R11 T02B01 Mag MTS Ci 0015

Download as pdf or txt
Download as pdf or txt
You are on page 1of 15

Design & Build MAG: Client:

Al Majal Al Arabi Company


The Red Sea Development
Company

Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works

DISCIPLINE: CIVIL

Contents

1. Scope of work

2. Purpose

3. Abbreviations

4. References

5. Responsibilities

6. Safety

7. Procedure

8. Attachments

HIRA

2
Design & Build MAG: Client:
Al Majal Al Arabi Company
The Red Sea Development
Company

Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works

1. Scope of work

The scope of this Method Statement is to define all the procedures and inspections to be
followed during Kerbstone and gravel spreading works at RS11-T02 DESIGN &

BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA Project, in


compliance with the project specifications and standards procedures.
2. Purpose
The purpose of this Method Statement is to describe the quality control procedure to be
followed during the Kerbstone and gravel spreading works at the mentioned project.
To ensure that the gravel spreading works above the ground, the proposed material and
workmanship to be used at the site are complying with the condition/ requirements as
stipulated in the TRSDC requirements. The works will be in accordance and conformance
to TRSDC’s surveillance, witness and approval.

3. Abbreviations
 PPE : Personal Protective equipment
 QA/QC : Quality Assurance/Quality Control
 ASTM : American Society for testing and materials
 HSE : Health, Safety and Environment
 MAG : Al Majal Al Arabi (Contractor)
 TRSDC : The Red Sea Development Company (Client)

4. References:
TRSDC construction specification
TRSDC employer’s requirements
Approval mobilization layout plan

3
Design & Build MAG: Client:
Al Majal Al Arabi Company
The Red Sea Development
Company

Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works

MAG Welfare Management Plan


TRSDC QA/QC and HSE requirements

5. Responsibilities

5.1 Project Manager

 Ensures that the content of this method statement is understood and implemented at all
times.
 Coordinate with the site engineer to ensure that the necessary resources to implement the
approved Method Statement have been allocated to the task.
 Determine all the requirements needed in order to comply with quality and safety
standards and regulations as required.

5.2 QA/QC Engineer

 Will ensure that the construction of the Kerbstone and gravel spreading works activities
are conducted according to the approved Method Statement and project contract
documents.
 Will be responsible of the implementation of this procedure.
 Will ensure that the materials being delivered and used are in accordance with the project
specifications and approved material submittal.
 Will be responsible for the inspection, preparation of all documents and compiling them
for the inclusion in the final documentation packaged.

4
Design & Build MAG: Client:
Al Majal Al Arabi Company
The Red Sea Development
Company

Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works

5.3 HSE Engineer & Officer.

 Will ensure that all the activities related to the specified task are being followed safely
and all workers are wearing PPE.
 Identify and take measure control the risks associated with the hazard

5.4 Site Supervisor

 It will be ensured at all time that the Kerbstone and gravel spreading works will be
carried out under the control of competent works supervisor. Assigned supervisor will
have extensive experience in site temporary facilities works undertaken.
 Pre task briefing shall be provided by the relevant supervisor or site engineer prior to start
of work activity and to be recorded.
 Will explain the Method Statement for his subordinates and responsible for executing the
works in accordance with the method statement.
 To ascertain that the work is being carried out as per the instructions of site engineer and
in conformance with the approved drawings & specs.
 Also to instruct workers to eliminate hazards and encourage safety actions or initiatives.

6. Safety

 Safety inspector and direct supervisor will ensure that PPE are worn by site personnel at
all times during this activity.
 Safety inspector will ensure that all workers and workplaces are safe.
 All personnel must adhere to the safety rules and regulations at the site.

5
Design & Build MAG: Client:
Al Majal Al Arabi Company
The Red Sea Development
Company

Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works

 Works permit has been issued prior to commencing of installation of the water tank (site
office) works
 Hazard identification and control measures has been implemented.
 It will be ensured that the equipment used at site will be maintained and relevant 3rd party
certification (including operator training certification and / or licenses) will be submitted
to TRSDC for review / approval prior to commencement of work.

7. Procedures

7.1 Material delivery, handling & storage

1. Material must be as per approved material submittal conforming to standard specification


and contract document.

