0% found this document useful (0 votes)
303 views1 page

ExamTopics Questions - 092039

The document discusses a project manager who reduces time for project retrospectives due to pressure from the sponsor. This could cause discussions that yield no results and lessons learned from other teams to not be considered.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
303 views1 page

ExamTopics Questions - 092039

The document discusses a project manager who reduces time for project retrospectives due to pressure from the sponsor. This could cause discussions that yield no results and lessons learned from other teams to not be considered.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Question 443

A project sponsor commonly asks the project manager to skip project retrospectives due to
time constraints. However, the project manager persists in running this critical ceremony by
reducing the time for preparation and for discussion.
What are two issues that these actions by the project manager could cause? (Choose two.)

 A. A lot of discussions that yield no results or possibly too many results


 B. A lack of direction and motivation for the team in the workshop
 C. Lessons learned from other teams to not be considered
 D. Time management plan for the retrospective workshop to not be updated
 E. A focus on the negative and a disinterest in further improvements
Answer 443
A project sponsor commonly asks the project manager to skip project retrospectives due to
time constraints. However, the project manager persists in running this critical ceremony by
reducing the time for preparation and for discussion.
What are two issues that these actions by the project manager could cause? (Choose two.)

 A. A lot of discussions that yield no results or possibly too many results


 B. A lack of direction and motivation for the team in the workshop
 C. Lessons learned from other teams to not be considered
 D. Time management plan for the retrospective workshop to not be updated
 E. A focus on the negative and a disinterest in further improvements
Hide Answer

Suggested Answer: AC

Question

You might also like