Module 2
Module 2
PROJECT MANAGEMENT
CECPM
ENGR. MARY GRACE M. VENTANILLA - CALILUNG
MODULE 2
CONSTRUCTION ESTIMATES
Ø Site Development Plan
Ø Architectural Plan
Ø Structural Plan
Ø Electrical Plan
Ø Plumbing Plan
ü Floor Plan
ü Elevation
ü Section
ü Roof Plan / Roof Deck Plan
ü Reflected Ceiling Plan
ü Schedule of Doors and Windows
ü Detail of Toilet
ü Detail of Railings / Stairs
ü Spot Details
ü Foundation Plan
ü Framing Plan
o 2nd Floor Framing Plan
o Stair Framing Plan
o Roof Framing Plan
ü Truss Details
ü Schedule
o Footing
o Column
o Beams / Girders
o Slab
ü Legend
ü Lighting Layout
ü Power Layout
ü Details
ü Isometric View
ü Rough – in Layout
ü Plumbing Layout
Ø Excavation Ø Windows
Ø Reinforced Concrete Ø Carpentry
Ø Masonry Ø Roof Truss & Accessories
Ø Plastering Ø Roofing Materials
Ø Embankment Ø Plumbing Fixtures
Ø Tileworks Ø Electrical Works
Ø Floor Finish Ø Painting
Ø Doors Ø Railings
WHAT’S IMPORTANT?
• Foundation Plan
• Schedule of Footing
WHAT TO COMPUTE?
• Volume
• Dimension of Footing / Tie Beam / Wall Footing
• Depth of Excavation
WHAT DO WE NEED?
ü Foundation Plan
ü Schedule of Footing / Tie Girder / Wall Footing
𝑽𝒐𝒍𝒖𝒎𝒆 = 𝑳 𝒙 𝑾 𝒙 𝑫 𝒙 𝑪𝒐𝒖𝒏𝒕
Distance from NGL
to Bottom of
Footing
FOUNDATION PLAN COLUMN SCHEDULE
ELEVATION OF COLUMN
WHAT DO WE NEED?
ü Foundation Plan
ü Framing Plan
ü Elevation Plan
ü Schedule of Footing / Tie Girder / Wall Footing
ü Schedule of Column / Beam / Slab
FOUNDATION PLAN COLUMN SCHEDULE
ELEVATION OF COLUMN
2nd & 3rd FLOOR FRAMING PLAN
SCHEDULE OF SLABS
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
JUST AN ESTIMATE
HOW TO COMPUTE?
ü Footing
𝑽𝒐𝒍𝒖𝒎𝒆 = 𝑳 𝒙 𝑾 𝒙 𝒕 𝒙 𝑪𝒐𝒖𝒏𝒕
ü Column
𝑽𝒐𝒍𝒖𝒎𝒆 = 𝑳 𝒙 𝑾 𝒙 𝑯 𝒙 𝑪𝒐𝒖𝒏𝒕
ü Beams / Girders
𝑽𝒐𝒍𝒖𝒎𝒆 = 𝑩 𝒙 𝑫 𝒙 𝑳 𝒙 𝑪𝒐𝒖𝒏𝒕
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
JUST AN ESTIMATE
HOW TO COMPUTE?
ü Slab
𝑽𝒐𝒍𝒖𝒎𝒆 = 𝑳 𝒙 𝑾 𝒙 𝒕 𝒙 𝑵𝒐. 𝒐𝒇 𝒔𝒑𝒂𝒏𝒔
S1 S1
S1 S1
ü Slab on Fill
𝑽𝒐𝒍𝒖𝒎𝒆 = 𝑳 𝒙 𝑾 𝒙 𝒕
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
JUST AN ESTIMATE
HOW TO COMPUTE?
LANDIN
ü Stairs G
o Landing OF
HY
G TH
𝑽𝒐𝒍𝒖𝒎𝒆 = 𝑳 𝒙 𝑾 𝒙 𝒕 E PO N
TE LE EAD
N
US TR
o Stair Slab
𝑽𝒐𝒍𝒖𝒎𝒆 = 𝑯𝒚𝒑𝒐𝒕𝒆𝒏𝒖𝒔𝒆 𝒙 𝑳𝒕𝒓𝒆𝒂𝒅 𝒙 𝒕
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
JUST AN ESTIMATE
HOW TO COMPUTE?
