Tech Requirements Interconnection
Tech Requirements Interconnection
TRRA
ANN SS M
M II SS SS II O
ONN SS E
ERRV
V II C
CEE SS SS T
TAAN
NDDA
ARRD
D
TABLE OF CONTENTS
1. INTENT...................................................................................................................... 5
1.1 Applicable Codes, Standards, Criteria and Regulations............................. 6
1.2 Effect of the National Environmental Policy Act.......................................... 6
1.3 Safety, Protection, and Reliability................................................................. 6
1.4 Responsibilities of the Parties ...................................................................... 6
1.5 Special Disturbance Studies ......................................................................... 7
1.6 Cost Estimates................................................................................................ 7
2. DEFINITIONS ............................................................................................................ 8
3. BACKGROUND....................................................................................................... 16
3.1 Revision History ........................................................................................... 16
4. REQUIRED INFORMATION FOR INTERCONNECTIONS ..................................... 17
4.1 Introduction................................................................................................... 17
4.2 Connection Location.................................................................................... 17
4.3 Electrical Data............................................................................................... 17
4.3.1 Electrical One-Line Diagram .................................................................... 17
4.3.2 Generator Data ........................................................................................ 17
4.3.3 Load Information Requirements............................................................... 18
5. SYSTEM PLANNING & PERFORMANCE REQUIREMENTS ................................ 20
5.1 General Configurations................................................................................ 20
5.2 Special Configurations ................................................................................ 20
5.2.1 Connection to Main Grid Transmission Lines and Substations................ 20
5.2.2 Connection to 287 kV and 345 kV Lines .................................................. 21
5.3 Generators (General Requirements)........................................................... 21
5.3.1 Generator Operation During Emergency System Conditions................... 21
5.3.2 Generator Performance During System Disturbances (Swings) .............. 21
5.3.3 Generator Low Voltage Ride Through Capability..................................... 21
5.3.4 Reactive Power Requirements ................................................................ 21
5.3.5 Asynchronous Generators ....................................................................... 22
5.3.6 Synchronous Generators ......................................................................... 26
5.3.7 Generator Performance Testing, Monitoring and Validation .................... 28
5.3.8 Blackstart Capability ................................................................................ 29
5.4 System Stability and Reliability................................................................... 30
Submitted Concurred Approved
1. INTENT
The Bonneville Power Administration, Transmission Services (TS) prepared this
Technical Requirements For Interconnection To The BPA Transmission Grid document
to identify technical requirements for connecting transmission lines, loads and
generation resources into the BPA Grid. Also included are the Balancing Authority Area
(BAA) requirements for generation connected to a utility system located within BPA’s
BAA. The purpose of these requirements is to assure the safe operation, integrity and
reliability of the BPA Grid.
This document is not intended as a design specification or an instruction manual. The
information presented is expected to change periodically based on industry events and
evolving standards. Technical requirements stated herein are consistent with BPA’s
current internal practices for system additions and modifications. These requirements
are generally consistent with principles and practices of the North American Electric
Reliability Corporation (NERC), Western Electric Coordinating Council (WECC),
Northwest Power Pool (NWPP), Institute of Electrical and Electronics Engineers (IEEE)
and American National Standards Institute (ANSI). Standards of the above listed
organizations are also subject to change. The most recent version of such standards
shall apply to each interconnection request.
Contractual matters, such as costs, ownership, scheduling, and billing are not the focus
of this document. Official requests for Interconnections or Transmission Service are not
addressed by this document. BPA’s Open Access Transmission Tariff governs the
commercial aspects of interconnections and transmission service. Please refer to the
BPA web site, www.bpa.gov, or contact a TS Account Executive for more information on
the interconnection process, business practices, contractual matters or transmission
services. Refer to the Large Generator, Small Generator and Line/Load procedures
and business practices for additional information.
http://www.transmission.bpa.gov/business/generation_interconnection/
Requests to interconnect generating resources or loads (Projects) are typically
submitted by the project developer but may be made in conjunction with what
Transmission Services refers to as a “Host Utility”, a utility located within BPA’s
Balancing Authority Area. BPA refers to the entity that submits the interconnection
request as the Requester. BPA evaluates and studies each Project individually, as it
was described in the request and determines impacts to BPA transmission facilities and,
if applicable, impacts to neighboring affected systems.
This document also addresses interconnection through another utility that may not
result in a direct interconnection to the BPA Grid. Through telemetering and
communications interconnections, BPA may incorporate loads, generators or
transmission lines into the BPA Balancing Authority Area. This type of interconnection,
which uses dynamic signals and telemetering, may transfer ancillary services from one
party to another.
Interconnection evaluations and studies usually result in a proposed plan of service for
physical and communications interconnections. Physical laws that govern the behavior
STD-N-000001-00-03 11/6/13 Page 5 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
protection, and safe operation and maintenance of their own facilities unless otherwise
identified in the construction, operation and/or maintenance agreements.
1.5 Special Disturbance Studies
BPA uses series and shunt capacitors, shunt reactive devices, high-speed reclosing,
single-pole switching and high-speed reactive switching at various locations. These
devices and operating modes, as well as other disturbances and imbalances, may
cause stress on interconnected facilities. This may include the possibility of electro-
mechanical resonance between a generator and the power system, or large angle
changes when considering high-speed reclosing. BPA conducts studies of
interconnection impacts to BPA facilities at the Requester’s expense. The Requester is
solely responsible for any additional studies necessary to evaluate possible stresses on
their equipment and for any corrective actions.
1.6 Cost Estimates
BPA develops application-specific cost estimates as part of the interconnection studies
since each interconnection is different and causes different impacts to BPA facilities.
Cost estimates progress with study development, from typical estimates used in the
feasibility and system impact stages, to budget quality cost estimates used for business
case and work order approval.
2. DEFINITIONS
For industry standard definitions of electric industry terminology, please refer to:
The Authoritative Dictionary of IEEE Standards Terms, IEEE 100.
For Bonneville Power definitions of electric utility terminology, please refer to:
BPA Definitions, available through BPA’s Document Request Line (800) 622-4520 or
www.bpa.gov/corporate/kcc/defn/starttx.shtml
For the purposes of this document the following definitions apply:
Active Power: The ‘real’ component of complex power carried by an alternating-
current circuit, produced by mutually-in-phase components of voltage and current
waveforms. Active power can be calculated as the product of apparent power and the
power factor. Measured in units of watts (W), kW or MW, active power is associated
with useful work, including mechanical work and heat. Active power used or transmitted
over time is energy, measured in kilowatt-hours (kWh) or megawatt-hours (MWh.). Also
known as ‘real power’. See also ‘power factor’.
Ancillary Services: The term used by FERC to describe the special services that must
be exchanged among generation resources, load customers and transmission providers
to operate the system in a reliable fashion and allow separation of generation,
transmission and distribution functions. These include: 1) scheduling, system control
and dispatching, 2) reactive power supply and voltage control from generators, 3)
regulation and frequency response, 4) energy imbalance, 5) spinning reserves, and 6)
supplemental reserves. Most of these services are included in a similar set by NERC
and termed Interconnected Operations Services, which also include load following and
black start capability.
WECC Definition: Interconnected Operations Services identified by the U.S. Federal
Energy Regulatory Commission (Order No. 888 issued April 24, 1996) as necessary to
affect a transfer of electricity between purchasing and selling entities and which a
transmission provider must include in an open access transmission tariff.
Area Control Error (ACE): Area Control Error (ACE) is the instantaneous difference
between net actual and scheduled interchange, taking into account the effects of
frequency bias including a correction for meter error.
Automatic Generation Control (AGC) System: A system that measures
instantaneous loads at interchange points (boundaries with adjacent control area) and
adjusts generation to follow load. It consists of continuous, real time load signals (kW),
telemetered to AGC computers at a transmission control center.
NERC Definition: Equipment which automatically adjusts a control area’s generation
from a central location to maintain its interchange Schedule Plus frequency bias.
Balancing Authority Area: A term adopted by FERC, NERC and WECC to replace
“Control Area”.
The electrical (not necessarily geographical) area within which a controlling utility has
the responsibility to adjust its generation to match internal load and power flow across
interchange boundaries to other control areas.
A resource or portion of a resource that is scheduled by a specific utility. If the utility
schedules the resource, the resource becomes part of its control area. Physical
location of the connection point does not determine its control area.
WECC Definition: An area comprised of an electric system or systems, bounded by
interconnection metering and telemetry, capable of controlling generation to maintain its
interchange schedule with other control areas, and contributing to frequency regulation
of the interconnection.
Blackstart Capability: The ability of a generating plant to start its unit(s) with no
external source of electric power. (WECC definition)
BPA Dispatcher: The BPA Dispatcher or system operator is the ultimate authority on
all operations, switching, etc. that can affect the BPA Grid. The BPA Dispatchers work
24/7 in two control centers located at Mead and Vancouver, Washington.
BPA Grid: The transmission facilities owned or controlled by Bonneville Power
Administration, Transmission Services.
Control Area: See definition for “Balancing Authority Area”.
Coordinated Voltage Control (CVC): Using AGC data links to the power plant, BPA
will request a power plant to deviate from the published time-of-day high side bus
voltage schedule to coordinate closely coupled power plants to operate at the same
power factor. By minimizing circulating var flow between power plants, all power plants
will minimize their var production requirements. The CVC program runs once every
two-minutes. It is a slow adjustment of voltage schedules and is not intended to replace
the function of the automatic voltage regulator. Closely coupled power plants are
determined by incrementing and decrementing the bus voltages 0.01 pu in a power flow
study. Plants that show significant response by a change in var production are
considered closely coupled. Examples include: Chief Joseph and Grand Coulee 230
kV and 500 kV; Centralia and Big Hanaford and Chehalis 500 kV; John Day and
Boardman and Coyote Springs and Calpine Hermiston 500 kV and McNary and US Gen
230 kV.
Directional Relay: A relay that responds to the relative phase position of a current with
respect to another current or voltage reference, with the intent of distinguishing the
direction of the fault location.
Distribution: That part of the electric grid associated with delivery of energy to
customers. Distribution-level nominal voltages are generally considered to be 34.5 kV
or lower. The set of distribution facilities owned, leased, or operated by BPA is not
extensive, and BPA policy is to sell low voltage delivery facilities to distribution utilities
whenever possible.
Disturbance: An unplanned event that produces an abnormal system condition.
(WECC definition) The most common disturbances are: (a) faults with subsequent
tripping of a transmission line or distribution feeder and (b) loss of a generator with
subsequent temporary system frequency decrease.
Dynamic Signal: A telemetered reading or value that is updated in real time, and
which is used either as a tie line flow or as a schedule in the AGC/ACE equation
(depending on the particular circumstances). Common applications of dynamic signals
include ‘scheduling’ jointly owned generation to or from another control area and to
move control area boundaries. Another application provides for an entity to request
(schedule) a change in power flow. The resulting response is telemetered to the entity
signifying the actual movement of a resource. This form of dynamic signal is applied to
supplemental control area services. The integrated value of this signal is used for
interchange accounting purposes, as appropriate.
Eccentric (Non-Conforming) Loads: Any cyclic load with the ability to change
periodically by more than 50MW at a rate of greater than 50MW per minute, regardless
of the duration of this change.
Effectively Grounded: A system that provides an X0/X1<3 & R0/X1<1 where X0 and
R0 are zero sequence reactance and resistance respectively, and X1 is positive
sequence reactance.
Fault: A short circuit on an electrical transmission or distribution system between
phases or between phases(s) and ground, characterized by high currents and low
voltages.
Feeder: A radial electrical circuit, generally operating at or below 69 kV serving one or
more customers.
FERC: Federal Energy Regulatory Commission On-line at www.ferc.gov.
