Saep 310

Download as pdf or txt
Download as pdf or txt
You are on page 1of 38

Engineering Procedure

SAEP-310 30 November 2005


Pipeline Repair and Maintenance
Piping Standards Committee Members
Al-Sannaa, M.S., Chairman
Al-Dossary, M.B.
Al-Nasri, N.I.
Al-Qahtani, K.D.
Al-Sabti, R.A.
Al-Sharif, T.M.
Al-Teraiki, A.M.
Balhareth, N.M.
Chen, J.T.
Fadley, G.L.
Ismail, A.A.
Khashab, J.M.
Kim, S.U.
Lewis, T.
Mahmoud, K.A.
Mullen, M.A.
Phan, H.C.
Solaiman, M.Z.
Stark, G.D.

Saudi Aramco DeskTop Standards


Table of Contents

1 Scope............................................................. 2
2 Applicable Documents................................... 2
3 Instructions.................................................... 4

Attachment 1 - Hydrogen Induced Cracking


(HIC) Decision Tree.............................. 37
Attachment 2 - Saudi Aramco Pipeline Field
Welding Checklist................................. 39

Previous Issue: 29 January 2003 Next Planned Update: 1 April 2006


Page 1 of 38
Primary contact: Muhsen S. Al-Sannaa on 874-6679
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

1 Scope

This SAEP describes the procedures to be followed for the repair and maintenance of
onshore pipelines, as covered by ASME B31.4 and ASME B31.8. The methods and
procedures set forth herein are minimum requirements and are not a release from the
responsibility for prudent action that circumstances make advisable. Any deviation to
this SAEP requires the approval of the Manager, Consulting Services Department,
Dhahran.

2 Applicable Documents

2.1 Saudi Aramco References

Saudi Aramco Engineering Standards


SAES-A-004 General Requirements for Pressure Testing
SAES-B-064 Onshore and Nearshore Pipeline Safety
SAES-H-002 Internal and External Coating for Steel Pipeline
and Piping
SAES-H-203 Hand-Applied Tape Wrapping of Buried Pipe
SAES-L-046 Pipeline Crossings Under Roads and Railroads
SAES-L-051 Construction Requirements for Cross Country
Pipelines
SAES-L-052 Hot Tap Connections
SAES-W-012 Welding Requirements for Pipelines
SAES-X-400 Cathodic Protection of Buried Pipelines

Saudi Aramco Engineering Procedures


SAEP-311 Installation of Hot Tapped Connections
SAEP-312 Plidco Weld+Ends Couplings
SAEP-313 Plidco Split Sleeves
SAEP-314 Plidco Pipeline Repair Clamps
SAEP-315 Stoppling
SAEP-321 Performance Qualification Testing and
Certification of Saudi Aramco Welders

Saudi Aramco General Instructions


GI-0002.100 Work Permit System

Page 2 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

GI-0002.102 Pressure Testing Safely


GI-0002.711 Fire and Safety Watch
GI-0006.012 Isolation, Lockout and Use of Hold Tags
GI-0006.021 Safety Requirements for Abrasive Blast Cleaning
GI-0150.001 Asbestos Regulations
GI-1780.001 Atmosphere-Supplying Respirators

Saudi Aramco Standard Drawings


AB-036029 Non-Pressure Containing Repair Sleeves with
Welded Buttstraps
AC-036261 Pipeline Corrosion Barrier Patch
AB-036262 Pressure Containing Repair Sleeves with Full
Penetration Butt Welded Seams
AC-036263 Weld Metal Build-Up for the Repair of Pipeline
Surface Defects
AE-036265 Pipeline Repair Patch for Minimum Wall
Thickness Violations
AC-036279 Corrugated Weld Repair Sleeve Pipe Size 6"
Through 48"
AA-036352 Details of Installation, Galvanic Anodes for Road
& Camel Pipelines Crossing, Pipeline Repair
Locations
AB-036381 Cathodic Protection Thermit Welding of Cables to
Buried Pipelines
AB-036478 Magnesium Anode Installation at Pipeline Repair
Locations, Layout, Sections and Details
AB-036526 Weld Over Sleeve for Repair of Leaking Sleeves
On 30" & 31" O.D. Pipe
AC-036655 Tie Rod Arrangement for Weld+Ends Coupling
AC-036660 Road Crossing for P/L Sht. 1, 2, 3, 4
AD-036786 Repair Sleeves (API 5L GR.65) for NGL Pipelines
AB-036788 Safety Ground Mat Plant & Details
AB-036880 Sleeved Crossing for Restrained Pipelines
AE-036833 Detail of Pipe Repair Plug

Page 3 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

AB-036899 Shoring Trenches

Saudi Aramco Manuals


Saudi Aramco Construction Safety Manual
Saudi Aramco Crane Safety Handbook

2.2 Industry Codes and Standards

American Society of Mechanical Engineers


ASME B31.4 Liquid Transportation Systems for Hydrocarbons,
Liquid Petroleum Gas, Anhydrous Ammonia
and Alcohols
ASME B31.8 Gas Transmission and Distribution Piping
Systems
ASME B31G Manual for Determining the Remaining Strength
of Corroded Pipelines

American Petroleum Institute


API STD 104 Standard for Welding Pipelines and Related
Facilities

National Association of Corrosion Engineers


NACE RP0177 Mitigation of Alternating Current and Lightning
Effects on Metallic Structures and Corrosion
Control Systems (Item 53039)

American Gas Association


Gas Purging Principles and Practices

3 Instructions

3.1 Safety

3.1.1 General Mandatory Compliance

3.1.1.1 The detailed requirements for safe working conditions are too
extensive to cover in this instruction. The job supervisor shall
be familiar with all the safety equipment and existing
procedures applying to work in the vicinity of combustible and
poisonous products, and high energy systems. The following
requirements furnish a reminder to the job supervisor.

Page 4 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

3.1.1.2 The Work Permit System shall be followed in strict


compliance. Job planning for work in restricted areas should
include a contingency plan for possible hazards to personnel
and equipment. Refer to paragraph 3.1 and GI-0002.100,
"Work Permit System".

3.1.1.3 When different crews are working at different locations on the


same pipeline, details of precautions and other work being
carried out should be mentioned on all work permits.

3.1.1.4 Persons permitted at the work area shall be kept to a minimum


to prevent congestion and to monitor the job safely. Only
personnel who are necessary and/or authorized in the scope of
the work shall be allowed in the work area. All work shall
cease until the area is cleared of all unauthorized personnel.
Refer to paragraph 3.1.4.5.9.

3.1.1.5 Combustible gas concentrations shall be monitored


continuously in the work area during Hot Work activities such
as welding, burning, or using spark producing machinery. Hot
Work shall cease if any flammable gas is detected. Hot work
can be restarted once the flammable concentration reaches 0%
L.E.L. Portable combustible gas indicators are available under
SAMS S/N 21-342-456. Refer to Sect. 3.1.4.3 and the Saudi
Aramco Work Permit Form 924-2, "Hot Work".

3.1.1.6 Should there be any possibility of a hydrogen sulfide, H2S,


release in the area, in excess of 10 ppm concentration, all
personnel in that area shall be provided with an adequate fresh
air breathing device. Refer to GI-1780.001,"Atmosphere-
Supplying Respirators". The hydrogen sulfide concentration in
the work area shall be monitored continuously. Refer to Saudi
Aramco Work Permit Form 924-1, "Release of Hazardous
Liquids or Gases".

3.1.1.7 GI-0002.102, "Pressure Testing Safely", shall be followed


during pressure testing.

3.1.1.8 It is Company policy to substitute safer materials for products


containing asbestos. Until that goal is achieved certain interim
precautions shall be implemented to minimize this hazard.
Refer to GI-0150.001, "Asbestos Regulations".

3.1.2 Excavation and Burial

Page 5 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

3.1.2.1 Locating of Pipe. Pipelines can be located by electronic


locating devices, manual probing, or test excavations. After
locating the pipeline, mark alignment with brightly colored
flags. If crawler dozers are used to remove dune sand, mark
and flag all lines within 60.96 m of the repair site.

