Microgrids
Microgrids
Microgrids
Microgrids:
An Overview of Ongoing
Research, Development, and
Demonstration Projects
a
Power Division of the School of Electrical and Computer Engineering of National Technical University
of Athens, Greece
b
University of Tokyo and Institute of Electric Power Industry in Tokyo, Japan
c
University of Toronto, Canada
d
Environmental Energy Technologies Division, Ernest Orlando Lawrence Berkeley National Laboratory, Berkeley
94720, USA
Environmental Energy
Technologies Division
July 2007
http://eetd.lbl.gov/EA/EMP/emp-pubs.html
The work described in this report was funded by the Office of Electricity Delivery and
Energy Reliability, Distributed Energy Program of the U.S. Department of Energy
under Contract No. DE-AC02-05CH11231.
Disclaimer
An Overview of Ongoing
Research, Development, and
Demonstration Projects
T
(DG) at medium and low voltages (MV and LV), both in util-
ity networks and downstream of the meter, is increasing in
developed countries worldwide. One key economic potential
of DG application at customer premises lies in the opportuni-
ty to locally utilize the waste heat from conversion of pri-
mary fuel to electricity by reciprocating engine generators
(gensets), gas turbines, microturbines (MTs), or fuel cells
(FCs) using small-scale combined heat and power (CHP)
equipment. Consequently, there has been significant progress
toward developing small (kW-scale) CHP applications.
These systems, together with solar photovoltaic (PV) mod-
ules, small wind turbines (WTs), other small renewables
(such as biogas digestors), heat and electricity storage, and
controllable loads are expected to play a significant role in
future electricity supply. These technologies are herein col-
lectively called distributed energy resources (DERs). They
can substantially reduce carbon emissions, thereby contribut-
ing to the commitments of most developed countries (or in
some cases regional governments, such as California) to
meet their greenhouse gas emissions reduction targets (typi-
cally based on the Kyoto Protocol), or otherwise substantial-
ly reduce their carbon footprints. Also, the presence of
generation close to demand can increase the power quality
and reliability (PQR) of electricity delivered to sensitive end-
uses. Indeed, DERs can be used to actively enhance PQR. In
general, these three perceived benefits, increased energy effi-
ciency through CHP, reduced carbon emissions, and
improved PQR, are the key drivers for DER deployment,
although many other benefits, such as reduced line losses
and grid expansion deferral, are also often discussed.
While the application of DERs can potentially reduce the
need for traditional system expansion, controlling a potential-
ly huge number of DERs creates a daunting new challenge
for operating and controlling the network safely and efficient-
ly. This challenge can be partially addressed by microgrids,
which are entities that coordinate DERs in a consistently
more decentralized way, thereby reducing the control burden
on the grid and permitting them to provide their full benefits.
In the context of this article, a microgrid comprises a LV (≈≤
1 kV) or MV (usually ≈1–69 kV) locally-controlled cluster
of DERs that behaves, from the grid’s perspective, as a single
producer or load both electrically and in energy markets. A
microgrid operates safely and efficiently within its local dis-
tribution network, but it is also capable of islanding. Micro-
grid design and operation demand new skills and technology,
while distribution systems containing high DER penetration
may nonetheless require considerable operational control
capabilities. While not strictly compliant with the above defi-
nition, small isolated power systems are included here as
microgrids. They apply similar technology and provide added
© EYEWIRE
Public Grid
U=10 kV University Laboratories
SM DCM DCM
DCM SM
Power
Supply 1
Power
Supply 2 EMC Laboratory Pump Laboratory
IM
IM IM IM DCM SM
S=175 kW S=400 kW
WWW
Supervisory
Control Unit
Crossbar LAN
Switch Cabinet 5 6 9 10 11
7 12 81 82 83 z z
4
IM SM SM 12
Loads
z
3
SM CM 15 kW
Mini Grid
80 kW Grid Simulator Simulator PV-Battery-System PV-Battery-Diesel-System 10 kV Hardware Network Simulator SINVERT Solar Three Phase
2 5 kW WEC Hybrid System Inverter
16
Simulator 17 52 51 Central Control and
CM
Visualisation Unit
14 13
for Presentations
20 kW Variable Speed Genset
1
IM
SM
30 kW Diesel Generator Set CHP Station PV-Inverters Mini Grid Kit Virtual Battery Battery Bank
JB
Power Line
Interbus-S Control Line 3 x 1 kW-Photovoltaic
Internet Communication Line Arrays
PV Array
PV Array
=
~ =
= ~
=
~ ~
AC Grid: 3~ 400 V
~ ~ ~ ~ ~ ~
= = = = = =
=
~
0.5 kW
0.2 kW
0.0 kW 0 kWh
00:00 10:00 13:00 24:00
Average Load and Cumulative Energy Consumption for Days with a Price Signal 10 a.m. – 1 p.m.
