Transmission Towers and Conductors May 2022
Transmission Towers and Conductors May 2022
Transmission Towers and Conductors May 2022
Transmission towers
and conductors
Purpose
This fact sheet provides general information about
the proposed Western Renewables Link overhead
transmission towers and conductors (wires).
Tr
Tr
Tr
Di
C
on
on
on
on
on
en
an
an
an
st
rib
ne
ne
ne
ne
su
er
sm
sm
sm
at
m
ut
ct
ct
ct
ct
iss
iss
iss
er
io
io
io
io
io
io
io
io
io
n
s
n
n
n
n
New overhead double circuit 220kV From there, a new overhead double circuit
transmission line between the existing 500kV transmission line connecting to a
Bulgana Terminal Station, connecting to the new terminal station at Sydenham.
existing Waubra Terminal Station and a new
terminal station to the north of Ballarat. For illustrative purposes only
2 WRLV2 – 31.05.2022
Suspension towers
What are transmission What will the Western What are strain towers?
towers? Renewables Link towers Strain towers are generally used where the
Transmission towers are used to support the look like? transmission line changes direction beyond
10 degrees. These towers need to pull on the
overhead conductors (wires) at the required wires and are designed to take the tension
height above the ground to meet regulations The towers proposed for the project are
load (or strain) of the wires. Generally, strain
and safety requirements. double circuit steel lattice towers. They are
towers are larger at the base and heavier
called ‘double circuit’ towers because each
compared to suspension towers. The insulators
tower supports two independent electrical
and wires are strung horizontally on the
circuits, one on each side of the tower.
What are conductors? crossarms on strain towers with some hanging
insulators to help hold the conductors in place.
The galvanised steel lattice structure is a
Transmission conductors, commonly referred to common tower type used elsewhere in Victoria
as ‘power lines’ or ‘wires’, are the metal cables and the national network. This type of structure
that carry high voltage electricity over long is proposed due to the large power transfer
distances. and redundancy requirements of the project.
The proposed transmission line will have both
suspension and strain towers.
Strain tower
3
Double circuit steel lattice transmission tower features
Insulators
Crossarm
Conductor bundle
Base
• Circuit - the unbroken conductive path for the flow of electricity between substations.
Transmission line circuits in Australia have 3 phases per circuit.
• Conductor – the metal wires that are suspended from the towers along which electricity
travels.
• Double circuit – arrangement in which the conductors (wires) make two different circuits.
• Ground (or earth) wire – safety control that directs electricity to the earth by creating
the shortest and easiest path in the event of a fault or lightning strike. Ground wires may
incorporate a fiber optic core to provide communication between substations. These
modified ground wires are commonly known as optical ground wires (OPGW).
• Insulator – a block of ceramic, glass or polymer that does not conduct electricity.
4
How many wires will there be on each tower?
220kV 500kV
Number of circuits 2 2
Crossarm
Insulators
Conductor bundle
Wires
5
Transmission tower height and easement
Height (metres)
70
60
50
40
30
20
10
5
6
How far above the ground will the What are ground wires?
conductors (wires) be?
The height of the conductors above the The typical minimum distances from the Ground wires are installed above the
ground will vary depending on a number of conductors to the ground proposed for the conductors (wires) to provide protection from
factors including the height of the towers, how project are: faults and lightning. When lightning strikes the
far apart the towers are, terrain and where in ground wire, the power in the strike is directed
the span between towers the measurement • For the 220kV section - 9.2m to ground safely into the ground through the ground wire
is taken. In each span between towers, the traversable by vehicles, such as an access and towers. One or more of the ground wires
conductors will typically be closest to the track or through a farm paddock. may have a fiber optic core within the cable to
ground in the middle of the span due to the provide communications between substations.
sag in conductors between the towers and will • For the 500kV section - 15m to ground
be highest above the ground closest to the traversable by vehicles, such as an access
towers which support the conductors. track or through a farm paddock.
The Electricity Safety (General) Regulations Closer to the towers, the distance from the
2019 govern the minimum distances above the conductors to the ground will be higher,
ground (clearance) the conductors must be. ranging between approximately 29 to 37m in
These clearances allow for thermal expansion, both the 220kV and 500kV sections.
the required electrical safety separation and
sufficient height for vehicles and equipment to The minimum clearances proposed for
work beneath the transmission line. Electric and the project are greater than the minimum
magnetic field levels are also considered when distances required by the regulations in
designing the tower and conductor heights. some areas to improve land use and farming
opportunities within the easement. Any
increase in tower heights is however being
balanced against other impacts, such as visual
and landscape impacts.