Ferroresonance: A phenomenon usually characterized by overvoltages and very
irregular wave shapes and associated with the excitation of one or more saturable
inductors through capacitance in series with the inductor. (IEEE definition). A condition
of sustained waveform distortion and overvoltages created when a relatively weak
source of voltage energizes the combination of capacitance and saturable transformers.
A sufficient amount of damping, or resistance, in the circuit usually controls or
eliminates the phenomenon.
Generation Site: The geographical location of the Project generator(s) and local
generator equipment. This may be near or far from either the Point of Interconnection
or the Interconnecting Substation.
Harmonic: A sinusoidal component of a periodic wave or quantity having a frequency
that is an integer multiple of the fundamental frequency. (IEEE definition) Harmonics
can damage equipment, cause misoperation of relays, and can interfere with
communications. Thus, they are an important aspect of power quality, and must be
controlled by filtering or other methods.
Host Control Area: A control area that is operated by an authority other than BPA
which does not overlap with the BPA Control Area.
Hybrid Single Pole Switching: A variation of single-pole switching that is used on
long lines to extinguish the secondary arc of single line-to-ground faults. The faulted
phase is detected and opened first via single-pole relaying. After approximately fifty
cycles the two unfaulted phases are opened to extinguish the secondary arc. Three-
phase automatic reclosing follows.
IEEE: Institute of Electrical and Electronic Engineers.
Interchange Metering: Metering at interchange points between two controlling utilities,
consisting of AGC (continuous kW) telemetering and hourly kWh (on-the-hour hourly
load kWh). These quantities must go to both controlling utilities so they can manage
their respective control areas.
Interchange Point: Locations where power flows from one control area to another (i.e.
connection between two controlling utilities).
Inter-Control Center Communications Protocol (ICCP): Inter-Control Center
Communication Protocol (ICCP) is an international standard communications protocol
for real time data exchange. The ICCP is defined in the international standard IEC 870-
6 TASE.2.
Island, intentional: A utility practice to deliberately isolate a portion of its distribution
line to use local generation to serve load during an outage of the transmission system.
Island, unintentional: A portion of an interconnected system that becomes isolated
due to a fault clearing or RAS action, resulting in a portion of the transmission system
divided split into isolated load and generation groups.
Main Grid: BPA’s Main Grid transmission facilities include all 500 kV lines, 345 kV
lines, as well as some lower voltage lines and supporting facilities (e.g., transformers)
that carry bulk power within the Northwest. Main grid lines and equipment include the
most critical equipment to the reliability of the BPA Grid.
MV-90: The Multi-Vendor Translation System interprets a variety of metering
communication protocols used for data collection and analysis. Data is retrieved over
dial-up (voice grade) telephone lines by the MV-90 master located at the BPA Control
Center. The master automatically polls the remotes daily can be used to poll a remote
at any time. In addition to polling raw impulses from the recorders, MV-90 can
perform data validation, editing, reporting and historical database functions.
NERC: North American Electric Reliability Council is a not-for-profit corporation formed
by the electric utility industry in 1968 to promote the reliability of the electricity supply in
North America. NERC consists of 10 Regional Reliability Councils, one of which is the
Western Electricity Coordinating Council. On-line at www.nerc.com .
magnetic fields. Although reactive power does no useful work, it is inherently required
for operating any alternating-current power system or HVDC converter. By convention,
reactive power is absorbed or consumed by an inductance and generated or produced
by a capacitance. Reactive power transmitted over time is measured in var-hours
(varh). See also ‘power factor’.
Real Power: See ‘Active Power’.
Real-Time: Data reported as it happens, with reporting (update) intervals no longer
than a few seconds. Real-time applies to AGC type data, but not to kWh or RMS data,
which are accumulated and reported only when queried by a master station.
Remedial Action Scheme (RAS): A protection system that automatically initiates one
or more control actions following electrical disturbances. Also referred to as ‘Special
Protection System.’ Typical examples include tripping generators or loads and
switching of series capacitors, shunt capacitors or shunt reactors.
Requester: An electrical utility or other customer or their representative that is
requesting a new connection to the BPA Grid.
Reserve:
Operating Reserve: That reserve above firm system load capable of providing for
regulation within the hour to cover load variations and power supply reductions. It
consists of spinning reserve and non-spinning reserve.
Spinning Reserve: Unloaded generation which is synchronized and ready to serve
additional demand. It consists of Regulating Reserve and Contingency Reserve.
Regulating Reserve: An amount of operating reserve sufficient to reduce Area
Control Error to zero in ten minutes following loss of generating capacity, which
would result from the most severe single contingency. At least 50% of this operating
reserve shall be Spinning Reserve, which would automatically respond to frequency
deviation.
Nonspinning Reserve: That operating reserve not connected to the system but
capable of serving demand within ten minutes, or interruptible load that can be
removed from the system within ten minutes.
Revenue Metering: General term for metering which is calibrated to ANSI Standards
for Billing Accuracy.
Revenue Metering System (RMS): Provides hourly data daily (as compared to kWh
system that reports hourly load each hour). A meter and recording device are installed
at points where billing quality data is required. The device meters kW and Kvar (bi-
directional for Points of Interconnection) and records kWh and Kvarh data on an hourly
basis. Data is retrieved over dial-up (voice grade) telephone lines by the MV-90
system located at Dittmer Control Center. The MV-90 system automatically polls the
device every morning beginning at 0001 am. The MV-90 system can also other times
to poll a remote at.
Single Pole Switching: The practice of tripping and reclosing one phase of a three
phase transmission line without tripping the remaining phases. Tripping is initiated by
protective relays that respond selectively to the faulted phase. Circuit breakers used for
single pole switching must be capable of independent phase opening. For faults
involving more than one phase, all three phases are tripped. The purpose of single pole
switching is to improve system stability by keeping two of the three transmission line
phases energized and carrying power while the fault and secondary arc are removed
from the faulted phase. See also ‘hybrid single pole switching’.
Station Service: The electric supply for the ancillary equipment used to operate a
generating station or substation. (NERC definition) Generally, main grid substations
require two sources of station service for reliability.
Supervisory Control and Data Acquisition (SCADA): A system of remote control
and telemetering used to monitor and control the transmission system. (NERC
definition)
Tap Line: A line that connects to an existing transmission or distribution line without
breakers at the tap point, resulting in an additional terminal on the existing line. The
connection point may or may not include disconnect switches for isolation of one or all
terminals.
Telemetering: Continuous, real time data reporting, as for AGC and generation kW
(but not for kWh or RMS systems, which are not continuously reported).
NERC Definition - The process by which measurable electrical quantities from
substations and generating stations are instantaneously transmitted using
telecommunication techniques.
Transmission: That part of the electric grid associated with bulk transfer of energy, at
high nominal voltages (generally defined as 115 kV or above). BPA owns and operates
transmission facilities at voltages of 500, 345, 287, 230, 161, 138 and 115. of BPA’s
345 kV- and 287-kV transmission is on lines that are transformer-terminated at both
ends.
Transformers and Transformer Connections: Large three-phase power transformers
can be constructed using separate windings, as autotransformers or a combination of
these. Transformers can use one tank for each phase or have all three phases in a
single tank. The external winding connections can be delta (Δ) or grounded wye (YG),
creating winding combinations such as Δ - YG, YG - YG, YG - Δ – YG.
Autotransformer: Transformer construction using a single coil where the lower
voltage or ‘winding’ is created by simply tapping that coil at the desired voltage level,
creating a metallic connection between the two windings. This is the typical
construction used to transform voltages at transmission levels and uses a YG, three-
phase connection (e.g. 525:230 kV, 230:115kV).
Separate windings: Transformer construction where the higher and lower voltage
windings are individual coils, only coupled by a magnetic field. This is the typical
3. BACKGROUND
Copies of this document are available from:
BPA’s Document Request Line at (800) 622-4520 and requesting DOE/BP– 3624
Or Web: http://www.transmission.bpa.gov/business/generation_interconnection/
If you have questions or need additional information, please call:
BPA’s Public Information Center at (503) 230-7334 or (800) 622-4520
If you wish to make comments, please contact Transmission Planning or e-mail
comments to [email protected].
Revision 0 of this document superseded DOE/BP-3183 Technical Requirements for the
Connection of Transmission Lines and Loads and DOE/BP-3162 Technical
Requirements for the Interconnection of Generation Resources.
system; and to smooth shunt reactive switching steps. Continuously controllable, fast-
acting reactive power devices include synchronous generator excitation systems,
generators with electronically controlled output and electronically controlled reactive
power devices. The Primary response typical time frame is from several cycles (after
fault interruption) to a second, similar to synchronous generators with modern excitation
systems.
Secondary voltage control is slower acting to maintain a voltage schedule during normal
system operation, to aid system recovery after a disturbance, and to maximize the
availability of the generator installation’s fast acting, continuously controllable reactive
power devices for Primary voltage control. The Secondary response typical time frame
is several seconds to a minute. Secondary reactive power is often provided by
mechanically-switched shunt capacitors and reactors. Secondary voltage control is
usually implemented in a programmable logic controller as part of the generation
installation’s control system.
All large generator installations shall be designed to provide dynamic reactive power at
rated power output at the Point of Interconnection. The requirement is over the range of
0.95 leading to 0.95 lagging power factor (FERC requirement for synchronous
generation) or as determined by BPA studies.
BPA studies may allow the Large generator installation to provide the Primary reactive
power as a combination of low side bus fast-acting, continuously controllable reactive
power capability (e.g. synchronous generators, generators with electronically controlled
output or static var devices) and switched reactive equipment connected to the low side
bus or at the POI. Switched reactive power equipment shall be sized to compensate for
reactive power losses and injection between the generator installation and the POI and
to meet the total reactive power requirement at the POI as determined by BPA studies.
The compensation shall consider the effects of low voltage generator (collector) system
reactive losses, step-up transformer reactance, transmission line reactive losses,
voltage taps/turns ratios, and bus-fed auxiliary load. The compensation shall also
consider the effects of reactive power injection due to low voltage generator (collector)
systems and transmission lines at low generation levels when connected to the BPA
system.
Additional reactive capability may be required, as determined by BPA technical studies.
Large generation will be required to provide data on reactive capability. See section
12.2.2.3 for Dispatch and Data Requirements and Table 7.
5.3.5 Asynchronous Generators
Asynchronous generation includes wind, solar and other generation resources that rely
on induction generators or inverters to provide power to the transmission system.
5.3.5.1 Asynchronous Squirrel Cage Induction Generators (Type 1) or Wound
Rotor Induction Generators (Type 2)
Large asynchronous generators with only switched capacitors for PF correction shall
provide reactive power compensation via supplementary external equipment as
STD-N-000001-00-03 11/6/13 Page 22 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
specified in the BPA system planning studies. For Type 1 and 2 wind generators, the
dynamic reactive power is supplied by a separate fast-acting, continuously controllable
reactive power device (STATCOM typically) providing compensation in response to the
power plant voltage controller, while the individual generators operate in constant power
factor mode. The dynamic reactive power device is typically connected to the power
plant collector bus.
BPA Voltage
Reference
Wind Power
Raise / Lower
Plant Voltage
Controller
LDC
V
Q
W
Switched Shunt
Capacitors
SVC, DVAR
STATCOM WTG Power-factor
Correction capacitors
Figure 1..---Example of Type1, 2 wind turbine reactive power control with fast
acting, continuously controllable plant-level reactive compensation (SVC,
STATCOM, DVAR, etc). Switched shunts are used to meet the BPA reactive
requirements at the POI.
Additional switched reactive power devices required to meet the total reactive power
requirement at the POI shall be controlled by the power plant voltage controller. The
voltage controller is to switch shunt devices to optimize available dynamic reactive
reserves at the POI. The required dynamic reactive power device supports the
transmission system during disturbances and can be used to smooth shunt reactive
switching steps.