Average Load and Cumulative Energy Consumption for Days without a Price Signal
figure 3. Washing with the Sun encouraged customers to shift loads to high solar generation periods (source: MVV Energie).
✔ exploring the impact on the development of electricity Netherlands: Continuon’s MV/LV facility.
network infrastructures, including quantification of the Continuon operates a holiday camp with more than 200 cot-
benefits of microgrids, to the overall network, and to tages, equipped with grid-tied PV totaling 315 kW. The cot-
the reinforcement and replacement strategy of the tages are connected to an MV/LV transformer using four
aging EU electricity infrastructure approximately 400-m feeders. Daytime loads are low, so most
✔ executing extensive field trials of alternative control of the PV power is injected into the MV grid. During the
strategies in actual installations, with experimental val- evening and night, support from the grid is needed. High volt-
idation of various microgrid architectures in intercon- ages at the end of the feeder and a high level of voltage dis-
nected and islanded modes, and during transition tortion during high PV output have been noted. With the
testing of power electronics components and interfaces microgrid islanded, improvements in power quality are
and of alternative control strategies, communication sought using power electronic flexible ac distribution systems
protocols, etc. and storage.
Communications
Power Flow
Controller
Electric Wires
Circuit B : Controllable Loads
Static
Switch
Point of
Common
Coupling Traditional
Interconnection
Circuit C : Default Service
(Nonsenstive Loads)
governments under way in Germany, Spain, the United King- small sites (∼<2 MW peak) without need for costly fast
dom, the Netherlands, and elsewhere. electrical controls or expensive site-specific engineering.
No single device is essential for operation, creating a
RD&D Activities in the United States robust system.
The United States has had a modest but slowly expanding Figure 4 shows an example CM, whose salient features are:
microgrids research program for a number of years, supported ✔ a lack of fast electrical controls. The operation of gen-
both by the U.S. Department of Energy (DOE) under the erators is controlled locally by power electronic
Office of Electricity Delivery and Energy Reliability (OE), and devices incorporating droop characteristics that
by the California Energy Commission (CEC) through its Pub- respond to locally monitored frequency and voltage.
lic Interest Energy Research Program. Heightened demand for Consequently, devices that naturally require a power
high PQR in the U.S., primarily to match the high end of het- electronic interface, e.g., dc sources, are particularly
erogeneous end-use requirements, has naturally led to amenable to incorporation in a CM.
increased focus on enhancing PQR locally using microgrids. ✔ a single point of common coupling (PCC), and does
not export. To the utility the CM appears as a single
CERTS Microgrid Introduction
The most well-known U.S. microgrid RD&D effort has
been pursued under the Consortium for Electric Reliability
Technology Solutions (CERTS) (see http://certs.lbl.gov),
which was established in 1999 to explore implications for
power system reliability of emerging technological, eco-
nomic, regulatory–institutional, and environmental influ-
ences. From the inception of CERTS, the likely emergence
of DG was recognized as an important factor, and it has
been a focus of the CERTS RD&D agenda. The specific
concept of the CERTS Microgrid (CM) was fully developed
by 2002, when it was described in a white paper and pre-
sented at a CEC Workshop. Subsequently, building physical
examples was undertaken.
The CM, as with most microgrid paradigms, is intend-
ed to, as seamlessly as possible, separate from normal
utility service during a disruption and continue to serve
its critical internal loads until acceptable utility service is figure 5. Layout of the Dolan Technology Center CM test
restored. The CM provides this function for relatively bed (June 2006) (source: CERTS).
