R11 T02B01 Mag MTS Ci 0015
R11 T02B01 Mag MTS Ci 0015
R11 T02B01 Mag MTS Ci 0015
Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works
DISCIPLINE: CIVIL
Contents
1. Scope of work
2. Purpose
3. Abbreviations
4. References
5. Responsibilities
6. Safety
7. Procedure
8. Attachments
HIRA
2
Design & Build MAG: Client:
Al Majal Al Arabi Company
The Red Sea Development
Company
Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works
1. Scope of work
The scope of this Method Statement is to define all the procedures and inspections to be
followed during Kerbstone and gravel spreading works at RS11-T02 DESIGN &
3. Abbreviations
PPE : Personal Protective equipment
QA/QC : Quality Assurance/Quality Control
ASTM : American Society for testing and materials
HSE : Health, Safety and Environment
MAG : Al Majal Al Arabi (Contractor)
TRSDC : The Red Sea Development Company (Client)
4. References:
TRSDC construction specification
TRSDC employer’s requirements
Approval mobilization layout plan
3
Design & Build MAG: Client:
Al Majal Al Arabi Company
The Red Sea Development
Company
Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works
5. Responsibilities
Ensures that the content of this method statement is understood and implemented at all
times.
Coordinate with the site engineer to ensure that the necessary resources to implement the
approved Method Statement have been allocated to the task.
Determine all the requirements needed in order to comply with quality and safety
standards and regulations as required.
Will ensure that the construction of the Kerbstone and gravel spreading works activities
are conducted according to the approved Method Statement and project contract
documents.
Will be responsible of the implementation of this procedure.
Will ensure that the materials being delivered and used are in accordance with the project
specifications and approved material submittal.
Will be responsible for the inspection, preparation of all documents and compiling them
for the inclusion in the final documentation packaged.
4
Design & Build MAG: Client:
Al Majal Al Arabi Company
The Red Sea Development
Company
Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works
Will ensure that all the activities related to the specified task are being followed safely
and all workers are wearing PPE.
Identify and take measure control the risks associated with the hazard
It will be ensured at all time that the Kerbstone and gravel spreading works will be
carried out under the control of competent works supervisor. Assigned supervisor will
have extensive experience in site temporary facilities works undertaken.
Pre task briefing shall be provided by the relevant supervisor or site engineer prior to start
of work activity and to be recorded.
Will explain the Method Statement for his subordinates and responsible for executing the
works in accordance with the method statement.
To ascertain that the work is being carried out as per the instructions of site engineer and
in conformance with the approved drawings & specs.
Also to instruct workers to eliminate hazards and encourage safety actions or initiatives.
6. Safety
Safety inspector and direct supervisor will ensure that PPE are worn by site personnel at
all times during this activity.
Safety inspector will ensure that all workers and workplaces are safe.
All personnel must adhere to the safety rules and regulations at the site.
5
Design & Build MAG: Client:
Al Majal Al Arabi Company
The Red Sea Development
Company
Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works
Works permit has been issued prior to commencing of installation of the water tank (site
office) works
Hazard identification and control measures has been implemented.
It will be ensured that the equipment used at site will be maintained and relevant 3rd party
certification (including operator training certification and / or licenses) will be submitted
to TRSDC for review / approval prior to commencement of work.
7. Procedures
6
Design & Build MAG: Client:
Al Majal Al Arabi Company
The Red Sea Development
Company
Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works
7.3.1 General
1) All the temporary facilities will be located according to the approved mobilization
layout.
2) Ensure an approved drawing is available for execution and properly coordinated with
various respective field of discipline
3) Ensure the manpower required for this activity is available & ready.
4) Ensure that all tools and equipment to be use in this activity will be available and are
in good conditions.
5) Ensure that the surveys have been completed in the planned areas of works.
1) A survey shall be carried out to establish the limit of boundaries for Kerbstone and
gravel spreading works and shall be duly guided by and equipped with approved
drawings.
2) Surveyor is to check and clearly mark all the required levels, alignment, set outline
where the Kerb stone is to be installed according to the drawing.
3) Warning signs, safety cones, sign boards and safety barriers will be placed around the
designated areas.
4) The kerbstone is to be made accessible near the specified work area.
5) Insert a containing kerb-stone around the edges of the area to be paved, with edges
strong enough to ensure effective retention.
6) Kerb stone is to be laid on a cement-sand (1:4) mortar bed, maintain 10mm joints.
7) Kerb stone joints are to be fixed side-by-side and touching one another. Joints to be
pointed/flushed with cement-sand mortar bed.
8) Curing is to be achieved for joints and mortar bed with 2 days of spraying water.
7
Design & Build MAG: Client:
Al Majal Al Arabi Company
The Red Sea Development
Company
Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works
9) The location and levels of the crushed gravel spreading above the ground to the
dimensions and levels will be set out first.
10) Prior to start the gravel spreading original or disturbed/ uneven ground surface will be
flattening, well compacted and free from foreign debris or any material obstructions
prior to start.
11) The crushed gravel shall be windrowed uniformly upon the designated area and spread
to the required cross-section and depth.
12) Crushed gravel material shall be placed in a single layer
13) The crushed gravel material shall be watered as dust control measure.