7.2 Equipment & tools

1. Meter Tape, Pegs, Nylon Cord, Warning Tape,


2. Wheel barrow,
3. Forklift/Tele-handler
4. Spirit level
5. Hammer
6. Shovel and rake
7. Water tanker
8. Hand Compactor,

6
Design & Build MAG: Client:
Al Majal Al Arabi Company
The Red Sea Development
Company

Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works

7.3 Pre commencement:

7.3.1 General
1) All the temporary facilities will be located according to the approved mobilization
layout.
2) Ensure an approved drawing is available for execution and properly coordinated with
various respective field of discipline
3) Ensure the manpower required for this activity is available & ready.
4) Ensure that all tools and equipment to be use in this activity will be available and are
in good conditions.
5) Ensure that the surveys have been completed in the planned areas of works.

7.3.2 Sequence of works

1) A survey shall be carried out to establish the limit of boundaries for Kerbstone and
gravel spreading works and shall be duly guided by and equipped with approved
drawings.
2) Surveyor is to check and clearly mark all the required levels, alignment, set outline
where the Kerb stone is to be installed according to the drawing.
3) Warning signs, safety cones, sign boards and safety barriers will be placed around the
designated areas.
4) The kerbstone is to be made accessible near the specified work area.
5) Insert a containing kerb-stone around the edges of the area to be paved, with edges
strong enough to ensure effective retention.
6) Kerb stone is to be laid on a cement-sand (1:4) mortar bed, maintain 10mm joints.
7) Kerb stone joints are to be fixed side-by-side and touching one another. Joints to be
pointed/flushed with cement-sand mortar bed.
8) Curing is to be achieved for joints and mortar bed with 2 days of spraying water.

7
Design & Build MAG: Client:
Al Majal Al Arabi Company
The Red Sea Development
Company

Project:
RS11-T02 DESIGN & BUILD OF WORKERS ACCOMMODATION, TRSDC, KSA
Document: Doc Ref: R11-T02B01-MAG-MTS-CI-0015 Rev.00
Method Statement for construction of the Kerbstone and
gravel spreading works

9) The location and levels of the crushed gravel spreading above the ground to the
dimensions and levels will be set out first.
10) Prior to start the gravel spreading original or disturbed/ uneven ground surface will be
flattening, well compacted and free from foreign debris or any material obstructions
prior to start.
11) The crushed gravel shall be windrowed uniformly upon the designated area and spread
to the required cross-section and depth.
12) Crushed gravel material shall be placed in a single layer
13) The crushed gravel material shall be watered as dust control measure.

7.3.3 QA/QC Procedure

This activity will be executed as per the approved method statement. The procedure
will be monitored and surveillance by TRSDC.

8. Attachment
HIRA
ITP and Checklist

8
RISK ASSESMENT MATRIX CONTROL SHEET SF-13b
PROJECT: DESIGN & BUILD, CONSTRUCTION OF VILLAGE HOUSING PROJECT, TRSDC, KSA

RISK ASSESSMENT
ACTIVITY: Kerb Stone/Gravel spreading work Ref: HIRA/ME/00
RISK RESIDUAL RISK
CONTROL MEASURES
SN. HAZARD HARM/HAZARD LX
LXS L M H L M H
S
 MAG will Implement permit-to-work system
for activity to be carried out,
 Task will be briefed by MAG supervisor and
Dust Exposure record will be maintained.
Site / work Slip, Trip  Limit the working time of the workers
4
1 preparation Defective Equipment or 3x3 9M exposed to adverse environmental
L
Supervisor
Machinery condition.
High speed vehicles  Site staff and workers must be competent
to execute the job.
 Site traffic speed limit must be followed
 Site access routes must be clearly defined.
 Allocate adequate resources
(personnel and equipment) for
continuous housekeeping.
 Train employees on housekeeping.
 Ensure an appropriate housekeeping
level at all times.
Fire  Ensure instant and regular waste
Poor Slips/Trips/Falls 3x4 12M removal from site. 4
2 Supervisor
Housekeeping Ill-health  Provide proper welfare facilities such L
Environmental Pollution as toilets, rest area, hand wash, and
drinking water to the employees.
 Maintain an adequate housekeeping
 Adequate fire extinguishers must be
available
RISK ASSESMENT MATRIX CONTROL SHEET SF-13b
PROJECT: DESIGN & BUILD, CONSTRUCTION OF VILLAGE HOUSING PROJECT, TRSDC, KSA