3.1.2.2 Means of Excavation. When using heavy duty equipment for


excavation, such as a dozer, discontinue use when the depth of
cover from the top of the pipeline has been reduced to 1219 mm.
Likewise, when excavating around the sides of the pipeline, a
minimum clearance of 914 mm for a dozer and 305 mm for a
Gradall must be retained to prevent accidental damage to the
pipeline. All of the remaining excavation shall be done
manually.

3.1.2.3 Uncovering Restrictions. Underground sections of pipeline


requiring repairs may be uncovered, while under pressure, in
sections up to 15.24 m, long and separated by buried sections
of equal length. There is no limitation on the total length of
pipeline that may be uncovered in alternating 15.24 m sections.
However, for restrictions necessary at transitions, sag bends,
over bends and horizontal bends, consult the Area Operations
Engineering Supervisor.

If it is necessary to excavate sections of the pipeline longer


than 15.24 m, contact the Consulting Services Department
(CSD) for the maximum excavation span.

3.1.2.4 Clearance for Repair. The minimum working clearance shall


not be less than 400 mm all around the pipe. Refer to SAES-
W-012.

3.1.2.5 Safe Routes of Exit. For excavations over 1219 mm deep, the
sides of the pits and trenches should be sloped back to the
natural repose of the soil to avoid a cave-in. Sides which
cannot be sloped to natural repose shall be shored adequately to
resist earth movement and protect workers. Minimum
requirements for shoring are shown in Std. Dwg. AB-036899.
Saudi Aramco Work Permit Form SA-924-4, "Confined Space
Entry" is required for excavations 4 ft and deeper. Also refer
to the "Saudi Aramco Construction Safety Manual".

3.1.2.6 Burial. Backfill to the original requirements or to a minimum of


914 mm shall be with clean sand, free of rocks or other material

Page 6 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

which may damage the coating. Refer to SAES-L-051,


paragraph 5.

3.1.3 Protection against Electric Shock from Induced Voltage and


Underground Cables

This section contains mandatory practices which can safeguard personnel


against the hazards of electric shock that can occur during the
installation, operation, or maintenance of above ground and buried
pipelines routed near overhead, high-voltage power lines. These
practices apply to pipelines routed within 152.4 m of any energized 115-
kV and 230-kV power lines, and also to 69-kV lines if parallel lengths
are 1.6 km or greater. Refer to SAES-B-064, paragraph 10.

Safety precautions to prevent shock due to induced voltage, as stated in


Section 3.1.3, for pipelines routed in the vicinity of lower voltage power
lines, i.e., (4.16-kV and 13.8-kV), are normally not required.

All work on pipelines shall stop during lightning and thunderstorms.


Vehicles shall not park under power lines.

The following conditions are not exempt from the mandatory practices of
this section:
1) Line not cathodically protected.
2) Line section isolated by insulation flanges.
3) Cathodic protection rectifiers and generators shutdown.

3.1.3.1 Buried Pipelines

3.1.3.1.1 No special precautions need to be taken during


local excavations exposing less than 152.4 m of
pipeline except when cutting into an existing line
and/or removing a section of the pipeline when
Paragraph 3.1.3.2.4 shall be observed.
Commentary Note:

Pressurized pipelines are subject to a maximum


excavation of 15.24 m as stated in paragraph
3.1.2.3.

3.1.3.1.2 When work on existing buried pipelines requires


the exposing of 152.4 m or more of the line, it
shall be regarded as an above ground pipeline.

Page 7 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

Appropriate precautions, taken in accordance with


Section 3.1.3.2, shall be implemented.

3.1.3.1.3 Prior to the start of excavation, the Operations


Department shall identify all underground cables
crossing in the vicinity of the pipeline excavation,
and notify the appropriate authorities, i.e., (Power
Distribution Dispatchers, SCECO), to assist in the
supervision of the excavation. SAES-B-064,
paragraph 10.5 requires a minimum spacing of
914 mm between the bottom of the pipeline and
the top of the cable duct bank. Therefore, extreme
care must be taken when excavating below the
pipe. Normally, buried cable markers indicate the
location of the cables, but they may have been
inadvertently removed or never installed. When
cable markers are not shown, a safe maximum
distance of 610 mm from the bottom of the pipe
should not be exceeded.

3.1.3.2 Above Ground Pipelines

3.1.3.2.1 All work on exposed pipelines shall be carried out


from a wire mat that is electrically bonded to the
pipeline at each end of the repair area. The detail
of the mat is shown on Std. Dwg. AB-036788.

3.1.3.2.2 If the ground mat can not be bonded to the


pipeline as per Std. Dwg. AB-036788, two (2)
carbon steel, 13 mm diameter studs shall be
welded at each end of the pipeline repair area to
provide the required grounding connections. The
areas where the studs are to be welded shall be
cleaned prior to welding as per SAES-W-012. If
studs are removed, the weld areas shall be ground
flush with the pipe and a Liquid Penetrant or
Magnetic Particle Test (PT or MT) inspection
shall be made to insure no harmful defects remain.
Refer to SAES-W-012.

3.1.3.2.3 Rubber gloves shall be worn for all operations on


the line until the mat is properly positioned and
bonded to the line. Similarly, rubber gloves shall
be worn when removing the bonds. Gloves equal to

Page 8 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

those specified in SAMS S/N 14-695-546, 549, 561


shall be used.

3.1.3.2.4 When the repair of a pipeline requires cutting an


existing line or unbolting flanged connections, a
flexible bonding cable, no less than No. 2 AWG,
shall be attached across the section of line to be
separated prior to cutting or unbolting. Bonding
cables may be thermit welded to the pipe as per
Std. Dwg. AB-036381. The cable shall remain
attached until after the line is repaired. After the
removal of the of the bonding cable, the
attachment areas shall be ground flush with the
pipe surface and a Liquid Penetrant or Magnetic
Particle Test (PT or MT) inspection shall be made
to insure no harmful defects remain. Grounding mats
shall not be used as a bonding cable. The cable
shall be installed so that it is fully protected from
movement of workers and equipment. Refer to
NACE RP0177 Item No. 53039.

3.1.3.2.5 All electric arc welding operations shall be carried


out with the welding machine bonded to the
ground mat and pipeline, with the welder working
on the ground mat.

3.1.3.2.6 When working on lines supported on steel


structures, such as at road crossings, etc., ground
mats are not necessary. However, the lines should
be bonded to the steel structure to ensure a proper
ground and the requirements of Paragraph
3.1.3.2.4 implemented.

3.1.3.3 Valves on Above Ground and Buried Pipelines

3.1.3.3.1 Unless noted otherwise on the Work Permit, no


special precautions need to be taken when
operating or maintaining valves located below
ground and form part of a buried pipeline.

3.1.3.3.2 Where metal platforms or temporary scaffolds are


installed to provide access to valves on an above
ground pipeline, the platforms shall be electrically
bonded to the pipeline on each side of the valve
before work starts. The requirements of Paragraph

Page 9 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

3.1.3.2.3 shall be observed when making and


removing the bonding connection.

3.1.3.3.3 The electrical bond shall consist of a No. 2 AWG


flexible conductor, such as a welding cable,
connected to the platforms at one end and
terminated at the free end by a 50 amp rated test
clip (SAMS S/N 14-106-521) with insulator
(SAMS S/N 14-73-746). Access to the platform
shall be by a 36 inch square rubber mat.

3.1.4 Welding and Burning Safety Rules

3.1.4.1 The appropriate Hot Work Permit, signed by the Operations


Supervisor/Shift Superintendent, is required prior to the start of
work. It should be emphasized that welding and/or burning on
hydrocarbon pipelines is a hazardous operation and requires
strict adherence to established safety rules. Failure to follow
established safety rules and practices is unsafe and may cause
injury or loss of life to personnel. Refer to paragraph 3.1.1.4
and GI-0002.100, "Work Permit System".

3.1.4.1.1 Fire protection equipment for the job must be


onsite, properly located and manned, and in good
working condition. Refer to GI-0002.711 "Fire
and Safety Watch".

