PMI Lexicon
PMI Lexicon
PMI Lexicon
14 Campus Boulevard
Phone: +610-356-4600
Fax: +610-356-4647
Email: customercare@pmi.org
Internet: www.PMI.org
"PMI", the PMI logo, "PMP", the PMP logo, "PMBOK", "PgMP”, “Project Management Journal", "PM Network", and the
PMI Today logo are registered marks of Project Management Institute, Inc. The Quarter Globe Design is a trademark
of the Project Management Institute, Inc. For a comprehensive list of PMI marks, contact the PMI Legal Department.
PMI Publications welcomes corrections and comments on its books. Please feel free to send comments on
typographical, formatting, or other errors. Simply make a copy of the relevant page of the book, mark the error, and
send it to: Book Editor, PMI Publications, 14 Campus Boulevard, Newtown Square, PA 19073-3299 USA.
To inquire about discounts for resale or educational purposes, please contact the PMI Book Service Center.
No part of this work may be reproduced or transmitted in any form or by any means, electronic, manual,
photocopying, recording, or by any information storage and retrieval system, without prior written permission of the
publisher.
10 9 8 7 6 5 4 3 2
PREFACE
The PMI Lexicon of Project Management Terms is PMI’s newest tool for project,
program, and portfolio (PPP) managers. PMI stakeholders now have access to a set of
frequently used project, program, and portfolio management terms with clear and
concise definitions. Further, PMI standards committees—now equipped with a uniform
set of definitions that span related PMI standards—will be required to use the Lexicon
definitions without modification. However, like all dynamic resources at PMI, the
Lexicon will evolve and improve through a change control process. This process is
included herein to encourage recommendations for changes, new terms/definitions, and
other suggestions for improvement.
The PMI Lexicon of Project Management Terms contains only foundational terms
used within professional project, program, and portfolio management. This tool should
be used by lexicographers and standards teams as a reference source and not as a
glossary of every possible project, program, and portfolio management related term
that would normally be defined in the Glossary section of a typical PMI global standard.
PMI would like to thank the PMI standards volunteers who developed this
lexicon. Without their expertise, dedication to detail, and passion for their profession,
this Lexicon would not have been possible. The members of this committee are:
Carol Steuer, PMP, Chair
Dorothy Kangas, PMP, Vice Chair
Thomas Kurihara
Debra Miersma
Nanette Patton, PMP
Biagio Tramontana, PMP
Jesus Ruiz, PMP
M. Elaine Lazar, AStd., M.A., Project Specialist (PMI)
PMI would also like to thank the members of the Standards Member Advisory
Group (MAG) for their beneficial and important guidance on this project:
Monique Aubry, PhD, MPM
Margareth F.S. Carneiro, MSc, PMP
Chris Cartwright, MPM, PMP
Terry Cooke-Davies, PhD
Laurence Goldsmith, PMP
Paul E. Shaltry, PMP
Cyndi Snyder, PMP, EVP, MBA
This Lexicon is the intellectual property of PMI and, as such, may only be used as
permitted by PMI. PMI permits and encourages the use of specific terms and definitions
contained in this Lexicon provided that attribution to PMI is provided. However, the PMI
Lexicon of Project Management Terms may not be reproduced in whole or in part nor
may derivative works be created based on it (including but not limited to translations),
without the express written permission of PMI. For information regarding permissions,
please log onto PMI.org and click on “Knowledge Center” for links to the Permissions
FAQ and the Permissions Form.
Actual Cost. The realized cost incurred for the work performed on an activity during a
specific time period.
Backward Pass. A critical path method technique for calculating the late start and late
finish dates by working backward through the schedule model from the project end
date.
Baseline. The approved version of a work product that can be changed only through
formal change control procedures and is used as a basis for comparison.
Budget at Completion. The sum of all budgets established for the work to be
performed.
Change Control System. A set of procedures that describes how modifications to the
project deliverables and documentation are managed and controlled.