On-Site
ag
Refrigeration and
S
Utility
rm
Natural
Th
Conventional
Wind Photovoltaics Generation
Market
Operations
Load
Substation
Centralized
Energy
Manager
POCC
Water
Treatment
MEM: Communication
and Control Network
MEM: Local
Energy Control Network
Storage Thermal Network
Electrolyzer H2 Fuel Electrical Network
Storage Cell
Local Protection
Elements
Digestor Gas
Digestor
Holder
Gas
Digestion
Chamber
Heat
PCC
Hachinohe Hachinohe City Hall (360 Kw) Hachinohe City Hall
Regional Water Supply Annex
Authority (40 Kw)
PV (10 kW)
WT (2 × kW)
Commercial Grid
figure 10. Overview of the Aomori project (source: Y. Fujioka, et. al., 2006, in further reading).
DER-CAM is a fully technology-neutral optimizing operating condition. Moving leftward along the x-axis repre-
model of economic DER adoption, written in the General sents tighter and tighter carbon caps imposed on this site. For
Algebraic Modeling System software. Its objective is to example, at a 1,000-t/a cap, the optimal system still includes
minimize the cost of operating on-site generation and CHP the thermal generator, but with additional solar thermal
systems, either for an individual customer site or a micro- capacity of about 2.7 MW, and also 900 kW of PV. Using
grid (http://der.lbl.gov). Figure 7 shows some of the major DER-CAM in this way, the economically optimal combina-
energy flows within a microgrid, from fuel inputs to the left tion of equipment to install in a microgrid can be found,
to useful energy end-uses to the right. DER-CAM chooses given environmental and other constraints.
the cost-minimizing equipment installation from an arbi-
trary list of available technologies that could include solar GE Global Research Microgrid
thermal or PV, thermal and electrical storage, any thermal DOE also co-funds with General Electric (GE) a second, sep-
prime mover, heat recovery devices, and CHP equipment arate two-year, approximately US$4 million microgrid effort
including absorption cooling. Since it finds the optimal led by GE Global Research. GE aims to develop and demon-
solution, the simultaneity of CHP-powered cooling with strate a microgrid energy management (MEM) framework for
absorption chillers is considered so that, for example, the a broad set of microgrid applications that provides a unified
benefit of downsizing generator capacity is traded off controls, protection, and energy management platform (Fig-
against the cost of nonelectrical cooling equipment. An ide- ure 9). At the asset level, MEM is intended to provide
alized operating schedule including grid and other fuel pur- advanced controls for both generation and load assets that are
chases is also produced. robust with respect to low-inertia environments. At the super-
Figure 8 shows DER-CAM results for a huge building in visory level, MEM will optimize the coordinated operation of
the hot southeastern part of California. Without any concern interconnected assets in the microgrid to meet customer
for carbon emissions, this site emits about 1,275 t/a of ele- objectives such as maximizing operational efficiency, mini-
mental carbon including emissions incurred by utility-deliv- mizing cost of operation, minimizing emissions impact, etc.,
ered electricity. DER-CAM chooses a 1-MW natural gas and is also intended to enable integration of renewables and
genset and 1.4 MW of solar thermal heat recovery for this microgrid dispatchability.
250 50.5
Frequency
200 50
Frequency (Hz)
Machine (37 kW)
Started Up Battery Output
100 49
Demand
0 48
0 1 2 3 4 5
Time (s)
figure 11. Frequency control characteristics in islanded operation (source: Y. Fujioka, et. al., 2006, in further reading)
PCC
NG Remote Measuring
250 kW
Gensets Fuel Cell and Control System
50 kWp PV 2 × 350 kW MCFC
DVR2
Quality Quality
A dc B1 Quality Quality
B2 B3
City-Owned Road
City Zone
figure 12. System configuration of the Sendai demonstration project (source: K. Hirose et. al., 2006, in further reading).