5.3.5.2 Asynchronous Double-fed Wound Rotor Induction Generators (Type 3)
and Generators with Solid-State Inverters (Type 4)
For Type 3 and 4 wind generation (may include solid state Inverter type generation such
as solar PV), the continuous dynamic response reactive power is provided by each
generator or the solid state equipment at each generator per BPA system planning
studies. The generation facility has a voltage controller that dispatches reactive power
output from each generating unit (Type 3 or 4) and controls switched shunt reactive
devices.
BPA Voltage
Reference
Wind Power
Raise / Lower
Plant Voltage
Controller
LDC
V
Q
W
equipment including voltage regulators and tap changers. This may typically require the
control system to adjust reactive compensation in less than 20 seconds and the reactive
step size such that switching action does not cause voltage change outside regulator’s
voltage band.
Perceptible flicker may also result from the change in voltage at the terminal of the
generation project for changes in generation output and / or as the power output
changes the line loading voltage. As the power plant output fluctuates, so does the
customer POI voltage, even if the voltage at plant POI is held constant.
When the need is identified by BPA studies or from operational experience, the project
will be required to provide dynamic controllable reactive compensation such as static
VAR compensators (SVC).
V2 V1
P
Additional reactive
support is needed
V3
G
V
V1
V3
V2
transmission system conditions; and shall not deviate more than 1% due to changes in
generation output caused by rapid fluctuations in the prime mover output.
5.3.6 Synchronous Generators
5.3.6.1 Voltage Control
Automatic Voltage Regulation (AVR) is required for an individual generator with
nameplate rating 20 MVA or above, and on each generator regardless of size in a group
installation where the aggregate nameplate rating is 75 MVA or above.
Power System Stabilization (PSS) is required on each individual generator with
nameplate rating 20 MVA or above.
Regardless of whether the GO/GOp registers, if the above criteria apply, BPA will
require that the generation facility is equipped and operated in a manner that supports
BPA’s compliance with mandatory reliability standards. Therefore, the requirement for
AVR and PSS will apply at the same MVA ratings listed above if the individual
generating unit or generating plant/facility is covered by the NERC Statement of
Compliance Registry Criteria.
The Interconnection Customer shall equip each generator with Automatic Voltage
Regulation (AVR). Interconnection Customer shall operate AVR in voltage control
mode at all times when the generator is synchronized to the transmission system.
The Interconnection Customer shall include a Power System Stabilizer (PSS) feature in
the generator AVR. The PSS shall be dual input integral of accelerating power type
(IEEE type PSS2A). Minimum PSS performance requirements shall be as described in
the Western Electric Coordinating Council’s “WECC PSS Design and Performance
Criteria”. Interconnection Customer shall maintain the PSS in service at all times when
the generator is synchronized to the transmission system.
All large generators shall operate on voltage control or as determined by BPA studies.
Power factor control is not allowed except as determined by BPA. The power plant
voltage controller must coordinate the mechanically switched shunts and dynamic
reactive resources to optimize the Primary (dynamic) response for support of the
transmission system during disturbances. The voltage controller shall coordinate the
mechanically switched shunts and dynamic reactive resources to provide smooth shunt
reactive switching steps. The preferred voltage control point for Primary voltage control
is the power plant generator bus (or collector bus for wind and other multi-generator
systems) with line drop compensation looking approximately two-thirds forward through
the substation step-up transformer impedance. The power plant voltage controller shall
be capable of receiving BPA voltage reference raise and lower signals. When the
voltage at the control point is above the scheduled voltage, the plant is expected to
consume reactive power (inductive operation). When the voltage at the control point is
below the scheduled voltage, the plant is expected to supply reactive power (capacitive
operation).
For applications where no dynamic devices are required, the automatic voltage control
system shall be sufficiently fast to react to the maximum change in generation
STD-N-000001-00-03 11/6/13 Page 26 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
anticipated without invoking the operation of system voltage control devices such as
shunt capacitors and tap changers. Further, the control system shall be coordinated to
minimize operation of customer load regulation equipment including voltage regulators
and tap changers. This typically requires the control system to adjust switched reactive
compensation in less than 20 seconds. For switched reactive equipment supporting
generation reactive power requirements, voltages at the POI shall not vary more than
0.5% per switching operation; and POI voltage shall not deviate more than 1% due to
changes in generation output caused by rapid fluctuations in the prime mover speed.
When the need is identified by BPA studies, the requester will be required to provide
dynamic controllable compensation such as static VAR compensators (SVC).
5.3.6.2 Excitation Equipment
Synchronous generator excitation equipment shall follow industry best practice and
applicable industry standards. The excitation equipment includes the exciter, automatic
voltage regulator, power system stabilizer and over-excitation limiter. Supplementary
controls are required to meet BPA transmission voltage schedules.
All synchronous generators shall be operated with their excitation system in the
automatic voltage control mode unless approved otherwise by the transmission system
operator. The intent and BPA requirement is that continuous automatic voltage control
not be overridden by supplementary power factor or reactive power controls that are
either part of the automatic voltage regulator or the power plant distributed control
system.
Generators shall maintain a network voltage or reactive power output as required by
BPA within the reactive capability of the units. Generator step-up and auxiliary
transformers shall have their tap settings coordinated with the electric system voltage
requirements.
Voltage regulator controls and limit functions (such as over and under excitation and
volts/hertz limiters) shall coordinate with the generator’s short duration capabilities and
protective relays.
The synchronous generator exciter is normally of the brushless rotating type or the
static thyristor type. The excitation system nominal response shall be 2.0 or higher (for
definitions see IEEE Standard 421). The excitation system nominal response defines
combined response time and ceiling voltage. In some cases, the high initial response
static type may be required to economically improve power system dynamic
performance and transfer capability.
Automatic voltage regulators (AVRs) should be of continuously acting solid-state analog
or digital design. Generator voltage regulators to the extent practical should be tuned
for fast response to step changes in terminal voltage or voltage reference. It is
preferable to run the step change in voltage tests with the generator not connected to
the system so as to eliminate the system effects on the generator voltage. Terminal
voltage overshoot should generally not exceed 10% for an open circuit step change in
voltage test. Tuning results should be included in commissioning test reports provided
to BPA.
STD-N-000001-00-03 11/6/13 Page 27 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
WECC requires that generating unit voltage regulators on generating units where rated
output exceeds certain thresholds, individually or in aggregate, be equipped with a
power system stabilizer (PSS). The PSS should be tuned in accordance with WECC
guidelines and other industry practices. The ‘integral of accelerating power’ type of PSS
is preferred. Its input can be a speed-related signal derived from terminal voltage and
current measurements used in the basic AVR. The PSS can be implemented as a
software module within the AVR. BPA recommends that the PSS be included in the
procurement specifications as an integral part of the voltage regulator and that AVR and
PSS tuning and commissioning be performed.
The voltage regulator shall include an over-excitation limiter. The over-excitation limiter
shall be of the ‘inverse-time’ type, adjusted to coordinate with the generator field circuit
time-overcurrent capability. Automatic voltage regulation shall be restored automatically
when system conditions allow field current below the continuous rating. BPA may
request connection of the voltage regulator line drop compensation circuit to regulate a
virtual location 50–80% through the step-up transformer reactance.
The supplementary automatic control is required to adjust the AVR set point to meet the
BPA network side voltage schedule. This supplementary control should operate in a
10–30 second time frame, and may also balance reactive power output of the power
plant generators.
5.3.6.3 Governors
To comply with the upcoming NERC BAL-003-1 Reliability Standards, BPA will need to
acquire frequency response from generators within its Balancing Authority. BPA,
therefore, requires that all generators have capabilities to provide frequency response,
specifically:
Prime mover control (governors) shall operate with appropriate speed/load
characteristics to regulate frequency
Prime mover control (governors) should operate freely to regulate frequency.
Governor droop should generally be set at 5% and total governor dead band
(intentional plus unintentional) should generally not exceed ±0.06%. These
characteristics should in most cases ensure a coordinated and balanced response to
grid frequency disturbances. Prime movers operated with valves or gates wide open
should control for overspeed/overfrequency.
Load controllers, when used, must have a frequency bias setting
BPA realizes that some generating facilities will operate at maximum turbine output
unless providing frequency control and spinning reserve ancillary services. BPA
interprets G6 to require governor controls to be set for ‘droop control mode’.
5.3.7 Generator Performance Testing, Monitoring and Validation
Each generator owner is responsible to provide a dynamic model of its generating plant
to BPA. The model will characterize plant responses to system disturbances (voltage
and frequency deviations at point of interconnection, oscillations) and control signals
STD-N-000001-00-03 11/6/13 Page 28 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
(power and voltage schedule). The dynamic model will be a part of the power system
model used in system studies to determine operating transfer limits and network
reinforcements. An incorrect model may result in incorrect transfer limits, which can
either put the system at risk of failure or unnecessarily restrict transmission use.
5.3.7.1 Parametric Testing
Parametric testing is a detailed test performed on a generator to determine parameters
of a synchronous machine and its controls, as defined in the WECC test guidelines.
Parametric testing shall be done for the following equipment:
Synchronous machines
Exciter and Automatic Voltage Regulator (AVR)
Turbine – governor
Power System Stabilizer (PSS)
Over-Excitation Limiter (OEL)
Typical data cannot be substituted for actual parametric test data when required by
NERC or WECC standards. Testing is required:
On a new generator during commissioning.
When the generator or turbine is retrofitted.
When the generator controls are replaced or retuned.
When a severe discrepancy is observed in performance validation.
5.3.7.2 Performance Validation
Performance validation of the generator model is done using measurements recorded
during actual disturbances and tests. Recorded generator voltage and frequency are
input into the model to verify that simulated real and reactive power responses are in
good agreement with the recorded responses. Generator owners shall submit an
Evidence of Performance Validation every five years. Performance validation shall
include:
Responses to at least three frequency excursions greater than 0.1 Hz (alternatively
1% speed or 20% power reference steps);
Responses to at least three voltage changes greater than 2% (alternatively 2%
voltage reference steps).
5.3.7.3 Performance Monitoring
BPA will monitor performance of a generating plant as described in Section 6.5
5.3.8 Blackstart Capability
Blackstart is the term describing the startup of a generating plant under local power,
isolated from the power system. Blackstart capability is needed in some rare
be protected against lightning and switching surges. Typically this includes station
shielding against direct lightning strokes, surge arresters on all line terminals,
transformers, reactors, and station entrance shielding with OHGW as specified in
Section 5 on the incoming lines.
5.4.6 Temporary Overvoltages
Temporary overvoltages can last from seconds to minutes, and are not characterized as
surges. Although BPA follows NESC operating procedures such that voltage control
practices do not normally cause temporary overvoltage, temporary overvoltages may be
present during islanding, faults, loss of load, or long-line situations. All new and existing
equipment must be capable of withstanding temporary overvoltage.
5.4.7 Ancillary Services
All new connections to the BPA Grid require an interconnection agreement. The
interconnection agreement does not imply or guarantee transmission service or ancillary
services.
All loads and transmission facilities must be part of a balancing authority area. The
balancing authority area provides critical ancillary services, including load regulation,
and frequency response, operating reserves, voltage control from generating resources,
scheduling, system controls and dispatching service, as defined by FERC, or their
successors. A transmission contract is optional. The Requester must choose the
balancing authority area in which the new facilities will be located and the source or
provider of ancillary services. This election should be identified in the ancillary service
exhibit of the transmission contract.
Of particular importance is the Requester’s selection of the source for regulating and
contingency reserves, if needed. BPA will then determine the telemetering, controls,
and metering that will be required to integrate the load or facility into the chosen
balancing authority area and to provide the necessary ancillary services. If the
Requester chooses a self-provision or a third party provision of reserves, then special
certification and deployment procedures must be incorporated into the BPA automatic
generation control, (AGC) system. The provision of the required ancillary services must
meet all relevant NERC, WECC and NWPP reliability policies and criteria.
