Evolution of Operating Reserve Determination in Wind Power Integration
Evolution of Operating Reserve Determination in Wind Power Integration
W IND power has seen rapid growth in the past decade. Its
zero-cost fuel and emissions-free output provide great
benefits to consumers and society. Utility-scale wind is a new
power system operations for a particular study area, and
therefore the actual utilization of the designated operating
reserve capacity is not in fact realized in detail. Therefore,
resource and is increasing at such a rapid rate that utilities and operating reserve requirements are determined statistically, but
system operators are becoming concerned about the usually not validated in simulations. Two important objectives
integration issues and costs that it introduces. Wind power that often form part of these studies are the costs or savings of
integration studies have been performed by numerous entities integrating additional wind power and the operational changes
to help understand and quantify these impacts [1], [2]. The that are recommended at high penetrations of wind power.
studies typically simulate a future power system with high Many of the studies recommend the use of incremental
wind penetrations, and evaluate the impacts on the grid and operating reserves, which will also affect the total costs. This
the incremental operating costs that result [3]. These studies makes the assumptions used in the methodology to assess
have been maturing continuously as the state of the art operating reserve a very important component of the overall
advances, with each study generally building on previous study. Many areas will adopt these methodologies from the
studies. studies as wind penetrations increase and therefore it is
Some of these studies have compared the costs and additionally important for actual system operations in the
operational differences between a system with high wind future.
penetration and a system that does not bring the incremental This paper will focus on methods of determining operating
variability and uncertainty that wind presents. The additional reserves for power systems with high penetrations of wind
costs generally occur because the unit commitment is power. Section II will describe current practices and
inefficient due to forecast errors and because it is adjusted to definitions of operating reserves in North America, mainland
provide more flexibility, accommodating wind’s increased Europe, and Ireland. Section III will cover some recent wind
variability and uncertainty. Additional flexibility can be in the power integration studies that have been performed, and will
form of increased ramp rates, decreased minimum generation focus on the methods used in each study when calculating the
limits, and increased amounts of operating reserve. Noting that operating reserve requirements. In section IV, the authors will
provide insight into the strengths of different methods,
E. Ela and M. Milligan are with the National Renewable Energy including analysis on how the operating reserve determination
Laboratory (email: [email protected], [email protected]) problem may change in wind power integration studies and in
E. Lannoye, D. Flynn, and M. O’Malley are with the University College
Dublin (email: [email protected], [email protected],
actual system operations. Section V concludes the discussion.
[email protected])
1
B. Kirby is a private consultant (email: [email protected]) Additionally, operating reserves or ancillary services can include voltage
B. Zavadil is with Enernex Corporation (email: [email protected]) or reactive power support as well as black start service.
978-1-4244-6551-4/10/$26.00
Authorized ©2010
licensed use limited to: UNIVERSIDADE IEEEDO RIO DE JANEIRO. Downloaded on February 20,2024 at 02:56:44 UTC from IEEE Xplore. Restrictions apply.
FEDERAL
2
II. OPERATING RESERVE DEFINITIONS AND STANDARDS capacities to account for other transmission contingencies,
Variability and uncertainty are not unique to wind similar to generator operating reserve.
generation: similar characteristics in aggregate electric Other standards and policies detail how much a balancing
demand and even supply resources have always posed area will require of each type of operating reserve [4]. For
challenges for power system operators. Future loads cannot instance, the NERC BAL-002 standard requires that a
be perfectly predicted, loads and generator outputs can vary balancing authority or reserve sharing group maintain at least
substantially in different time frames, and large power system enough contingency reserve to cover the most severe single
equipment can fail at any given time without notice. Power contingency. For the western interconnection, this is extended
system operators secure different amounts and types of by a proposal by WECC to state that the minimum amount of
operating reserves to compensate for these characteristics in contingency reserve should be the greater of the most severe
order to serve load reliably and maintain the system single contingency or the sum of 3% of the balancing area
frequency. There are many different definitions and rules load and 3% of the balancing area generation. Detailed
concerning what operating reserves entail. For example, the specifications of contingency reserve requirements, including
North American Electric Reliability Corporation (NERC) the amount of spinning compared to supplemental reserve, are
defines operating reserves as the following: established by each Regional Reliability Organization.
