CEP233 - M8 - Leveling Methods
CEP233 - M8 - Leveling Methods
Chapter 3 |
Measurement of Vertical Distances and
Leveling Methods
MODULE 8:
Leveling Methods
Overview
This module provides a thorough discussion on the terms and procedures
undertaken in different leveling methods. These methods include differential
leveling, profile leveling, trigonometric leveling, and inverse leveling.
Objective
To understand the step-by-step procedures in undertaking various leveling
methods.
To determine the appropriate method to be used in a specific scenario.
Definition of Terms
It is important that bench marks are easily recognized and located where they will
have the smallest likelihood of being disturbed. Accurate records should be kept for
each bench mark since they may be frequently referred to later by other surveyors.
They should be thoroughly described in field notes. In some areas, bench marks may
have to be re-established where their position and elevation have been disturbed by
earth movements such as those caused by slides, earthquakes, floods, engineering
constructions, and mining operations.
2. Backsight (BS)
3. Foresight (FS)
The backsight distance is measured from the center of the instrument to the rod on
which a backsight is taken.
The horizontal distance from the center of the instrument to the rod on which a
foresight is taken is referred to as the foresight distance. Its length is usually made
nearly equal to its corresponding backsight distance.
A turning point is an intervening point between two bench marks upon which point
foresight and backsight rod readings are taken to enable a leveling operation to
continue from a new instrument position. It is also sometimes referred to as a change
point (CP), and is established as far away as practical in the general direction of the
line of levels. In order that the rod can be removed and later positioned back in the
same place as many times as may be necessary, the turning point should be located
on some stable object. For this purpose, a rock, a stake driven into the ground, or a
paint mark on a concrete pavement is preferable. Turning points are usually
numbered consecutively and it is not necessary to described them in detail since they
are only used to carry forward a line of levels.
The height of instrument (or height of collimation) is the elevation of the line of sight
of an instrument above or below a selected reference datum. It is determined by
adding the rod reading on the backsight to the elevation of the point on which the
sight is taken.
The leveling instrument is set up at any convenient location along the level route and
a backsight is taken on a leveling rod held vertically on BMa. The backsight reading
added to the known or assumed elevation of the initial bench mark gives the height
of the instrument above datum or:
𝐻𝐼 = 𝐸𝑙𝑒𝑣 𝐵𝑀𝑎 + 𝐵𝑆
The rodman moves forward along the general direction of BMb and holds the rod at
a convenient turning point (TP1). The instrumentman takes a foresight on the rod.
This foresight reading subtracted from the height of instrument gives the elevation
above datum of the turning point or:
𝐸𝑙𝑒𝑣 𝑇𝑃1 = 𝐻𝐼 − 𝐹𝑆
The level is then transferred and set up at another convenient location beyond TP1,
but still in the general direction of BMb. The exact location at which the level is set up
is of little importance. The more important thing to consider is that the level is set up
at a location where backsight and foresight rod readings can be made. A backsight is
then taken on TP1 to establish a new height of instrument (HI2). The rodman finally
moves forward to the location of BMb and a foresight is taken on the rod held on it.
Since the new HI has already been determined, the elevation of BMb is computed by
subtracting the foresight reading from the height of instrument.
If the terminal point (BMb) is still some distance away such that more turning points
have to be established before it could be foresighted, the procedure of reading a
backsight, the rodman moving ahead to establish another turning point, and reading
a foresight is repeated. This is done as many times as necessary until the elevation of
BMb is finally obtained.
Leveling Notes
A check on the addition and subtraction in each step is made by adding separately the
backsight and foresight readings. The difference between the two sums should equal
the difference in elevation between the first and last stations unless a mistake is made
in arithmetic. An agreement between these two quantities that the process of adding
and subtracting has been done correctly. It does not, however, provide a check against
mistakes in observing and recording data or whether the field work was performed
SAMPLE PROBLEMS:
E8-1 DIFFERENTIAL LEVELING. Complete the differential level notes shown below
and perform the customary arithmetic check.