3.1.4.1.2 In no case shall spilled hydrocarbon be in the


general vicinity of Hot Work. Oil saturated sand
can be a fire hazard unless it is completely
covered with clean sand. An alternative to
covering with clean sand is to remove the oil
saturated sand. In the case of spilled condensate,
remove as much of the condensate saturated sand
as possible to a safe distance away from the Hot
Work. Cover the excavated area with clean sand
and place a plastic cover on it. Cover the plastic
with more clean sand.

3.1.4.1.3 In the absence of oxygen, sulfur compounds or


hydrogen sulfide in hydrocarbon streams react
with steel to form iron sulfide. This material is
called "Pyrophoric" because it tends to ignite
spontaneously when exposed to air. Pyrophoric
material should be kept wet to prevent auto-

Page 10 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

ignition. Sludge in pipelines suspected of


containing iron sulfide should be drained to an
isolated area, at least 30.48 m away from any
flammable substance, and the line flushed with
water. Flare lines should be inspected carefully
for Pyrophoric material.

3.1.4.1.4 Combustible gas tests shall be conducted by the


Operations Supervisor or his designated
representative prior to and during any welding,
burning, grinding or operation of any spark
producing equipment in the vicinity of the open
hydrocarbon line as stated in paragraph 3.1.1.4.

3.1.4.1.5 All mechanized repair equipment shall be located


at a safe distance, preferably upwind and in no
case less than 15.24 m from area of repair. If
space permits, at least 30.48 m distance is
recommended. Idle equipment shall be parked at
least 60.96 m from work site. Exceptions to the
above would be the use of cranes and side-booms,
etc., which must be closer than 15.24 m to
accomplish their job. A Hot Work Permit shall be
in force when this equipment is in use. Refer to
the Saudi Aramco "Crane Safety Handbook" for
further safe working practices.

3.1.4.2 If welding is required on opened hydrocarbon pipelines, the


line shall be cleaned, preferably by scraping, and vented. The
open ends shall be plugged, when possible, to isolate the areas
during the welding, burning, or grinding operations. The use
of plugs and vents does not eliminate the desirability of using
blinds to isolate the line. When removal of plugs after welding
is a problem, such as in the case of butt welding replacement
sections in a long pipeline, the entire pipeline shall be de-
gassed to a safe, permissible concentration of hydrocarbon
gases, O2, H2S, or other toxic/hazardous gases, prior to any Hot
Work. Refer to paragraph 3.1.4.3. Valves, blinds, or plugs
used to segregate combustible or poisonous substance from the
repair area shall be identified and secured. Likewise, when
venting or purging lines during Hot Work operations,
associated valves must be kept in the Lock-Open position.
Refer to GI-0006.012, "Isolation, Lockout, and Use of Hold
Tags".

Page 11 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

Saudi Aramco stocks three types of plugs: Balloons, Mud


Plugs and Mechanical Plugs. Plugging devices can also be
designed and fabricated from steel or wood and braided
packing. Any plug containing pieces of metal or wood shall be
removed before the line is closed.

3.1.4.2.1 Balloons. Inflatable balloons are available for


nominal pipe sizes 2 through 60 inch, under the
SAMS numbers indicated in Table 1.

The canvas covers of the balloons are at best only


moderately fire resistant. Additional precautions
that make their use safer include mud dams, vents,
and inert gas purges.

Balloons shall be inflated carefully so as to ensure


that the relatively low allowable pressures are not
exceeded. A suitably graduated pressure gauge
shall be utilized during inflation. For sizes 22 inch
and larger, the pressure gauge shall be graduated
in inches of water.

3.1.4.2.2 Mud Plugs

The Advantages of Mud Plugs:


1) A mud plug can be located closer to the end
of the line where welding is being done. A
balloon would be a fire hazard should it
rupture from the heat or inadvertent
puncture.
2) Mud plugs can be left in the line after
welding. They can be washed away by the
line fluid. Balloons require special hot taps
for insertion and removal except when they
are used to weld flanges or valves to the
open end of the line.

The Disadvantages of Mud Plugs:


1) For large lines, mud plugs are difficult to
erect. Mud shrinks as it dries. Plugs that are
too wet may slump and fail. For these last
two reasons, cutting and welding work must

Page 12 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

be completed as soon as possible after the


plug is completed.
2) There is no sure way to estimate how much
pressure a mud plug will hold, so the job
must be planned to provide zero pressure on
the plug.
3) They may be carelessly or unskillfully made
so that they do not provide an adequate seal.
Mud material is not always readily available.

The following materials used in the construction


of mud plugs are available through SAMS:
Bentonite (clay), 23 kg sack
S/N 45-601-101

Cottonseed hull, 23 kg sack


S/N 45-601-323

Expanded Vermiculite, 15 kg sack


S/N 32-180-861

Gypsum Plaster, 45 kg sack


S/N 09- 255-173

In building a mud plug, Bentonite should be


mixed with only sufficient water to make a very
stiff paste. For lines larger than about 305 mm
diameter, light-weight material such as expanded
Vermiculite can be added to reduce the tendency
of the plug to slump. Mix the Bentonite and
Vermiculite dry, in a mortar box. Add only
enough water to make a very stiff paste. The
Vermiculite will shrink when handled, so try to
avoid excessive mixing. Avoid the use of heavy
materials in the mud mixture, such as Baryte
(Baroid). They are not sticky and can only make it
more difficult to build the plug up to the top of the
pipe. If Gypsum plaster is used to increase the
strength of the plug, it must be removed prior to
closing the line.

Structural support for starting a mud plug can be


provided by a balloon. Effectiveness of the
balloon can be increased by running a rope

Page 13 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

through the end ring to hold the balloon while the


mud is forced against it. A balloon should not be
used unless provisions are made for removing it
after closing the line. In very large lines, a dam
can be started with full sacks of Bentonite or
Baryte. However, the sacks must be removed
after welding is completed. As an added
precaution, it may be advisable to use two plugs
separated by a purged section of line.

3.1.4.2.3 Mechanical Plugs. Saudi Aramco stocks


mechanical plugs for nominal pipe sizes 3 through
12 inch. Larger sizes may be obtained on a direct
requisition form. These proprietary plugs can
withstand considerable pressure, therefore, they
create a much better seal than balloons or mud
plugs for use in welding flanges or valves onto the
open ends of operating lines. The information
contained in Table 3 will aid in the use of these
plugs.

Additional safety precautions for mechanical


plugs can include: venting, use of mud plugs for
added sealant, inert gas purges, and water seals.

3.1.4.3 Displacing and Purging. Displacing or purging of hydrocarbon


gases requires special planning and equipment. A Displacing
or Purging Procedure, written and issued by the appropriate
Pipelines Operations Engineering Unit and approved by the
Loss Prevention Dept., shall be followed. The following
information will facilitate planning. Refer to "Purging
Principles and Practice", by the American Gas Association for
further information and guidance.

3.1.4.3.1 Displacing and purging are two methods of


ensuring a safe, non-combustible atmosphere in
the pipeline. A fire hazard exists when air
(oxygen) is allowed to mix with a limited
concentration of hydrocarbon vapor. The
flammable concentration range for most
hydrocarbons is between 1 to 15%.

3.1.4.3.2 When purging, the oxygen content shall be


measured frequently with the aid of an oxygen

Page 14 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

analyzer or an ORSAT apparatus to ensure the


oxygen content is below 5%.

3.1.4.3.3 Air movers may be used to displace (remove)


hydrocarbon vapors out of long sections of
pipeline. Care must be taken to ensure the line is
free of any sludge or residue that might produce
more vapors. Scraping and flushing with water
will usually insure this. It is often advantageous to
force liquid out of a short line with carbon dioxide
at fairly high pressure before cutting the line.

3.1.4.3.4 Purging with carbon dioxide, CO2, fire


extinguishers or bottles of inert gas, such as CO2
or nitrogen, N2, is often used for shorter sections
of pipe. An inert gas generator may be used for
larger projects. Whenever gas purging is
employed, an outlet must be provided for the
displaced vapors.

3.1.4.3.5 The following equipment is available under


SAMS or through local vendors:
CO2 Cylinder, 23 kg S/N 26-239-305
N2 Cylinder, 5.1 m³ S/N 26-239-324
CO2 Fire Extinguisher, 4.5 kg S/N 21-102-437
Air Mover / Ventilator S/N 21-302-437
Inert Gas Generator Available through direct
requisition.