ü Stairs
o Treads
𝟏
𝑽𝒐𝒍𝒖𝒎𝒆 = 𝑳𝒓𝒖𝒏 𝒙 𝑯𝒓𝒊𝒔𝒆 𝒙 𝑳𝒕𝒓𝒆𝒂𝒅 𝒙 𝑵𝒐. 𝒐𝒇 𝒔𝒕𝒆𝒑𝒔
𝟐
RUN
RISE
OF
TH
E NG D
L EA
TR
How to compute total volume?
How to compute formworks? BOARD FOOT OF WOOD FRAME FOR COLUMN AND BEAM PER
PLYWOOD FORM pg.184
POST BEAM
Ø Columns SIZE OF WOOD 12 MM 12 MM
Ø 𝑃 = 2 𝑏 + 𝑑 + 0.20𝑚 FRAME 6 MM (1/4") (1/2") 6 MM (1/4") (1/2")
How to compute formworks? BOARD FOOT OF WOOD FRAME FOR COLUMN AND BEAM PER
PLYWOOD FORM pg.184
POST BEAM
Ø Beams / Girders SIZE OF WOOD 12 MM 12 MM
Ø 𝑃 = 2𝑑 + 𝑏 + 0.10𝑚 FRAME 6 MM (1/4") (1/2") 6 MM (1/4") (1/2")
Ø Slab
)*+,
Ø 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑜𝑓 𝑃𝑙𝑦𝑤𝑜𝑜𝑑 =
-$.+ '/ 012#''3
How to compute scaffolding / staging?
Ø Column / Post
Ø 𝑇𝑜𝑡𝑎𝑙 𝐿𝑒𝑛𝑔𝑡ℎ = 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑒𝑎𝑐ℎ 𝑐𝑜𝑙𝑢𝑚𝑛 𝑥 𝑁𝑜. 𝑜𝑓 𝐶𝑜𝑙𝑢𝑚𝑛𝑠
Ø 𝑉𝑒𝑟𝑡𝑖𝑐𝑎𝑙 = 𝑇𝑜𝑡𝑎𝑙 𝐿𝑒𝑛𝑔𝑡ℎ 𝑥 𝐹𝑎𝑐𝑡𝑜𝑟
Ø 𝐻𝑜𝑟𝑖𝑧𝑜𝑛𝑡𝑎𝑙 = 𝑇𝑜𝑡𝑎𝑙 𝐿𝑒𝑛𝑔𝑡ℎ 𝑥 𝐹𝑎𝑐𝑡𝑜𝑟
Ø 𝐵𝑟𝑎𝑐𝑒 = 𝑇𝑜𝑡𝑎𝑙 𝐿𝑒𝑛𝑔𝑡ℎ 𝑥 𝐹𝑎𝑐𝑡𝑜𝑟
Simplified Construction Estimate by Max B. Fajardo
QUANTITY OF LUMBER FOR SCAFFOLDING OR STAGING pg.195
LUMBER COLUMN BEAM FLOORING
SIZE BOARD FT. PER M. HT. BOARD FT. PER M. HT. BOARD FT.
VERTICAL HOR. BRACE VERTICAL HOR. PER SQ.M.
2" x 2" 4.70 21.00 11.70 4.00 4.70 6.10
2" x 3" 7.00 31.67 17.50 6.00 7.00 9.10
2" x 4" 9.35 42.25 23.35 8.00 9.35 12.10
How to compute scaffolding / staging?