Level Notes from BM1 to BM4:
STA BS HI FS ELEV
BM1 1.256 127.133 m
TP1 1.116 1.885
TP2 1.228 1.527
BM2 1.189 2.246
BM3 1.070 2.017
TP3 1.831 2.656
BM4 2.765
Solution
a) Level Route from BM1 to TP2:
STA BS HI FS ELEV
BM1 1.256 128.389 127.133 m
TP1 1.116 127.619 1.885 126.503 m
TP2 1.228 127.320 1.527 126.092 m
BM2 1.189 126.263 2.246 125.074 m
BM3 1.070 125.316 2.017 124.246 m
TP3 1.831 124.491 2.656 122.660 m
BM4 2.765 121.726 m
Arithmetic Check:
127.133 𝑚 + 7.690 𝑚 − 13.097 𝑚 = 𝟏𝟐𝟏. 𝟕𝟐𝟔 𝒎
E8-2 DIFFERENTIAL LEVELING. The accompanying schematic arrangement of lines
portray a differential level route. The values indicated represent backsight and
foresight readings taken at different points as labeled. Prepare and complete
differential level notes for the information shown and show the customary arithmetic
check.
Solution:
STA BS HI FS ELEV
BM1 2.35 359.00 356.65 m
TP1 1.37 357.09 3.28 355.72 m
TP2 3.08 358.13 2.04 355.05 m
TP3 1.54 356.06 3.61 354.52 m
TP4 0.85 353.22 3.69 352.37 m
BM2 3.07 350.15 m
Total +9.10 -15.69
Arithmetic Check:
356.65 + 9.19 − 15.69 = 𝟑𝟓𝟎. 𝟏𝟓 𝒎
8.2 Profile Leveling
The process of determining differences in elevation along a fixed line at designed
short measured intervals is referred to as profile levelling. The fieldwork involved is
identical to differential levelling since it also requires the establishment of turning
points on which foresight and backsight readings are taken before the terminal point
is reached. The main difference between these two methods of levelling lies in the
number of foresights taken from each setup of the instrument. In differential levelling
only one foresight is necessary whereas in profile levelling any number of foresights
can be taken. In profile levelling, a series of benchmarks intended for use at a later
date are also set up.
Profile level routes may be run as a single straight line or as a series of straight lines
connected by curves. Intermediate foresights are taken where necessary to portray
accurately the existing ground surface along the route surveyed. For most
engineering projects, the profile is usually taken along the centerline with the level
set up a convenient distance away from it so that sights of more uniform lengths can
be obtained. Upon completion of profile levelling work, it is important to check (while
still in the field) the gathered before any plotting is made. A check may be made by
trying into a previously established benchmark or by running a line of differential
levels back to the starting point.
Definition of Terms
1. Profile
The profile is a curved line which graphically portrays the intersection of a vertical
plane with the surface of the earth. It depicts ground elevations of selected critical
points along a surveyed line and the horizontal distances between these points.
2. Stationing
A numerical designation given in terms of horizontal distance any point along a
profile line is away from the starting point. Each stake used is marked with its station
and plus.
3. Intermediate Foresights
These sights, which are also known as ground rod readings, are taken along the
centerline of the proposed project to provide an accurate representation of the
ground surface. Intermediate foresights are observed at regular intervals and at
points where sudden changes in elevation occur.
4. Full Stations
Are points which are established along the profile level route at uniformly measured
distances. These points are usually made in multiples of 100, 50, 30, 20, or 10 meters.
5. Plus Stations
Any other intermediate point established along a profile level route which is not
designated as a full station is called a plus station. These points are taken at breaks in
the ground surface slope and at critical points such as the intended location of
culverts, bridges, and other structures.
6. Vertical Exaggeration
It’s a process of drawing the vertical scale for a profile much larger than the horizontal
scale in order to accentuate the differences in elevation.
7. Profile Paper
A special heavy grade graphing paper used for plotting profiles. The paper has
horizontal and vertical lines drawn in green, blue, or orange which are spaced
accordingly to represent certain distances to the horizontal and vertical axis.