designers, operators, system integrators, and equipment manu- energy sources might degrade the country’s outstanding
facturers. Implementation of this guide will expand the benefits PQR. Traditionally, customers that operate fossil fuel-fired
of using DERs by targeting improved electric power system DERs, such as natural gas gensets with CHP do so base-
reliability and build upon the interconnection requirements of loaded at rated power. Others that use intermittent renewable
IEEE 1547-2003, Standard for Interconnecting Distributed sources balance supply and demand through purchased grid
Resources with Electric Power Systems. power. In either case, residual purchases from the grid are
Northern Power and the National Renewable Energy Labo- volatile. Conversely, a microgrid can contribute load-follow-
ratory (NREL) have completed a project that examines the ing capability to a utility grid by balancing its own energy
regulatory and technical issues associated with installation and requirement using controllable prime movers to balance fluc-
operation of a microgrid in rural Vermont. Northern Power tuating load and renewable output. For example, a microgrid
worked with the local electricity utility to predict the impact with electrical storage and/or gensets can potentially fully
and effects of the microgrid at the end of a low capacity distri- compensate for its intermittent renewable supply and present
bution feeder with the poor PQR typical of rural areas. itself to the grid as a constant load. This principle has moti-
vated much of the RD&D in Japan, and has led to an empha-
RD&D Activities in Japan sis on controls and electrical storage.
Japan is the current world leader in microgrid demonstration
projects. The Japanese government has set ambitious targets NEDO Microgrid Projects
for increasing the contribution of renewable energy sources, The New Energy and Industrial Technology Development
such as WT and PV, but the fluctuating power of renewable Organization (NEDO), the research funding and management
Wind Plant
Feeder # 2
System
Master
PFC
Wind Plant
Control
Master
Load
Regulator
WTC WTC WTC WTC WTC WTC
#1 #2 #3 #4 #5 #6
generated from high temperature (1,200 °C) treatment of B3 is not backed up. If the grid has a momentary voltage sag
wood waste and plastic bottles. Both the MCFCs and SOFC or outage, the switch-over time for the highest quality B serv-
are baseloaded while the PAFCs load follow. Total PV capac- ice is less than 15 ms. The cost of supplying multiple power
ity is 330 kW, and a 500-kW NAS battery is used for balanc- quality levels must be less than that of existing UPS, save
ing. Experiment results of intentional islanding mode have space, and reduce low power loss.
also been obtained. The integrated power system consists of a two-way mode
power module, dc-ac inverter, dc-dc converters, and a battery
The Kyoto Project at Kyotango bank. In an outage, the battery becomes a power source and
The municipal government of Kyotango City, north of feeds to each connected load. The electric power to the highest
Kyoto, leads this first virtual microgrid demonstration proj- quality, B1, load is supplied by the two-way mode power mod-
ect covering a 40-km span called the Kyoto Eco Energy Pro- ule. The power flows of premium quality A and dc do not
ject, which started operation in December 2005. It change, and the feed of stable electric power continues without
incorporates the following generation capacities: 50-kW of an outage. A dynamic voltage restorer is used for B2, while B3
PV, 50 kW of WTs, 5 × 80-kW biogas gensets, a 250-kW equipment is limited to momentary voltage dip compensation.
MCFC, and a 100-kW battery bank. An energy control cen-
ter communicates with the DERs by internet protocol over Private Sector Microgrid RD&D
the legacy telecom network to balance demand and supply, In addition to the government-sponsored projects described
and energy is fed into the legacy distribution system. Imbal- above, significant private sector research activities are also
ances can currently be rectified over 5-minute time-steps, in progress. Shimizu Corporation, a major commercial
and shorter ones are planned. building construction company, with the cooperation of the
University of Tokyo, is developing a microgrid control sys-
NEDO’s Sendai Project Under Its Advanced tem using a test microgrid at its research center in Tokyo.
Regional Electricity Network Program The DERs include two natural gas gensets of 90 kW and
In Sendai, NEDO also sponsors a multiple PQR service 350 kW, 4 × 100-kW-400-kJ electric double layer capaci-
demonstration which was completed in October 2006. The tors, and a 200-kW × 2-h NiMH battery bank. The princi-
purpose of this research is to demonstrate multiple simultane- ple project objective is to develop an optimum operation
ous PQR supply, as may be requested by a range of customers. and control system. The target market includes urban devel-
Over the research period of 2004–2008, the goals are: opments, university campuses, and high PQR demanding
✔ to prove that multiple power quality levels can be sup- facilities, such as hospitals, banks, data centers, etc.
