0% found this document useful (0 votes)
45 views2 pages

Automated Test Schedule

This document outlines an automated test for aircraft systems that requires connecting to SAT Datalink and entering a flight plan. Upon successful logon, the test station establishes an ADS-C contract and sends a CPDLC test message. The message confirms a successful logon and notes the system will log off in 5 minutes.

Uploaded by

Wong Benny
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views2 pages

Automated Test Schedule

This document outlines an automated test for aircraft systems that requires connecting to SAT Datalink and entering a flight plan. Upon successful logon, the test station establishes an ADS-C contract and sends a CPDLC test message. The message confirms a successful logon and notes the system will log off in 5 minutes.

Uploaded by

Wong Benny
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Automated Test

Test Action Result P/F


Apply power to aircraft systems.
This test requires connection to
3.1.1. SAT Datalink. Put aircraft outside N/A
to establish connection.

On the CDU/RTU, enter a Aircraft tail number shows as the Flight ID on


Flight ID of the aircraft tail XPDR page.
3.1.2. number.

Enter a Flight Plan in the Flight Plan is shown on the FMS Plan page.
FMS, with origin, destination
and at least 2 waypoints. When flight plan is entered, an ATC flag may show
on the PFD, and an ATC ALERT may be shown on
(Suggested: KCID, ALO, the Datalink pages. Press ATC ALERT, and WPT
3.1.3. MCW, ROC, KMSP) ALT keys and enter values in the TO+000 and
TO+001 entries.
Press EXEC.

GMT Time: __________

Pull 3rd VHF CB.


On CDU IDX page, select
3.1.4. DATALINK. If not currently on Application Menu shown on CDU
Application Menu, press Return
until Application Menu is shown.

Press TECHNICAL, then press Verify SDU shows PRESENT in the connect
3.1.5. PERIPHERALS, then next column, and OK in the STAT column.

Verify that SDU shows ABSENT in


PERIPHERALS connect column.
3.1.6. Pull SATCOM CB

Verify SDU shows PRESENT in the connect


3.1.7. Push in SATCOM CB column, and OK in the STAT column.

Select Return, then LINK Verify that SAT shows POA COMM.
STATUS and observe the
3.1.8. Link Status page. Note: If this step fails, correct the problem before
proceeding.

On the CDU, select return Message “Logged on to ARDC” is displayed.


twice to view the Application CDA shows station identifier (ARDC).
3.1.9. Menu. Select CPDLC, then
Logon/Status. Log on to Note: This is the Current Data Authority, and would
ARDC (or ARDD). be the letters assigned to that Ground station.
Upon successful logon, the “ATC MSG” message is posted.
automated test station will
establish one ADS-C contract Incoming message tone is heard in
and send one CPLDC test the cockpit.
message.
The message reads: "You have
3.1.10. logged onto the ARINC Direct FANS
Pre-Check System. The system will
log off in 5 minutes. If you need
further support, contact the (ADFANS
email address) or call (tech support
phone number)."

To very ADS-C contract,


press return until the Verify that the first line is populated,
3.1.11. Application Menu is and the NXT column is counting
shown. Press ADS-C, then down.
ADS Report.
On the CDU, select return
until the Application Menu is
3.1.12. in view. Select CPDLC, then System is logged off.
Logon/Status.
Select *LOGOFF.
Test Complete.
3.1.13. N/A