“That capability above firm system demand required to Regions typically require at least half of the contingency
provide for regulation, load forecasting error, equipment reserve to be spinning. An example of how reserves are
forced and scheduled outages and local area protection. It deployed following a contingency is provided in Fig. 1.
consists of spinning and non-spinning reserve.” [4] Regulating reserve usually does not include explicit
In most of North America, these reserves can be further requirements. Instead, balancing areas will maintain sufficient
placed in three categories: regulating reserves so that they meet their CPS1 and CPS2
• Spinning reserve – The portion of Operating Reserve performance requirements. In some areas that currently have
consisting of: Generation synchronized to the system high penetrations of wind power, such as the Electric
and fully available to serve load within the Disturbance Reliability Council of Texas (ERCOT), the forecasted wind
Recovery Period following the contingency event; or power output is considered when defining regulating and other
Load fully removable from the system within the types of operating reserve requirements [5].
Disturbance Recovery Period following the
Market Response
contingency event.
• Supplemental reserve – The portion of Operating Supplemental Operating Reserve
Reserve consisting of: Generation (synchronized or
capable of being synchronized) that is fully available to Contingency Spinning & Non-Spinning Reserve
Occurs
serve load within the Disturbance Recovery Period
following the contingency event; or Load fully
removable from the system within the Disturbance Reserves "Should" Reserves
Recovery Period following the contingency event. be Restored "Must" be
Restored
• Regulating Reserve – An amount of reserve responsive Frequency
Response
to Automatic Generation Control which is sufficient to
provide normal regulating margin.
-10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
Further definitions can separate the second category by Minutes
response time and response sustainability. In North America, Fig. 1. Reserve deployment as defined by NERC [6]
the spinning reserve and supplemental reserve described above
are often combined and referred to as “contingency reserve”, In Europe, broad guidelines are given by the former TSO
only being used for instances of generator or network groupings such as Nordel and the Union for Coordination of
contingency events. Though contrary to the NERC definition Transmission of Electricity (UCTE), now part of the European
of operating reserve described above, regulating reserve is Network for Transmission System Operators for Electricity
generally procured in both the upward and downward (ENTSO-E). ENTSO-E defines reserve in three categories;
directions (i.e. in cases of over-generation). Fast frequency primary, secondary and tertiary control [7]. Primary control is
response (governor response) is not yet explicitly addressed by activated when system frequency deviates by 20 mHz from the
NERC as a distinct operating reserve, but the Western set point value (nominally 50 Hz) and must be fully
Electricity Coordinating Council (WECC) has started to study operational within 30 seconds. The purpose of primary control
the need for a 30 second response: frequency responsive is to limit the deviation of system frequency following a
reserve (FRR). Transmission also impacts the need for system event.
operating reserves, since it can provide access to additional Secondary control consists of units controlled by automatic
reserve supplies and reduce the overall need for reserves by generation control (AGC) and fast starting units. These are
increasing the reserve sharing pool. Limited transmission may engaged 30 seconds after a contingency event and must be
also mean more localized reserve requirements. Transmission fully operational within 15 minutes. This category of control
lines may be operated at levels below their maximum attempts to restore the frequency to its nominal value and
reduce the area control error. Tertiary control has a slower
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DO RIO DE JANEIRO. Downloaded on February 20,2024 at 02:56:44 UTC from IEEE Xplore. Restrictions apply.
3
TABLE I
NAMES AND DEFINITIONS OF RESERVES
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DO RIO DE JANEIRO. Downloaded on February 20,2024 at 02:56:44 UTC from IEEE Xplore. Restrictions apply.
4
spinning reserve are characteristics of each of the other types, reserve requirement similarly evaluated the added variability
as seen in the diagram. of wind but calculated it to be a 2 MW standard deviation for
every 100 MW wind plant installed. This calculation was
based on operational data from existing wind plants. The ratio
was used to calculate the regulating reserve requirement as
seen in equation (1).
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DO RIO DE JANEIRO. Downloaded on February 20,2024 at 02:56:44 UTC from IEEE Xplore. Restrictions apply.
