WORK METHODOLOGY

Tender for Construction of Crematorium (Electrical & Wooden &


O&M – 5 Years) under Nischay-2 in various locations in Bihar, India

 Detail survey and Geotech investigation shall be carried out at site using survey instruments and
Geotech instruments.
 Discussion will be made with client and other stakeholders to understand the requirements at site.
 Based on the requirements, layout will be prepared for the work.
 According to the approved layout, detail design will be done and the drawings will be prepared.
The design and drawings shall be vetted by NIT/ IIT.
 Based on RCC Design Drawing and Architectural Layout plan, we shall start excavation work with
help of excavators and disposal carried out by engaging sufficient dumpers.
 Where piling is required, piles of designed size will be casted and pile cap will be cast.
 Individual Footing, Stub Columns, Wall footing of Main Plant and Non-Plant bldg. shall be
constructed and backfilling carried out by earth available at site or brought from outside as per
Owner/Consultant advice.
 Rubble Soling and Grade Slab of Bldg./ Structure shall be carried out after duty compacting the
back filled earth.

SUPER — STRUCTURE:-

a) Based on Structural/RCC Drawing, Framed structure such as columns, beams, slabs shall be
constructed within time schedule with best material and workmanship.
b) Centering and from work activity for RCC slab shall be carried out with conventional plywood
/steel plates / steel prop-support etc.
c) There enforcement steel laying and concreting activity shall follow after the shuttering /
formwork is completed.
d) We shall fabricate structural steel members at site / factory fabricated and erection carried out
as per specification laid out in tender. The sheeting and tensile fabric shall be executed at site.

BRICK BLOCK MASONRY:-

The Brick / Block work shall start simultaneously with completion of farmed structure and front available
floor / area wise. The Brick / Block work shall be carried out with best locally available blocks / bricks
as per programmed.

PLASTER (INTERNAL & EXTERNAL) :-

a) The internal plastering work shall be carried out as per the Bar Chart and curing carried out
sufficiently.
b) The external plastering work of brick wall of Brick wall of Building and other structure shall be
carried out as soon as internal plaster and fixing of Door / window base frame is completed.
We shall mobilize adequate manpower / scaffolding material for carrying out this activity.
ELECTRO MECHANICAL: -

All Electro Mechanical valve viz crematorium, scrubber, fan, pump, firefighting, Electrical LT & HT and
transformer work along with plumbing shall be carried out as per specification. All materials shall be
used from standard makes. The crematorium shall be checked for proper functioning before and after
installation. The detailed check list shall be provided along with design drawings.

OTHER MISC. STRUCTURE:-

Construction of Other Misc. Structure such as underground tanks, Drainage, Roads Proving, Equipment
foundations, Equipment Foundations, Pipe racks etc. shall be carried out as per the drawings issued
by consulates and specification laid out intender / I.S. Code.

MACHINERY MOBILIZATION

DEPLOYMENT OF PLANT AND MACHINERY DURING PEAK PERIOD


Dumpers : As Required.

Concrete Mixer : As Required.

Concrete Pump : As Required.

Steel Cutting Machine : As Required.

Excavator : As Required.

Welding Machine : As Required.

Gas Cutting Set : As Required.

Shuttering formwork : As Required.

Dewatering Pump : As Required.

Polishing — Machine for Floor : As Required.

Vibrator (Elec.) : As Required.

Earth Rammer : As Required.

Wheelbarrows : As Required.

Tractor : As Required.

JCB : As Required.