Procedure of Profile Leveling
Before profile levels are run, the line joining the initial and terminal points must first
be established. A transit and tape survey are undertaken starting at the beginning of
the line which is designated as station 0+00. The length of the level route is measured,
and stakes are set at each full station to define the path to be followed.
The instrument is set up at a convenient location and a backsight is taken on a
reference benchmark near the initial point to determine the height of the instrument.
It is preferable to set up the level about 20 meters away from the level route when
readings must be taken on a series of intermediate points. A suitable setup should be
selected such that the rod is visible through the telescope and rod readings could be
made more easily. A series of intermediate foresights are next taken along the center
line to determine elevations of ground points. This is done without transferring the
instrument. By the time it is no longer possible to continue with the foresight readings
on intermediate point from the instrument position, a turning point is established.
This permits the instrument to be moved to a new location which will allow additional
foresights to be taken forward of the line or just to continue the line of levels.
Intermediate foresights readings should be taken at regular intervals of 10 to 30
meters along the centerline, and at points foresighted should provide data which will
portray accurately the configuration of the terrain along the level route.
Benchmarks may be established ahead during the execution of a transit and tape
survey or at the same time profile levelling is undertaken. Usually, benchmarks are
spaced much farther apart when the differences in elevation along the level route are
not so large. The spacing should be made closer where the differences in elevation is
quite considerable. It is important that benchmarks be so located that they will not be
disturbed or obliterated during any construction that may be undertaken later. Also,
since benchmarks are intended to be used as reference points for determining
differences in elevation, it is important that their elevations are accurately
determined and subsequently verified as well.
Stationing
Before levels are taken, the line along which the profile is required must be properly
marked by stakes on the ground. The choice of intervals between stakes will depend
largely on the desired accuracy and type of terrain to be traversed. Usually, stakes
which mark full stations are spaced at 100-m intervals. Spacing between plus stations
could not be regularly fixed as they depend on breaks in the slope of the ground
surface and on the location of critical points where structures are to be positioned
along or transverse to the level route.
Stationing is used to indicate the distance of any ground stake from the beginning
point of the level route. It is carried continuously along the route. In the case of a
highway or a railroad, the stationing is also carried around the curves. A station and
a plus are adapted to mark each stake. For example, full stations which are 100, 200,
400, and 1300 meters from the beginning point (Sta 0+00) of the profile route are
designated as stations 1+00, 2+00, 4+00, and 13+00, respectively. Other intermediate
points are designated as plus stations. Thus, a stake that is 1,650 meters from the
point of beginning is marked as 16+50, and one set 228.35 m from the same starting
point is marked as 2+28.35.
If the distance from the point of beginning of any full or plus station is known, its
stationing can be readily calculated. For example, a point that is 172.45 m beyond
station 5+50 is 550+172.45 = 722.45 m from station 0+00, and the point is marked as
7+22.45 m. The horizontal distance between any two stations may also be
determined. Thus, if the given stationing of two points is 18+15.65 and 24+04.73, the
distance between the two stations is 2404.7301815.65 = 589.08 m.
Profile Level Notes
The level notes kept for profile levelling are similar to those for differential levelling
except for the addition of a separate column for intermediate foresights (IFS) which
is used for recording side shots or ground sights. Although a single column could be
used to record foresight and intermediate foresight readings, many surveyors prefer
to record intermediate foresights separately. This is done to allow easier reading and
interpreting of the notes. A typical set of profile level notes is shown in figure.
On the left-hand page, all the six columns of the standard form of level notes are used.
The column headings indicated include the following: Station, Backsight, Foresight,
Intermediate Foresight, and Elevation. These column headings are usually arranged
in the sequence as given. Accepted abbreviations are normally used to identify each
column. Remarks or concise descriptions for each bench mark, station, and other
relevant information are indicated on the right-hand page. Simple sketches which will
better explain the levelling work performed may also be shown with the remark.