The generator is required to operate in automatic voltage control mode, regulating the
voltage to a BPA provided schedule. Typically the generator should supply reactive
power for its station service loads and reactive power losses up to the POI. Generator
projects may be requested to supply reactive power as an ancillary service.
Normally, the generator will operate its governor to respond independently for frequency
deviations. If the governor is controlled through the plant central controller, the
governor shall be in ‘droop control’ mode. Droop setting and performance shall comply
with NERC and WECC reliability standards.
Manual, the BPA Work Standards, and done at the direction of BPA Dispatchers. BPA
personnel may lock the isolating device in the open position and install safety grounds:
For the protection of maintenance personnel when working on de-energized circuits.
If the connected facilities or BPA equipment presents a hazardous condition.
If the connected facilities jeopardize the operation of the BPA Grid.
6.4 Configuration for Sectionalizing and Maintenance
The configuration of interconnected facilities shall provide sufficient flexibility to allow
taking each transmission line or line section, and each circuit breaker and other key
equipment out of service, for both operation and maintenance purposes.
6.5 Synchro-phasers (Phasor Measuring Units)
BPA monitors the response to system events by generation projects connected to the
BPA grid by measuring bus voltage and frequency, and generation current and power.
Performance monitoring is required to fully validate performance and verify the model
provided under Section 5.3.8. BPA will collect disturbance data and will perform
performance validation. If BPA observes a severe discrepancy between Requester-
provided data and monitored results, the generation project owner shall be required to
perform parametric testing of the generation equipment.
BPA uses a Phasor Measuring Unit (PMU) to monitor generator performance. A PMU
provides digital high-speed time-synchronized voltage and current phasors and
frequency measurements. BPA requires PMU functionality at all generation projects
that are directly connected to the BPA grid at voltages 230-kV and above, and at some
lower voltage interconnections when identified during the interconnection studies. The
PMU will be installed at the project substation (typically a collector station if a wind
generation project) and will measure quantities at either the low side or high side of
each substation step-up transformer (e.g. 34.5/230 kV).
BPA will install the PMU and the required communication circuits/equipment at the
project substation to transport the information to the Control Center. After a system
event, BPA will download data from the PMU. Depending on the Point of
Interconnection to the BPA grid, and as identified during the interconnection studies,
BPA may also require a continuous data stream to a BPA Phasor Data Concentrator
(PDC) located at the BPA Point of Interconnection via the installed communications
network at the project substation. The PMU must be tested after configuration (but prior
to installation) for compliance with IEEE C37.118 standard and WECC filtering and
dynamic performance requirements. A typical PMU installation is shown in Figure 4
below.
BPA PDC
3-phase Voltage
230-kV
PMU
60 messages/sec 3-phase Current
IEEE C37.118
G G
7.3 Switchgear
7.3.1 General Requirements
Circuit breakers, disconnect switches, and similar equipment connected to BPA’s
transmission facilities shall be capable of carrying both normal and emergency rating
load currents, and must also withstand available fault currents without damage. This
equipment shall not become a limiting factor, or bottleneck, in the ability to transfer
power on the BPA Grid. During prolonged steady-state operation, all such equipment
shall be capable of carrying the maximum continuous current that the interconnected
facility can reasonably deliver.
All circuit breakers and other fault-interrupting devices shall be capable of safely
interrupting fault currents for any fault that they may be required to interrupt. Application
shall be in accordance with ANSI/IEEE C37 Standards. These requirements apply to
the equipment at the POI as well as other locations on the BPA Grid. BPA supplies the
fault-interrupting requirements.
The connection of a transmission line or load can coincidentally include other
generating resources. When this system configuration is connected to the low-voltage
side of a -YG transformer, the high-voltage side may become ungrounded when
remote end breakers open, resulting in high phase-to-ground voltages. This neutral
shift phenomenon is described in Section 7.4.3. Switchgear on the high side of a -YG
transformer that interrupt faults or load must be capable of withstanding increased
recovery voltages.
Circuit breakers shall be capable of performing other duties as required for specific
applications. These duties may include capacitive or inductive current switching, and
out-of-step switching. Circuit breakers shall perform all required duties without creating
transient overvoltages that could damage BPA equipment.
Generally, circuit breakers for transmission lines are required to provide automatic high-
speed reclosing, with reclose times ranging from 1/3 of a second to two seconds (20 to
120 cycles). Circuit breakers for 500 kV lines will also typically be required to perform
single-pole switching. 500 kV breakers without resistors on transmission lines will use
staggered three-pole closing, in which each phase is closed about one cycle (16 ms)
apart.
7.3.2 Circuit Breaker Operating Times
Table 1 specifies the interrupting times typically required of circuit breakers on the BPA
Grid. These times will generally apply to equipment at or near the POI. System stability
considerations may require faster opening times than those listed. Breaker close times
are typically three to eight cycles. Circuit breaker interrupting time may vary from those
in Table 1 but must coordinate with other circuit breakers and protective devices.
Below 100 kV ≤8
100 kV to 138 kV ≤5
161 kV to 230 kV ≤3
287 kV to 345 kV ≤2
500 kV ≤2
In general, bulk transfers delivering generation to load centers occur across the 500 kV
main grid transmission system. A radial 500/230 kV transformer (Hub) connection to
the 500 kV system reduces the cumulative effects of large number of individual
generation projects connecting to the 230 kV system in the area and the associated
reliability mitigation issues. This plan of service injects the generation directly into the
500 kV main grid system, avoiding 230 kV system expansion and reinforcements
needed to deliver the generation to the main grid. Potential overloads are limited and
easier to manage across the 500 kV system. Transmission Planning will decide which
plan of service is warranted based on system conditions in the area of the requested
generation interconnections and the number of requests anticipated in the area.
7.4.3 Neutral Shifts
When generation is connected to the low-voltage, grounded wye side of a delta-
grounded wye (Δ – YG) transformer, opening the high voltage connection due to fault
clearing may cause overvoltage on the high voltage terminal. These high voltages can
affect personnel safety and damage equipment. This type of overvoltage is commonly
described as a neutral shift and can increase the voltage on the unfaulted phases to as
high as 1.73 per unit. At this voltage, the equipment insulation withstand duration can
be very short. Several alternative remedies to avoid neutral shift and its potential
problems are possible.
7.4.3.1 Effectively Grounded System
Utilize appropriate transformer connections on the high-voltage side to make the system
‘effectively grounded’. Effectively grounded is defined as a system X0/X1 ≤ 3.0 and
R0/X1 ≤ 1.0. Any of these methods can result in an effectively grounded system that
will minimize the risk of damage to surge arresters and other connected equipment.
Methods available to obtain an effective ground on the high voltage side of a
transformer include the following:
A transformer with the transmission voltage (BPA) side connected in a YG
configuration and low voltage side in a closed .
A three winding transformer with a closed Δ tertiary winding and both the primary
and secondary sides connected YG.
Installation of a grounding transformer on the high voltage side.
7.4.3.2 Increase Insulation Levels
Size the insulation of equipment connected to the transmission line high-voltage side to
be able to withstand the expected amplitude and duration of the neutral shift. This may
include equipment at other locations.
7.4.3.3 High Speed Separation
Rapidly separate the back-feed source from the step-up transformer by tripping a
breaker, using either remote relay detection with pilot scheme (transfer trip) or local
relay detection of the overvoltage condition.
The Requester must provide metering for station service and alternate station service,
as specified by the metering section of this document or negotiate other acceptable
arrangements.
If the Requester intends to schedule station service energy to the Project, the
Requester is responsible to make arrangements for TSIN registration, appropriate
Source/Sink identification, commercial transmission service and scheduling. The
Requester should contact the BPA Transmission Services Account Executive at least
six months prior to the desired energization date.
transmission line, the tap line shall be shielded in accordance with the requirements
above; except for short taps (whose total lengths are less than the shielding lengths
listed above). In this case, the tap line shall be shielded for its entire length.
8.4 Surge Protection
All lines connecting to a BPA substation shall include substation entrance surge
protection, typically in the form of Station class MOV surge arresters. BPA will
determine the appropriate level of surge protection as described in section 5.4.5.
Line sectionalizing switching stations or switching terminals utilizing power circuit
breakers, circuit switchers or similar electronically controlled switching device shall
include surge protection on both line sides.
8.5 Underbuild
BPA transmission lines are not designed to accommodate underbuilds. Site specific
analysis must be completed to determine if BPA will allow an underbuild. If permitted,
the permitting shall be documented with requirements set forth by a pole contact
agreement.
BPA will work with the Requester to achieve an installation that meets the Requester’s
and BPA’s requirements.
BPA cannot assume any responsibility for protection of Requester’s equipment.
Requesters are solely responsible for protecting their equipment in such a manner that
faults, imbalances, or other disturbances do not cause damage to their facilities or result
in problems with other customers.
9.1.2 Protection Criteria
The protection system must be designed to reliably detect faults or abnormal system
conditions and provide an appropriate means and location to isolate the equipment or
system automatically. The protection system must be able to detect power system
faults within the protection zone. The protection system should also detect abnormal
operating conditions such as islanding, equipment failures or open phase conditions.
Special relaying practices may also be required for system disturbances, such as
undervoltage or underfrequency detection for load shedding or reactive device
switching. For most generation and some loads, the Requester will also be required to
participate in special protection schemes or RAS including automatic tripping or
damping.
9.1.2.1 General Protection Practices
The following summarizes the general protection practices as required by NERC and
WECC, as well as specific practices and applications as applied to BPA transmission
lines and interconnections. The protection schemes and equipment necessary to
integrate the new connection must be consistent with these practices. Table 2 specifies
maximum allowable operating times for protection systems and breakers by voltage
category.
9.1.2.1.1 Selection and Review Considerations
The POI protection system security and dependability and the related effects on the
power system must be carefully weighed when designing the protection system. BPA
reserves the right to review and require changes to the POI protection system and
settings.
9.1.2.1.2 Regulatory Requirements
Protective relays and their settings are required to follow various regulatory
requirements such as NERC and WECC Standards. These requirements are subject to
change. Although BPA attempts to provide guidance to customers regarding these
requirements, BPA is not responsible for the failure of a customer’s protective relay
systems to meet these requirements.
9.1.2.1.3 Reliability and Redundancy
Protective relay systems must be designed for reliability and redundancy. The
protection system must be capable of meeting the operating times for the appropriate
voltage class specified in Table 2, and redundancy is required so that the failure of any
single protection system component will not prevent the system from meeting the
STD-N-000001-00-03 11/6/13 Page 48 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
may require the application of special protective devices or schemes. The following
discussion identifies the conditions under which relay schemes must operate.
9.1.2.2.1 Phase Fault Detection
The relay system must be able to detect multi-phase faults and trip at high speed for
high fault currents. Non-directional overcurrent, directional overcurrent, distance, and
line differential relays may be applicable depending on system requirements.
Infeed detection to faults within the power system usually requires directional current-
sensing relays to remove the contribution to the fault from the POI. The distance relay
(IEEE device 21) is a good choice for this application since it is generally immune to
changes in the source impedance.
9.1.2.2.2 Ground Fault Detection
Ground fault detection has varying requirements. The availability of sufficient zero-
sequence current sources and the ground fault resistance both significantly affect the
relay’s ability to properly detect ground faults. The same types of relays used for phase
fault detection are suitable for ground fault detection. If ground fault distance relays are
used, backup ground time-overcurrent relays should also be applied to provide
protection for the inevitable high-resistance ground fault.