Roller : As Required.
INDICATIVE FIELD QUALITY PLAN ANNEXURE-

Construction of Crematorium (Electrical & Wooden & O&M – 5 Years) under Nischay-2 in various PROJECT: PACKAGE:

places in Bihar, India ITEM : CIVIL WORK


LOGO
Sl. No Activity and operation Characteristics / instruments Class of Type of Check Quantum Of check Reference Document Acceptance Format of Remarks
check Norms Record
1 2 3 4 5 6 7 8 9 D* 10

1 MATERIALS

1.1 CEMENT (PPC)

Retesting of cement A EIC Approved 100% As per relevant IS Codes Test 


source and review of Report
MTC/ test reports
2 BRICK MASONARY

2.1 Test on Bricks

Dimensions , shape, compressive strength, water As agreed / required B Measurement/ As per relevant IS Code/ Relevant IS code Inspectio
absorption, warpage, efflorescence. Physical Test One Sample for 30,000 n Report
nos. or part thereof
2.2 Masonry construction Workmanship, verticality and alignment As agreed / required B Visual/ Physical 100% Relevant IS code , Tech SR/LB
Specs and Const. Drawings

3 FINISHING AND ALLIED WORKS

3.1 PLASTERING- MATERIAL

i Sand Deleterious Material As agreed / required B Physical Once per source Relevant IS code, Tech SR
Specs and Const. Drawings

3.2 PLASTERING - WORKMANSHIP

i Curing As agreed / required C Physical 100% Tech specifications, SR


construction drawings and
agreed methodology
ii Thickness grooves etc and finishing if plaster As agreed / required B Visual/ Random in each shift Tech Specs and Const. SR/LB
Measurement Drawings
iii Truness of plastering system As agreed / required B Visual/ Physical Random in each shift Tech Specs and Const. SR
Drawings
4 SHEETING AND OTHER WORKS

4.1 PAINTING SYSTEM - CONCRETE WORKS AND PLASTERED MASONARY SURFACES

i Materials and accessories- Oil Shade, type from brand and manufacturer as As agreed / required A EIC Approved Each batch of delivery Tech Specs and Const. Drawings SR/MTC 
Bound, Acrylic Emulsion, Chemical approved by EIC source and review of
Resistant, Oil Resistant Paint etc. MTC/ test reports

ii Surface prepration As required As agreed / required C Physical /visual Random in each shift Tech Specs and Const. Drawings SR

iii Acceptance of painted surfaces As required As agreed / required B Physical Each surface at random Tech Specs and Const. Drawings SR

5 DOORS , WINDOWS VENTILATORS & GRILL

5.1 Anodised aluminium works

i Materials- Aluminium sections As agreed / required A Visual/ Physical / For each lot received at site Relevant IS code, Tech Specs and Const. SR / LB 
MTC Drawings
ii Particle Door As agreed / required A EIC Approved For each lot received at site Relevant IS code, Tech Specs and Const. SR 
source and review of Drawings
MTC/ test reports
iii Acceptance As agreed / required B Visual/ Physical Random Tech Specs and Const. Drawings SR

5.2 Glass and glazing

i Clear float glass, wired glass, Material As agreed / required B EIC Approved For each lot received at site Relevant IS code, SR
tinted glass, curtain glass, source Tech Specs and Const. Drawings
hermetically sealed glass
ii Installation finishing and acceptance As agreed / required B Visual/ Physical Random Tech Specs and Const. Drawings SR

5.3 False Ceiling

i Materials ( gypsum glass, glass fibre membrane, As agreed / required A EIC Approved For each lot received at site Tech Specs and Const. Drawings SR 
fibre board acoustical tiles etc) source and review of
MTC/ test reports
ii Installation finishing and acceptance As agreed / required B Visual / physical Random Tech Specs and Const. Drawings SR

5.4 FLOOR FINISHES AND ALIED WORKS

5.4.1 Tiles

Ceramic, vitrified, glass mosaic, EIC Approved


acid alkali resistant, heavy duty source and review of
i Materials As agreed / required A Each lot of delivery Tech Specs and Const. Drawings SR 
cement concrete tiles MTC/ test reports

ii Finishing and acceptance As agreed / required B Physical 100% Tech Specs and Const. Drawings SR