3.1.4.4 Venting & Draining. Balloons or mud packs are only safe
when an adequate means are provided for venting gases to a
place away from the open end of the pipe and monitoring
pressure in the line.

3.1.4.4.1 When utilizing a balloon and mud pack as a plug,


vent capabilities must be provided within 3048 mm
of the repair location. The vent shall draw off
vapor from the top of the pipe. If a pipe vent does
not already exist, a temporary, hard piped vent line
shall be run between the top of the pipe ID surface
and the balloon/mud pack interface. The vent line
shall be discharged downwind at least 12.2 m from
the area being repaired and at least 3048 mm above
grade.

Page 15 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

3.1.4.4.2 If liquid is standing in the line at the place to be


worked on, it may be necessary to tap and drain
the line to a remote point at least 30.48 m from the
planned Hot Work.

3.1.4.4.3 Drains should be sized to permit draining the line


section in one hour with atmospheric pressure.
Use the rough guide that the square of the pipeline
diameter in inches equals the number of barrels in
304.8 m of pipe. Use Table 4 to determine the
size of the drain.

These capacities can be increased if a vent is


added to increase suction on the drain, or if an
inert gas pressure (not compressed air), such as
CO2, is carefully applied through the vent opening.
Care must be exercised not to inadvertently over
pressurize the section of line. The vent opening,
should be approximately one-fourth the nominal
pipe size of the drain.

3.1.4.5 Welding on Pipelines Under Pressure

The need for welding on in-service lines has become a


requirement for the repair or modification of most pipeline
systems. The greatest hazard encountered with this practice is
the possibility of a local "weld burn-through", sometimes
called "weld metal blow-out", at the time of welding. This is
caused by the heat of welding. Heat reduces the strength of the
metal to support the hoop stress created by the pressure in the
pipe. One way to reduce the chances of "weld blow-out" is to
reduce the pressure in the pipe during welding. Likewise,
increasing the wall thickness increases the capability of the
pipe to sustain higer pressure and reduces the chances of "weld
metal blow-out".

3.1.4.5.1 Although arbitrary, the following Formula No. 1


can be used to calculate the maximum allowable
operating pressure (MAOP) of a pipeline while
welding on the surface.

Formula No.1

2St(0.35)
Pmax. =
O.D.

Page 16 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

Where:
Pmax. = MAOP of the pipeline during welding, (psig)
S = Specified minimum yield strength of the pipe, (psi)
t = Minimum measured wall thickness of the weld area, (in)
OD = Outside diameter of the pipe, (in)

The calculated MAOP of the pipeline during


welding is directly proportional to the minimum
wall thickness of the weld area. Prior to any
welding on pressurized pipelines, the responsible
Operations Piping & Valves Unit/M&CED/CSD
shall perform an Ultrasonic Testing (UT)
inspection to determine the remaining minimum
wall thickness in the weld area. As a minimum
requirement for using Formula No. 1, UT wall
thickness measurements shall be made every inch
around the circumference of the pipe weld area.

3.1.4.5.2 Some pipeline operating conditions require higher


MAOP values than those derived from the
Formula No. 1. The following Formula No. 2 has
been developed through numerous experiments on
pressurized pipe to determine actual, safe pressure
and wall thickness requirements for welding on
pipelines under pressure. To ensure the wall
thickness is thoroughly measured, consecutive,
slightly overlapping, individual UT thickness
measurements shall be made around the
circumference of the pipe weld area.

Formula No. 2

2S(t − 0.10in.)F
Pmax =
O.D.
Where:
Pmax. = MAOP of the pipeline during welding, (psig)
S = Specified minimum yield strength of the pipe, (psi)
t = Minimum measured wall thickness of the weld area, (in.)
F = Design factor of the pipeline (Refer to SAES-L-003, paragraph
3.2)
OD = Outside diameter of the pipe, (in.)

Page 17 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

NOTE: The minus 0.10 inch wall thickness takes into account the molten
and heat affected portion of the base metal which does not
contribute to pressure containment.

3.1.4.5.3 To further minimize the possibility of "weld blow-


out", no welding will be allowed in areas with a
wall thickness below 5.1 mm.

3.1.4.5.4 If welding does not begin within Sixty (60) days


of the initial UT thickness examination, the weld
area wall thickness shall be re-examined.

3.1.4.5.5 The calculated MAOP shall be recorded on the


Hot Work Permit prior to any welding on the line.

NOTE: Differences in the head pressure along


the pipeline shall be considered when
calculating the MAOP at the repair
location.

The calculated MAOP shall be monitored during


the entire welding operation. Welding shall
immediately cease if the line pressure exceeds the
calculated MAOP. Refer to paragraph 3.1.4.5.10.

3.1.4.5.6 All welding on pipelines under pressure shall be


done with low hydrogen electrodes. For handling
and storage of electrodes, refer to SAES-W-012.

3.1.4.5.7 No welding is permitted on compressed air lines


while in service since they usually contain
flammable, oily deposits. Refer to SAEP-311 and
SAES-L-052.

3.1.4.5.8 No leaks shall be evident at the area to be welded.


Refer to paragraph 3.2.3.1.

3.1.4.5.9 Repair personnel not required to directly perform


the repair work should stand clear, at least 15.24
m or more away from the pipeline. The distance
is dependent on the pipeline contents, process
conditions, and weather. Personnel should stand
upwind and be prepared to evacuate the area, if
necessary, to a safe location across wind. Fire
watch personnel shall be located at the repair work
area as per GI-0002.711.

Page 18 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

3.1.4.5.10 Prior to the start of welding, the Operations


Superintendent or his designee shall ensure that
the flow in the line has been established and the
internal pressure of the line has been adjusted,
without surges, to desired welding pressure.
Welding must stop if for any reason the flow or
pressure cannot be maintained within the
prescribed limits. The minimum flow during
welding on pipelines under pressure shall be
0.40 m/sec or the maximum attainable under
normal working pressure. For water lines, refer to
paragraph 3.1.4.5.11.

A stand-by man, equipped with a radio to allow


continuous contact with the flow controller, must
be on site throughout the welding operation to
warn of flow failure or of pressure which exceeds
the maximum allowable for welding purposes.

3.1.4.5.11 The purpose of establishing flow is to ensure that


no combustible mixtures can exist on the inside of
the pipe while welding on the outside. Sufficient
flow must be maintained for a sufficient time to
ensure that any potentially explosive gas pockets
in the line have been swept clear of the weld area.
The flow is not intended to keep the weld area
cool, since additional cooling of the weld is
undesirable. For any system where combustible
mixtures are definitely not a possibility, flow is
not necessary. "No-Flow" situations shall be
approved by the General Supervisor Operations
Engineering and the Operations Superintendent.
Operations shall verify a non-combustible mixture
in the line and arrangements shall be made to
prevent any in advertent introduction of
hydrocarbons or oxygen into the line. This must
be stated in the remarks section of the Hot Work
Permit.

3.2 Pipe Repair Procedures

3.2.1 Responsibilities

Page 19 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

Prior to starting repairs, the Maintenance Field Supervisor / Foreman


shall consult with the Operations Superintendent / Foreman and the
Piping & Valves Unit/M&CED/CSD Supervisor to determine:
1) Whether the pipeline repair can be delayed or scheduled to normal
working hours.
2) Whether the pipeline can be repaired while in service.
3) The recommended method of repair and procedure.
4) Inspection requirements before, during, and after the repair.
5) The type of Work Permit(s) required.

If the decision is made to take the line out of service, the pipeline
operator at the site will inform the OSPAS Planner and obtain an
operating order to isolate the leak or repair location. If the repair is
sufficiently complex, the appropriate Pipelines Operations Engineering
Unit will draft a recommended procedure for the job.

3.2.2 Pipe Replacement

For a pipeline crack, rupture or any other case which cannot be repaired
by hot tapping, patching or sleeving, the failed section shall be removed
by cold cutting and a replacement section installed. Sections of pipeline
can be removed during scheduled shut-down, or by using Stopples on
lines in operation. Refer to SAEP-315.

3.2.2.1 The repair of cracks, other than their complete removal, shall
be reviewed and approved by Consulting Services Department
(CSD).