plied simultaneously by a microgrid Tokyo Gas also aims to establish distributed energy net-
✔ to compare the economic viability of the multiple PQR works including microgrids within its service territory. A
approach compared conventional uninterruptible power microgrid is under development that again utilizes control-
supply (UPS) equipment. lable prime movers such as natural gas gensets to compensate
The system configuration is shown in Figure 12. The for fluctuating demand and renewable output. Costly battery
Energy Center and distribution line are installed and con- capacity can also be reduced if gensets can compensate for
nected to the utility line at a single PCC. The major DERs fluctuating renewable output. Partnering with the University
are a 250-kW MCFC, two 350-kW natural gas gensets, and of Tokyo, Tokyo Gas is developing an integrated DER control
a 50-kW battery bank. The microgrid directly serves some system based on simulation studies and experiments at its test
dc loads and additionally supplies four different qualities of facility in Yokohama. The test facility includes 2 × 25-kW
ac service to a university, a high school, and a sewage plant. and 2 × 9.9-kW natural gas gensets, 2 × 6-kW WTs, 10 kW
Premium quality A service is never interrupted and is of PV, batteries, and a biogas engine is under development.
conditioned by voltage and waveform correction. A B service This microgrid will also supply three PQR levels to a build-
is supplied at three qualities, the differences based on backup ing of the Yokohama Research Institute.
during utility grid outages. The highest quality B1 supply is In Japan, multiple field tests of microgrids are demon-
backed up by storage, while B2 is backed up by a genset, and strating the technical feasibility of microgrids with a focus
Temp – Feeder
CB2 1 2 3 5
9.7 km 4.6 km Main Substation
2.5 km
L1 L2
43 MW L4 25 / 69 kV
X/R = 1.74 R1 2×6 MW
PCC
L sub CB1 69
S2 2.8 km
Rsub 69 kV
13 12
L12 11 10 9 8 260 MW
L10 L9 L8 L7 6
X / R= 1.6
14.2 km L5
5.0 km 6.8 km 10.6 km 4.6 km
R3 16.7 km
R2
S13
S12
S9 S8
S5
S6
4.32 MW 4.32 MW
8 MW
Power Producer
Small Hydro Plant
M
Feeder3: 4 MVA
M M VWVE3
L1
figure 16. HQ distribution system for planned islanding site (source: Hydro Québec).
it, depending on adequate availability of power from local on grid-connected and autonomous operating modes
DERs; however, slow response of the hydro unit and the (after islanding generator protection is also extended to
intermittent nature of the WTs impose restrictions that per- feeder protection)
mit only planned islanding. Furthermore, the wind intermit- ✔ resynchronization capability to connect the
tency and hydro water level dependency impose challenges autonomous island to the BC Hydro network without
for load following while islanded. Integration of fast-acting interruption
dispatchable DERs is an option to overcome these islanding ✔ black-start capability for the hydro unit using a 50-kW
operational issues. diesel genset.
A portion of the Hydro Québec (HQ) distribution sys-
Planned Microgrid Islanding tem connected to the Senneterre substation is also under
Planned islanding is a central element within the microgrid consideration for planned microgrid islanding. The sub-
concept used to maintain continuity of supply during station supplies 15 MW of residential and commercial
planned outages; e.g., substation maintenance periods. Fig- loads (Figure 16). The substation is supplied partly by a
ure 15 shows a one-line diagram of the British Columbia 125-kV line and partly by a privately owned and operated
(BC) Hydro Boston Bar system that adopts planned island- 31-MW thermal power plant that can also export excess
ing. The system is composed of a 69-kV/25-kV substation power. Planned islanding capability is required to prevent
supplying three radial feeders. One feeder incorporates an service interruption when the 125-kV line is not avail-
8.64-islanded-MW run-of-river hydro unit operated by an able. In October 2005, islanding tests were performed
independent power producer (IPP) and a 3-MW peak load. and a 12-hour islanding about an 11-MW load was suc-
The hydro units are equipped with the capability to accom- cessfully achieved.
modate planned islanding of the corresponding feeder, Microgrid related aspects of the Seneterre experiment are:
depending on generation availability, and the status of adja- ✔ control and mitigation of transients during switching to
cent feeder(s). islanded operation, based on load and generation bal-
The microgrid-related operating aspects of the project are: ancing prior to islanding
✔ load management of the island, including the two adja- ✔ stability based on a generator speed-droop governor
cent feeders control
✔ load-following capability with limited frequency fluc- ✔ protection coordination for the island
tuations ✔ power quality provision for specific loads during
✔ two modes of generator control and protection based autonomous operation.