c6 - Project Time Management
c6 - Project Time Management
2
Project Scope Management
3
Chapter 06 - Contents
5
Individual Work Styles and Cultural
Differences Cause Schedule Conflicts
• One dimension of the Meyers-Briggs Type
Indicator focuses on peoples’ attitudes toward
structure and deadline
6
Project Time Management Processes
8
Chapter 06 - Contents
10
Activity Lists and Attributes
11
Milestones
• Examples:
– obtaining customer sign-off on key documents
– completion of specific products
12
Chapter 06 - Contents
14
Three types of Dependencies
• Mandatory dependencies
– inherent in the nature of the work being performed on a
project, sometimes referred to as hard logic
• Discretionary dependencies
– defined by the project team; sometimes referred to as
soft logic and should be used with care since they may
limit later scheduling options
• External dependencies
– involve relationships between project and non-project
activities
15
Network Diagrams
16
Sample Activity-on-Arrow (AOA)
Network Diagram for Project X
17
Arrow Diagramming Method (ADM)
18
Process for Creating AOA Diagrams
20
Task Dependency Types
21
Sample PDM Network Diagram
22
Chapter 06 - Contents
26
Three-Point Estimates
• Symbols include:
– Black diamonds: milestones
– Thick black bars: summary tasks
– Lighter horizontal bars: durations of tasks
– Arrows: dependencies between tasks
30
Gantt Chart for Project X
Note: Darker bars would be red in Project 2007 to represent critical tasks.
31
Gantt Chart for Software Launch
Project
32
Adding Milestones to Gantt Charts
33
SMART Criteria
34
Best Practice
36
Critical Path Method (CPM)
39
More on the Critical Path
• The critical path is not the one with all the critical
activities; it only accounts for time
40
Using Critical Path Analysis to Make
Schedule Trade-offs
• Free slack or free float is the amount of time an
activity can be delayed without delaying the early
start of any immediately following activities
• Total slack or total float is the amount of time an
activity may be delayed from its early start
without delaying the planned project finish date
• A forward pass through the network diagram
determines the early start and finish dates
• A backward pass determines the late start and
finish dates
41
Calculating Early and Late Start and
Finish Dates
42
Free and Total Float or Slack for
Project X
43
Using the Critical Path to Shorten a
Project Schedule
• Three main techniques for shortening schedules
– Shortening durations of critical activities/tasks by
adding more resources or changing their scope
44
Importance of Updating Critical Path
Data
• It is important to update project schedule
information to meet time goals for a project
45
Critical Chain Scheduling
46
Multitasking Example
47
Buffers and Critical Chain
49
Program Evaluation and Review
Technique (PERT)
• PERT is a network analysis technique used to
estimate project duration when there is a high
degree of uncertainty about the individual activity
duration estimates
50
PERT Formula and Example
52
Chapter 06 - Contents
56
Chapter 06 - Contents
58
Words of Caution on Using Project
Management Software
• Many people misuse project management software
because they don’t understand important concepts
and have not had training
59
Chapter 06 - Contents
61