3.2.2.2 Whenever any pipeline containing hydrocarbons is to be cut or


separated by opening a bolted connection, a flexible bonding
cable (conductor) not less than No. 2 AWG shall be installed
across the planned opening. Refer to paragraph 3.1.3.2.4.

3.2.2.3 Butt welding of replacement sections of pipeline or flanges to


the open ends of pipelines for installation of spool pieces shall
be carried out in accordance with Section 3.1.4, "Welding and
Burning Safety Rules", and Section 3.3, "Welding".

3.2.2.3.1 The length of any replacement section (insert


piece) into existing piping or pipelines shall not be
less than two times the pipe diameter. If
limitations do not permit the proper size insert,
then both butt joints shall be fully radiographed.

Page 20 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

3.2.2.3.2 The length of transition or pup pieces welded to


other pipe, pipe fittings, or valves shall be 152 mm
or longer. If shorter pieces are required, the
associated girth welds shall be fully radiographed.

3.2.2.3.3 Installation of replacement pipe using Plidco


Weld+Ends couplings shall be done in accordance
with SAEP-312, "Plidco Weld+ Ends Couplings".
These couplings are to be used where it is difficult
to make a quick safe connection by any other
means. Tie-rod connections, when required in
concert with Weld+Ends, shall be installed as per
Std. Dwg.AC-036655.

3.2.2.3.4 Installation of replacement pipe or the connection


of pipe sections using any type of sleeve,
including Plidco Split Sleeves, is not permitted.

3.2.2.3.5 Sections of cement lined water injection lines may


be replaced using specially designed and
fabricated couplings. Refer to the Consulting
Services Department (CSD) for guidance in
material selection and procedures.

3.2.3 Repair of Pipeline Leaks

3.2.3.1 Stopping or Diverting Leaks

Leakage must be mechanically stopped or diverted before


welding a pressure containing repair sleeve to the pipe. When
possible, the leak may be stopped by using a suitable wooden
or steel plug (SAMS S/N 02-913-724 through 751). Refer to
Std. Dwg. AE-036833 and Paragraph 3.2.3.1.1.

Alternatively, a Plidco Split Sleeve or a Plidco Repair Clamp


may be used for temporary or permanent repairs. In the case
where a Plidco Split Sleeve is removed for a permanent repair,
it can be checked for damage and returned to stock if suitable
for future use. A Plidco Weld Cap may be welded over the
repair clamp for a permanent repair. Likewise, the split sleeve
may also be welded for a permanent repair. Plidco Split
Sleeves are high in cost compared to other methods of pipeline
repair, therefore, their use should be restricted to those cases
where speed of repair will provide sufficient economic
justification. Refer to SAEP-313 and SAEP-314.

Page 21 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

3.2.3.1.1 Steel, tapered pipe repair plugs will normally


extend into the bore of the pipe and will damage
the cups of pipeline scrapers, therefore, steel plugs
shall not be used on lines designed to be scraped
unless the tip of the plug is cut so that after
installation it will not protrude more than 3.2 mm
inside the pipe. This requires that the plug be
screwed in place, marked, removed and cut to
proper length before reinstallation. Exceptions to
the use of steel plugs without trimming must be
approved by the General Supervisor, Operations
Engineering Division, Pipeline Department or
Producing Department, as appropriate.

3.2.3.1.2 Leakage from splits or holes which cannot be


plugged, may be stopped by using repair sleeves
with neoprene gaskets which are clamped in place.
When gasketed sleeves are used without stopping
leaks, a welding boss shall be installed to permit
drainage of leaking oil to a point at least 30.48 m
downwind from the area being repaired. It may be
necessary to purge the void space between the
pipe and sleeve with carbon dioxide or nitrogen to
avoid a possible flammable mixture of air and
hydrocarbons behind the weld area. In which
case, another boss shall be installed. A fire and
safety watch shall be implemented as per GI-
0002.711.

3.2.3.2 Special Leak Repair Sleeves

3.2.3.2.1 Special sleeves may be installed as required for


repair of leaks at locations such as flanges, ells,
tees, reducers, and valves. Refer to the Plidco
Catalog.

3.2.3.2.2 Repair sleeves suffering leaks may be repaired


using specially designed "Weld Over Sleeves.
"Refer to Std. Dwg. AB-036526.

3.2.3.2.3 "Corrugated Weld Repair Sleeves" for nominal


pipe sizes 6 through 48 in. may be used for repair
of leaking girth welds. Refer to Std. Dwg. AC-
036279. The corrugated sleeves are stocked under
SAMS S/N 02-578-XXX.

Page 22 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

3.2.3.3 Pressure Containing Repair Sleeves

When sleeving a damaged section of pipeline, special


consideration must be taken whether the repair is to contain
pressure (leak), act as a barrier from further external corrosion,
or to protect the line from damaging stresses, such as dents,
gouges, or scratches, which may lead to the bulging and
eventual rupture of the pipe.

3.2.3.3.1 If a pipeline is leaking or the minimum design


wall thickness has been violated due to internal
corrosion, a fully welded encirclement sleeve with
longitudinal butt-welded seams shall be used in
the repair. Fully welded encirclement sleeves with
longitudinal butt-welded seams are preferred over
sleeves containing buttstraps. The lap-type joint
in the buttstrap is not as flexible as the butt-
welded seam to absorb the required strains
induced while containing the internal pipeline
pressure. These sleeves are more suitable for use
as corrosion barriers or to provide added
reinforcement to the pipe where minimum design
wall thickness has been violated due to external
corrosion. Refer to paragraph 3.4.5.

3.2.3.3.2 Fully welded encirclement sleeves with


longitudinal butt-welded seams shall use a carbon
steel backing strip to avoid fusion of the
longitudinal welds to the pipe. Carbon steel
sheeting material, currently stocked under SAMS S/N
12-157-XXX, may be used in fabricating backing
strips. The backing strips shall be thick enough to
prevent burn-through to the pipe wall and wide
enough to facilitate fit-up. The recommended
dimensions are at least 25.4 mm wide, a
minimum of 16 gauge thick, and a length to
accommodate the entire sleeve.

The sleeve shall be cut to provide close fit-up


dimensions for a root gap of 4.8 ± 1.6 mm, and a
maximum gap of 3.2 mm between the pipe and
sleeve surface around the entire circumference of
the pipe. A bevel of 37 ± 2½ degrees shall

Page 23 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

continue to the inside surface of the sleeve without


a land. Refer to Std. Dwg. AB-036262.

The minimum length of fully welded encirclement


sleeves with longitudinal butt welded seams shall be
at least 102 mm. There is no maximum length
limitation and multiple sleeves may be used.
Refer to paragraph 3.3.3.7 and 3.2.3.3.3.

3.2.3.3.3 To sustain the maximum allowable operating


pressure of a pipeline, the minimum design
thickness of a fully welded encirclement sleeve, ts,
shall be calculated using the following formula.

Formula No. 3

ts = tp(4Dp + 1)(SMYSp)/4[(Dp)(SMYSs)-2tp(SMYSp)]

Where:
Dp outside diameter of the pipeline (inches)
Ds outside diameter of the encirclement sleeve
(inches)
tp nominal wall thickness of the pipeline (inches)
ts nominal wall thickness of the encirclement
sleeve (inches)
SMYSp specified minimum yield strength of the
pipeline material (psi)
SMYSs specified minimum yield strength of the sleeve
material (psi)

3.2.4 Repair of Surface Defects and External Corrosion

3.2.4.1 Unless otherwise stated in this SAEP, the limits and disposition
of pipe surface defects shall be as established in ASME B31.4,
paragraph 451.6.2 and ASME B31.8, paragraph 851.4. Refer
also to ASME B31 G, "Manual for Determining the Remaining
Strength of Corroded Pipelines".

3.2.4.2 Pipelines, suffering loss of wall thickness due to external


corrosion or excessive grinding and not violating minimum
wall thickness requirements, require no repair, other than
possible coating or wrapping. Refer to Section 3.6,
"COATINGS AND WRAPPING".

