. The parabola can be approximated with
2 ft chords. The total discharge is the sum of the discharges in all segments.
The crown height, H, and half width, B, vary from one design to another. Since discharge is directly
related to the configuration of the cross-section, discharge-depth (or spread) relationships
developed for one configuration do not apply for roadways of other configurations, therefore, the
designer develops relationships for each roadway configuration.
The following procedure illustrates the development of a conveyance curve for a parabolic
pavement section with a half width, B = 23.9 ft and a crown height, H = 0.48 ft. The Manning’s n
= 0.016. Table B.1 summarizes the results of the procedure for spreads of 2, 4, and 6 ft.
Step 1. Choose the width of segment, ∆x.
Choose the segment width for which the vertical rise will be computed. In this case, select 2 ft
and record this in column 1 of Table B.1.
275
Appendix B – Spread-Discharge for Parabolic Sections HEC-22, 4th edition
276
HEC-22, 4th edition Appendix B – Spread-Discharge for Parabolic Sections
T = 2 ft T = 4 ft T = 6 ft
Dis- Ave. Ave. Ave.
tance Vertical Ave. Flow Flow Flow
From Rise Rise Depth Depth Depth
Curb y Ya (d) d5/3 (d) d5/3 (d) d5/3
(1) (2) (3) (4) (5) (6) (7) (8) (9)
0 0 0.0384 0.0383 0.0043 0.1083 0.0244 0.1716 0.0527
2 0.0767 0.1117 - - 0.0350 0.0037 0.0983 0.0208
4 0.1467 0.1784 - - - - 0.0316 0.0031
6 0.2100 0.2384 - - - - - -
8 0.2667 0.2917 - - - - - -
10 0.3167 0.3384 - - - - - -
12 0.3600 0.3784 - - - - - -
14 0.3967 0.4118 - - - - - -
16 0.4268 0.4385 - - - - - -
18 0.4501 0.4585 - - - - - -
20 0.4668 0.4718 - - - - - -
22 0.4768 0.4784 - - - - - -
24 0.4800 - - - - - - -
Sum - - - 0.0043 - 0.0281 - 0.0766
Table B.2 summarizes the results of the analyses for spreads of 8 to 24 ft, which are also plotted
in Figure B.2. For a given spread or flow depth at the curb, the conveyance can be read from the
figure and the discharge computed from Q = KS0.5. For a given discharge and longitudinal slope,
the flow depth or spread can be read directly from the figure by first computing the conveyance,
K = Q/S0.5, and using this value to enter the figure.
As shown in the figure, for a conveyance of 30 ft3/s (based on Q = 3 ft3/s and S = 0.01 ft/ft) the
water depth at the curve equals 0.275 ft. Using the spread curve at that depth yields a spread of
8.4 ft for the given parabolic curve parameters (H = 0.48 ft and B = 24 ft)
T (ft)
Quantity 8 10 12 14 16 18 20 22 24
d (ft) 0.267 0.317 0.360 0.397 0.427 0.450 0.467 0.477 0.480
K (ft3/s) 27.53 44.71 64.45 85.26 105.54 123.63 137.98 147.26 150.5
277
Appendix B – Spread-Discharge for Parabolic Sections HEC-22, 4th edition
Figure B.2. Conveyance curve for a parabolic cross-section with example application.
278
HEC-22, 4th edition Appendix C – Mean Velocity in a Triangular Channel
Time of flow can be estimated by use of an average velocity obtained by integration of the
Manning’s equation for a triangular channel with respect to time. The assumption of this solution
is that the flow rate in the gutter varies uniformly from Q1 at the beginning of the section to Q2 at
the inlet. Using the gutter equation (equation 5.2), Q is:
K
With K1 = u SL0.5 S1.67
x
n
where:
Q = Gutter flow, ft3/s (m3/s)
n = Manning’s roughness coefficient
SL = Gutter longitudinal slope, ft/ft (m/m)
Sx = Gutter transverse scope, ft/ft (m/m)
T = Spread, ft (m)
Ku = Unit conversion constant, 0.56 in CU (0.376 in SI)
279
Appendix C – Mean Velocity in a Triangular Channel HEC-22, 4th edition
2K u 0.5 0.67
With K 2 = SL S x
n
where:
V = Gutter velocity, ft/s (m/s)
n = Manning’s roughness coefficient
SL = Gutter longitudinal slope, ft/ft (m/m)
Sx = Gutter transverse scope, ft/ft (m/m)
T = Spread, ft (m)
Ku = Unit conversion constant, 0.56 in CU (0.376 SI)
0.25
Q
T 0.67 = (C.3)
K1
Substituting equation C.3 into equation C.2 with V = dx/dt results in:
dx K2
0.25
= 0.25 dt (C.4)
Q K1
where:
dx = Change in longitudinal distance, ft (m)
dt = Change in time, s
Here, Q = Q1 + qx and therefore dQ = qdx. Combining these with equation C.4 and performing
the integration results in:
4 0.75 K 0.25
=t
3
(Q2 − Q10.75 1 ) (C.5)
qK 2
L 3 qK 2 L
Va= = 0.25 0.75 0.75
(C.6)
t 4 K1 Q2 − Q1
3 T − T12.67
2.67
Va = K 2 2 2 2 (C.7)
4 T2 − T1
280
HEC-22, 4th edition Appendix C – Mean Velocity in a Triangular Channel
K G = ( SL0.5 S0.67
X ) / n (C.8)
T 2.67 − T12.67
Va = K u K G 2 2 2 (C.9)
T2 − T1
where:
Va = Average velocity in the gutter section between T1 and T2 locations, ft/s (m/s)
T1 = Upstream spread, ft (m)
T2 = Downstream spread, ft (m)
KG = Gutter geometry parameter
Ku = Unit conversion constant, 0.840 in CU (0.564 in SI)
281