The process of computing heights of instrument and elevation of points and stations
along a profile level route is exactly the same as in differential leveling. Such
computations should be made on the level notebook as the survey progresses. From
a recorded set of profile level notes, differences in elevation between points and
stations along the level route can be determined. For instance, the difference between
the sum of all backsights and the sum of all foresights is equal to the error of closure,
or equal to the difference in elevation between the initial bench mark and the final
point. Also, the intermediate foresight reading subtracted from the height of
instrument gives the ground elevation of a plus station. And at one setup of the
instrument, the difference between the elevation of any two points is equal to the
difference between the foresights taken on these points.
It is customary to always show an arithmetic check for each set of profile level notes.
As done in differential leveling, the sum of all backsight reading is added to the
elevation of the initial or reference bench mark. From the sum of these two quantities,
the sum of all foresight readings is then subtracted. If the resulting difference is equal
to the elevation of the final bench mark or the last station indicated in the level notes,
the additions and subtractions performed are assumed to have been done correctly.
These computations are shown at the lower portion of the level notes.
In most instances, backsight and foresight readings on established benchmarks are
recorded to the nearest hundredth of a meter (cm). The intermediate foresights are
recorded to the tenths of a meter (dm) since they are used only for plotting the profile
and have no relation to the determination of benchmark elevations.
Plotting Profiles
The plotted profile should give an accurate and useful representation of the existing
ground configurations. It is plotted on a linear scale which shows the correct length
of the surveyed line. The profile is plotted as a curve in which the distance of each
station from the point of beginning is shown on the abscissa and the elevation of each
station is plotted on the ordinate. As shown in figure a typical profile of the center line
of a road.
They may be used to determine depths of cut and fill such as on proposed roads and
railroads. Profiles are also used when designing the most economical grade location
and planning out grade crossings. They are also referred to when locating and
positioning tunnels, pipelines, irrigation, canals, and sewer lines.
Profiles are plotted on a special graph paper called a profile sheet. It has horizontal
and vertical lines printed in blue, green, or orange to represent distances both
horizontally and vertically. The profile is plotted by using the lines of the profile sheet
as scale. It is first drawn in pencil and inked later to a finished copy. Heavy grade
paper is used if only a single copy of the profile is needed. However, if additional
copies of the profile are required either tracing paper or tracing cloth is used to allow
reproduction by blue or white prints.
The elevations of ground points on the profile are usually plotted and connected
freehand with a smooth heavy line. The resulting profile is expected to be a better and
more accurate representation of actual ground irregularities than by using straight
lines to connect ground points. It should include all other pertinent information which
are likely ot be required during the actual phase of construction. The following
information should be indicated:
a) Plotting Scales
The horizontal and vertical scales used in plotting the profile should be properly
identified.
b) Stationing
The full stations along the level route should be indicated to portray the overall linear
length of the line.
c) Reference Points
Important reference points and other ground points which need to be emphasized or
pointed out should easily seen.
d) Marginal Information
Any other valuable information which should explain the profile better or in detail
should be indicated. Such information may include the following: a title to identify the
leveling operation, location of the profile taken, what the profile represents, the date
it was surveyed, names of the survey party members, and the name of the draftsman
who plotted the profile.
To portray the ground profile, a certain balance between the horizontal and vertical
scale is necessary. The vertical scale is always made much larger than the horizontal
scale to accentuate or make more pronounced the differences in elevation. This
referred to as vertical exaggeration. Usually, a ratio of 10:1 is used. The ratio of
exaggeration depends upon:
a) Use of the Profile
If a highly accurate representation of vertical dimensions is required, the vertical
scale should be increased.
b) Character of the Terrain
In order to portray the irregularities of flat or fairly level ground, a greater amount of
vertical exaggerations should be used. Correspondingly, a small ratio is used for
rugged terrain where differences in elevation between ground points are significantly
large.
c) Horizontal Scale
The horizontal scale is often chosen to fit the plotted profile into a convenient size of
paper. If the selected horizontal scale is drawn large, a smaller vertical scale is used.
Consequently, a smaller horizontal scale would require a greater amount of vertical
exaggeration.
SAMPLE PROBLEMS:
E8-3 LOCATING STATIONS
Work out the following problems regarding points and stations along a profile level
route.