Page 24 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

3.2.4.3 Stress risers such as sharp or deep scratches, gouges, and


grooves shall be removed by grinding. Care must be taken to
prevent excessive grinding to avoid minimum wall violation.
A PT or MT inspection shall be made to ensure these stress
risers have been removed.

3.2.4.4 Dents that are in violation of the applicable Code shall be


repaired by either removal of the damaged section or by
applying a fully welded encirclement sleeve with butt-straps.
Refer to Standard Drawing AB-036029.

3.2.4.5 Minimum Wall Thickness Violations

Non-leaking pipelines suffering minimum wall thickness


violations due to excessive grinding or external corrosion may
be repaired by using either weld metal build-up, specially
designed repair patches, fully welded repair sleeves with
welded butt straps, or replacement.

Non-leaking sections of pipeline suffering minimum wall


thickness violations due to internal corrosion shall either be
replaced or repaired with fully welded encirclement sleeves
with longitudinal welded seams. Refer to paragraph 3.2.2 and
3.2.3.3.1.

3.2.4.5.1 Patches used to repair pipe minimum wall


thickness violations shall be fabricated from a
material grade equal to or higher than the pipe.
The patch length or width dimensions shall not
exceed 152 mm and it's thickness shall be at least
1.25 times the nominal pipe wall thickness of the
pipe. The patch shall be fabricated to form with
the contour of the pipe and it's corners shall be
rounded with a minimum 51 mm radius. Refer to
Std. Dwg. AE-036265.

3.2.4.5.2 Straight sleeves with buttstraps, fabricated with


X60 material, are stocked under SAMS S/N 02-
579-XXX. Other sleeves, fabricated with X52
material, are stocked under SAMS S/N 02-578-
XXX. These sleeves are fabricated in 3048 mm
lengths. Do not modify these sleeves without the
consent of the Consulting Services Dept. (CSD).
Refer to Std. Dwg. AB-036029.

Page 25 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

3.2.4.5.3 Weld metal build-up may be used to repair small


areas on pipe or fittings suffering minimum wall
thickness violations due to external corrosion,
gouges, grooves, or excessive grinding.

The maximum length or width of any individual


repair area is limited to 102 mm. Each repair area
shall be separated by at least 102 mm from any
other repair area. As a minimum area, the
deposited weld build-up shall be at least three (3)
passes wide and 51 mm long. There are no
limitations, other than economics, to the number
of repair areas allowed. A decision should be
made whether it is more economical to repair the
damaged areas by weld build-up or by
sleeving/patching. Refer to Standard Drawing
AC-036263 for complete repair details.

3.2.4.6 Corrosion Barrier

External corrosion, not violating minimum wall thickness


requirements, on pipelines with a specified minimum yield
strength less than 448 MPa may be repaired by using a steel
plate patch with rounded corners. A maximum width of one-
half the circumference of the pipe and a maximum length of
3048 mm shall not be exceeded. Similarly, pipe with SMYS of
448 MPa or greater may be repaired using patches with a
width or length not to exceed 152 mm. Refer to Std. Dwg.
AC-036261.

3.2.5 Repairs of Hydrogen Induced Cracking (HIC) in Pipelines

If the replacement of hydrogen damaged pipelines is not chosen, then the


requirements of this Section shall be followed.

3.2.5.1 Expose the full joint of pipe as well as a portion of the adjacent
joint on each side and determine the extent of the defect
indications. Continue exposing as much pipe as necessary until
the extent of the area with defect indications is determined.
The 15.24 m limit of exposed buried pipe as required in
paragraph 3.1.2.3 shall be observed.

3.2.5.2 Determine the size and depth of the defects with ultrasonic
testing. Ultrasonic indications may mean any of several things,
including on-going cracking, corrosion damage, the presence

Page 26 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

of pre-existing and rather harmless laminations, or simply


elongated inclusions in the steel. When ultrasonic or
radiographic inspection reveals crack-like defects, further
examination is required to determine the nature of the defects.

3.2.5.3 The HIC decision tree, (Attachment 1), assesses the severity of
the hydrogen damage and provides recommendation for
corrective action. Assessment may require removal by Hot-
Tapping of coupons for metallurgical analysis. Refer to SAEP-
311. Hydrotesting, monitoring, increased inhibition, sleeving
or replacement of cracked areas may be required. No
corrective action shall be taken without the concurrence of the
Coordinator, Materials Engineering and Corrosion Control
Division, Consulting Services Department.

3.2.6 Repairs to Sleeved and Non-Sleeved Pipeline Crossings at Roads and


Railways

Pipeline leaks at road or railway crossings require immediate action and


repair to minimize hazardous conditions for both pedestrians and motor
traffic. After the repairs, all crossings shall be restored to the original
required cover and contour.

3.2.6.1 Repairs to Leaking Non-Sleeved Road Crossings shall be


handled in the same manner as any buried pipeline. In
addition, warning signs, traffic barriers, detours, etc., will be
required to direct traffic around the hazardous leak area. Refer
to Section 3.2 and Standard Drawings AC-036660, Sheets 1
and 4.

3.2.6.2 Repairs to leaking road crossings with non-pressured sleeves


shall also be handled as in paragraph 3.6.1 above and Standard
Drawing AC-036660 Sheets 2 and 3.

3.2.6.3 Repairs to leaking road crossings with diesel filled or nitrogen,


N(2), pressure sleeves shall be in accordance with Std. Dwg.
AB-036880, "Sleeved Crossing for Restrained Pipelines". The
existing sleeve shall be removed for inspection and repair of
the pipeline, after which a new sleeve shall be installed. It
should be noted that these specialized types of sleeves are no
longer used.

3.2.6.4 A specific Job Procedure shall be prepared to cover repairs in


the following situations:

Page 27 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

1) Leaks inside casing sleeves under Government highways


and Saudi Aramco roads that cannot be closed to traffic
and railways.
2) Leaks in pipelines under concrete slabs.
3) Leaks located under pavement, shoulders and high road
way berms of Government highways, military roads or
Saudi Aramco roads that cannot normally be closed to
traffic.

3.2.7 Repairs on Internally Coated Pipelines

3.2.7.1 All internal coatings, except possibly cement lining, presently


in use by Saudi Aramco, are destroyed by welding. Cement
lining, used for water service (including oily water), will not
normally be destroyed as long as heat inputs are minimized.
Refer to paragraph 3.2.2.3.5. The maximum welding interpass
temp. shall not exceed 121°C. Welding (including Thermit
welding), brazing, and torch cutting is not allowed on
internally coated pipe, other than cement lined pipe, without
the concurrence of the Operating Department. If welding is
necessary, it shall be kept to a minimum, since it will destroy
the adjacent internal coating. Whenever possible, flow shall be
maintained during welding in order to minimize the
temperature rise on the internal diameter of the pipe.
Commentary Note:

Do not mistake this situation with that of welding on lines


carrying hydrocarbons.

3.2.7.2 Whenever possible, repairs on internally coated pipe will be


made by cutting out the defective section and replacing it with
a flanged, internally coated spool piece.

3.2.7.3 Flanges welded to the existing sound pipe must be internally


coated, including the field girth weld area.

3.2.7.4 To minimize repair time on site, the flanges and the spool piece
should be internally coated prior to transportation to the site.
Remember, all field-applied epoxy paint type coatings require
multiple coats and curing times of up to 7 days before they can
be put into service. Refer to the SAES-H-101V Data Sheets.

3.3 Welding

Page 28 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

Prior to any welding, the following paragraphs shall be reviewed and understood
by all personnel involved with the welding operation. Both the welder and
welding inspector shall be responsible for ensuring that all parameters of the
welding procedure are followed during the entire welding operation.
Compliance and verification by the Responsible Maintenance and Piping &
Valves Unit/M&CED/CSD shall be documented on the "Saudi Aramco Pipeline
Field Welding Checklist", (Attachment 2). Completed checklists shall be kept
on file by the Responsible Maintenance Unit for future reference.

3.3.1 Welder and Welding Procedure Qualification

All welding shall be performed in accordance with an approved,


qualified welding procedure as specified in SAES-W-012. Welders shall
be qualified in accordance with SAEP-321. Also refer to SAES-W-012.