Ø Beams / Girders
Ø 𝑇𝑜𝑡𝑎𝑙 𝐿𝑒𝑛𝑔𝑡ℎ = 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑒𝑎𝑐ℎ 𝐵𝑒𝑎𝑚 𝑥 𝑁𝑜. 𝑜𝑓 𝐵𝑒𝑎𝑚𝑠
Ø 𝑉𝑒𝑟𝑡𝑖𝑐𝑎𝑙 = 𝑇𝑜𝑡𝑎𝑙 𝐿𝑒𝑛𝑔𝑡ℎ 𝑥 𝐹𝑎𝑐𝑡𝑜𝑟
Ø 𝐻𝑜𝑟𝑖𝑧𝑜𝑛𝑡𝑎𝑙 = 𝑇𝑜𝑡𝑎𝑙 𝐿𝑒𝑛𝑔𝑡ℎ 𝑥 𝐹𝑎𝑐𝑡𝑜𝑟
Simplified Construction Estimate by Max B. Fajardo
QUANTITY OF LUMBER FOR SCAFFOLDING OR STAGING pg.195
LUMBER COLUMN BEAM FLOORING
SIZE BOARD FT. PER M. HT. BOARD FT. PER M. HT.
BOARD FT.
VERTICAL HOR. BRACE VERTICAL HOR. PER SQ.M.
2" x 2" 4.70 21.00 11.70 4.00 4.70 6.10
2" x 3" 7.00 31.67 17.50 6.00 7.00 9.10
2" x 4" 9.35 42.25 23.35 8.00 9.35 12.10
How to compute scaffolding / staging?
Ø Slab
Ø 𝑇𝑜𝑡𝑎𝑙 𝐴𝑟𝑒𝑎 = 𝐴𝑟𝑒𝑎 𝑜𝑓 𝑒𝑎𝑐ℎ 𝑆𝑙𝑎𝑏 𝑥 𝑁𝑜. 𝑜𝑓 𝑆𝑙𝑎𝑏𝑠
Ø 𝐹𝑙𝑜𝑜𝑟 𝑆𝑙𝑎𝑏 𝑆𝑐𝑎𝑓𝑓𝑜𝑙𝑑𝑖𝑛𝑔 = 𝑇𝑜𝑡𝑎𝑙 𝐴𝑟𝑒𝑎 𝑥 𝐹𝑎𝑐𝑡𝑜𝑟
ü Foundation Plan
ü Framing Plan
ü Elevation Plan
ü Schedule of Footing / Tie Girder / Wall Footing
ü Schedule of Column / Beam / Slab
FOUNDATION PLAN COLUMN SCHEDULE
ELEVATION OF COLUMN
2nd & 3rd FLOOR FRAMING PLAN
SCHEDULE OF SLABS
HOW TO COMPUTE?
ü Footing
o Main Bar
x-bar: 𝐵𝑎𝑟 𝐿𝑒𝑛𝑔𝑡ℎ = 𝐿 − 2(𝑐𝑙𝑒𝑎𝑟 𝑐𝑜𝑣𝑒𝑟) Lx
y-bar: 𝐵𝑎𝑟 𝐿𝑒𝑛𝑔𝑡ℎ = 𝑊 − 2(𝑐𝑙𝑒𝑎𝑟 𝑐𝑜𝑣𝑒𝑟) Ly
ü Footing
o Tie Wire
𝑁𝑜. 𝑜𝑓 𝐼𝑛𝑡𝑒𝑟𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑠 = 𝑆𝑒𝑡𝑠 𝑜𝑓 𝑥 − 𝑏𝑎𝑟 𝑥 𝑆𝑒𝑡𝑠 𝑜𝑓 𝑦 − 𝑏𝑎𝑟 𝑥 𝑁𝑜. 𝑜𝑓 𝑓𝑜𝑜𝑡𝑖𝑛𝑔𝑠
ü Column Ties
ü Estimating Bill of Materials by Vicente A. Tagayun pp D-30 to D-37
ESTIMATING VERTICAL REINFORCING BARDS FOR COLUMNS Estimating Bill of Materials by Vicente A. Tagayun
LONGITUDINAL BARS IN CONTINUOUS BEAMS AND GIRDERS
Estimating Procedures Formulas for Calculating Straight Length of
Size/Diameter of Longitudinal Bar
Longitudinal Bars
1. Study the FOUNDATION PLAN and the FLOOR FRAMING PLANS of the project 12mm (1/2") Bar Straight Length = Beam overall Length + 0.30m
to find out the number of columns to be erected. Classify or group them by length
of column and size of vertical bars
16mm (5/8") Bar Straight Length = Beam overall Length + 0.35m
20mm (3/4") Bar Straight Length = Beam overall Length + 0.45m
2. From the DETAILS OF COLUMNS AND FOOTINGS or SCHEDULES OF 25mm (1") Bar Straight Length = Beam overall Length + 0.55m
REINFORCING BARS of the project, determine the number and sizes of vertical
bars used in each column.