This activity will be executed as per the approved method statement. The procedure
will be monitored and surveillance by TRSDC.
8. Attachment
HIRA
ITP and Checklist
8
RISK ASSESMENT MATRIX CONTROL SHEET SF-13b
PROJECT: DESIGN & BUILD, CONSTRUCTION OF VILLAGE HOUSING PROJECT, TRSDC, KSA
RISK ASSESSMENT
ACTIVITY: Kerb Stone/Gravel spreading work Ref: HIRA/ME/00
RISK RESIDUAL RISK
CONTROL MEASURES
SN. HAZARD HARM/HAZARD LX
LXS L M H L M H
S
MAG will Implement permit-to-work system
for activity to be carried out,
Task will be briefed by MAG supervisor and
Dust Exposure record will be maintained.
Site / work Slip, Trip Limit the working time of the workers
4
1 preparation Defective Equipment or 3x3 9M exposed to adverse environmental
L
Supervisor
Machinery condition.
High speed vehicles Site staff and workers must be competent
to execute the job.
Site traffic speed limit must be followed
Site access routes must be clearly defined.
Allocate adequate resources
(personnel and equipment) for
continuous housekeeping.
Train employees on housekeeping.
Ensure an appropriate housekeeping
level at all times.
Fire Ensure instant and regular waste
Poor Slips/Trips/Falls 3x4 12M removal from site. 4
2 Supervisor
Housekeeping Ill-health Provide proper welfare facilities such L
Environmental Pollution as toilets, rest area, hand wash, and
drinking water to the employees.
Maintain an adequate housekeeping
Adequate fire extinguishers must be
available
RISK ASSESMENT MATRIX CONTROL SHEET SF-13b
PROJECT: DESIGN & BUILD, CONSTRUCTION OF VILLAGE HOUSING PROJECT, TRSDC, KSA
be available on site
First aid kit/trained firs aider will be
available on site during works
Never allow a worker to work alone
by him in remote places unless
proper communication and
emergency
Proper transportation, use, handling
and disposal of hazardous
substances (spill/contamination) must
be observed strictly
Uncontrolled waste
Ensure Proper dust suppression
generation & improper
method and determine the frequency
handling & Disposal
of work to be done by water tankers
Environmental Leaks / spills of 2
9 3x4 12M Declare the whole site as “No L
Supervisor
Hazards (Air, hazardous liquid
Burning” zone for all types of waste
Ground, Water, dust suppression
materials
Dust, Noise) measures Air Pollution
Ill-health Ensure engineering / Administrative
controls for operatives working around
noisy areas / machines above the
workplace exposure limit for 8 hour
work.
ASSESSED BY
REV. No: 00
(NAME): SIGNATURE:
REVIEWED BY
MAG HSED REV. DATE:
(NAME):
SIGNATURE:
APPROVED BY
(NAME):
SIGNATURE:
Inspection & Test Plan I&TP APPROVED DATE DISCIPLINE
INSPECTION RESPONSIBILITY
ITEM
OUTPUT TASK / ACTIVITY Reference Checklist Employer REMARKS
NO. Contractor
Representative
1.0 DOCUMENT REVIEW
Approved
1.1 Method statement method NA R R
statement
TRSDC
1.2 Works permits NA R R
Requirements
site
1.3 Set outline for the Kerbstone mobilizagtion NA W R
layout
Approved
3.1 Pre-placement/ Site Preparation Inspection method N/A W W
statement
Approved
3.2 Set outline for the Kerbstone method N/A W W
statement
Approved
3.3 Mortor Mix 1:4 ratio method N/A W W
statement
Approved
3.4 Curing, method N/A W W
statement
4.0 PRE-COMMISSIONING
GENERAL NOTES
1. The Work Inspection Request (WIR) and the laboratory reports shall only be transmitted through PMIS - Aconex electronic platform.
The first three incidents of each Inspection or testing activity listed require 100 % participation by the Consultant. After this period, the Employer or the Consultanat may adjust the levels of the Employer participation upon
1
the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
3 Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
organization representative is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Consultant.
LEGEND
H Hold Point for QC Inspection/ Test R Review Documents and Reports
W Witness Inspection/Test
S Surveillance
Inspection Checklist Checklist APPROVED DATE DISCIPLINE
ITEM NO. Check Points Reference Pass Fail Not Applicable Re-Inspection
1.0 The set outline of the Kerbstone shall be accordance with the mobilization plan layout. TRSDC Specification
The disturbed surface shall be compacted by a hand roller compactor to max density of
2.0 TRSDC Specification
nearby soil.
3.0 kerbstone cement mortor bedding shall be 10mm Approved Method Statement
4.0 Cement Mortor Ration shall be 1:4 (cement : Sand) Approved Method Statement
5.0 Curing of the Mortor joint shall be water spray. Approved Method Statement
The crushed gravel shall be windrowed uniformly upon the designated area and spread to
6.0 Approved Method Statement
the required cross-section and depth.
7.0 Final survey should be conducted to verifiy the alignment. Approved Mobilization Layout
Remarks
PM/Conatractor Consultant
The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
The work is ready for inspection Document Reviewed Work Inspected Test Records Verified