 Ensure only lighter items are unloaded by


hand. Use manual lifting procedures.
 Use Mechanical lifting equipment to Lift where
possible.
 Do not allow anyone to carry loads above his
capacity (25 kg / person per lift) and also
Serious or long term injury allocate enough people to handle the load.
Manual Handling from incorrect manual handling  Ensure all materials are to be moved by 4 Supervisor/Site
3 techniques
3x3 9M L
hands, the size of material should not be engineer
above the size and the employee can be
easily to move.
 The bulky materials which are restricting
visibility should not be moved by hand.
 Use handling aids to lift / move the load.
 Allocate sufficient number of people for heavy
items shifting by manual.
 All Surveyors must have undergone basic
safety induction
 Areas to be surveyed must be free from all
obstruction
Slipping / Tripping
 Good housekeeping practices must be
Surveying Works Fall from height 4 Supervisor/Site
4 3x3 9M maintained all the times
Heat Stress L engineer
 The use of proper PPE must be observed
Traffic Risks
 Train all employees on heat stress and
ensure provision of proper precautions and
adequacy of drinking water supply and
welfare facilities.
 All mobile plants must be equipped with
necessary warning and alarm system
Use of Mobile Vehicular mishaps  Regular maintenance and check-up must
Plants during Injury to personnel be conducted 4 Supervisor/Site
5 4x4 16
Installation of kerb Environmental Pollution  Ensure that only trained and authorized L engineer
stones operatives are operating.
 A banks man must be assigned as
necessary
RISK ASSESMENT MATRIX CONTROL SHEET SF-13b
PROJECT: DESIGN & BUILD, CONSTRUCTION OF VILLAGE HOUSING PROJECT, TRSDC, KSA

 Plant and equipment must have valid 3rd


party certificates
 Plant and equipment must be shifted to
designated area after activity.
 All workers to be made aware of the MSDS
for cement uses and handling

 PPE to be provide eye protection / dust mask


/ hand and face protection
Eye contact / skin burns / 3x3 9M 4 Supervisor/Site
6 Cement Works  MSDS to be available at the work sites
respiratory problems L engineer
 Operatives to wash hands and face before
eating and drinking

 Work area to be restricted access

 Ensure operatives understands the


Working in High Heat Stress basic things needed when working
Temperature Delayed rescue effort in such condition 2
6 Supervisor
 Job rotation to be carried out L
3x3 9M
 Rest shelter will be available
 Availability of cold water
 Operatives must be physically fit
 Person must be experienced / Trained in
4x4 16 activity to be assigned for the job. Method 4
7 Unfit / untrained
L
Supervisor
statement/Risk Assessment must be
Operatives Personal injuries
addressed to all operatives prior to enter in
excavated area.
 Emergency contacts detail will be
posted on site.
Lack of awareness in case
 Emergency response procedure
Emergency of emergency 4
8 will be discussed by site L
Supervisor
Response Workers are not fully
3x3 9M supervisor/HSED prior to
trained/personal injuries
commence the job
 Stand by Emergency vehicle will
RISK ASSESMENT MATRIX CONTROL SHEET SF-13b
PROJECT: DESIGN & BUILD, CONSTRUCTION OF VILLAGE HOUSING PROJECT, TRSDC, KSA

be available on site
 First aid kit/trained firs aider will be
available on site during works
 Never allow a worker to work alone
by him in remote places unless
proper communication and
emergency
 Proper transportation, use, handling
and disposal of hazardous
substances (spill/contamination) must
be observed strictly
Uncontrolled waste
 Ensure Proper dust suppression
generation & improper
method and determine the frequency
handling & Disposal
of work to be done by water tankers
Environmental Leaks / spills of 2
9 3x4 12M  Declare the whole site as “No L
Supervisor
Hazards (Air, hazardous liquid
Burning” zone for all types of waste
Ground, Water, dust suppression
materials
Dust, Noise) measures Air Pollution
Ill-health  Ensure engineering / Administrative
controls for operatives working around
noisy areas / machines above the
workplace exposure limit for 8 hour
work.
ASSESSED BY
REV. No: 00
(NAME): SIGNATURE:
REVIEWED BY
MAG HSED REV. DATE:
(NAME):
SIGNATURE:
APPROVED BY
(NAME):
SIGNATURE:
Inspection & Test Plan I&TP APPROVED DATE DISCIPLINE

