Tutorial 03with Answers
Tutorial 03with Answers
Tutorial 03
The longest path of sequential events is used to establish the projects duration because
the events in the path must be performed one after another.
Adding the duration time of activities in the critical path will result in the shortest project
length (i.e., how long it will take to perform required serial activity) to completion.
4. The float associated with each project task can only be derived following the completion of the
forward and backward passes. Explain why this is true.
The forward pass established the earliest time that activities in the network can begin and
end.
The backwards path determines the latest time that activities in the network can begin and
end.
Float time is the difference between the task’s latest and earliest end time (or the task’s
latest and earliest start time).
Hence, float cannot be calculated until forward and backward path has been completed.
5. What is the time estimate of an activity in which the optimistic estimate is 4 days, pessimistic is
12 days, and most likely is 5 days? Show your calculations.
6. Using the following information about Project A, its activities and predecessor activities below:
Activity Predecessors
A -
B A
C B
D B
E C, D
F C
G E, F
H D, G
A 7 5 2 4.8 =5 0.69
B 5 3 2 3.2 =3 0.25
C 14 8 6 8.7 =9 1.78
D 20 10 6 11 5.44
E 8 3 3 3.8 =4 0.69
F 10 5 3 5.5 =6 1.36
G 12 6 4 6.7 =7 1.78
H 16 6 5 7.5 =8 3.36
8. Using the following information about Project B, its activities and predecessor activities below:
Activity Predecessors
A -
B A
C A
D B
E C
F C
G D, E
H F, G
9. The following table contains the pessimistic, likely, and optimistic estimates for how long activities are
estimated to take for Project B.
C 16 10 8
D 22 12 8
E 10 5 5
F 12 7 5
G 14 8 6
H 18 8 7
A 9 7 4 6.8=7 0.69
B 7 5 4 5.2=5 0.25
C 16 10 8 10.7=11 1.78
D 22 12 8 13 5.44
E 10 5 5 5.8=6 0.69
F 12 7 5 7.5=8 1.36
G 14 8 6 8.7=9 1.78
H 18 8 7 9.5=10 3.36
10. Draw the AON diagram for the table given below.