3. Determine the length of a typical column in each group by computing the distance
between the bottom of the footing to the top of the highest beam or girder
supported by the columns.
4. Calculate the length of each vertical bar by adding to the height of the column
minimum factor for determining the straight length of bars in beams found on page
D.5, based on the diameter of the bars.
5. Compute the total length of all the bars in each column by multiplying the number
of bars per column by the length of each bar
6. Get the total length of all the bars for all columns in the group by multiplying the
total length of all bars in each column by the total number of columns
7. Finally, calculate the total number of full-length bars required by multiplying the
total length of all the bars for all columns in each group by 1.10 – to add 10% as
allowance for splices and wastages; then dividing it by the selected length of full-
length bars to be ordered from the supplier
ü Column
o Tie Wire
𝑁𝑜. 𝑜𝑓 𝐼𝑛𝑡𝑒𝑟𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑠 = 𝑁𝑜. 𝑜𝑓 𝑀𝑎𝑖𝑛 𝐵𝑎𝑟𝑠 𝑥 𝑆𝑒𝑡𝑠 𝑜𝑓 𝑇𝑖𝑒𝑠
ü Beams / Girders
o Tie Wire
𝑁𝑜. 𝑜𝑓 𝐼𝑛𝑡𝑒𝑟𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑠 = 𝑁𝑜. 𝑜𝑓 𝑀𝑎𝑖𝑛 𝐵𝑎𝑟𝑠 𝑥 𝑆𝑒𝑡𝑠 𝑜𝑓 𝑇𝑖𝑒𝑠
ü Slab
o Identify whether the slab is one – way or two – way slab
𝑆𝑚𝑎𝑙𝑙𝑒𝑟 𝐷𝑖𝑚𝑒𝑛𝑠𝑖𝑜𝑛
𝑅𝑎𝑡𝑖𝑜 =
𝐿𝑎𝑟𝑔𝑒𝑟 𝐷𝑖𝑚𝑒𝑛𝑠𝑖𝑜𝑛
ü Slab
o Compute the area of each slab and multiply by the factor based on the
spacing of bars (schedule of slab) and length of RSB. Use Table from
Fajardo (Table 3-10 pp. 133 or Table 3-12 pp. 137)
o Compute the quantity of tie wires in kilograms by multiplying the area by
the factor based on the length of tie wire, bar spacing and length of RSB.
Use Table from Fajardo (Table 3-11 pp. 133 or Table 3-13 pp. 137))
Simplified Construction Estimate by Max B. Fajardo
REINFORCEMENT TABLE 3-10 QUANTITY OF REINFORCING STEEL BARS IN ONE-WAY REINFORCED CONCRETE SLAB
Number of Steel Bars per Square Meter
Bar Spacing cm.
6.00 M 7.50 M 9.00 M 12.00 M
10.0 3.764 2.937 2.421 1.769
12.5 3.062 2.381 1.934 1.427
15.0 2.584 2.004 1.636 1.197
17.5 2.232 1.726 1.407 1.033
10.0 1.980 1.528 1.258 0.914
22.5 1.786 1.369 1.109 0.810
25.0 1.627 1.250 1.014 0.736
TABLE 3-11 QUANTITY OF TIE WIRE ON A ONE-WAY REINFORCED CONCRETE SLAB IN KG PER SQM
Length of Steel Bars
Bar Spacing cm. 6.00 M 7.50 M 9.00 M 12.00 M
0.30 0.40 0.30 0.40 0.30 0.40 0.30 0.40
10.0 0.474 0.632 0.462 0.616 0.460 0.614 0.448 0.598
12.5 0.316 0.422 0.307 0.409 0.295 0.394 0.293 0.391
15.0 0.228 0.303 0.217 0.289 0.214 0.285 0.207 0.276
17.5 0.168 0.224 0.162 0.216 0.158 0.210 0.153 0.204
10.0 0.132 0.175 0.126 0.168 0.125 0.167 0.120 0.160
22.5 0.110 0.147 0.102 0.135 0.099 0.132 0.095 0.126
25.0 0.089 0.118 0.086 0.114 0.081 0.108 0.077 0.103
Simplified Construction Estimate by Max B. Fajardo
REINFORCEMENT TABLE 3-12 QUANTITY OF REINFORCING STEEL BARS IN TWO-WAY REINFORCED CONCRETE SLAB
Number of Steel Bars per Square Meter
Bar Spacing cm.