5
unit capable of meeting the replacement reserve standard was horizons. In Fig. 6, where portfolio 5 contains 6 GW of wind
an off-line unit with a start up time of less than 60 minutes and generation, the requirement for replacement reserve is seen to
online units whose capacity was not allocated to the spinning exceed 3 GW in one instance. This is due to a 1 GW load rise
reserve requirement. This is a highly simplified model given at the same time as a 1 GW decrease in wind, combined with a
the existing structure of reserve provision in the Irish system. forecast error.
The requirements for spinning and replacement reserve were
based on a mixture of existing and proven requirements and
newer techniques for the provision of reserve for wind
generators.
The spinning reserve requirement is calculated as being the
size of the largest on-line unit plus an additional contribution
for wind generation, calculated based on the work in [13].
Ireland is an island system with one 500 MW interconnector
in operation and a 500 MW interconnector under construction.
System modeling for the year 2020 assumed that 100MW of
spinning reserve can be obtained through interconnection.
Another 50MW of reserve is assumed to be provided from
interruptible contract loads. Of the remainder, a constraint of a
maximum of 50% of reserve demand can be provided by Fig. 5. Average requirement for replacement reserve by time horizon
pumped storage. Wind generators are allowed to provide
spinning reserve through curtailment. 4000
Replacement Reserve
The demand for spinning reserve is illustrated in Fig. 4 on a
2000
weekly averaged basis. Spinning reserve is required more
Demand (MW)
frequently as the amount of wind increases in the portfolio, 0
significantly so in portfolio 6. The scheduled outage of the
1441
1921
2401
2881
3361
3841
4321
4801
5281
5761
6241
6721
7201
7681
8161
8641
1
481
961
largest unit on the system (480MW CCGT unit) is seen to
reduce the spinning reserve requirement significantly during
weeks 31 to 34. While the variable generation requires Hour
additional spinning reserve, the largest contributing factor
remains the loss of the largest conventional unit. P5 P3 P1
Fig. 6. Hourly requirement for replacement reserve
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DO RIO DE JANEIRO. Downloaded on February 20,2024 at 02:56:44 UTC from IEEE Xplore. Restrictions apply.
6
1%
3 2
3 IV. EVOLVING METHODS FOR DETERMINING RESERVE
REQUIREMENTS WITH HIGH PENETRATIONS OF WIND
GENERATION
The treatment of the reserve determination problem has
evolved substantially for both wind power integration studies
and in actual system operations. The authors believe that this
is a continuing trend and that there are still a number of
inconsistencies with the data and methodologies used, where
2 improvements can be made. The key issue to recognize is that
Calculations based on a balancing area with 100 GW load and 60 GW
wind, which was about the average for the largest ISO balancing areas that it is generally not difficult to be overly conservative and hold
were a part of the study. much more reserves than is needed. The real issue is knowing
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DO RIO DE JANEIRO. Downloaded on February 20,2024 at 02:56:44 UTC from IEEE Xplore. Restrictions apply.
7
what is causing the need for different types of reserves today, storage resources from providing operating reserves, when in
how high penetrations of wind power will change the needs of fact, in some cases, they could provide the service with as
reserves, and how to use as much information as is available at good or better performance than the generating resources that
any given time to determine an optimal and efficient amount had currently provided them. The amount of spinning reserve,
of operating reserves. compared to non-spinning reserve, for all of the different
The data quality used in wind power integration studies is categories should be evaluated both economically and
very crucial in the reserve determination problem. Studies are operationally. The response times for different categories
evaluating high penetrations of wind power that do not should be evaluated regarding what is optimal, and may also
currently exist so the estimated power output of the wind change depending on predicted system conditions. The sharing
generation must be modeled. Different modeling techniques between reserves should also be evaluated. For instance, if all
are usually employed where issues can often occur that differ ramping reserves are used up but a net load event continues to
the modeled output from what would be realistic. Data ramp, what are the consequences from taking contingency
quantity is also important as longer data sets and higher reserves for that purpose? Also, how should reserves be
resolution data can give much more information on the accounted for with a stochastic scheduling system that
anticipated behavior of wind power and how it affects reserve inherently schedules reserves without explicitly calling for
requirements. Lastly, the wind power forecasts used in studies them? This team has built a high resolution power system
are yet another model that may not be totally representative of model similar to those used in wind power integration studies.