INSTALLATION OF THE KERBSTONE AND GRAVEL SPREADING I&TP-0015-R 0 CIVIL


Proejct Titile RS11-T02 DESIGN & BUILD OF 5,000 WORKERS ACCOMMODATION, TRSDC, KSA Program/Asset CONTRACTOR/SUBCONTRACTOR

Location 5,000 WORKERS ACCOMMODATION, TRSDC, KSA Al Majal Al Arabi Company


MTS-CI-0015

INSPECTION RESPONSIBILITY
ITEM
OUTPUT TASK / ACTIVITY Reference Checklist Employer REMARKS
NO. Contractor
Representative
1.0 DOCUMENT REVIEW
Approved
1.1 Method statement method NA R R
statement

TRSDC
1.2 Works permits NA R R
Requirements

site
1.3 Set outline for the Kerbstone mobilizagtion NA W R
layout

2.0 MATERIAL RECEIVING


Material Inspection Material
2.1 Kerbstone and Crushed gravel NA W R
Report Submittal
3.0 INSTALLATION

Approved
3.1 Pre-placement/ Site Preparation Inspection method N/A W W
statement
Approved
3.2 Set outline for the Kerbstone method N/A W W
statement
Approved
3.3 Mortor Mix 1:4 ratio method N/A W W
statement
Approved
3.4 Curing, method N/A W W
statement

4.0 PRE-COMMISSIONING

4.1 Not Applicable

GENERAL NOTES

1. The Work Inspection Request (WIR) and the laboratory reports shall only be transmitted through PMIS - Aconex electronic platform.

The first three incidents of each Inspection or testing activity listed require 100 % participation by the Consultant. After this period, the Employer or the Consultanat may adjust the levels of the Employer participation upon
1
the Contractor’s performance.

2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization

3 Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
organization representative is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
representative in attendance.

5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Consultant.

LEGEND
H Hold Point for QC Inspection/ Test R Review Documents and Reports
W Witness Inspection/Test
S Surveillance
Inspection Checklist Checklist APPROVED DATE DISCIPLINE

Installation of the Kerbstone and Gravel Spreading Works Checklist 1 CIVIL


RS11-T02 DESIGN & BUILD OF 5,000 WORKERS
PROJECT TITLE: Program/Asset CONTRACTOR/SUBCONTRACTOR
ACCOMMODATION, TRSDC, KSA
I&TP I&TP-007-R 0
Location Coastal Village Office Plot MTS-CI-015 Al Majal Al Arabi Company
Reference Documents:-

ITEM NO. Check Points Reference Pass Fail Not Applicable Re-Inspection

1.0 The set outline of the Kerbstone shall be accordance with the mobilization plan layout. TRSDC Specification

The disturbed surface shall be compacted by a hand roller compactor to max density of
2.0 TRSDC Specification
nearby soil.

3.0 kerbstone cement mortor bedding shall be 10mm Approved Method Statement

4.0 Cement Mortor Ration shall be 1:4 (cement : Sand) Approved Method Statement

5.0 Curing of the Mortor joint shall be water spray. Approved Method Statement

The crushed gravel shall be windrowed uniformly upon the designated area and spread to
6.0 Approved Method Statement
the required cross-section and depth.

7.0 Final survey should be conducted to verifiy the alignment. Approved Mobilization Layout

Remarks

PM/Conatractor Consultant

Contractor QC Supervisor Contractror QC Inspector

The work is ready for inspection Document Reviewed Work Inspected Test Records Verified

Name Signature Date Name Signature Date

PM Representative Supervision Consultant

The work is ready for inspection Document Reviewed Work Inspected Test Records Verified

Name Signature Date Name Signature Date