6.00 M 7.50 M 9.00 M 12.00 M
10.0 4.369 3.337 2.772 2.022
12.5 3.603 2.662 2.245 1.635
15.0 3.221 2.296 1.921 1.382
17.5 2.647 2.025 1.650 1.196
10.0 2.360 1.775 1.461 1.056
22.5 2.168 1.601 1.312 0.907
25.0 1.977 1.466 1.217 0.862
TABLE 3-13 QUANTITY OF TIE WIRE ON A TWO-WAY REINFORCED CONCRETE SLAB IN KG PER SQM
Length of Steel Bars
Bar Spacing cm. 6.00 M 7.50 M 9.00 M 12.00 M
0.30 0.40 0.30 0.40 0.30 0.40 0.30 0.40
10.0 0.592 0.896 0.648 0.863 0.648 0.864 0.596 0.794
12.5 0.416 0.554 0.420 0.560 0.431 0.574 0.421 0.561
15.0 0.350 0.466 0.307 0.409 0.257 0.343 0.297 0.396
17.5 0.247 0.330 0.231 0.308 0.223 0.298 0.206 0.275
10.0 0.174 0.232 0.171 0.227 0.173 0.231 0.163 0.217
22.5 0.168 0.224 0.150 0.200 0.148 0.198 0.130 0.173
25.0 0.142 0.189 0.134 0.178 0.114 0.152 0.116 0.155
HOW TO COMPUTE?
Length per set
ü Slab on Fill
𝐿𝑒𝑛𝑔𝑡ℎ − 2 (0.075𝑚)
𝑁𝑜. 𝑜𝑓 𝑠𝑒𝑡𝑠 (𝑦 − 𝑏𝑎𝑟) = +1
𝑆𝑝𝑎𝑐𝑖𝑛𝑔
𝑊𝑖𝑑𝑡ℎ − 2 (0.075𝑚)
𝑁𝑜. 𝑜𝑓 𝑠𝑒𝑡𝑠 (𝑥 − 𝑏𝑎𝑟) = +1
𝑆𝑝𝑎𝑐𝑖𝑛𝑔
𝐿𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑠𝑒𝑡 𝑥 𝑁𝑜. 𝑜𝑓 𝑠𝑒𝑡𝑠
𝑁𝑜. 𝑜𝑓 𝑝𝑐𝑠 = 𝑥1.10
𝐶ℎ𝑜𝑠𝑒𝑛 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑟𝑒𝑏𝑎𝑟
HOW TO COMPUTE?
ü Slab on Fill
o Tie Wire
𝑁𝑜. 𝑜𝑓 𝐼𝑛𝑡𝑒𝑟𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑠 = 𝑆𝑒𝑡𝑠 𝑜𝑓 𝑥 − 𝑏𝑎𝑟 𝑥 𝑆𝑒𝑡𝑠 𝑜𝑓 𝑦 − 𝑏𝑎𝑟
ü Stairs
o Landing - the same as slab (one – way or two – way)
o Stair Slab – almost same concept as slab on fill and slab / landing
o Treads – estimate per tread then multiply it with the number of treads
WHAT DO WE NEED?
ü Floor Plan
ü Elevation Plan
ü Schedule of Doors and Windows
ü Spot Details
FOUNDATION PLAN COLUMN SCHEDULE
HOW TO COMPUTE?