9.1.2.2.3 Breaker Failure Protection
Breaker Failure Protection is required on all breakers at transmission voltage, which
BPA defines as 69 kV and above. For three-cycle or faster breakers, the breaker failure
relay is generally set to trip if the fault has not been cleared within 8 cycles after the
relay trip command. Breaker failure relays are not required to be redundant.
9.1.2.2.4 Islanding
Intentional islanding is a utility practice to deliberately choose to isolate its distribution
system and use local generation to feed loads during transmission system outages.
Unintentional islanding describes a condition in which the power system splits into
isolated load and generation groups, usually when breakers operate for fault clearing or
system stability remedial action. Delayed fault clearing, overvoltages, ferroresonance,
extended undervoltage and off-nominal frequency operation, and degraded service
quality for other customers can result from a local unintentional islanded condition.
BPA does not allow unintentional islanding conditions to persist that include its facilities,
except for a controlled, temporary, area-wide grid separation. Where generation is
connected to the BPA transmission system, implications of unintentional islanding must
be addressed to minimize adverse impacts on connected loads.
Generation facilities equipped with over and under frequency (81O/U) and over and
under voltage (59/27) protective relays may also use those relays to partially meet
BPA’s requirements to detect and trip on unintentional islanding conditions. Settings for
these relays shall be in accordance with WECC underfrequency load shedding
requirements. BPA reserves the right to require more extensive unintentional islanding
protection.
9.1.2.2.5 Relay Performance and Transfer Trip Requirements
Relay systems are designed to isolate the transmission line and/or other facilities from
the BPA Grid. However, the performance (clearing time) of local relay systems and the
associated isolating devices (circuit breakers, etc) will vary. The protection equipment
of the new connection must, at least maintain the performance level of the existing
protection equipment at that location.
In general, protective relay schemes at 230kV and above require the relays to be
capable of providing an instantaneous trip for faults anywhere on the protected line.
This will require some type of pilot communications to insure secure, high-speed fault
clearing. Lower voltages may also require pilot communications to insure secure, high-
speed fault clearing. BPA normally uses direct under-reaching and permissive
overreaching transfer trip for its pilot schemes, but other types of pilot tripping such as
directional comparison, phase comparison or current differential may also be acceptable
if the chosen scheme can achieve the total clearing times required and is compatible
with the selected method of pilot communication.
There are several other situations that will require a transfer tripping scheme to facilitate
the operation of a remote breaker. Some of these situations are given below.
Transient or steady-state studies identify conditions where maintaining system
stability requires immediate high-speed separation of the POI facility from the power
system.
Special operational control considerations require immediate separation of the POI
from the BPA Grid.
Extended fault duration represents an additional safety hazard to personnel and can
cause significant damage to power system equipment.
Slow clearing or other undesirable conditions such as extended overvoltages or
ferroresonance which, cannot be resolved by local conventional protection
measures, will require the addition of pilot tripping using remote relay detection at
other substation sites. This scenario is a distinct possibility should a BPA circuit that
connects other customer loads become part of an unintentional island that includes
a generator.
When remote circuit breaker tripping is required, in order to clear faults in a
transformer not terminated by a high side breaker, high-speed transfer tripping will
be required. The transfer trip may also be required to block automatic reclosing.
Other unique configurations may impose the same requirement.
Relay operate times are adjusted to coordinate for faults on the local configuration
such as a three terminal lines, fault currents available, etc. Total clearing times must
be less than those listed in Table 2. Refer to Section 10 for telecommunication
issues as they pertain to control and protection requirements.
STD-N-000001-00-03 11/6/13 Page 51 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
proposed relay system. If there are special performance requirements for the protective
relays at the POI, BPA will notify the Requester.
9.1.3.2 Protection System Coordination and Programming
The following are basic considerations that must be used in determining the settings of
the protection systems. Depending upon the complexity and criticality of the system at
the POI, complete model line testing of the protection system, including the settings and
programming, may have to be performed prior to installation to verify the protection
system performance.
Fault study models used for determining protection settings should take into account
significant zero-sequence impedances. Up-to-date fault study system models shall
be used.
Protection system applications and settings should not normally limit transmission
use.
Application of zone 3 relays or other relays with settings overly sensitive to overload
or depressed voltage conditions should be avoided where possible. These relays
must meet NERC and WECC standards for relay loadability.
Protection systems should prevent tripping for stable swings on the interconnected
transmission system. During a system disturbance, power swings may result which
can affect operation of protective relays, especially distance relays. Out-of-step
blocking is commonly applied to distance relays to prevent inadvertent operation
during a power swing. However, the application of such schemes must be
coordinated with BPA to assure that blocking the distance elements will not result in
the inappropriate or undesirable formation of islands.
Protection system applications and settings should be reviewed whenever significant
changes in generating sources, transmission facilities, or operating conditions are
anticipated.
All protection system trip misoperations shall be analyzed for cause, and corrective
action taken.
9.1.3.3 Relays for the Point of Interconnection
The following list of relays has been developed in recognition of varied interconnection
requirements. Relay performance under certain fault scenarios is also a consideration
in the selection of these relays. The specific relays used must be functionally consistent
with and complementary to BPA’s general protection practices identified in Section
9.1.2.
The relay functions generally necessary to serve this purpose as used by BPA include:
Except as otherwise agreed by BPA, BPA will furnish, install, operate and maintain all
relaying at the POI for the purposes of protecting the BPA Grid. Other relaying for
protection of the Requester’s equipment will be the responsibility of the Requester. All
relays, which can adversely affect the BPA Grid, shall be ‘utility grade’ quality, subject to
review by BPA.
Refer to Section 10 for telecommunication issues as they pertain to control and
protection requirements.
9.1.4 Generator Protection - Special Requirements
Integration of new generation has special requirements in addition to the previously
described protection requirements. This section primarily deals with the protection
requirements for the integration of synchronous and asynchronous rotating machines.
Wind turbine installations require special considerations. The actual protection
requirements and choice of relay type will vary depending upon several factors:
MVA capacity of the generation
Generation Type: synchronous or asynchronous
Location of the generation interconnection on the transmission grid
Voltage level of the generation interconnection
Transformer winding configuration for the generator step-up transformer and/or
interconnecting transformer
Change in the fault current capacity as a result of the added generation
Availability of telecommunications facilities
STD-N-000001-00-03 11/6/13 Page 54 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
Examples of some typical generator integration plans are shown in Table 3 and Figures
5 through 9. Table 3 identifies only the protection equipment, which may affect the
operation of the BPA Grid. The type of resource proposed and location of the POI will
determine any special protection requirements for other types of resources, such as
photovoltaic, wave, etc.
9.1.4.1 Fault Protection
Protective relays are required to detect phase and ground faults on the generator
interconnection. The relay systems shown in Figures 5 through 9 are designed to
isolate the generator from the BPA grid at or near the POI. However, the performance
(clearing time speed) of these local relay systems and the associated isolating devices
(circuit breakers, circuit switches etc.) will vary. In most cases, protective devices
described in Section 9.1.3 will also be appropriate for this interconnection.
Ground fault detection has varying requirements. The most significant consideration in
the ability to detect ground faults on the BPA Grid is the winding configuration of the
transformer connecting the generator to the grid. The scenarios below assume that the
generator is connected to the low-voltage side of this transformer.
9.1.4.1.1 Transformer Grounded Wye (YG) Connection on the BPA Grid
Side
This is the BPA required transformer connection when adding a new generation
resource to the transmission grid. The transformers will either be YG- or YG--YG.
Either of these connections provides a solid ground source for the transmission grid.
For a transformer connected with a grounded-wye on the primary (high-voltage) side, a
ground overcurrent relay (50/51-G) connected in the neutral of the wye winding provides
transmission fault detection. This relay also protects the transformer.
A directional ground overcurrent relay (67-N) is generally provided for detection of
ground faults in the transmission system when transformer connections are of the types
identified above. Since this relay function complements zone-distance protection used
for phase fault detections, it is included in many presently manufactured relays. See
Figures 5, 6 and 9 for typical examples of this configuration.
9.1.4.1.2 Transformer Delta () Connection on the BPA Grid Side and
Potential Overvoltages
Some smaller generation projects are proposed for integration into existing utility power
systems through a delta transformer connection to the transmission grid. This -YG
transformer was originally designed only to serve loads; e.g., connection at the 12.5 kV
side of the 115 kV/12.5 kV transformer. This common transformer configuration
requires special relay considerations when generation is proposed for connection to the
low voltage terminal. The existing protection at these installations was applied under
the assumption that there was not a source from the low-voltage side to infeed to faults
in the power system. BPA will review all such requests on a case-by-case basis to
determine acceptability. New relays, transfer trip, ground detection equipment, or a
STD-N-000001-00-03 11/6/13 Page 55 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
The following relays are intended for the interconnecting substation to detect faults on
the BPA Grid and isolate the interconnecting substation from the BPA Grid.
Table 3 Continued…
The following devices are typically used at the interconnecting substation to provide
protection of the power transformer that interfaces between the generator and the BPA
Grid.
Generator Interconnection
The following relays are required at or near the generation. These relays do not provide
fault protection for the generator itself, which is the responsibility of the generator owner.
Table 3 Continued…
L R
~
~
~
~
(3V0) 79
X
67 21- 21-
N 2 1
62 C
79 79 (3V0)
X X
Interconnecting 21- 21- 67
Substation 1 2 N
A B 62
Line to R
21-1, 21-2/62, 67N B, C
Line to Generator
87 A, B, D 50/
51G
21 and 67N Relays with POTT may
also be used.
Other Loads
Remote Station Remote Station
"L" "R"
L R
79 HB/DL Automatic 79
X reclose supervision X
A (3V0)
Distance and directional
ground relays "look" into
Interconnecting 21- 21- 67 transmission system -
Substation 1 2 N additional zones may be
used.
62
50/
51G
Feeder Protection
50/51, 50/51N B
Generator
25
50/51, 50/51N D or E E
27/59 D or E
81 D or E
Loads G
L R
79 HB/DL Automatic 79
X reclose supervision X
(3V0)
59
Z
Fuse
Interconnecting
Substation
Distance and directional
ground relays "look" into
21- 21-
1 2
59 transmission system -
additional zones may be
used.
62
Pilot trip requirements contingent upon To existing 51V Relays may be appropriate for
specific project details. customer loads Generator at D.
Relay Trips
D
Generator
Line Protection 50/ 50/ Project
21-1, 21-2/62 B 51 51N
O.C's
59Z, 59 B
Feeder Protection
50/51, 50/51N B
25
Generator E
50/51, 50/51N D or E
27/59 D or E
81 D or E
27/
81
59
Relays used specifically for generator
protection not shown. Loads G
Other Loads
Remote Station Remote Station
"L" "R"
L R
79 HB/DL Automatic 79
X reclose supervision X
A
Distance and directional
ground relays "look" into
21- 21-
59
transmission system -
Interconnecting 1 2 additional zones may be
Substation used.
62
50/
51G
Relay Trips
~
~
appropriate for a short line between B and
D.
To existing
Line Protection customer loads 51V Relays may be appropriate for
Generator at D.
21-1, 21-2/62 B D
59Z, 59 B
Generator
Transformer Protection 50/ 50/ Project
50/51 A, B 51 51N
O.C's
50/51G A, B
Feeder Protection
50/51, 50/51N B
25
Generator Protection E
50/51, 50/51N D or E
27/59 D or E
81 D or E
27/
81
59
Relays used specifically for generator
protection not shown. Loads G
L R
79 HB/DL Automatic 79
X reclose supervision X
C D E F
Station
Service
G
G
G Additional Strings or
Power Factor Collectors
Correction Capacitors G
G
Wind String, Collector #1
generator operator permission before a generator is synchronized to the BPA Grid. All
circuit breaker closing operations must automatically synchronize the generator to the
transmission system.
If the generator connects to an existing line, automatic reclosing schemes at the remote
terminals require modification to accommodate the generator interconnection. A hot
bus/dead line check is usually applied at one terminal before attempting an automatic
reclose. Hot bus/hot line with synchronism check supervision is necessary for
automatic reclosing at the other terminal.
9.1.4.3 Required Relay Settings for Generators Connected to the Transmission
Grid
Voltage and frequency relays used for protecting a generator and preventing an
unintentional island condition from persisting must meet the requirements listed below
to allow proper coordination with the power system. These relays are usually installed
at the generation site or at the interconnecting substation. See Section 9.1.2.2.4.
The ranges, settings, and delays below for both voltage and frequency relays are
understood by BPA to be well within the capabilities of small and large modern steam
turbines as well as other generators. BPA will evaluate proposed alternative
voltage/frequency settings based upon the impact on system performance and
reliability. The settings must comply with existing WECC and NERC requirements.
9.1.4.3.1 Voltage Relays (27, 59)
The over/under voltage relay setting/delays listed below are intended to insure that
generators trip when the connections to the power system have been interrupted,
preventing extended unintentional islanding. However, minimum time delays before
tripping are required to allow generators to ride through temporary low or high voltages
that result from system faults or other transient events. The table below shows these
minimum time delays and follow the voltage ride-through requirements of NERC PRC-
024.
In areas where under-voltage load shedding plans are in use it is critical that generators
do not trip prior to the completion of all automatic undervoltage load shedding. BPA
may require additional time delays to those shown below on generation applied in an
area which is part of an under-voltage load shedding plan.
Overvoltage (59)
Voltage Action
≥1.200 pu Instantaneous tripping allowed
≥1.175 pu 0.20 second minimum delay before unit tripping
≥1.150 pu 0.50 second minimum delay before unit tripping
≥1.100 pu 1.00 second minimum delay before unit tripping
<1.100 pu no over-voltage tripping allowed
Undervoltage (27)
Voltage Action
<0.45 pu 0.15 second minimum delay before unit tripping
<0.65 pu 0.30 second minimum delay before unit tripping
<0.75 pu 2.00 second minimum delay before unit tripping
<0.90 pu 3.00 second minimum delay before unit tripping
≥0.90 pu no under-voltage tripping allowed
9.1.4.3.2 Frequency Relays (81)
If a generator facility includes a frequency relay (81) for under and/or overfrequency
protection, the frequency settings and time delays must coordinate with the
underfrequency load shedding plan. The frequency ranges and minimum setting/delay
requirements for over/under frequency relays (81), shown in Table 4, were established
by the WECC Coordinated Off-Nominal Frequency Load Shedding and Restoration
Program and the NWPP Enhanced Underfrequency Load Shedding Program and have
now been incorporated in NERC Standard PRC-024. The objective of these settings is
to use the machine capability to support the power system and prevent unnecessary
loss of system load during disturbances, and ultimately, to help prevent system
collapse. Generating resources must not trip off before load is shed by underfrequency
relays. A generator should not be tripped by frequency relays for frequencies between
59.4 Hz and 60.6 Hz. For frequencies equal to or below 57.0 Hz or above 61.7 Hz there
are no special requirements for tripping times. Table 4 specifies the under and
overfrequency limits and minimum time delays. The intent is to coordinate generator
tripping with load shedding schemes.
Table 4.— Under and Overfrequency Relay Settings and Operate Times
60.0 > f > 59.4 60.0 < f < 60.6 No generator tripping allowed
For generators that are not susceptible to damage for the frequency ranges listed above
(e.g. typical hydro units), tripping above 61.7 Hz and at or below 57.0 Hz, with no
intermediate steps is suggested. For steam turbines and similar units, relay(s) with
multiple frequency setpoints and discrete time delays could be used to realize the
settings above.
Often, large generation resources are directly connected to a substation at the
transmission level voltage and would not be part of the unintentional islanding condition
previously described in Section 9.1.2. For these generators, the 61.7 Hz trip level may
be raised and the 57.0 Hz trip level may be lowered. However, the minimum delays
listed above for all frequency deviations from 60 Hz must be maintained. For those
generators that may become part of an unintentional island, a maximum delay of 0.1
sec at 57.0 Hz and >61.7 Hz should be used. This will help insure that the generator
trips for the unintentional island condition.
Voltage and frequency relays must have a dropout time no greater than two cycles.
Frequency relays shall be solid state or microprocessor technology; electro-mechanical
relays used for this function are unacceptable.
9.1.4.4 Generator Relays
Except as specifically identified in these technical requirements, BPA does not have
requirements for the type of protection used for a generator. Generator protection is the
responsibility of the Requester. However, the protection should meet the general
requirements of NERC and WECC Standards. The level of redundancy and overlap of
protection schemes are determined by the Requester. BPA's primary concern with
generator protection is that the protection is available to isolate a generator fault from
the BPA Grid. Types of protection used to isolate a generator from the BPA Grid
include:
Thermal (49)
*The settings of 27, 59 and 81 relays must be reviewed and approved by BPA.
9.1.5 Special Protection or Remedial Action Schemes
Connections to the BPA Grid may require special protection or Remedial Action
Schemes (RAS). BPA determines the RAS requirement during the interconnection
studies. All Wide Area Protection RAS schemes must be fully compliant with WECC
Class 1 requirements. WECC RAS criteria specifies that there be “no credible single
point of failure” that would keep the scheme from operating, which, in most cases,
requires geographically diverse communication paths. Redundancy or equivalent, as
determined by BPA, is required for all RAS. WECC compliant RAS schemes must also
be tested regularly by BPA personnel. BPA’s Wide Area Protection RAS target
functional test date is Annually, with a do not exceed date of two years. BPA’s Local
Area Protection RAS target functional test date is every 5 years with a do not exceed
date of 75 months. BPA reserves the right to alter the test frequency for all RAS as
rules change at WECC. BPA selects the timing of the RAS functional test during times
of low transmission system stress in the area protected by the RAS. The most common
special protection schemes include load shedding, line loss detection, and generator
tripping.
BPA staff will design the RAS schemes to ensure the design meets BPA and WECC
requirements.
The Requester is expected to provide sufficient rack space in their facilities to
accommodate additional equipment for relaying, telecommunications, special protection
or RAS Schemes needed to facilitate the interconnection.
9.1.5.1 Load Shedding
The proposed connection may require special load shedding schemes based upon BPA
Control Area requirements. These may include underfrequency load shedding,
undervoltage load shedding, or direct load tripping. The intent of load shedding is to
balance the load to the available generation resources, reduce the possibility of voltage
collapse, and to minimize the impact of a system disturbance. Underfrequency load
shedding generally includes a coordinated restoration plan, which is intended to
minimize frequency overshoot following a load shedding condition. Tripping levels,
restoration, and other details of load shedding schemes will be determined by BPA,
following NERC, WECC and NWPP criteria. Section 9.1.4.3 includes specific
requirements for generation tripping by voltage and frequency relays.
9.1.5.1.1 Direct Load Tripping
Direct load tripping may be required for large loads, typically in excess of 50 megawatts.
Direct load tripping is achieved with the use of redundant, dedicated transfer trip
schemes from the remedial action scheme controllers to the load. Communication
channels should be alternately routed. BPA Dispatchers will enable or disable direct
load tripping schemes depending upon system conditions.
9.1.5.1.2 Underfrequency Load Tripping
Underfrequency load tripping may be required to balance generation resources and
loads. Underfrequency load shedding must meet the following requirements:
Electromechanical frequency relays (81) are not allowed.
Frequency relays should utilize the definite time characteristic.
Total operate time for underfrequency load tripping, including circuit breaker tripping,
shall not exceed 14 cycles.
The frequency relay should be voltage supervised to prevent operation when the bus
voltage drops below 0.7 pu voltage.
The frequency element (81) may be included as a part of a multifunction protective
relay.
Frequency setting levels will be supplied by BPA.
Load restoration settings will be supplied by BPA.
9.1.5.1.3 Undervoltage Load Tripping
Undervoltage load tripping may be required to prevent possible voltage collapse on loss
of major transmission paths or generation resources. Undervoltage load shedding must
meet the following requirements:
Electromechanical voltage relays (27) are not allowed.
Voltage relays should utilize the definite time characteristic.
The voltage transformer source for the voltage relay (27) must be on the source side
of any automatic load tap changers or voltage regulators.
A three-phase voltage element must be used to detect the undervoltage condition.
Averaging of the three phase voltages is not acceptable.
The undervoltage element (27) may be included as a part of a multifunction
protective relay.
The undervoltage relay should not operate for a single-phase low voltage nor for a
three phase low voltage below 0.5 pu.
STD-N-000001-00-03 11/6/13 Page 70 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
Total operate time for undervoltage load tripping shall be greater than expected fault
clearing times, typically 30 cycles or 0.5 seconds.
Voltage setting levels and operate time delays will be supplied by BPA. Typical
settings may be in the range of 0.9 to 0.92 pu voltage with a delay of 3.5 to 8
seconds.
Restoration settings will be determined by BPA.
9.1.5.2 Generation Tripping
New generation installations are required to participate in any Remedial Action Scheme
required to assure reliability of the transmission system. BPA uses RAS generator
tripping to maintain dynamic stability, voltage stability, and prevent transmission system
overload. BPA Dispatchers arm and disarm generator tripping schemes based upon
system conditions. RAS schemes must be fully redundant. BPA RAS controllers will
send generator reduction signals to the generators via redundant transfer trip channels.
If the new connection includes generation not previously part of the BPA Control Area,
the generation may also require additional special trip schemes and RAS arming
procedures. These schemes typically require a sequential events recorder as described
in Section 9.1.6.1
It is the plant operator's responsibility to develop and maintain procedures for RAS
arming of the individual generator units, and procedures for plant restoration following a
RAS action.
9.1.5.3 Transmission Line Loss Detection Logic
To sense an outage that would trigger RAS action, transmission lines may require Line
Loss detection Logic, (LLL). Line loss is typically sensed by the position of the circuit
breaker (52/b) auxiliary switch, isolating disconnect switch status, and also from the
circuit breaker trip bus. Substation bus configuration and the type of protective line
relaying will determine the exact requirements for implementing line loss detection logic.
Line loss sensing must be implemented at all terminals of the transmission line. Line
loss detection is sent to the appropriate BPA RAS controllers via redundant
telecommunications channels.
9.1.5.4 Other Special Protection and Control Schemes
The location of the POI, the amount of load or generation expected, and various other
system conditions may require special protection schemes. The need for and type of
schemes required are determined during the interconnection studies. For example,
RAS may be required for stability purposes or out-of-step tripping may be needed for
controlled system grid separations. Generator or load tripping may be required to
prevent line or equipment overloading. Special breaker tripping or closing schemes
such as staggered closing or point-on-wave closing may be necessary to reduce
switching transients. These special protection and control schemes may require stand-
alone relay systems or additional capabilities of particular substation equipment.
must have capability for remote communications to connect to BPA's SER master
station. At lower voltage substations, multifunction digital relay event recording
capability may serve as a possible substitute for a dedicated SER.
9.1.6.2 Digital Fault Recorders (DFR)
The Digital Fault Recorder (DFR) must have sufficient analog channels to monitor
critical currents and voltages. The DFR may also include digital channels to monitor
selected equipment status in the substation. The DFR must be time synchronized via a
GPS satellite clock. A stand-alone DFR is required in 500 kV substations. For lower
voltages, it may be acceptable to use multifunction digital relays that have oscillographic
capability; if so, the relay must be synchronized to a GPS clock.
lines connected to the BPA Main Grid. This performance level is also required for RAS
circuits that must meet WECC compliance criteria. These circuits require totally
redundant schemes.
Availability is determined for the total path of the protective relaying circuit, from one
end of the transmission line to the other. Options for achieving these availability
requirements by utilizing two or more separate telecommunication methods, routes or
systems may be considered. When alternately routed telecommunications for
protective relaying schemes are required, a combination of two of these
telecommunications methods may be used to meet availability requirements.
10.7.2 Speed of Operation
Throughput operating times of the telecommunications system must not add
unnecessary delay to the clearing or operating times of protection or RAS. System
studies and WECC trip time requirements determine maximum permissible throughput
operating times of control schemes.
10.7.3 Equipment Compatibility
Protection systems and supporting telecommunications equipment installed at the
interconnecting facility must be functionally compatible or identical to the corresponding
equipment employed at the BPA facility. This functionality need not extend to
peripherals, such as signal counters and test switches that might be present on BPA’s
equipment. Teleprotection equipment employed by the Requester must be approved by
BPA prior to installation. At the time of the request for interconnection BPA will supply
the Requester with a list of acceptable, pre-qualified equipment. Should the Requester
choose to employ equipment not on this list, BPA reserves the right to test the
equipment for acceptable performance in the required control application. Equipment
that passes this testing can be approved by BPA for subsequent installations.
Teleprotection systems, including transfer trip, must be properly designed and tested to
demonstrate that they perform their intended functions. When applying digital
telecommunications systems to protection schemes, care must be taken ensure
equipment compatibility .
10.8 Telecommunications During Emergency Conditions
10.8.1 Emergency Conditions
Emergency telecommunications conditions may develop that affect telecommunications
equipment with or without directly affecting power transmission system facilities.
Examples of telecommunications emergencies include the following:
Interruption of power to telecommunications repeater and relay stations
Telecommunications equipment failure, whether minor or catastrophic
Interruption or failure of commercial, public switched telephone network facilities or
services
11. COMMISSIONING
11.1 Pre-energization Inspection and Testing
The Requester is responsible for the pre-energization and testing of their equipment.
For equipment that can impact the BPA Grid, the Requester shall develop an Inspection
and Test Plan for pre-energization and energization testing. BPA may request to review
the test plan prior to the test(s). BPA may require additional tests. The Requester shall
make available to BPA, upon request, all drawings, specifications, and test records of
the POI equipment. Also upon request BPA will make available to the Requester similar
documents describing the BPA POI equipment.
11.1.1 Installation and Commissioning Test Requirements for Metering
BPA requires meter testing prior to commissioning. Refer to Section 13.5 and the BPA
Metering Application Guide, STD-DC-000005, for additional information.
Verify interconnections between protection system and other devices are intact and
match drawings.
Verify that the drawings are correct.
11.1.2.4 Verify All Protective System Outputs
Verify that all trip outputs will trip intended trip coil(s).
Verify that all close outputs will properly close the breaker(s).
Verify proper relays key the appropriate pilot channel.
Verify other outputs such as breaker failure initiate, special protection scheme
signals, reclose initiate and reclose block, relay alarms, event recorder points, and
any other relay outputs to other equipment.
11.1.2.5 Perform Trip or Other Operational Tests
Assure correct operation of the overall protection systems.
Test automatic reclosing.
11.1.2.6 Pilot Schemes
Measure channel delays.
Check for noise immunity.
Check for proper settings, programming, etc.
Check transmit and receive levels.
If automatic channel switching or routing is utilized, check for proper relay operation
for alternate routing.
11.1.2.7 In Service, Load and Directional Tests
Measure AC current and/or voltage magnitudes applied to the relay system.
Measure AC current and/or voltage phase angles applied to the relay system.
Test the relay system for proper directional operation when applicable.
11.1.2.8 Special Protection Scheme/Remedial Action Scheme Testing
The RAS must be thoroughly tested prior to energization. This includes an end-to-
end test, functional test, or operational tests.
If the RAS is a part of a WECC compliant RAS, an annual functional or operational
test is required.
Many utilities now use coordinated end-to-end tests to verify the overall operation of the
protection system and the pilot channel as part of their commissioning tests. This
method is acceptable to BPA.
Modifications to a protection system or RAS scheme also requires testing similar to that
listed above. The extent of testing and types of tests required depend upon the
changes made. Modifications include changes or additions to protection circuits,
changes or upgrades of protective relay firmware, and changes in protective relay logic
and/or programming. Many utilities also consider it good practice to perform various
levels of tests and calibrations following changes in protective relay settings. When
making protection system modifications, attention must be paid to any circuits that may
be inadvertently affected (e.g.) an auxiliary relay having multiple circuits tied to its
outputs.
11.2 Technical Operations Requirements
See Operations Requirements for Generation Interconnection, STD-N-000002.
Operating,
Generation spinning, Actuals as
Actuals as delivered
Reserves regulating, & MW delivered
capability
Notes:
1. A kW reading for revenue billing may be required where special transmission
arrangements are necessary.
2. Direct Incoming Dial Public Switched Telephone Line or its equivalent required for
RMS.
3. All balancing authority area boundaries & customer connections providing ancillary
services.
5. Electric Industry Data Exchange (EIDE) data link is an alternative to acquire and
share kWh and other hourly data between utilities.
6. kV system quantity not required for generation connected to a host utility distribution
system at or below 34.5 kV.
Table 6.— Metering, Telemetering and SCADA Data Requirements for Loads (L),
Including Station Service, At the Meter Point and inside BPA Balancing Authority
Area.
Quantity L < 1 MW L 1 MW
Yes
3 2
Billing Information [RMS ]; Hourly kWh & Kvarh If L 1 kW Yes
Telemetering Equipment
No No6
Failure Alarm
kV No No6
Kvar No No6
Notes:
1. Hourly estimate of load must equal the sum of transmission schedules for delivered
power.
2. Hourly integration of Kvar may be used for reactive billing if Kvarh not available from
meters.
3. Direct Incoming Dial Public Switched Telephone Line or its equivalent required for
RMS.
4. Required from the scheduling agent to BPA.
5. BPA’s standard revenue meter is bi-directional for kW. Refer to BPA’s Revenue
and Interchange Metering standard for additional details.
Table 7.— Metering, Telemetering and SCADA Data Requirements for Generation
Yes, if
Billing Information (RMS) Yes Yes
G 200 kW
Hourly Estimate of Generation 1
Conditional2 Yes Yes
(by web, FAX, or phone)
Hourly kWh (telemetered) No Yes Yes
kW Continuous Data10 No Yes Yes
Notes:
1. Hourly estimate of generation must equal the sum of transmission schedules for
marketed power. It is required from the scheduling agent to BPA
2. Hourly estimate is not required if generation is serving local load only. It is required
if generation is being used as a marketing resource. Local load is defined as load
that is on the generator side of the meter.
3. Separate meters for each unit are required when generators per line are not
identical.
STD-N-000001-00-03 11/6/13 Page 85 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
5. Station service metering is required for all generation, and station service
telemetering may be required. See Sections 12.2.3 and 12.2.4.
6. For generating resources with nameplate rating greater than 200 kW and located in
the BPA Balancing Authority Area, BPA revenue metering is required. Refer to the
BPA Metering Application Guide requirements for Generation Integration Metering.
For generating resources 200 kW and less connected to a Host Utility (i.e. not
directly connected to the BPA transmission grid), the Host Utility is responsible for
the metering requirements.
7. Wind generating plants with aggregate nameplate rating between 3 and 50 MW may
use BPA’s alternative Wind Limit communications (email and website) until the total
wind generation connected to a single BPA POI equals or exceeds 70 MW. See
Section 12.2.6.
Metering and telemetering for temporary generation installations (planned for less than
one year of service) will be determined on a case-by-case basis.
Generation sites with an aggregate output equaling or exceeding 50 MVA may require a
direct link with BPA via a generation ICCP communication server or SCADA RTU in
order to send and receive data directly from the BPA AGC System. ICCP is the Inter-
Control Center Communications Protocol, defined by IEC 870-6 TASE.2 standard. See
Section 12.2.2.3 for additional details on the ICCP requirements.
WECC requires any generation plant over 200 MVA to have data sent to the Extra High
Voltage (EHV) Data Pool. BPA will provide the required data to the EHV Data Pool for
any plant over 200 MVA in the BPA Balancing Authority Area unless the generator is a
WECC member. In that case, the generator is responsible for reporting to the EHV
Data Pool directly or via an agent.
12.2.1.3 Jointly-owned Load or Generation
Telemetering for interconnection of shared or jointly owned loads or generation
commonly use dynamic signals. These signals are usually a calculated portion of an
actual metered value. The calculation may include adjustments for losses, changing
ratios of customer obligations or shares, or thresholds and limits. Two-way dynamic
signals are used when a customer request for MW change that can only be met by an
actual change in generation. In this case, a return signal is the official response to the
request and its integrated value is designated the official meter reading. Previous
integration intervals were typically one hour. Some types of dynamic signals may
require shorter integration intervals. The integration interval is determined by the type
of service provided consistent with BPA tariffs to properly account for transmission
usage. BPA uses the NERC recommended ‘accumulator method’ for accounting, not
the ‘rounding method’ for integrated values.
12.2.1.4 Generation in the BPA Balancing Authority Area Not Controlled by BPA
Telemetering is required for generation located internal to the BPA Balancing Authority
Area to account for the scheduling that is required to deliver that energy to the
appropriate host balancing authority area. The requirements are similar to interchange
telemetering requirements. In this case, GenICCP is typically not required by BPA.
12.2.2 Data Requirements for Balancing Authority Area Services
The following are the data requirements for balancing authority area services if the
requestor wishes to locate a load or generator in the BPA Balancing Authority Area.
12.2.2.1 Requirements for Interconnected Loads
Non-traditional sources are sometimes used for supplying ancillary services. If a load
provides regulating or contingency reserve services, data requirements for deployment
of the reserves will be similar to those applied to generating resources. To the extent
that a third party may externally supply regulating or contingency reserve services at the
BPA Balancing Authority Area interconnecting boundary, data requirements for their
deployment may be similar to those applied to generating resources.
STD-N-000001-00-03 11/6/13 Page 87 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
Technical discussions are necessary before the specific data requirements can be
determined. The following provides a brief overview of these requirements:
12.2.2.1.1 Supplemental AGC Services
If BPA is purchasing supplemental AGC services, AGC interface is required on a long-
term basis. Prior to BPA purchasing supplemental services, an investigation into the
capabilities, cost, and benefits of AGC control is required to determine the specific AGC
requirements. Most supplemental services are scheduled and delivered using real-time
dynamic signals, thus requiring telemetering.
12.2.2.2 Ancillary Services
Ancillary Services requirements are also driven by how the interconnected customer
chooses to meet these obligations. Either the Requester or the entity making the
transmission arrangements is responsible for meeting obligations for necessary
ancillary services associated with the interconnection. Most self-provided ancillary
services are scheduled and delivered using real-time dynamic signals, which require
telemetering. The responsible party may fulfill these obligations in any of the following
ways:
Directly provide ancillary services by making resources available to BPA to deploy
Contract with a third party to make resources available to BPA to deploy
Contract with BPA to cover this ancillary services obligation
The Requester must demonstrate that the selected options are technically sound and
meet all relevant reliability policies and criteria of NERC, WECC and NWPP or their
successors as well as the BPA business practices.
Where a third party is providing ancillary services, the following data is required with a
sampling rate established in BPA’s business practices – typically four seconds between
samples for regulation and ten seconds for operating reserves:
Net instantaneous active power transferred (in MW)
Instantaneous reactive power (in Mvar) and total reactive power (Mvarh) transferred
Operating reserve capability during the upcoming ten minutes
kWh for most-recent hour
Area Control Error (Station Control Error for Generating unit)
Actual Scheduled Interchange
12.2.2.2.1 Supervisory Control and Data Acquisition System (SCADA)
Additional data may be required from loads such as steel rolling mills and wind tunnels,
in order to make generation control performance more predictable. Such additional
data may include, but not be limited to, precursor signals of expected load changes.