Solution:
a) A turning point along a profile level route measures 126.44 m beyond station
8+24.50. Determine the stationing of this turning point.
𝑑𝑡𝑝 = 126.44 𝑚
𝑑𝑠𝑡𝑎 = 8 + 24.50 = 824.50 𝑚
𝐷 = 𝑑𝑡𝑝 + 𝑑𝑠𝑡𝑎 = 824.50 + 126.44 = 950.94 𝑚
𝑑𝑡𝑝 = 83.45 𝑚
𝑑𝑠𝑡𝑎 = 8 + 24.50 = 824.50 𝑚
𝐷 = 𝑑𝑠𝑡𝑎 − 𝑑𝑡𝑝 = 824.50 − 83.45 = 741.05 𝑚
Solution:
Computation of HI′ and Elevation of Stations
125.50 + 0.95 = 126.45 (𝐻𝐼1 )
126.45 − 3.0 = 123.5 (𝐸𝑙𝑒𝑣 𝑆𝑡𝑎 0 + 00)
126.45 − 2.3 = 124.2 (𝐸𝑙𝑒𝑣 𝑆𝑡𝑎 0 + 10)
126.45 − 0.64 = 125.81 (𝐸𝑙𝑒𝑣 𝑇𝑃1 )
125.81 + 3.13 = 128.94 (𝐻𝐼2 )
128.94 − 2.7 = 126.2 (𝐸𝑙𝑒𝑣 𝑆𝑡𝑎 0 + 22)
128.94 − 2.8 = 126.1 (𝐸𝑙𝑒𝑣 𝑆𝑡𝑎 0 + 30.5)
128.94 − 3.1 = 125.8 (𝐸𝑙𝑒𝑣 𝑆𝑡𝑎 0 + 34.2)
128.94 − 0.5 = 128.4 (𝐸𝑙𝑒𝑣 𝑆𝑡𝑎 0 + 39.3)
128.94 − 0.8 = 128.1 (𝐸𝑙𝑒𝑣 𝑆𝑡𝑎 0 + 42.5)
128.94 − 1.28 = 127.66 (𝐸𝑙𝑒𝑣 𝑇𝑃2 )
127.66 + 2.16 = 129.82 (𝐻𝐼3 )
129.82 − 0.9 = 128.9 (𝐸𝑙𝑒𝑣 𝑆𝑡𝑎 0 + 45)
129.82 − 0.9 = 128.9 (𝐸𝑙𝑒𝑣 𝑆𝑡𝑎 0 + 48.6)
Arithmetic Check:
125.50 + 8.41 − 9.78 = 𝟏𝟐𝟒. 𝟏𝟑 𝒎
8.3 Trigonometric Leveling
Trigonometric leveling or indirect leveling is defined as the determination of
difference in elevation from observed vertical angle and either horizontal or inclined
distances. Vertical measurements determined by trigonometric methods are only
approximate unless the observed vertical angles and the required distances are
precisely measured. This method of leveling is used extensively when undertaking
topographic surveys over rugged or rolling terrain since it provides a rapid means of
determining vertical distances and elevation of points.
In figure, illustrates a typical setup for trigonometric leveling where the observed
vertical angle is α and the known horizontal and inclined distances, measured in
meters, are d and s, respectively. The height of the instrument above point A is
denoted as H.I., and the reading on the rod held at the distant point B is RR. The
vertical distance, V, could be determined in two ways as follows:
𝑉 = 𝑑 (𝑡𝑎𝑛𝛼 ) ; 𝑉 = 𝑠(𝑠𝑖𝑛𝛼)
Correspondingly, the difference in elevation between A and B may be determined by
any of the following equations:
𝐷𝐸𝑎𝑏 = 𝑑 (𝑡𝑎𝑛𝛼 ) + ℎ. 𝑖. −𝑅𝑅
𝐷𝐸𝑎𝑏 = 𝑠(𝑠𝑖𝑛𝛼 ) + ℎ. 𝑖. −𝑅𝑅
If the elevation of A is known, the elevation of B can then be determined as follows:
𝐸𝑙𝑒𝑣 𝐵 = 𝐸𝑙𝑒𝑣 𝐴 + 𝐷𝐸𝑎𝑏
This method of determining difference in elevation should be limited only to
horizontal distances not exceeding 300 meters. When distances are much longer, the
combined effects of earth’s curvature and refraction must be considered and applied
in the calculation of vertical distances. It must also be understood that in
trigonometric leveling the observed vertical angle may either be an angle of elevation
(+ sight) or angle of depression (- sight). An upward positive sight is illustrated in
figure. In previous equations will be slightly different if a downward or negative sight
is observed. The correct equations can easily be determined by simply drawing a
sketch of a particular setup.