ü Rectangular Area
𝑨𝒓𝒆𝒂𝑬 = 𝑳 𝒙 𝑯 − 𝑨𝒐𝒑𝒆𝒏𝒊𝒏𝒈𝒔
EXPOSED:
Those above the FGL
𝑨𝒓𝒆𝒂𝑼𝑬 = 𝑳 𝒙 𝑯
UNEXPOSED:
Those below FGL
ü Triangular Area
𝟏
𝑨𝒓𝒆𝒂 = (𝑳 𝒙 𝑾)
𝟐
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
JUST AN ESTIMATE
HOW TO COMPUTE?
HOW TO COMPUTE?
ü Determine the vertical spacing as well as the layer spacing and the
preferred length of tie wire.
𝑸𝒖𝒂𝒏𝒕𝒊𝒕𝒚 𝒐𝒇𝑻𝒊𝒆 𝑾𝒊𝒓𝒆𝒔 (𝒌𝒈𝒔) = 𝑨𝒓𝒆𝒂 𝒙 𝒇𝒂𝒄𝒕𝒐𝒓 Table 3-6 pp
102 Fajardo
Book
What do we need?
ü Floor Plan
ü Elevation Plan
ü Schedule of Doors and Windows
ü Spot Details
Simplified Construction Estimate by Max B. Fajardo
HOW TO COMPUTE? TABLE 2-4 QUANTITY OF CEMENT AND SAND FOR PLASTER PER SQ.M AREA
Cement in Bags Thickness of Plaster
Mixture Class
8 mm 12 mm 16 mm 20 mm 25 mm
A 0.144 0.216 0.288 0.360 0.450
B 0.096 0.144 0.192 0.240 0.300
C 0.072 0.108 0.144 0.180 0.225
ü Area D
Sand
0.060
0.008
0.090
0.012
0.120
0.016
0.150
0.020
0.188
0.025
𝑨𝒓𝒆𝒂 = 𝑬𝒙𝒑𝒐𝒔𝒆𝒅 𝑨𝒓𝒆𝒂 𝒙 𝟐 𝒇𝒂𝒄𝒆𝒔
Area
computed in
ü Identify the Class and thickness of plaster
masonry
ü Cement 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 = 𝐴𝑟𝑒𝑎 𝑥 𝑚𝑢𝑙𝑡𝑖𝑝𝑙𝑖𝑒𝑟
ü Sand 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 = 𝐴𝑟𝑒𝑎 𝑥 𝑚𝑢𝑙𝑡𝑖𝑝𝑙𝑖𝑒𝑟
Table 2-4 pp.
56 Fajardo
Book
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
JUST AN ESTIMATE
HOW TO COMPUTE?
ü Foundation Plan
ü Schedule of Footing, Column, Beams, Slab
ü Elevation
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
JUST AN ESTIMATE
HOW TO COMPUTE?
HOW TO COMPUTE?
ü Floor Plan
ü Detailed Plan of Toilet
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
JUST AN ESTIMATE
HOW TO COMPUTE?
ü Floor Area
𝑨𝒓𝒆𝒂 = 𝑳𝒆𝒏𝒈𝒕𝒉 𝒙 𝑾𝒊𝒅𝒕𝒉
ü Wall Area
𝑨𝒓𝒆𝒂 = 𝑳𝒆𝒏𝒈𝒕𝒉 𝒙 𝑾𝒊𝒅𝒕𝒉 − 𝑶𝒑𝒆𝒏𝒊𝒏𝒈𝒔
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
JUST AN ESTIMATE
HOW TO COMPUTE?
ü Quantity of Tiles
𝑨𝒓𝒆𝒂 𝒐𝒇 𝑭𝒍𝒐𝒐𝒓 𝒐𝒓 𝑾𝒂𝒍𝒍
𝑵𝒐. 𝒐𝒇 𝒑𝒊𝒆𝒄𝒆𝒔 = 𝒙 𝑭. 𝑺
𝑳 𝒙 𝒘 𝒕𝒊𝒍𝒆
Table 7-1 pp.