wind power forecasts used in actual operations. The The model will focus on the utilization of reserves, however,
requirements for ramping reserves, load following reserves, at a very fine timescale (4-6 seconds for one day) and attempt
and regulating reserves may be highly dependent on how good to capture all of the different contributing factors that would
a wind forecast is, so it is important that the error cause the utilization of different types of operating reserves.
characteristics of the synthetic forecasts closely match those in This research should help highlight how different operating
operations today and in the future. reserves could be determined based on a function of the
Dynamic reserve requirements have been proposed in many predicted operating condition inputs. Table II shows further
of the recent studies [2], [5], [11], and [14]. In operations additional research ideas for each of the operating reserve
today, most reserves are static and even those that vary hour categories defined in Table I.
by hour are usually based on hourly rules, not on forecasted
conditions. It is important that if more reserves are needed TABLE II
OPERATING RESERVE DETERMINATION TRENDS
because of certain operating conditions, those conditions must
be taken into account when the control area operator decides
Name Trends and future research questions
the operating reserve requirement. In the future, we see it Spinning Reserve For each operating reserve category, the percentage of
possible that each balancing area operator will have a reserve reserve that is spinning should be based on reliability
requirement that is a function of load forecast, variable and economics. Quicker responses need to be spinning.
generation forecast, net load variability forecast, uncertainty For event reserves, events that occur frequently should
have more spinning reserve, based on a tradeoff between
predictions (i.e. confidence of forecasts), and possibly even spinning reserves having a higher standby cost, but non-
information on the predicted behavior of conventional spinning reserves having a higher utilization cost. Should
generation. demand response or generation that can be started in
In addition to reserve requirements that vary by time, they extremely quick times (e.g. < 1 minute) be considered
spinning?
may also vary by time horizon. Today, the majority of Non-Spinning See above. How quickly must these resources start up for
operating reserves are dominated by contingency and Reserve the different categories?
regulating reserves (considering the first tier of Fig. 3). These Contingency Should this only be used for major failures? Can we
reserves are mostly used today due to generation and Reserve share this with other categories? Can we use a fully
probabilistic approach with forced outage rates of all
transmission failures, and load and generation variability. generators and facilities, rather than simply using the
These phenomena generally are as likely to happen in the next largest hazard (for instance if many smaller units
five minutes as they are tomorrow (i.e. their likelihood does dominate a region rather than larger ones)?
not change with look-ahead horizon). On the other hand, Regulating Is this based on variability or forecast errors? Can
Reserve uncertainty or variability predictions (rather than energy
events that are caused by wind may be much better predicted
forecasts) be used for determination of the requirement?
as the operating time gets closer. This was introduced in the How good does regulating reserve have to be?
All Island Grid Study [11] for the use of replacement reserves. Load following Unit commitments are performed on an hourly resolution
When operators are more confident in the outcome of Reserve and normally load trends monotonically in one direction
operating conditions the need to hold reserves is reduced. This within an hour. High wind penetrations may change this
assumption so that load following reserves are set aside
applies mostly to ramping and load following reserves but for the hour to meet changes within the hour. Conditions
may apply to other categories as well. where the short-term economic generation and load
The last point that the authors would like to make concerns response stack has insufficient response capability need
the traditional requirements that areas throughout the world to be identified and addressed with a dedicated response
service.
have set for operating reserves. The requirements should Frequency What type of response is needed (appropriate droop)?
always be set towards the needs of the power system, not Responsive
towards the resources that are currently available to provide Reserve
those needs. This issue has arisen recently due to requirements Ramping Should the response time requirement be a function of
Reserves the net load ramp prediction? Should the spinning and
that originally precluded many demand response resources and non-spinning contribution be a function of the
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DO RIO DE JANEIRO. Downloaded on February 20,2024 at 02:56:44 UTC from IEEE Xplore. Restrictions apply.
8
confidence of the anticipated ramp event? [14] Enernex Corporation, “Eastern Wind Integration and Transmission
Supplemental How quickly should each of the categories be replaced? Study,” Prepared for the National Renewable Energy Laboratory,
Reserve Is there any reason that downward reserves should be January 2010. Available:
considered so that if too much are used that they can be http://www.nrel.gov/wind/systemsintegration/pdfs/2010/ewits_final_rep
replaced? ort.pdf.
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DO RIO DE JANEIRO. Downloaded on February 20,2024 at 02:56:44 UTC from IEEE Xplore. Restrictions apply.