SCADA control may also be required. Specific requirements and needs are determined
for each load. This may require a separate SCADA remote terminal unit or it may
require data be added into an existing SCADA as determined by BPA.
12.2.2.3 Dispatch and Data Requirements for Interconnected Generation
Dispatch and Data requirements for balancing authority area services, such as
regulation or operating reserves, apply only to generation resources inside the BPA
Balancing Authority Area. For resources that are not part of BPA’s Balancing Authority
Area, the operator of the Host balancing authority area determines the data
requirements.
Inter-Control Center Communication Protocol (ICCP) is a standard communications
protocol for data exchange used by BPA and many other entities. ICCP is an
international standard for communications of real time data. The IEC 870-6 TASE.2
Standard defines the ICCP. The ICCP protocol is being revised to include certificate
authentication and encryption for security purposes. When this package is available, all
ICCP servers must be retrofitted. BPA has two systems that communicate via ICCP.
The first is GenICCP used for exchanging generation data between the BPA Control
Center and the Generation facility. It is an internal, point-to-point service. The second
system, called simply ICCP, was previously known as inter-utility data exchange. It is
used to exchange SCADA data between BPA and other utilities and balancing authority
area operators. This form of data exchange uses public switched telecommunications
services, not general internet communications.
For generation resources inside the BPA Balancing Authority Area, Ancillary Services,
(e.g. reserves) must be acquired. Provision for all Ancillary Services are specified in the
Interconnection Agreement (LGIA or SGIA) or Balancing Authority Area Services
Agreement (BAASA). BPA must specifically approve all arrangements for generators
intending to provide Ancillary Services to BPA. If the generator is capable of providing
Ancillary Services in excess of its obligation, then BPA may choose to contract with the
generator operator to provide additional Ancillary Services.
Technical discussions between BPA and generator developers are necessary before
the specific implementation requirements can be determined. For generation facilities
with a total capacity of 50 MVA or above, GenICCP will generally be required to transmit
automated Dispatch instructions and unit status,MW, Mvar and kV from the project,
among other data requirements. The AGC data to be passed over the data link may
include some or all of the data quantities listed in Tables 8 and 9. For each project a
detailed data requirements list with definitions will be provided during the design phase
of the interconnection of the project. Actual generator specific data requirements are
developed after an Interconnection Agreement or Balancing Authority Area Services
Agreement is signed.
All interconnected generation projects are required to implement and maintain
automatic voltage control on a voltage schedule provided by BPA Dispatchers. The
status and availability of each auxiliary reactive support device is also required.
Generation facilities are required to receive automated Dispatch instructions and
provide other status and data as needed for the operation of the transmission system.
STD-N-000001-00-03 11/6/13 Page 89 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
(Wind) greater than 50 MVA. Tables 10 and 11 show the typical data and dispatch
requirements.
Table 8.— Automatic Generation Control (AGC) Quantities
Generation Plant to BPA Control Center(s):
1. Plant in BPA AGC mode / local mode 1
2. Net instantaneous power output (MW), unit MW output for plants >200 MW
3. Plant output attributed to natural governor response (MW)
4. Plant ramp rate capability – maximum raise and lower
Plant jerk rate capability (rate of change of ramp rate) – maximum raise and
5.
lower
6. Regulating reserve capability - during next 10-minutes
7. Spinning reserve capability - during next 10-minutes
8. Operating reserve capability - during next 10-minutes
9. Maximum capability - normal conditions
10. Maximum capability - power system emergency conditions
11. Minimum generation capability
12. Unit power system stabilizer and automatic voltage regulation status
Unit status - defined below for each generator unit in numerical order.
Out of Service - unit not available for use on 10 minutes notice.
Standby Mode - unit available for use on 10 minutes notice.
13. Standby Mode - unit available for use within 60 minutes
On-line / Not on AGC
On-line / On AGC
On-line / Condensing
14. Total Mvar output, unit Mvar output for plants >200 MW
15. Total instantaneous maximum Mvar capacity boost or each POI voltage level
16. Total maximum Mvar capacity boost or each POI voltage level
17. Total instantaneous maximum Mvar capacity buck or each POI voltage level
18. Total maximum Mvar capacity buck
19. Plant in BPA kV mode / local kV mode 2
20. Acknowledge Limit Wind Generation
STD-N-000001-00-03 11/6/13 Page 91 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
Notes:
1. When plant is in BPA AGC mode, the BPA AGC system is enabled at the plant. The
plant is controlling power output to meet the generation request and generation rate
of response (MW/minute) originating from BPA. When the plant is in local mode the
BPA AGC system is disabled. The plant is not controlling its power output to meet
generation request and generation rate of response originating from BPA.
2. When plant is in BPA kV mode, the coordinated var control system is enabled at the
plant. The plant is controlling reactive power output to meet the voltage schedule
originating from BPA. When the plant is in local kV mode, the BPA coordinated var
control system is disabled at the plant but automatic voltage regulators must remain
in service. The plant is controlling its reactive power output to meet the nominal
voltage schedule originating from BPA.
5. Voltage of each bus (kV) High side and each collector bus
Plant high speed cutout (MW – wind only) (sum of all units out due to high
8.
winds)
14. Status of each high side Breaker between generation and BPA system
Notes:
1. Available generation capability is sum of all units in service available to generate
times the MW rated capability of each unit.
2. Plant operational limit is the MW amount the plant is limited to at any time less than
the sum of the units available for generation (by BPA Dispatch or plant operator).
3. Total all units in service, available, net at POI.
The service should only allow specific IP addresses on the remote end to pull or
push data.
12.2.6.3.3 Historical data (last 2 years, or as available)
Data to include:
Available Capacity (hourly average)
Plant meteorological data (10 minute average preferred)
Anemometer coordinates (Latitude/Longitude/height)
Wind speed (mph, integer)
Wind direction (degrees of north, integer)
Temperature (degrees F, integer)
Humidity (relative %, integer)
Pressure (inches of Mercury, in Hg, three significant figures, xx.xxx)
Data is to be emailed to BPA in excel or mutually acceptable format.
12.3 Voltage Schedules
Voltage schedules are necessary, in order to maintain optimal voltage profiles across
the transmission system. Optimal profiles minimize transmission of reactive power, and
preserve flexibility in use of reactive-power control facilities. To this end, a voltage
schedule will be mutually developed between BPA and the Requester, which will be
coordinated via time changes developed by the NWPP for such coordination purposes.
BPA maintains voltages according to the ANSI Standard C84.1. This allows for
variances of ±5% from nominal for all voltage levels except the 500 kV system. The
500 kV system has a nominal voltage of 525 kV with a variance from 500 kV to 550 kV.
Equipment connected to the BPA Grid must be compatible with this range of operation.
Deviations from the voltage schedule may be ordered by the BPA Dispatcher. Usually
the deviations are due to load changes occurring earlier than the NWPP coordinated
schedule.
12.4 Reactive Power
Each entity shall provide for its own reactive power requirements, at both leading and
lagging power factors unless otherwise specified by BPA. BPA generally requires
customers to minimize exchange of reactive power with BPA’s system, especially under
peak load conditions. This can be accomplished by installing equipment to allow
matching of internal supply and demand of reactive power. Closely coupled generators
may also receive telemetered voltage schedules or receive the voltage schedule
through ICCP to minimize var conflict. (See Section 12.1) Minimizing flow of reactive
power on a given line can increase its transfer capability and reduce its losses.
Reactive flows at interchange points between control areas should be kept at a
minimum as per the WECC Minimum Operating Reliability Criteria.
area operator. All parties have the responsibility for clear communications and to report
promptly any suspected problems affecting others.
13. MAINTENANCE
13.1 Outage Planning
The Requestor’s facilities may be part of or connected to key transmission lines that
must be kept in service as much as possible. They may be removed from service only
after power flow studies, in accordance with WECC requirements, indicate that system
reliability will not be degraded below acceptable levels. The entity responsible for
operating such transmission line(s) shall promptly notify other affected control areas,
per the WECC Procedure for Coordination of Scheduled Outages and Notification of
Forced Outages, ”Dispatcher/System Operator Handbook” when removing such
facilities from and returning them back to service.
The Requester shall not energize any de-energized BPA equipment unless the BPA
Dispatcher specifically approves the energization. Where the connection is to a radial
load the circuit may be interrupted and reclosed by BPA. In cases where the
interconnection taps or breaks an existing BPA line, an auto isolation scheme may be
required to maintain service continuity of the BPA line. If the interconnected facilities
are networked or looped back to the BPA Grid or where generation resources are
present, a switching device must open to eliminate fault contributions or neutral shifts.
Once open, the device must not reclose until approved by the BPA Dispatcher or as
specified in the interconnection agreement.
13.2 Switchable Devices
Devices frequently switched to regulate transmission voltage and reactive power shall
be switchable without de-energizing other facilities. Switches designed for
sectionalizing, loop switching, or line tripping shall be capable of performing their duty
under heavy load and maximum operating voltage conditions.
13.3 Frequency and Duration of Outages
Planned outages of significant system equipment shall be coordinated with all affected
parties to minimize their impact on the remaining system. The operator of the
Requester’s facilities should respond promptly to automatic and forced outages in order
to mitigate any impacts on the remaining system, and in a manner that treats all
interruptions with the same priority.
13.4 Inspection, Test, Calibration and Maintenance
Transmission elements (e.g. lines, line rights of way, transformers, circuit breakers,
control and protection equipment, metering, and telecommunications) that are part of
the proposed connection and could affect the reliability of the BPA Grid need to be
inspected and maintained in conformance with regional standards. The Requester has
full responsibility for the inspection, testing, calibration, and maintenance of their
equipment, up to the location of change of ownership or POI. Transmission
Maintenance and Inspection Plan (TMIP) requirements are a portion of the WECC
Reliability Management System for Transmission. The Requester or utility may be
required by WECC to annually certify that it has developed, documented, and
implemented an adequate TMIP.
STD-N-000001-00-03 11/6/13 Page 103 of 107
Technical Requirements for Interconnection to the BPA Transmission STD-N-000001
Grid
14. REFERENCES
14.1 Bonneville Power Administration - United States and Other Codes
Accident Prevention Manual (APM)
http://www.transmission.bpa.gov/business/generation_interconnection/
ANSI/IEEE Std 81 Part 1 - Guide for Measuring Earth Resistivity, Ground Impedance,
and Earth Surface Potentials of a Ground System & Part 2: Guide for
Measurement of Impedance and Safety Characteristics of Large, Extended or
Interconnected Grounding Systems
IEEE Std 367 - Recommended Practice for Determining the Electric Power Station
Ground Potential Rise and Induced Voltage from a Power Fault
ANSI/IEEE Std 421.1 – IEEE Standard Definitions for Excitation Systems for
Synchronous Machines
IEEE Std 421.2 – IEEE Guide for Identification, Testing, and Evaluation of the Dynamic
Performance of Excitation Control Systems
IEEE Std 487 - Recommended Practice for the Protection of Wire-Line Communication
Facilities Serving Electric Power Stations
IEEE Std 519 - IEEE Recommended Practices and Requirements for Harmonic Control
in Electrical Power Systems
IEEE Std - 837 - Standard for Qualifying Permanent Connections Used in Substation
Grounding
IEEE Std – 1159 – Recommended Practice for Monitoring Electric Power Quality
IEEE Std – 1547 – Interconnecting Distributed Resources with Electric Power Systems
IEEE Std – C37.118 – Enclosed Field Discharge Circuit Breakers for Rotating Electric
Machinery
ANSI C84.1 – Electric Power System and Equipment – Voltage Ratings (60 Hz)