6 WATER SUPPLY / SANITORY INSTALLATIONS

6.1 Sanitary fittings and fixtures

i Material Sanitory items and fixtures i.e. water As agreed / required B EIC Approved Each lot of delivery as per Tech Specs and Const. Drawings SR
closets, urinals, wash basins, sinks, mirrors, source Specifications
shelves, towel rail, soap containers, geyser, water
cooler, EWC etc, water supply / sanitation pipes,
manhole cover and frames etc

ii Acceptance of installations of all sanitory items As agreed / required B Acceptance 100% Tech Specs and Const. Drawings SR
and fixtures

6.2 Water Storage Tanks

i Material Over head / loft type As agreed / required A EIC Approved Each lot of delivery as per Tech Specs and Const. Drawings SR 
source Specifications
ii Aceptance and leakage As agreed / required B Acceptance Random Tech Specs and Const. Drawings SR

7.1 Coarse Aggregate Moisture content B Physical Once for each stack of Relevant IS code , Tech Specs and Const. SR/LB
100 Cu.M. or part there Drawings
of
ii Specific gravity, water absorption B Physical Once for each source & Relevant IS code , Tech Specs and Const. SR/LB/
for every change of Drawings Test
source Report
iii Sieve analysis, flakiness index, B Physical One per 100 cum., or Relevant IS code , Tech Specs and Const. SR/LB
elongation index, part thereof Drawings

viii Crushing value abrasion value B Physical -do- Relevant IS code , Tech Specs and Const. SR/LB/
Drawings Test
Report
7.2 Fine Aggregate

i Moisture content, water absorption balance , oven etc B Physical To be done every day Relevant IS code , Tech Specs and Const. SR/LB/TR
before start of work Drawings
iii All other tests similar to coarse Relevant IS code , Tech Specs and Const. SR/LB/TR
aggregates as mentioned above. Drawings
7.3 CONCRETE
ii Crushing strength (works Tests cubes) A Physical One set of 6 cubes per Relevant IS code , Tech Specs and Const. SR/LB/ 
50 CuM or part thereof Drawings Test
for each grade of Report
concrete per shift
whichever is earlier.
7.4 Concrete conveying,
placing& compaction
v Placement of concrete Visual B Physical 100% As per construction/erection methodology and SR
tech.specs / No segregation

vii Placement Visual B Physical 100% As per approved construction methodology SR

viii Compacting As required B Physical At Random IS:456 SR

ix Curing As required B Physical At Random Period of curing as per IS 456 (use gunny SR
bags / curing compound)

LEGEND: D * Records, indentified with “Tick” () shall be essentially included by supplier in QA

Legend to be used: Class # : A = Critical, B=Major, C=Minor; SR, TR, MTC, LB

Categorization Witnessing & Accepting (As per owner QA&I System)


Category ‘A’ FQA Engineer in association with Executing Engineer, Category ‘B’ Executing Engineer, Category ‘C’ Executing Engineer ;SR = Site Register , TR= Test Report,MfrTC = Manufacturer's Test Certificate

This document shall be read in conjunction with owner Tech. Specifications, BOQ, Drawings
CONSTRUCTION SCHEDULE
PROJECT NAME Construction of Crematorium (Electrical & Wooden) Under Nischay-2 in Various ULB
LOCATION Muzaffarpur
Month 1 Month 2 Month3 Month4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12

1 Mobilisation
2 Survey and investigation
3 Preparation and submission drawings
Site preparation, barricading &
4
levelling
Pile foundation with Earth
5
work(1st Stage)
Completion of all components of
6
RCC including Concreting
7 Internal- External plaster & Putty
8 All Flooring
9 Door, Window & Ventilator
10 Terrace Waterproofing
11 Plumbing( piping works)
12 Plumbing( Sanitary fittings)
13 All Electrical
Supply , Fabrication And Installation of
14
Electric Crematorium
Supply , Fabrication And Installation f
15
Wooden Crematorium
16 Solar light, SS Work, Thrash bin
17 Ornamental Work, GRC Jali
18 Horticulture
19 Balance work and handover

20 Operation and Maintenance 5 years from date of handing over