ü Additional 244 Fajardo
Book
ü Cement Mortar 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑖𝑛 𝐵𝑎𝑔𝑠 = 𝑇𝑜𝑡𝑎𝑙 𝐴𝑟𝑒𝑎 𝑥 0.086
ü W.C. Joint Filler 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑖𝑛 𝐾𝑔𝑠. = 𝑇𝑜𝑡𝑎𝑙 𝐴𝑟𝑒𝑎 𝑥 0.50
ü Tile Adhesive𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑖𝑛 𝐵𝑎𝑔𝑠 = 𝑇𝑜𝑡𝑎𝑙 𝐴𝑟𝑒𝑎 𝑥 0.11
WHAT TO DO?
A
8 mm
0.144
12 mm
0.216
16 mm
0.288
20 mm
0.360
25 mm
0.450
B 0.096 0.144 0.192 0.240 0.300
C 0.072 0.108 0.144 0.180 0.225
ü Floor Area D
Sand
0.060
0.008
0.090
0.012
0.120
0.016
0.150
0.020
0.188
0.025
HOW TO COMPUTE?
HOW TO COMPUTE?
ü For ceiling using plywood, get the total area and divide
it by the standard size of plywood, 8’x4’ (2.40mx1.20m)
ü For the joist, compute the total length and divide it by
the commercially available length to know the number
of pieces needed
𝑻𝒐𝒕𝒂𝒍 𝑳𝒆𝒏𝒈𝒕𝒉 𝒊𝒏 𝒎𝒆𝒕𝒆𝒓𝒔
𝑵𝒐. 𝒐𝒇 𝒑𝒊𝒆𝒄𝒆𝒔 =
𝑪𝒉𝒐𝒔𝒆𝒏 𝑳𝒆𝒏𝒈𝒕𝒉 𝒊𝒏 𝒎𝒆𝒕𝒆𝒓𝒔
ü For woods, covert it to board foot
𝑵𝒐. 𝒐𝒇 𝒑𝒊𝒆𝒄𝒆𝒔 𝒙 𝒍𝒆𝒏𝒈𝒕𝒉 𝒇𝒕 𝒙 𝒘𝒊𝒅𝒕𝒉 𝒊𝒏 𝒙 𝒕𝒉𝒊𝒄𝒌𝒏𝒆𝒔𝒔 (𝒊𝒏)
𝑩𝒐𝒂𝒓𝒅 𝑭𝒐𝒐𝒕 =
𝟏𝟐
What’s important?
• Roof Framing Plan
• Truss Details
• Spot Details
What to compute? ü Cross – bracings
ü Angle Bar
ü Gusset Plate
ü Base Plate
ü Anchor Bolts
ü Purlins
ü Sagrods
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
JUST AN ESTIMATE
HOW TO COMPUTE?
HOW TO COMPUTE?
HOW TO COMPUTE?
ü For C – Purlins:
ü Divide the length of the top chord (each side) and divide it by the purlin
spacing plus 1 to get the number of sets needed in the entire length (as
seen on the roof plan). This is where you nail the roofing materials. Total
length shall be divided by 6m which is the standard length of purlins
ü For Sagrods:
ü Determine the spacing of purlins and the number of trusses. Typically, it is
located in between purlins and between trusses. The length of sagrods is
basically equal to spacing of purlins plus an additional length where screw
can be placed
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
JUST AN ESTIMATE
HOW TO COMPUTE?
DETAIL OF T-I
PURLIN CONNECTION DETAIL CONNECTION DETAIL HALF TRUSS CONNECTION DETAIL SAG ROD CONNECTION DETAIL TYPICAL TRUSS ANCHORAGE DETAIL
WHAT IS NEEDED?
ü Roof Plan
ü Detail of Eaves
WHAT TO COMPUTE?