Constraint. A limiting factor that affects the execution of a project, program, portfolio,
or process.
Control Account. A management control point where scope, budget, actual cost, and
schedule are integrated and compared to earned value for performance measurement.
Corrective Action. An intentional activity that realigns the performance of the project
work with the project management plan.
Cost Variance. The amount of budget deficit or surplus at a given point in time,
expressed as the difference between the earned value and the actual cost.
Crashing. A technique used to shorten the schedule duration for the least incremental
cost by adding resources.
Critical Chain Method. A schedule method that allows the project team to place
buffers on any project schedule path to account for limited resources and project
uncertainties.
Critical Path. The sequence of activities that represents the longest path through a
project, which determines the shortest possible duration.
Critical Path Activity. Any activity on the critical path in a project schedule.
Critical Path Method. A method used to estimate the minimum project duration and
determine the amount of scheduling flexibility on the logical network paths within the
schedule model.
Data Date. A point in time when the status of the project is recorded.
Decision Tree Analysis. A diagramming and calculation technique for evaluating the
implications of a chain of multiple options in the presence of uncertainty.
Decomposition. A technique used for dividing and subdividing the project scope and
project deliverables into smaller, more manageable parts.
Discrete Effort. An activity that can be planned and measured and that yields a
specific output. (Note: Discrete effort is one of three earned value management [EVM]
types of activities used to measure work performance.)
Early Finish Date. In the critical path method, the earliest possible point in time when
the uncompleted portions of a schedule activity can finish based on the schedule
network logic, the data date, and any schedule constraints.
Early Start Date. In the critical path method, the earliest possible point in time when
the uncompleted portions of a schedule activity can start based on the schedule
network logic, the data date, and any schedule constraints.
Earned Value. The measure of work performed expressed in terms of the budget
authorized for that work.
Effort. The number of labor units required to complete a schedule activity or work
breakdown structure component, often expressed in hours, days, or weeks.
Estimate at Completion. The expected total cost of completing all work expressed as
the sum of the actual cost to date and the estimate to complete.
Estimate to Complete. The expected cost to finish all the remaining project work.
Forward Pass. A critical path method technique for calculating the early start and
early finish dates by working forward through the schedule model from the project start
date or a given point in time.
Free Float. The amount of time that a schedule activity can be delayed without
delaying the early start date of any successor or violating a schedule constraint.
Gantt Chart. A bar chart of schedule information where activities are listed on the
vertical axis, dates are shown on the horizontal axis, and activity durations are shown
as horizontal bars placed according to start and finish dates.
Lag. The amount of time whereby a successor activity is required to be delayed with
respect to a predecessor activity.
Late Finish Date. In the critical path method, the latest possible point in time when
the uncompleted portions of a schedule activity can finish based on the schedule
network logic, the project completion date, and any schedule constraints.
Late Start Date. In the critical path method, the latest possible point in time when the
uncompleted portions of a schedule activity can start based on the schedule network
logic, the project completion date, and any schedule constraints.
Lead. The amount of time whereby a successor activity can be advanced with respect
to a predecessor activity.
Lessons Learned. The knowledge gained during a project which shows how project
events were addressed or should be addressed in the future for the purpose of
improving future performance.
Level of Effort. An activity that does not produce definitive end products and is
measured by the passage of time. (Note: Level of effort is one of three earned value
management [EVM] types of activities used to measure work performance.)
Most Likely Duration. An estimate of the most probable activity duration that takes
into account all of the known variables that could affect performance.
Opportunity. A risk that would have a positive effect on one or more project
objectives.
Optimistic Duration. An estimate of the shortest activity duration that takes into
account all of the known variables that could affect performance.
Path Convergence. A relationship in which a schedule activity has more than one
predecessor.
Path Divergence. A relationship in which a schedule activity has more than one
successor.
