L15-L16 Testing of CB
L15-L16 Testing of CB
L14-L15
Testing of CB
Dr. H.V. Gururaja Rao
Associate Professor
Department of E&EE
MIT, MAHE, Manipal
Directtesting: Here the complete circuit breaker is tested under actual conditions that exist on the CB in
the power system.
Major equipments in laboratory type testing station
• Short circuit generator: Specially designed generator to supply short circuit current(power) required for
testing. Usually IM driven.
• Impulse exciter: Specially designed exciter to supply excitation current to generator during a very short
period.
• Short circuit transformer: Specially designed transformer to obtain various voltages required for testing.
• Master CB: A tested CB of slightly higher rating than the test CB, as a back up CB.
• Making switch: Designed to close on heavy currents, to initiate short circuit current flow.
• Reactor: To adjust the SC current to the desired value.
• Resistors: To control the value of circuit power factor, frequency of oscillations etc.
• Inductor and capacitor: To adjust RV, RRRV etc.
• Oscillograph: To record (store) current and voltage waveforms.
Circuit diagram for direct testing
Test for breaking Capacity
Procedure:
• ‘X’ isadjusted to get required short circuit current
• ‘C’, ‘R1’ and ‘R2’ are adjusted to get desired RV,RRRV and power factor.
• Short circuit transformer is used to get required voltage for testing.
• Master CB and Test CB are kept in closed position.
• Using the driving motor, the generator is run to the required speed and then the motor is switched off.
• Impulse exciter is switched on and field current is adjusted to the required value.
• Oscillograph is switched on.
• Short circuit current is initiated by closing the making switch.
• Test circuit breaker is opened; Slightly later master circuit breaker is opened.
• Exciter circuit to the short circuit generator is switched off.
All these operations might be over with in 0.2 seconds!
• From
the oscilloscope record, following measurements are done:
Symmetrical and asymmetrical breaking current
RRRV and frequency of oscillations
Recovery voltage.
Circuit breaker must be capable of breaking all currents up to its rated capacity.
Hence breaking current test is usually performed at 10%, 30%, 60% and 100% of its
rated breaking current.
Short time current test
• Current is adjusted to rated breaking current.
• Master and test CB are closed.
• Making switch is closed.
• Test CB is opened after 1 sec or 3 sec, depending on the used standard.
• Master CB is opened slightly later.
• TheCB should be capable of withstanding the associated thermal stresses and there should not be
any mechanical or insulation failure.
Test for making capacity
• Current is adjusted to the required value.
• Master CB and the making switch are closed.
• Short circuit is initiated by closing the test CB.
• Test CB and Master CB are opened.
• From the oscilloscope record, peak value of the first major loop of the short circuit current is measured.
Duty Cycle test
• Following duty cycle tests are performed at 10%, 30%, 60% and 100% of rated breaking
current.
a) For CBs not intended for rapid autoreclosure:
i) O – t – CO – T – CO or ii ) O – t´ – CO
b) For CBs intended for rapid autoreclosure
O – td – CO;
Indirect testing
• Testing of HV CBs of large capacity requires very large capacity (Power) of the testing station, which is
uneconomical.
• Indirect methods can be used to test large CBs