Solutions
Solutions
A plastic extrusion plant will be built to produce 30 million meters of plastic extrusions per
year. The plant will run three 8-hour shifts per day, 360 days per year. For planning purposes,
the average run length = 3000 meters of extruded plastic. The average changeover time between
runs = 2.5 hr, and average extrusion speed = 15 m/min. Assume scrap rate = 1%, and average
uptime proportion per extrusion machine = 95% during run time. Uptime proportion during
changeover is assumed to be 100%. How many machines will be required to meet demand?
Solution:
30 , 000 , 000 m/ yr
Production: WL = 15(60 )m/hr(1−0 . 01) = 33,670.0 hr/yr
AT = 360(3)(8)(0.95) = 8208 hr/yr.
30 , 000 , 000 m/ yr
Changeover: number runs/yr = 3000 m/run = 10,000 runs/yr = 10,000 changeovers/yr
WL = 10,000(2.5) = 25,000 hr/yr
AT = 360(3)(8) = 8640 hr/yr per machine
33 , 670 25 , 000
+
n = 8208 8640 = 4.102 + 2.894 = 6.995 7 machines.
1. A manual assembly line must be designed for a product with annual demand = 100,000
units. The line will operate 50 wks/year, 5 shifts/wk, and 7.5 hr/shift. Work units will be
attached to a continuously moving conveyor. Work content time = 42.0 min. Assume line
efficiency = 0.96, balance delay = 0.08, and repositioning time = 6 sec. Determine
a) average hourly production rate to meet demand,
b) cycle time,
c) theoretical minimum number of workers required on the line,
d) how many workers will actually be required?
Solution:
15.11. The table below defines the precedence relationships and element times for a new model toy. (a)
Construct the precedence diagram for this job. (b) If the ideal cycle time = 1.1 min. repositioning time = 0.1
min, and uptime proportion is assumed to be 1.0, what is the theoretical minimum number of workstations
required to minimize the balance delay under the assumption that there will be one worker per station? (c)
Use the largest candidate rule to assign work elements to stations. (d) Compute the balance delay for your
solution.
Work element Te (min) Immediate predecessors
1 0.5 -
2 0.3 1
3 0.8 1
4 0.2 2
5 0.1 2
6 0.6 3
7 0.4 4,5
8 0.5 3,5
9 0.3 7,8
10 0.6 6,9
Solution: (a) Precedence diagram:
0.2
0.3 4 0.4
2 7
0.1 0.3
5 0.5
0.5 9
8
1 0.6
0.8 10
3 0.6
6
15.12Solve the previous problem using the Kilbridge and Wester method in part (c).
Solution: (a) Precedence diagram same as in Problem 15.11.
(c) Line balancing solution using the Kilbridge & Wester method:
15.13. Solve the previous problem using the ranked positional weights method in part (c).
Solution: (a) Precedence diagram same as in Problem 15.11.
(c) Line balancing solution using the Kilbridge & Wester method: