Project Management Introduction and Over
Project Management Introduction and Over
1
Acknowledgements
This material is for teaching purposes only.
Not to be distributed without explicit
permission of the author.
All the material is prepared from the
following sources.
1. C F Gray, E W Larson and G V Desai,
“Project Management, The Managerial
Process”, Tata McGraw Hill, 2010
2. S J Mantel, Jr., J R Meredith, S M Shafer,
M M Sutton with M R Gopalan, “Project
Management Core Text Book” John Wiley
India, 2011 2
3.PPT slides from the Project Management
Course at Edmund T. Pratt, Jr. School of
Engineering at Duke University, USA.
4.Project Management in Practice, A short
note by V. Srinivasa Rao.
5.Project Management Body of Knowledge
(PMBOK) Guide Fourth Edition.
6.Personal thoughts, views, ideas and
experience.
7.Project implementation status of Central
Sector Projects, April – June 2009, MOPSI
Introduction
5
Unique set of activities to achieve a
defined outcome within a specified time
frame using specific resources”.
Characteristics
Not routine work
Objective with specifications that can
be measured
Divided into interdependent tasks
Life cycle with a specified due date
A B
Project Management
Application of knowledge, skills, tools and
techniques to project activities to meet
requirement
Integrative approach
Integration of projects with strategic plan
Integration with the process of managing
Project Management
A B
9
Importance of Project Management
Business
Projects define and redefine the
business
Businesses are built through series of
projects that define
Physical infrastructure
Products and / or services that are
sold
Processes for making a product or
deliver a service
10
Future projects are identified based on
strategic needs to change or define the
company.
Assets in place :
14
“o e “ur eys o Proje t I ple e tatio …
CIO.com cites a Dynamic Markets survey of
800 IT managers –
62% of IT projects fail to meet their
schedules.
49% suffered budget overruns
47% had higher-than-expected
maintenance costs, and
41% failed to deliver the expected
business value and ROI
Source: CNET News, 09/10/2012, 62 percent of
IT Projects fail. Why?
Refers to: Why do IT projects fail, and is there
anything we can do about it? - by Matt Asay,
March 21, 2008
http://advice.cio.com/remi/two_reasons_why_
it_projects_continue_to_fail
“o e “ur eys o Proje t I ple e tatio …
Source: Project implementation status of Central Sector Projects, April – June 2009, MOSPI
17
“o e “ur eys o Proje t I ple e tatio …
Source: Project implementation status of Central Sector Projects, April – June 2009, MOSPI
18
“o e “ur eys o Proje t I ple e tatio …
Source: Project implementation status of Central Sector Projects, April – June 2009, MOSPI
19
“o e “ur eys o Proje t I ple e tatio …
Source: Project implementation status of Central Sector Projects, April – June 2009, MOSPI
20
Strategic Project Management
• Logical Framework Approach *
– Also known as
• Goal Oriented Project Planning (GOPP)
• Objectives Oriented Project Planning (OOPP)
– Developed in 1969 for US Agency for
International Development (USAID)
• Design, Monitoring and Evaluation of
projects
* “trategi Ma age e t Made “i ple: Pra ti al Tools for Leader
a d Tea s y Terry “ h idt
Wikipedia: Logical framework approach
The logi al fra e ork approa h y Keerti Bhusan Pradhan
• Four Critical Questions
– What is to be accomplished and why
– How is success to be measured
– What other conditions are necessary
– How do we get there
• Four by four Table
– Four rows
• Describe different types of events
– Four columns
• Provide information about the events
• Four levels / rows
– Goal
• High level objective to which the project
contributes
– Purpose
• Anticipated impact from outcomes
– Outcomes
• Results that the project must deliver
– Inputs
• Activities and resources necessary to deliver
outcomes
• Four columns
– First Column
• Narrative description of event
– Second Column
• Success measures / Objectively Verifiable
Indicators (OVI)
– Third Column
• Means of Verification (MoV)
– Fourth Column
• Assumptions
–External factors that influence positively or
negatively the events
–List includes all the factors that have an
impact
–Not directly controllable
–Project dependency on external factors
–Killer assumptions
• Temporal Logic
– If activities are undertaken and the
assumptions hold, then the outputs will be
delivered
– If the outputs are delivered and the
assumptions hold, then the purpose will be
achieved
– If the purpose is achieved and the
assumptions hold, then the Goal will be
realised
Narrative Summary Verifiable Indicators Means of Important
(OVI) verification assumptions
(MOV)
1. Goal: Contribute to Decrease in eye health Testing for eye
improved eye health in the issues/ problems by a health
specified community specified percentage
3. Outputs: (a) Increased access i) Types and cost of i) Records People are
to eye health services services offered maintained willing to pay
(b) Provision of cost effective ii) Location of facilities, ii) Survey of the charges for
comprehensive and high quality timings of service community better eye
eye health services iii) Capability of staff health care
4 . Inputs/activities: (a) Provide i) Facilities and (i) Records Budget and
health care facilities consumables procured maintained manpower are
(b) Procure consumables and ii) Contents of training (ii) Training available
sessions
equipment sessions
iii) Attendance of staff
(c) Training of staff iv) Publicity generated conducted
(d) Create awareness (iii) Attendance
Project Life Cycle
Time between the start and end of the
project
Consists of various phases
Each phase includes
Work to be done
Set of inter-related activities
Deliverables
28
Hand off from one phase to another
Results upto that point are reviewed
Necessary directional inputs are given
Acts as a control gate
Different from Product Life Cycle
Product Life Cycle
Inception
Creation
Use till the end 29
Project life cycle is a subset of product
life cycle
Inception and creation of Product
Typical Project
Slow start followed by
Quick Momentum followed by
Slow finish
Figure 1-2 from Text: Page 7
31
Project Life Cycle Phases
Phase1: Project definition and initiation
Project Management Body of
Knowledge (PMBOK) Guide : Starting
the project
Defining stage
Project is conceived
32
Preliminary scope, budget, schedule,
etc., estimated
Approvals obtained
Project charter is deliverable
Handed over to project team for detailed
planning
Project Life Cycle Phases …contd…
Project Charter:
Document issued by project initiator / sponsor
Authorizes existence / creation of the
project
Authority to project manager to utilize
resources
Reference for making all major decisions
during project life cycle
Document includes a summary of all
important aspects considered while
authorizing the project
34
High level study should have been
undertaken prior to issue of charter
Includes
Justification of project
Alignment with strategy
Major objectives
Measurable criteria for success
High level description of
requirements and outcome of the
project
Overview of project risks
Constraints and assumptions based on
organizational and external factors
Major project activities completion
milestones / dates
Project cost estimate and budget
Nomination of project manager and
members of project team
Responsibilities and authority levels of
Name, designation and authority of
project team
person authorizing the project charter
Phase 2: Project planning and scheduling
PMBOK Guide : Organizing and preparing
Planning Stage
Integrated detailed plans for
Activities
Proactively managing
Scope, Schedule and budget
Procurement, quality and communications
Project team
Detailed plans are deliverable
Handed over for execution
37
Phase 3: Project Implementation
PMBOK Guide: Carrying out the project work
Executing Stage
Project manager and team ensure that
Work planned during the planning
stage is carried out
Authorized resources are used
Monitor and control to ensure
Quality, technical and performance
specifications
Completion as per milestones and budget
38
Phase 4: Project termination
PMBOK Guide : Closing the project
Delivering stage
Deliverables are checked to ensure
meeting
• Agreed specifications and
• Criteria for success
Settle procurement contracts
Hand over documentation and project to
client
Disbanding the team
39
Project Life Cycle Phases
…contd…
At each phase, a review process is
structured and carried out
Outcome of review is to
Continue or
Redirect or
Hold or
Terminate the project
40
Project Life Cycle Phases …contd…
Examples
Golden quadrilateral corridors
Defense Research Department
Organizations’ program for
defense missile systems
42
Portfolio
Collection of projects and programs
To focus on specific business
grouped together
strategy
Wider than projects and programs
Need not be related projects
May be in different sectors
Strategic diversification
Managed at the highest managerial
level
43
Project Manager
Same functions as other managers
Plan, Schedule, Motivate and Control
Manage
Temporary and non-repetitive
Fixed life project
activities
Customer expectations
Feasible and reasonable
Create
Project Team
Structure / organization
44
Work with diverse set of people
Provide to team members
Direction, Co-ordination and
Integration
Other functional managers
Support in terms of
• Knowledge / expertise
• Availability of team members
45
Outsiders
Typically do not have project
allegiance
Vendors / Suppliers
Sub contractors
Other stakeholders
Conflict Resolution
Responsible for performance
Scope
Work Breakdown structure
Schedules
Resource allocation
Budgets
Status Reports
47
Monitoring
Quality
Appropriate trade off between Time,
Cost and Performance requirement
Closure of project
Documentation
Dissolution of team
Stakeholders
Individuals or organizations
Actively involved
Impacted by the project
Many more people than initially thought of
Different stakeholders may want different
and possibly conflicting outcomes
49
PMBOK Guide : Page 24 50
PMBOK Guide 51
Organization Structure
Existing functional hierarchy
Grouping by functions
Engineering, Production
Marketing, Accounting etc.
Further sub-divisions also may be there
Each employee reports to one person
52
Segments of project delegated to
functional department
Each department will do the project work
independently
May be appropriate if one functional area
has a dominant role
High ranking manager in that area is
given responsibility to coordinate Project
Advantages
No change
Flexibility in use of staff
Expertise of the dominant functional
area can be utilized
Easy transition after closure of
project
54
Disadvantages
Lack of focus
Staff have other work
Slow
Priority may be to other work
Poor Integration
Each concerned only with their work
Not concerned about fit with work
done by other departments
Lack of ownership
55
Dedicated Project Team
At the other end of the spectrum to
functional organization
Independent of other functions
Full time project manager
Team members chosen
56
Advantages
Functional organization remains in tact
Cohesive team
High motivation
Cross functional integration
Specialists from various functions work
together
Faster completion
Members devote full time
57
Disadvantages
Can be expensive
New position of project manage
Resources assigned on a full time basis
Conflict
Between team and other units
Apple example
Inadequate expertise
Expertise may be limited to only team
members
Difficult transition after closure of project
58
Matrix organization
No unity of command
One boss too many
PMBOK Guide : Page 28
69
Organization Culture
Project friendly culture
Team work and cross-functional
cooperation are dominant
Commitment to Excellence
Functional organization or weak
matrix organization can deliver results
70
Project unfriendly culture
Individualism is encouraged
Promotions / increments based on
Low tolerance for conflict
relationships with superiors
Project manager and team have to
overcome the negative forces
Better to insulate the project team from
Create a distinct team sub-culture
the organization culture
Dedicated project team is preferred.
Alternatively a strong matrix structure
would be required
Other cultural situations