3.3.1.1 All welding of patches, sleeves, and weld build-up shall be in


accordance with Saudi Aramco Welding Procedure
Specification (WPS) Numbers PL-R1 and PL-R2.

3.3.1.2 Welding longitudinally to the axis of the pipeline is not


permitted except as approved for repairs using patches or weld
metal build-up. Refer to paragraphs 3.2.4.5 and 3.2.4.6.

3.3.1.3 Should any girth weld on a full encirclement sleeve be welded


parallel to an existing girth weld on the pipeline at a distance
less than 19 mm or 3 times the wall thickness of the pipe,
whichever is greater, a MT or PT inspection will be required on
both the girth welds and the heat affected zone. Likewise,
patches welded within the same distance as stated above of a
girth weld or a longitudinal seam weld of a pipe shall require a
MT or PT inspection. It is permissible to weld across an
existing longitudinal, spiral or girth weld seam of the pipeline.
These welds shall be ground flush with the pipe wall when they
interfere with the fit-up the sleeves or patches.

3.3.1.4 Procedures for installation and welding of Plidco Split Sleeves,


Weld+Ends, and, Weld Caps for pipeline repairs shall be in
accordance with SAEP-312, SAEP-313 and SAEP-314 and this
SAEP.

3.3.2 Fit-up of Repair Sleeves with Longitudinal Butt Welded Seams

3.3.2.1 Refer to Std. Dwg. AB-036262 and paragraph 3.2.3.3.2 for


bevel and backing strip dimensions.

Page 29 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

3.3.2.2 A fit-up root gap of 3.2-6.4 mm shall be maintained for the


longitudinal groove weld. If necessary, the sleeve shall be
removed and the bevel faces buttered to provide the proper
gap. Refer to SAES-W-012 for limitations of buttering.

3.3.2.3 Prior to fillet girth welding the sleeve to the pipe, a maximum
fit-up gap of 3.2 mm between the two surfaces shall not be
exceeded. If the fit-up gap exceeds 3.2 mm, a weld build-up
(buttering) shall be made at the deficient area to reduce the
distance. Do not start any fillet girth weld or tie-in weld until
the fit-up gap has been reduced to 3.2 mm or less.

3.3.2.4 If girth clamps are used to facilitate the positioning and fit-up
of the sleeves, the welder (s) shall deposit at least 9.6 mm or
25% of the weld thickness, whichever is greater, on both
longitudinal welds before removing the clamps.

3.3.3 Welding Sequence of Repair Sleeves

3.3.3.1 The longitudinal welds on the sleeve shall be completely


welded before commencing with either girth weld.

3.3.3.2 The welding sequence shall be such as to minimize the


distortion and residual stress in the sleeve and at the same time
maintain an adequate interpass temperature. On long sleeves,
two welders should be welding simultaneously when possible.

3.3.3.3 On sleeve lengths equal to or greater than 1524 mm, both girth
welds may be welded simultaneously. For sleeve lengths less
than 1524 mm, one girth weld shall be completed and allowed
to cool before beginning the other. Refer to Std. Dwg. AB-
036262.

3.3.3.4 All passes on the girth fillet welds shall be in the following
sequence:
1) Weld from the 3:00 to 12:00 o'clock position.
2) Weld from the 6:00 to 9:00 o'clock position.
3) Weld from the 6:00 to 3:00 o'clock position.
4) Weld from the 9:00 to 12:00 o'clock position.

3.3.3.5 The girth fillet welds shall be full sized and blend in smoothly
with the pipe surface.

Page 30 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

3.3.3.6 For sleeving pipelines greater than 16 inch diameter, two


welders shall be used on opposite quadrants for each girth
weld.

3.3.3.7 In cases where multiple sleeves are used, the adjoining sleeve
ends shall be beveled, before installation, to 37 ± 2½ degrees
without a land. A backing strip, as described in paragraph
3.3.3.2, shall be fit up to avoid fusion to the pipe in the root
gap. The root gap shall be 4.8 ± 1.6 mm. For two adjoining
sleeves, all of the longitudinal welds shall be completed before
the adjoining or either end girth welds are made to the carrier
pipe. The girth welds shall be made in order, from one end
towards the other end. For sections with more than two
adjoining sleeves, each additional sleeve shall be added in
sequence after completing the welds on the previous sleeve.

3.3.4 Welding of Repair Patches

3.3.4.1 The maximum over-laying gap for all patches shall not exceed
3.2 mm.

3.3.4.2 Patches used to repair minimum wall thickness violations shall


have full sized fillet welds that blend in smoothly with the pipe
surface. The root pass shall be made using a 2.4 mm diameter
electrode. Refer to Std. Dwg. AE-036265.

3.3.4.3 Patches used to repair external corrosion shall have a minimum


4.8 mm fillet weld around the entire circumference. The welds
shall blend in smoothly with the pipe surface. Refer to
Standard Drawing AC-036261.

3.3.5 Weld Build-up

3.3.5.1 The maximum electrode diameter for any pass shall be 3.2 mm.

3.3.5.2 All welds shall be made using overlapping stringers. No


weaving is allowed. Refer to Std. Dwg. AC-036263 for repair
area limitations, welding sequence and technique.

3.3.5.3 The maximum excessive weld build-up above the pipe surface
shall be 1.6 mm. It is preferable to have the build-up flush
with the pipe surface. In any case, the build-up surface shall be
free from discontinuities which will show up during the
Magnetic Particle or Penetrant Testing (MT or PT) post weld

Page 31 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

inspection. It shall be up to the welding inspector to determine


the extent of post weld surface preparation required.

3.4 Non-Destructive Examination (NDE)

3.4.1 All welds made for the installation of pipe sleeving or patching for
pressure containment, and for weld metal build-up, shall have a final M.T. or
P.T. inspection.

3.4.2 Other than those welds which have been particularly chosen or randomly
selected in the repair procedure, additional inspection of any type on any
weld may be requested by inspection.

3.4.3 All NDE interpretation shall be to API STD 104.

3.5 Pressure Testing

3.5.1 If the decision is made to hydrotest the new repair section(s) prior to
installation into the pipeline, the test pressure and duration shall be as
required for new pipe. Refer SAES-A-004. Duration of the test when
pipe and all welds are accessible shall be only as long as required to
visually inspect the pipe and all welds, but in no case less than 10
minutes.

3.5.2 If the decision is made to hydrotest the new repair section(s) after
installation into the pipeline, the test pressure and duration shall be as
provided in SAES-A-004, paragraph 6.2.5.

3.5.3 Sections of Pipe Foregoing Pressure Testing

When a replacement section of pipe is not hydrotested prior to being


welded into an existing pipeline, a decision must be made whether or not
to hydrotest the entire pipeline to test the new section. Sometimes
hydrotesting the entire pipeline cannot be justified economically. If the
decision is made to forego the hydrotest, full compliance of SAES-A-
004, paragraph 3.2(b) shall be adhered to along with the following
requirements:
1) Visually inspect all mill applied welds of the spiral or
longitudinally welded joint(s) of new pipe prior to installation in
the pipeline.
2) Radiograph or ultrasonically check all suspect areas of the
manufacturers welds found to be defective by visual inspection.
3) Repair all manufacturers weld defects and radiograph repairs to
assure defects are removed.

Page 32 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

4) Visually inspect the pipe ends for proper bevel and evidence of no
laminations. Repair as required.
5) Radiograph all butt welds required to install the new pipeline
section and repair defects as required.

3.5.4 Refer to GI-0008.001, "Pressure Testing Safely", prior to commencing


any pressure test.

3.6 Coatings and Wrappings

3.6.1 Refer to SAES-H-002 and SAES-H-203 for selection and application of


internal and external coating systems and tape wrapping for pipelines.

3.6.2 Refer to GI-0006.021, "Safety Requirements for Abrasive Blast


Cleaning", when preparing pipe surfaces for coating using abrasive blast
cleaning.

3.7 Cathodic Protection

3.7.1 When repairs are made due to external corrosion, the appropriate
pipeline cathodic protection units shall determine when and where
supplemental "Hot Spot" cathodic protection will be used.

3.7.2 A minimum of two (2) magnesium anodes shall be used for


supplemental cathodic protection. The anodes shall be installed on
alternate sides of the pipeline. The placement shall be such that one
anode is installed at each end of the repair area.