Height ranges
from 60 to 80m
Height ranges
from 40 to 60m
Sag
Sag
15m minimum
9.2m minimum clearance
clearance
7
Typical transmission tower span
60–80m height
10m
22kV 500kV Span generally within 450 to 550m 500kV
Distribution Tower Tower
Pole
For illustrative purposes only
8
What size will the tower base and footings be?
220kV 500kV
The width of the base of the 220kV lattice The width of the base of the 500kV lattice Four concrete pile footings (or foundations) are
towers proposed for the project will range towers proposed for the project will range required for each transmission tower, which will
from approximately 8 to 14m (9m typical). from approximately 10 to 17m (16m typical). range from approximately 1.5 to 3m in diameter
(1.8m typical) and will range from 4.5 to 25m
deep (9m typical depth).
Diameter
ranges from
1.5 to 3m
(1.8m typical)
Depth
ranges from
4.5 to 25m
(9m typical)
9
Other tower types
Alternative overhead structures are being Single circuit steel lattice towers are being Monopoles, tubular steel towers, are also
considered in response to the Environment considered as an option in some areas and being considered as an option in some areas.
Effects Statement scoping requirements. may be required near Melton aerodrome for A monopole in the double circuit 500kV section
aviation safety because they are shorter. A of the project would be approximately 70 to
single circuit steel lattice tower supports one 75m high, with a base diameter of 3 to 4m.
circuit per tower, therefore two single circuit Two monopoles would be required side by side
towers would be located side by side, with a for heavy strain where the transmission line
required separation distance of approximately changes direction significantly.
40m (centre to centre), to provide the double
circuit transmission line required for the project.
A single circuit transmission tower in the 500kV
section would be approximately 50m high, with
a base footprint ranging from approximately
10 to 14m. The easement for a section of single
circuit lattice towers in the project may be up
to 100m wide.
50
40
30
20
10
5
40m
10-14m 500kV
Height approximately 50m
Required separation approximately 40m
Easement up to 100m
10
Transmission tower information summary
Tower type Double circuit lattice towers, suspension Double circuit lattice towers, suspension
towers and strain towers as required. towers and strain towers as required.
Minimum clearance from conductors (wires) 9.2m to ground traversable by vehicles, 15m to ground traversable by vehicles, such
to ground such as an access track or through a as an access track or through a
farm paddock. farm paddock.
Tower spacing Generally within 450 to 550m Generally within 450 to 550m
Tower footprint at base Base width ranges from 8m to 14m Base width ranges from 10m to 17m
(9m typical) (16m typical)
Foundation width ranges from 10m to 17m Foundation width ranges from 12m to 20m
(12m typical) (18m typical)
Tower footing dimensions Diameter ranges from 1.5m to 3m Diameter ranges from 1.5m to 3m
(1.8m typical) (1.8m typical)
Depth ranges from 4.5m to 25m Depth ranges from 4.5m to 25m
(9m typical) (9m typical)
Number of wires per tower 14 wires (2 circuits of 3 phases each, 26 wires (2 circuits of 3 phases each,
with 2 wires per phase, plus 2 ground with 4 wires per phase, plus 2 ground
wires / OPGW) wires / OPGW)
11
Info
Western Renewables Link Other sources of
information information
desktop www.westernrenewableslink.com.au Australian Energy Infrastructure Commissioner
phone 1300 360 795
envelope [email protected] (www.aeic.gov.au) including information about
how to make a complaint, best industry
Ballarat PO Box practice and resources for landholders.
PO Box 638, Ballarat VIC 3353
Australian Energy Market Operator
(www.aemo.com.au) including information on
Information straight the Regulatory Investment Test for Transmission
(RIT-T) process for this project.
to your inbox
Energy and Water Ombudsman Victoria
Sign up for information straight to
your inbox at the project website (www.ewov.com.au) including information
www.westernrenewableslink.com.au. about complaints and dispute resolution.
Need an interpreter?
If English is not your first language
or you need an interpreter, please
call 13 14 50.
The information in this document is for reference only – it is not designed to be, nor should it be regarded, as
professional or legal advice. You should seek appropriate independent professional and/or legal advice where
appropriate and before making any decisions based on material in this document. The information is an overview
(in summary form) and does not purport to be complete. This document, and the information in this document, will
not form the basis of any contract or commitment. AusNet Services does not guarantee or warrant the accuracy,
completeness, or currency of the information provided and AusNet Services, its directors, officers, employees,
agents and advisers disclaim all liability and responsibility (including for negligence) for any direct or indirect loss
or damage which may be suffered by any recipient through use or reliance on anything contained in or omitted
from this document.