Engineering Economic Analysis (Week 4) Basic Methodologies of Engineering Economic Analysis
Engineering Economic Analysis (Week 4) Basic Methodologies of Engineering Economic Analysis
Chapter 3
Basic Methodologies of Engineering
Economics
Lecture 4 (Week 4)
Minimum Attractive Rate of Return
(MARR), Equivalent worth Method and
Internal Rate of Return
Learning Objective
From studying this lecture the students will be able to understand on the topics:
The concept of Minimum Attractive rate of return (MARR)
The concept of Equivalent worth Method (Present worth, Future worth and
Annual worth)
The Concept of Rate of return method and internal rate of return (IRR)
method.
4.1 Introduction
If an organization have a huge sum of money in the investment pool and there are many
alternatives (projects) whose initial investment cost and annual revenues are known then the
organization has to select the best alternative among the different projects. The worthiness of
the project has to be determined, whether a proposed project can generate revenue or not to
recover the invested capital. [1]. There are various methods of analyzing the worthiness of a
project. These methods are:
Capital rationing refers to the situation where the funds available for capital investment are not
sufficient to cover potentially acceptable projects.
Opportunity cost refers to the value of benefit scarified in course of selection of alternative.
It is generally dictated by management considering the following points: [2]
The amount of money available for investment - Source and cost of these funds (equity,
borrowed funds etc.)
The number of good project available for investment
The amount of perceived risk associated with the investment
The type of organization involved (government, public, private)
Example
35 35%
AA
Annual rate of profit (%)
30 30%
Capital Supply
26%
25 B
C 23%
19%
20
D Reject project F and G
15 16%
14%
10
E
5
F
G
20 30 40 50 60 70 80
$ In million
Fig 3.1: MARR Determination [2]
• Last funded project = Project E
• Prospective rate of profit = 19%
• Best rejected project = F (by not being able to invest in project F, the firm
would presumably be forfeiting the chance to realize on 16% annual return)
• MARR = 16% per year (as the amount of investment capital and opportunities
available change over time, the firm’s MARR will also change)
Net present worth = Equivalent present worth of future cash flow – Initial investment
Here we use NPW or NPV as PW
Present Worth Analysis (PW)
Determine the interest rate that the firm wishes to earn on their investment, which is
referred as either required rate of return or MARR (minimum attractive rate of return).
[5]
Estimate the service life of the project.
Estimate the cash inflow and out flow for each service period.
Determine the net cash flows
= Cash inflow – cash out flow
Present worth of each net cash flow as shown in figure 3.2, at MARR as
A A A A A A
0
1 2 3 4 N -1 N
An will be +ve if the corresponding period has a net cash inflow and -ve if there is net cash
outflow. Positive ‘NPW’ means the equivalent worth of cash inflows is greater than equivalent
worth of cash out flows and vice versa.
N
=
n o
An (F/P, i%, + N-n)
(c) Annual worth Method (AW) or Net Annual worth Method (NAW)
Annual worth method provides the basis for measuring investment worth by determining
equal payments on an annual basis. [5]The AW of a project is its annual equivalent receipts
(R) minus annual equivalent expenses (E) minus annual equivalent capital Recovery (CR).
R, E, and CR are calculated at MARR (Sullivan)
AW (i%) = R – E – CR
Where,
R = annual revenues,
E = annual expenses,
CR = capital recovery
Knowing that any lump sum cash amount can be converted into a series of equal annual
payments we may first find the present worth of the original series and then multiply this
amount by the capital recovery factor:
Decision rule
The decision rule is same as PW and FW
0 N
PW inflow – PW outflow = 0
+
Based on FW formulation i*% i%
-
FW (i* %) = 0
FW inflow – FW outflow = 0 PW
Fig 3.3: Mathematical relation of IRR [2]
Based on AW formulation
AW (i* %) = 0
AW inflow – AW outflow = 0
Develop an equation for equivalent worth of any point of time indicating rate of
interest by i*% whose value is to be found.
Equate the developed equation as to zero.
Solve it to get the value of i*% which would be IRR
References:
[1] A Textbook of Engineering Economics: Damodar Adhikari, First Edition, Dreamland
Publication Pvt. Ltd. Kathmandu, Nepal, 2019.
[2] Engineering Economy: William G. Sullivan, James A. Bontadelli & Elin M. Wicks,
Eleventh Edition, Pearson Educations, Inc. 2000.
[3] Engineering Economics: James L. Riggs, David D. Bedworth and Sabah U. Randhawa,
Fourth Edition, Tata McGraw Hill Education Private Limited, New Delhi, India, 2004.
[4]Engineering Economics: Jose A. Sepulveda, William E. Souder and Byron S. Gottfried,
Tata McGraw – Hill Publishing Company Limited, New Delhi, India, 2005.
[5] Contemporary Engineering Economics, Chan S. Park Second Edition, Addison-Wesley
Publishing Company, 1997.
[6] https://www.investopedia.com/terms/r/rateofreturn.asp (viewed on September 2022)