The PERT chart was developed in 1958 for the Polaris missile program to schedule and organize complex projects. It uses network techniques to determine the minimum time needed to complete all tasks based on probabilistic time estimates for each activity. The PERT chart is widely used for large, non-routine projects requiring sequential and parallel tasks.
The PERT chart was developed in 1958 for the Polaris missile program to schedule and organize complex projects. It uses network techniques to determine the minimum time needed to complete all tasks based on probabilistic time estimates for each activity. The PERT chart is widely used for large, non-routine projects requiring sequential and parallel tasks.
The PERT chart was developed in 1958 for the Polaris missile program to schedule and organize complex projects. It uses network techniques to determine the minimum time needed to complete all tasks based on probabilistic time estimates for each activity. The PERT chart is widely used for large, non-routine projects requiring sequential and parallel tasks.
The PERT chart was developed in 1958 for the Polaris missile program to schedule and organize complex projects. It uses network techniques to determine the minimum time needed to complete all tasks based on probabilistic time estimates for each activity. The PERT chart is widely used for large, non-routine projects requiring sequential and parallel tasks.
Download as DOCX, PDF, TXT or read online from Scribd
Download as docx, pdf, or txt
You are on page 1of 3
PROGRAM EVALUATION REVIEW TECHNIQUE (PERT) CHART
How did the PERT chart came about?
PERT (Project Evaluation and Review Technique) was devised in 1958 for the POLARIS missile program by the Program Evaluation Branch of the Special Projects office of the U.S.Navy, helped by the Lockheed Missile Systems division and the Consultant firm of Booz-Allen & Hamilton. The calculations were so arranged so that they could be carried out on the IBM Naval Ordinance Research Computer (NORC) at Dahlgren, Virginia. SRI VIDYA COLLEGE OF ENGINEERING AND TECHNOLOGY COURSE MATERIAL (LECTURE NOTES) CS6704 RMT UNIT -5 Page 2 The methods are essentially network-oriented techniques using the same principle. PERT and CPM are basically time-oriented methods in the sense that they both lead to determination of a time schedule for the project. The significant difference between two approaches is that the time estimates for the different activities in CPM were assumed to be deterministic(USED IN: Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience) while in PERT these are described probabilistically( USED IN: Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates). These techniques are referred as project scheduling techniques. PROGRAM EVALUATION REVIEW TECHNIQUE (PERT) CHART
INTRODUCTION TO CPM / PERT TECHNIQUES
PERT chart is an acronym for Program Evaluation Review Technique. A PERT chart is regarded to be project management toot (PMT) used to schedule, organize and coordinate tasks within a project. It is basically a method to analyze the tasks involved in completing a given project, especially the time needed to complete a given project. It is really reliable that a PERT chart gives more importance to task termination or completion within a project thereby making this a great evaluation tool mostly applied world wide for great project planning. When the correct time laps needed to complete each task in a project are clearly and surely displaced, the pert chart will provide for accurate timing time management taking in to consideration all the task and their time of completion and launch (that is, the early and the late starting time, The early and the late finish time for each task and the whole project as a whole). The main objectives of a PERT are then to facilitate decision making and the to reduce both time and cost required to complete a project, in other words a PERT is a method of analyzing the tasks involved in completing a given project especially the time needed to complete each task and identify the minimum time needed to complete the whole project. A PERT chart is generally intended for very large scale, onetime non-routine complex projects with a high degree of inter task dependency projects which requires a series of activities some of which must be performed sequentially or in series and others that can be performed in parallel with other activities. Since it creation in the mid-1900s, the PERT chart has found its way home in many different industries and stand as an essential program management tool nowadays. This work is then made to provide a better understanding of this PMT and further outline it application in exampere common tasks in our society PROGRAM EVALUATION REVIEW TECHNIQUE (PERT) CHART