ü Area (sq.m)
ü Pieces of Corrugated GI Sheet
ü Pieces of Plain GI Sheet
ü Pieces of PVC Pipe
ü Pieces of Couplings
TABLE 6-2 EFFECTIVE COVERING OF G.I. ROOFING
JUST USE THE ON CENTER
HOW TO COMPUTE? DISTANCES SINCE THIS IS Length
SHEETS
Effective Covering
Purlin
Number of
Side Lapping Nails or
Feet - Spacing in
JUST AN ESTIMATE Meter 1 1/2 2 1/2 Meter
Rivets per
Sheet
5' - 1.50 0.70 0.60 0.60 14
ü GI Roofing 6' - 1.80
7' - 2.10
0.70
0.70
0.60
0.60
0.75
0.60
14
18
?'%,1 6+78%& 8' - 2.40 0.70 0.60 0.70 18
ü 𝑁𝑜. 𝑜𝑓 𝑝𝑐𝑠. 𝑝𝑒𝑟 𝑟𝑜𝑤 = 9' - 2.70 0.70 0.60 0.60 22
6,>>$78
10' - 3.00 0.70 0.60 0.67 22
6+78%& '/ '7+ ;$3+ ?'> S&'*3
ü 𝑁𝑜. 𝑜𝑓 𝑟𝑜𝑤𝑠 = 12' - 3.60 0.70 0.60 0.66 26
)>>*'>*$,%+ 6+78%& 5,;+3 '7 0(*1$7 ->,T$78
ü 𝑁𝑜. 𝑜𝑓 𝑃𝑖𝑒𝑐𝑒𝑠 = 𝑁𝑜. 𝑜𝑓 𝑝𝑐𝑠. 𝑝𝑒𝑟 𝑟𝑜𝑤 𝑥 𝑁𝑜. 𝑜𝑓 𝑟𝑜𝑤𝑠 𝑥 2 𝑠𝑖𝑑𝑒𝑠 (𝑖𝑓 𝑑𝑜𝑠 𝑎𝑔𝑢𝑎𝑠)
ü Roof Nails / Rivets
ü 𝑁𝑜. 𝑜𝑓 𝑝𝑐𝑠. = 𝑁𝑜. 𝑜𝑓 𝑝𝑐𝑠 𝐺𝐼 𝑅𝑜𝑜𝑓 𝑥 𝐹𝑎𝑐𝑡𝑜𝑟
Table 6-2 pp.
206 Fajardo
Book
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
HOW TO COMPUTE? JUST AN ESTIMATE
ü Plain GI Sheet
ü Ridge Roll
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑅𝑖𝑑𝑔𝑒 𝑅𝑜𝑙𝑙
𝑁𝑜. 𝑜𝑓 𝑝𝑐𝑠. 𝑜𝑓 𝑅𝑖𝑑𝑔𝑒 𝑅𝑜𝑙𝑙 =
2.20
ü Flashing Table 6-6 pp.
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐹𝑙𝑎𝑠ℎ𝑖𝑛𝑔 221 Fajardo
𝑁𝑜. 𝑜𝑓 𝑝𝑐𝑠. 𝑜𝑓 𝐹𝑙𝑎𝑠ℎ𝑖𝑛𝑔 = Book
2.30
ü Gutter
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐺𝑢𝑡𝑡𝑒𝑟
𝑁𝑜. 𝑜𝑓 𝑝𝑐𝑠. 𝑜𝑓 𝐺𝑢𝑡𝑡𝑒𝑟 =
2.35
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
HOW TO COMPUTE? JUST AN ESTIMATE
ü Downspout
ü PVC Pipe
𝑇𝑜𝑡𝑎𝑙 𝐿𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑑𝑜𝑤𝑛𝑠𝑝𝑜𝑢𝑡 𝑥 𝑁𝑜. 𝑜𝑓 𝐷𝑜𝑤𝑛𝑠𝑝𝑜𝑢𝑡
𝑁𝑜. 𝑜𝑓 𝑝𝑐𝑠. =
𝐶𝑜𝑚𝑚𝑒𝑟𝑐𝑖𝑎𝑙𝑙𝑦 𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 𝐿𝑒𝑛𝑔𝑡ℎ (3𝑚)
v 4 liters = 1 gallon
v 4 gallons = 1 tin
WHAT’S IMPORTANT?
• Architectural Plan
vFloor Plan
vElevation Plan
vSpot Detail
vDetail of Railings
WHAT TO COMPUTE?
• Length
JUST USE THE ON CENTER
DISTANCES SINCE THIS IS
JUST AN ESTIMATE
HOW TO COMPUTE?
𝑻𝒐𝒕𝒂𝒍 𝑳𝒆𝒏𝒈𝒕𝒉
𝑵𝒐. 𝒐𝒇 𝒑𝒄𝒔. = 𝟔𝒎