Pessimistic Duration. An estimate of the longest activity duration, which takes into
account all of the known variables that could affect performance.
Phase Gate. A review at the end of a phase in which a decision is made to continue to
the next phase, to continue with modification, or to end a project or program.
Preventive Action. An intentional activity that ensures the future performance of the
project work is aligned with the project management plan.
Probability and Impact Matrix. A grid for mapping the probability of each risk
occurrence and its impact on project objectives if that risk occurs.
Product Life Cycle. The series of phases that represent the evolution of a product,
from concept through delivery, growth, maturity, and to retirement.
Program. A group of related projects, subprograms, and program activities that are
managed in a coordinated way to obtain benefits not available from managing them
individually.
Project Calendar. A calendar that identifies working days and shifts that are available
for scheduled activities.
Project Charter. A document issued by the project initiator or sponsor that formally
authorizes the existence of a project and provides the project manager with the
authority to apply organizational resources to project activities.
Project Life Cycle. The series of phases that a project passes through from its
initiation to its closure.
Project Management Plan. The document that describes how the project will be
executed, monitored, and controlled.
Project Manager. The person assigned by the performing organization to lead the
team that is responsible for achieving the project objectives.
Project Phase. A collection of logically related project activities that culminates in the
completion of one or more deliverables.
Project Schedule. An output of a schedule model that presents linked activities with
planned dates, durations, milestones, and resources.
Project Scope. The work performed to deliver a product, service, or result with the
specified features and functions.
Project Scope Statement. The description of the project scope, major deliverables,
assumptions, and constraints.
Requirements Traceability Matrix. A grid that links product requirements from their
origin to the deliverables that satisfy them.
Resource Calendar. A calendar that identifies the working days and shifts upon which
each specific resource is available.
Resource Leveling. A technique in which start and finish dates are adjusted based on
resource constraints with the goal of balancing demand for resources with the available
supply.
Responsibility Assignment Matrix. A grid that shows the project resources assigned
to each work package.
Risk. An uncertain event or condition that, if it occurs, has a positive or negative effect
on one or more project objectives.
Risk Acceptance. A risk response strategy whereby the project team decides to
acknowledge the risk and not take any action unless the risk occurs.
Risk Avoidance. A risk response strategy whereby the project team acts to eliminate
the threat or protect the project from its impact.
Risk Mitigation. A risk response strategy whereby the project team acts to reduce the
probability of occurrence or impact of a risk.
Risk Register. A document in which the results of risk analysis and risk response
planning are recorded.
Risk Transference. A risk response strategy whereby the project team shifts the
impact of a threat to a third party, together with ownership of the response.
Schedule Baseline. The approved version of a schedule model that can be changed
only through formal change control procedures and is used as a basis for comparison to
actual results.
Schedule Model. A representation of the plan for executing the project’s activities,
including durations, dependencies, and other planning information, used to produce a
project schedule along with other scheduling artifacts.
Schedule Model Analysis. A process used to investigate or analyze the output of the
schedule model in order to optimize the schedule
Secondary Risk. A risk that arises as a direct result of implementing a risk response.
Sponsor. A person or group that provides resources and support for the project,
program, or portfolio, and is accountable for enabling success.
Staffing Management Plan. A component of the human resource plan that describes
when and how team members will be acquired and how long they will be needed.
Successor Activity. A dependent activity that logically comes after another activity in
a schedule.
Threat. A risk that would have a negative effect on one or more project objectives.
Total Float. The amount of time that a schedule activity can be delayed or extended
from its early start date without delaying the project finish date or violating a schedule
constraint.
Trigger Condition. An event or situation that indicates that a risk is about to occur.
Variance Analysis. A technique for determining the cause and degree of difference
between the baseline and actual performance.
Work Package. The work defined at the lowest level of the work breakdown structure
for which cost and duration can be estimated and managed.
Workaround. A response to a threat that has occurred, for which a prior response had
not been planned or was not effective.