3.7.3 Anode requirements and installation details are found in Std. Dwgs.
AB-036478, "Magnesium Anode Installation at Pipeline Repair
Locations; Layout, Sections and Details", and AA-036352, "Details of
Installation of Galvanic Anodes for Road and Camel Crossing and
Pipeline Repair Locations".

3.7.4 Anode connections to the pipeline shall be Thermit welded as per Std.
Dwg. AB-036381, "Cathodic Protection; Thermit Welding of Cables to
Buried Pipe lines".

Revision Summary
30 November 2005 Revised the "Next Planned Update". Reaffirmed the contents of the document, and
reissued with no other changes.

Page 33 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

Table 1 – Balloons Available for Pipe Size 2-60"


NOM. MAXIMUM INFLATION MAXIMUM P/L PRESSURE
SIZE (kPa) (psig) Water (kPa) (psig) Water SAMS S/N
(in) (in) (in)

2 103 15 413 69 10 275 02-945-450


3 103 15 413 69 10 275 02-945-453
4 103 15 413 69 10 275 02-945-455
6 103 15 413 69 10 275 02-945-458
8 83 12 330 48 7 193 02-945-461
10 69 10 275 48 7 193 02-945-465
12 55 8 220 34 5 138 02-945-469
14 48 7 193 28 4 110 02-945-471
16 41 6 165 28 4 110 02-945-473
18 38 5.5 151 21 3 83 02-945-477
20 34 5 138 21 3 83 02-945-481
22 28 4 110 14 2 55 02-945-485
24 24 3.5 97 14 2 55 02-945-490
26 22 3 83 14 2 55 02-945-492
30 17 2.5 70 10 1.5 40 02-945-545
38 17 2.5 70 10 1.5 40 02-945-550
40 14 2 55 7 1 30 02-945-556
46 14 2 55 7 1 30 02-945-560
48 14 2 55 7 1 30 02-945-562
56 12 1.5 41 6 1 30 02-945-570
60 11 1.5 41 6 1 30 02-945-575

Table 2 – Composition of Mud Plugs


NOM. SIZE BENTONITE VERMICULITE WATER
(in) (sacks) (sacks) (m³) (ft.³) (U.S. gal)

6 1 - 0.03 1 7.5
10 2 - 0.06 2 15
12 3 - 0.08 3 2.5
16 3 2 0.08 3 22.5
20 6 4 0.17 6 45
24 9 5 0.25 9 67.5
30 14 8 0.40 14 105
36 22 13 0.62 22 164.5
40 28 17 0.80 28 209.5
42 33 20 0.93 33 247
48 50 30 0.93 50 374

Page 34 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

Table 3 – Richmond Wing Nut Test Plugs (A-900 Series)


Unexpanded Max
Nominal Size O.D. of Rubber Pressure SAMS S/N
(In) (In) (Psig)*

3 2-3/4 20 02-958-074
4 3-5/8 18 02-958-078
6 5-1/2 10 02-958-082
8 7-1/2 5 02-958-086
10 9-1/2 3 02-958-090
12 11-1/2 2 02-958-094

NOTE: One pound per square inch gauge (1 psig) is equivalent to a column of water 704 mm (2.31 ft) high.

Table 4
Size Approx. Capacity
(in) (barrel/hr)

1 15 - 30
2 65 - 130
3 145 - 300
4 260 - 500
6 600 - 2000
8 1000 - 4000
EXAMPLE: Consider 609.6 m of 6 in flow line. Contents are approximately 2000/1000 x 6² = 72 barrels. A 2 in drain
should be provided.

Page 35 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

Attachment 1 – Hydrogen Induced Cracking (HIC) Decision Tree

(Refer to Sec. 3.5)

SWC = Step Wise Cracking


t = Wall thickness of vessel or pipe
Depth = defect depth below nearest surface, whether ID or OD
(a through i) See Notes, Page 38

Page 36 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

Notes for Attachment 1 – Hydrogen Induced Cracking (HIC) Decision Tree (Cont'd)
a) Once suspected hydrogen induced cracking (HIC) damage is located,it should be surveyed to determine the size and shape
of the damaged area, whether the suspected HIC occurs as small isolated spots or nearly continuous fields, and the depths
at which the suspected HIC is detected. Such surveys are normally conducted using ultrasonic examination.
b) Before assuming that the depth of a defect is less than 0.1 t, the area should be ultrasonically examined from both inside and
outside surfaces, when possible, to insure that additional areas of HIC at different depths are not masked from detection by
the near-surface defect.
c) Hydrogen blistering at mid-wall is a common anifestation of HIC. Such mid-wall blistering produces little strength loss unless
accompanied by Step-Wise Cracking (SWC), in which blisters are several different depths link up at shear steps.
d) Contact the CSD/ME&CCD/Materials Engineering Unit, for appropriate sample locations and for the metallographic
examination to detect SWC.
e) High, sharply crowned blisters may have SWC around the blister periphery which may be difficult to detect with ultrasonic
examination. Sample such areas as in note (d) to check for SWC.
f) Monitoring of items with HIC normally involves regular and frequent ultrasonic examination of the damaged area to determine
whether the HIC is growing or not. If the HIC continues to grow, periodic reassessment through the decision tree will be
necessary. Hydrogen evolution monitoring is used to check the inhibitor effectiveness in pipelines. In general, items with a
history of HIC should also be internally inspected more frequently than similar equipment free of HIC.
g) The inhibitor injection rates required for arresting HIC are much higher than those normally used for suppressing general
corrosion. Contact the CSD/ME&CCD, for specific application details.
h) It is assumed that arresting further HIC in plant piping, which cannot be coated in place and may be difficult to inhibit
effectively, may be uncertain and thus replacement will eventually be required. The urgency of replacement will vary widely
depending on operational circumstances and the extent of HIC damage. Consult the CSD/ME&CCD/MEU.
i) If blistering is extensive, of if SWC is observed, the residual strength of the item is best determined by a hydrostatic test at a
nominal stress of 90% of yield. After revalidation hydrotesting, vessels or cross-country pipelines with HIC may be continued
in service provided further HIC growth is arrested with coatings, inhibitors or both. Intensive monitoring may be required.

Page 37 of 38
Document Responsibility: Piping SAEP-310
Issue Date: 30 November 2005
Next Planned Update: 1 April 2006 Pipeline Repair and Maintenance

Attachment 2 – Saudi Aramco Pipeline Field Welding Checklist

Type of Weld
Line No. ________________ F.W.: ___________________
Butt Weld [ ] Weld Repair [ ]
O.D.: ___________Nom. Wall(1): ________ Grade ________ Sleeve [ ] Patch [ ]
Weld Build-Up [ ] Other [ ] ________

PRE-WELD INSPECTION
Check List Maintenance Sign-Off/Date Inspection Verification/Date

WPS No. _____________________ _______________/_______________ ____________/____________

Welder Symbol:________________ ______________/________________ ____________/____________


Qualified to WPS: Y/N

Filler Material: _________________ ______________/________________ ____________/____________


Size (Dia.)____________________

Fit-Up & Cleanliness: Acc/Rej. ______________/________________ ____________/____________

IN-PROCESS WELD INSPECTION


Check List Maintenance Sign-Off/Date Inspection Verification/Date

Pre-Heat:________________°F ______________/_______________ ____________/____________

Max. Interpass Temp:______°F ______________/________________ ____________/____________

Voltage: _________Amp.:________ ______________/________________ ____________/____________

Visual Insp. (Workmanship) Acc/Rej. ______________/________________ ____________/____________

FINAL WELD INSPECTION


Check List Maintenance Sign-Off/Date Inspection Verification/Date

Final Visual Insp. Acc/Rej. ______________/_______________ ____________/____________

NDE Completed: RT [ ] Acc/Rej


MT [ ] Acc/Rej.
PT [ ] Acc/Rej.
UT [ ] Acc/Rej. _____________/________________ ____________/____________
(1)
See Notes 1 and 2 on WPS No.s P1-R1 and P1-R2 for electrode diameter and welding technique restrictions for applicable
wall thickness measurement.

Page 38 of 38

You might also like