Model Answer Q2 2015
Model Answer Q2 2015
Model Answer Q2 2015
Institution of Structural
Engineers Chartered
Membership Examination
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
Although all care has been taken to ensure that all the information contained herein is
accurate, The Steel Construction Institute assumes no responsibility for any errors or
misinterpretations or any loss or damage arising therefrom.
Email: [email protected]
ii
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
FOREWORD
This document has been prepared to assist candidates preparing for the Institution of
Structural Engineers chartered membership examination. It forms one of a series of
answers, demonstrating steel solutions.
The document was prepared by Ed Yandzio and David Brown of the Steel Construction
Institute (SCI), with valuable input from Tom Cosgrove of the British Constructional
Steelwork Association (BCSA) and Owen Brooker of Modulus.
This answer was commissioned and funded by the BCSA and Steel for Life.
iii
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
iv
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
Contents
Page No
FOREWORD iii
1 THE QUESTION 1
1.1 General arrangement 1
1.2 Loading 3
1.3 Ground conditions 3
1.4 Section 1b modification 3
2 CALCULATIONS 5
3 DRAWINGS 35
4 METHOD STATEMENT 40
5 PROGRAMME 41
6 CLIENT LETTER 43
v
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
vi
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
1 THE QUESTION
A range of past papers is available from the Institution of Structural Engineers at the
following url: https://www.istructe.org/membership/examination/papers-etc
The question addressed by this model answer is Question 2 from January 2015; it is
recommended that the full question is reviewed.
1
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
Traffic lane
Possible support
zones
105.0 10.0
5.0
5.0
Control room
5.0
30.0
20.0
5.0
10.0
Supports were only permitted in the 5 m gap between lanes, within the 10 m zone shown
in Figure 1.
Although the supports were protected from impact, the brief required that the structure
must withstand the removal of a single interior support, under partial loading conditions.
Only three road lanes could be closed at any one time during construction.
2
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
1.2 Loading
The following loads were specified:
Basic wind speed of 46 m/s based on a 3 second gust, or a mean hourly wind speed of
23 m/s.
Borehole 1:
Borehole 2:
3
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
4
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
2 CALCULATIONS
5
Job No. Sheet 1 of 28 Rev
Title
Subject
Silwood Park, Ascot, Berks SL5 7QN
Telephone: (01344) 636525
Fax: (01344) 636570 Made by EDY Date Nov 17
Client
CALCULATION SHEET Checked by DGB Date DEC 17
The key to this question is the cantilever of the canopy roof, compounded by the lateral forces on
the control room tower, which will produce uplift on the foundations.
The quite different ground conditions across the site demand alternative arrangements for the clay
and for the rock.
Structurally, the modest challenge is that the supports to the control room tower are located
between supports (i.e. over a carriageway). A transfer arrangement is required if the control tower
is to be supported at the four corners.
A narrow tower could be provided, becoming wider under the control room itself, but this would
be tall and narrow, so not an efficient solution.
The different ground conditions mean that differential settlement across the site must be
accommodated – and mentioned in the submission.
Calculations Sheet 3 of 28 Rev
Framing arrangement
The roof will be clad in profiled metal sheeting, spanning 2 m between purlins. The purlins
span 10 m to the primary roof canopy trusses.
Roof canopy trusses
The primary roof canopy trusses are 30 m long, supported on a braced support system
within the 10 m permitted zone. The trusses have a 1 in 60 fall to the truss tip, to aid
drainage.
Under gravity conditions, the bottom chord of the cantilever will be in compression.
Lateral restraints will be required at appropriate intervals. In the wind uplift case, the
purlins restrain the compression chord.
Transverse trusses
Transverse trusses will be provided on lines A, B and C (see diagram) to provide stability
at the support locations and at the tips of the cantilever. These trusses do not carry
primary loads in normal conditions, but will be designed to carry the resulting load if one
support is removed.
Load transfer – canopy roof
Vertical loads are carried by the primary roof canopy trusses to the columns within the
10 m permitted support zone. Depending on the load combination, the columns will
experience compression or tension, meaning the foundations must be designed for both
cases.
Loads parallel to the carriageway are carried by the trusses to the vertical bracing within
the permitted support zone and thus to the foundations.
Loads perpendicular to the carriageway will be carried by plan bracing in the line of the
truss chords to bracing towers provided in five of the eleven permitted support zones.
Within these towers, diagonal bracing takes the lateral loads to the foundations.
Frame stability – canopy roof
Plan bracing is provided in each end bay and two further intermediate bays to stabilise
the structure under loads perpendicular to the carriageway. Plane bracing is also
provided over the full width of the structure, between Trusses A and B, to accommodate
loads parallel to the carriageway and to ensure the roof behaves as a diaphragm.
Control Tower
The control tower is a simple clad “box” supported on a braced tower. All four sides of
the tower are braced. A simple floor of precast slabs could be provided, with supporting
beams simply supported. A simple clad roof is envisaged, to suit the architectural details.
At the canopy roof level, due to the arrangement of the carriageways, the control tower
steelwork must be supported by transfer trusses which span to adjacent supports. At
this level, plan bracing is provided to transfer the horizontal loads to the adjacent braced
bays.
Control tower – load transfer
Vertical loads are carried by the four corner columns to the transfer trusses, and
then to vertical supports in the permitted support zones. Lateral loads are carried
by vertical bracing to the canopy roof level transfer trusses. At that level,
horizontal bracing transfers the horizontal loads to vertical bracing provided in
both directions within the permitted support zones.
Commentary Sheet 4 of 28 Rev
10 m is a relatively long span. A hollow section will be used for the purlin, primarily so that
lateral torsional buckling under uplift (where the member would be unrestrained) is not a
design consideration.
The transverse trusses (perpendicular to the carriageway) would normally carry no load – the
exceptions are the trusses carrying the column loads from the control tower. However, the
brief demands that a support be removed, so the trusses must function as double span, or as
a cantilever, and this will be the design condition.
Generally, examiners are keen to see issues of load transfer and stability addressed, so it may
be a good discipline to formally describe these.
Detailed arrangements around the control tower are not seen as significant, so are largely
ignored in the submission.
Calculations Sheet 5 of 28 Rev
In scheme 2, the spacing of trusses parallel to the carriageway is no longer constrained by the lane
spacing.
In any scheme with inclined members, the resulting forces in the rest of the structure must be
mentioned and managed in design. Here, additional compression is introduced.
The tension in the ties produces compression in the primary truss chords, which must be
included in the design. The inclined tie to grid C produces compression in the secondary
truss chord, which must be resisted by a substantial horizontal truss between grids A and B,
which spans from the ends of the canopy to the support tower.
In this scheme, the control room is supported on a narrow tower (5 m x 10 m) which is
located within the permitted support zone between carriageway lanes.
The support tower is subject to high loads, and asymmetric loading conditions – including
torque on plan, so will be heavily braced with diagonal members on all faces down to the
foundations.
Because the tower carries a large proportion of all the forces applied to the structure, the
foundations will be substantial.
Load transfer – canopy roof
In the gravity loadcase, purlins carry the load on the sheeting to the secondary trusses. The
secondary trusses are supported by primary trusses on grids A, B and C. The primary
trusses span from the outside of the canopy roof to the support tower, with an intermediate
support from an inclined tie, midway along the truss
The tie member is only effective in tension (the gravity loadcase), so in the wind uplift
loadcase, the primary trusses must span 50 m from the edge of the roof to the support
tower.
Load parallel to the carriageway is carried by the plan truss between grids A and B to the
vertical bracing at the ends of the canopy and at the support tower.
Load perpendicular to the carriageway is carried by the primary trusses to the vertical
bracing in the support tower.
Load transfer – control room
The vertical loads from the control room are small. The more significant loads are from the
component of the tie force that the columns must carry. All lateral loads will be carried by
bracing on all four sides of the tower to the foundations.
Frame stability
Frame stability is provided by the vertical bracing at the end of the canopy, and by vertical
bracing in both directions at the support tower. The support tower is relatively narrow, so
the resulting forces will be large.
Foundations
Foundations are only required at the ends of the canopy and under the support tower. The
foundations at the ends of the canopy will not be significant. The foundations under the
support tower must resist large vertical forces and large horizontal forces, so will be
substantial. Similar arrangements to scheme 1 are proposed – bored piles if clay and tension
bars if rock.
Scheme Selection
Although scheme 2 has greater architectural merit than scheme 1, the majority of force is
concentrated on the support tower leading to an inefficient design. Because the inclined ties
are ineffective in the uplift loadcase, the primary trusses will be substantial, and may be
competent in the gravity loadscase even without the inclined ties, rendering the ties
structurally redundant. Fewer foundations in scheme 2 are offset by the necessity for much
larger foundations, leading to increased cost.
Commentary Sheet 8 of 28 Rev
The narrow tower will lead to significant forces in the bracing, and tower legs, and in the
foundations. The possibility of asymmetric loading would also be considered.
As ties do not work in compression, the primary trusses perpendicular to the carriageway will need
to be substantial (and uplift is the more onerous design condition). Thus the trusses would be
capable in the ‘download’ case without the ties – making them redundant.
The structure is inefficient as the ties are effectively redundant. They do limit deflection in the
gravity loadcase.
Calculations Sheet 9 of 28 Rev
The inclined ties result in additional compression in several members, adding complexity to
the design
The structural connections between the canopy roof and the control room support tower are
likely to produce some movement and possibly vibration from the fluctuating wind loads on
the canopy roof, which may lead to discomfort. The control room is more isolated in
scheme 1 so any dynamic effects are reduced.
Temporary works will be more involved in scheme 2, to support the primary trusses until the
ties and the plan bracing is complete. In comparison, the scheme 1 steelwork can be
erected in self-contained, stable stages. Scheme 2 is more sensitive to asymmetric loading.
The structural redundancy demanded by the brief is readily provided in scheme 1.
Both schemes recognise that differential deflection across the canopy roof is possible; both
have sufficient flexibility to accommodate any anticipated movement
Scheme 1 is selected, for three primary reasons:
1. Scheme 1 is more robust in form.
2. Scheme 2 demands more temporary works.
3. The foundations for Scheme 2 will be much more expensive.
SECTION 2 – DESIGN CALCULATIONS
(for scheme 1)
Preliminary design calculations completed in accordance with BS EN 1993-1-1.
Design combinations of actions determined in accordance with expression 6.10 of
BS EN 1990.
All steelwork is S355, unless noted otherwise.
Roof canopy
Loading
Mean hourly wind speed is associated with BS 6399
No altitude given. Assume 150 m asl. so calt 1.15
vs = 1.15 × 23 = 26.5 m/s
Assume country terrain, close to sea (most onerous)
Then from BS 6399 Table 4, sb = 1.96 at 30 m height
ve = 26.5 × 1.96 = 51.9 m/s
qs = 0.613 × 51.92 × 10-3 = 1.65 kN/m2
BS 6399 Table 13 for overall coefficients (net)
Download = +0.2; uplift = -1.2
Download = 0.2 × 1.65 = 0.33 kN/m2
Uplift = -1.2 × 1.65 = -1.98 kN/m2
Assume permanent actions = 0.4 kN/m2
Assume snow load = 0.6 kN/m2
Imposed load (from brief) = 1.0 kN/m2
Commentary Sheet 10 of 28 Rev
In the scheme selection, consider structure, foundations, cost, aesthetics, erection, programme
and risk.
It is not clear how the demand to remove one support can be realised in scheme 2.
For the candidate, an equally important reason is that scheme 1 is straightforward to design.
A 3 second gust is compatible with CP2‐ChV. Wind data compatible with the Eurocode is not
provided in the brief.
Not enough data is given for a thorough assessment to BS 6399, so assumptions must be made
about altitude, distance from the sea, etc.
Note that in the Eurocode, the imposed load on a roof is separate to the snow load. Notably, the
imposed load is not combined with wind or snow. An assumption about the snow load must be
made, as this is not given in the brief.
Calculations Sheet 11 of 28 Rev
SHS has been chosen to avoid LTB being a design consideration. No deflection limits are needed at
this stage.
Although the compression in the bottom chord will be smaller, as the loading is reduced, restraints
are only provided at 4 m centres (compared to 2 m centres on the top chord) so this design
condition must also be verified.
Calculations Sheet 13 of 28 Rev
The internal member has been selected to be relatively wide, to minimise the likelihood of
punching through the face of the chord. In a full design, it is essential that the joint resistances are
checked in accordance with BS EN 1993-1-8.
EHF are normally 0.5% of the factored vertical loads. However, the use of 2.5% is considered
sufficient to ensure that if frame stability were considered, cr > 10 and second order effects would
be small enough to be ignored.
Calculations Sheet 17 of 28 Rev
A compression member could be used – but is inconvenient as the length falls outside the range in
the Blue Book.
A simple check is completed on the net area, using the yield strength. The Eurocode allows the
resistance to be based on gross area × yield, or net area × 0.9 × ultimate, whichever is lower.
This is the “normal” case. It will be compared with the accidental condition, to see which gives the
higher moment.
This second accidental condition assumes that the missing column is on grid 7
This design covers the trusses that do not support the tower – in the normal condition they are
merely framing the structure together, so the accidental case is the design condition to be verified.
Plan bracing need only be nominal. Four braced bays and wind loads only mean the forces are
small.
Foundations are the key design challenge. Two loading conditions exist – foundations that support
the tower, and those that do not. Two quite different ground conditions have to be assessed – on
clay, or over rock at relatively shallow depth.
Calculations Sheet 23 of 28 Rev
Some iteration is needed before a reasonable solution can be identified. More piles are less
efficient because of the group effect, but the pilecap is larger – and heavier, which reduces the net
uplift.
Reinforced Concrete Designer’s Handbook; Reynolds and Steedman. C&CA, 1981. Table 195.
This includes the 0.5 factor used when assessing skin friction in uplift.
End bearing has been neglected. Even if the 0.5 factor for skin friction under uplift is used, the
resistance is satisfactory in compression.
Calculations Sheet 25 of 28 Rev
The EHF could be reduced, as in this case they may be based on the permanent actions only.
Calculations Sheet 27 of 28 Rev
Pile Reinforcement
Adopt 4% reinforcement
0.4/100 × 442000 = 1768 mm2
Adopt 6 H 20 = 1880 mm2
Adopt H 10 links at 300 mm spacing
Commentary Sheet 28 of 28 Rev
From Brooker
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
34
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
3 DRAWINGS
The following sheets reproduce the A3 drawings prepared for the scheme.
35
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
4 METHOD STATEMENT
Preliminaries
The site should be secured to prevent unauthorised access by member of the
public.
As there is working at height, full PPE must be worn, including fall arrest
equipment and safe methods of work must be established and followed.
Additional ground investigation must be carried out to determine which
locations are founded on rock, and which are founded on clay. This will
necessitate lane closures of the two adjacent carriageways during the site
investigation works.
The first three lanes of the carriageway must be secured, with appropriate barriers to
protect the construction team, and to prevent the construction team accidentally
straying into a ‘live’ carriageway. Systems of safe access must be established. This
procedure must be repeated as the construction proceeds across the full carriageway
in stages.
Sequence of work
Lane closures provided between grids 1 and 4.
Verify that existing asphalt (assumed to be a carriageway construction) is
adequate for construction plant.
Install bored pile foundations, grids 1 – 3. If the location is over rock, bore to
rock level and install casing. Drill 50 mm holes in rock to prescribed depth,
before grouting 25 mm bars in position. Reinforce piles and complete.
Complete pile caps, grids 1 to 3.
Erect braced tower on grid 1 and erect supports and bracing on grids 2 and 3.
Erect roof canopy trusses, grids 1 – 3 and primary trusses on grids A, B and C,
with associated plan bracing at upper and lower chord levels. Note that this
part of the structure is stable, without the need for additional temporary
bracing.
Erect purlins grids 1 – 3 and roof cladding.
Repeat the previous steps, closing three lanes at a time. Each portion of the
structure is stable.
o Complete piling (and tension bar installation if founded on rock).
o Complete pile caps.
o Erect steelwork, bracing and cladding.
After completion of the roof canopy, close the carriageway, grids 5 – 7, so the
steelwork for the control tower may be erected.
Erect the control tower steelwork, installing the crossed flat bracing as erection
proceeds.
Install the flooring to the tower, cladding etc
40
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
5 PROGRAMME
The construction programme is shown on the following page, which assumes the
necessary additional site investigation has been completed.
The programme is by necessity lengthy, as the brief stipulates that only three lanes of
the carriageway may be closed at any one time, meaning that the works must be
completed as a linear progression.
41
Construction Programme
Week Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Activity
Initial works 2
Establish site and verify adequacy of hard standing 2
Grids 1, 2 and 3 6
Construct piles/ tension bars 3
Complete pile caps 2
Erect steekwork 1
Cladding 1
Grids 4, 5 and 6 6
Construct piles/ tension bars 3
Complete pile caps 2
Erect steekwork 1
Cladding 1
Grids 7, 8 and 9 6
Construct piles/ tension bars 3
Complete pile caps 2
Erect steekwork 1
Cladding 1
Grids 10, 11 5
Construct piles/ tension bars 2
Complete pile caps 2
Erect steekwork 1
Cladding 1
6 CLIENT LETTER
43
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
44
Model Answer Q2, 2015
Institution of Structural Engineers Chartered Membership Examination
45
Steel Construction Institute
SCI (The Steel Construction Institute) is the leading, independent provider of
technical expertise and disseminator of best practice to the steel construction
sector. We work in partnership with clients, members and industry peers to help
build businesses and provide competitive advantage through the commercial
application of our knowledge. We are committed to offering and promoting
sustainable and environmentally responsible solutions.
Follow us on:
Twitter: @steelcoinfo
LinkedIn: steelconstruction.info
Facebook: steelconstruction.info
Google+: steelconstruction.info
Produced for:
The British Constructional Steelwork Association
www.steelconstruction.org
and Steel for Life
www.steelforlife.org
by:
The Steel Construction Institute
www.steel-sci.com