When trigonometric leveling is employed in much longer sights, the slope distance is
measured using EDM instruments and precise optical theodolites are utilized for
measuring vertical angles. Also, the correction for the combined effects of curvature
and refraction is added when the vertical angle is an upward sight; it is subtracted
when a downward sight is observed. For the illustrated setup in figure, and assuming
that long sights are involved, the difference in elevation between points A and B
would be then be written as:
𝑑 2
𝐷𝐸𝑎𝑏 = 𝑑 (𝑡𝑎𝑛𝛼 ) + ℎ. 𝑖. −𝑅𝑅 + 0.0675 ( )
1000
𝑑 2
( )
𝐷𝐸𝑎𝑏 = 𝑠 𝑠𝑖𝑛𝛼 + ℎ. 𝑖. −𝑅𝑅 + 0.0675 ( )
1000
𝑉
sin(𝜃 ) =
; 𝑉 = 𝑠(𝑠𝑖𝑛𝜃 )
𝑠
𝑉 = 823.29 𝑚(sin(13°45′)) = 195.68 𝑚
𝑑 = 𝑠(𝑐𝑜𝑠𝜃) = 823.29 𝑚(𝑐𝑜𝑠13°45′ ) = 799.70 𝑚
𝑑 2 799.70 𝑚 2
ℎ𝑐𝑟 = 0.0675 ( ) = 0.0675 ( ) = 0.04 𝑚
1000 1000
𝐷𝐸𝑎𝑏 = ℎ. 𝑖. +𝑉 − 𝑅𝑅 + ℎ𝑐𝑟 = 1.35 𝑚 + 195.68 𝑚 − 1.23 𝑚 + 0.04 𝑚 = 𝟏𝟗𝟓. 𝟖𝟒 𝒎
𝐸𝑙𝑒𝑣 𝐵 = 𝐸𝑙𝑒𝑣 𝐴 + 𝐷𝐸𝑎𝑏 = 123.65 𝑚 + 195.84 𝑚 = 𝟑𝟏𝟗. 𝟒𝟗 𝒎
8.4 Inverse Leveling
In the conventional method of differential leveling we normally see to it that the line
of sight of the instrument is always higher than any point on which the leveling rod is
held. However, this is not always the case. It is sometimes necessary to determine the
elevation of a point located higher than the telescope of the instrument. For example,
Solution:
𝐻𝐼1 = 𝐸𝑙𝑒𝑣 𝐴 + 𝐵𝑆 = 528.25 𝑚 + 2.05 𝑚 = 530.30 𝑚
𝐸𝑙𝑒𝑣𝑤 = 𝐻𝐼1 − (−𝐹𝑆) = 530.30 𝑚 − (−2.60 𝑚) = 532.90 𝑚
𝐻𝐼2 = 𝐸𝑙𝑒𝑣𝑤 + (−𝐵𝑆) = 532.90 𝑚 + (−3.92 𝑚) = 528.98 𝑚
𝐸𝑙𝑒𝑣 𝐵 = 𝐻𝐼2 − 𝐹𝑆 = 528.98 𝑚 − 2.68 𝑚 = 𝟓𝟐𝟔. 𝟑𝟎 𝒎
𝐴𝑟𝑖𝑡ℎ𝑚𝑒𝑡𝑖𝑐 𝐶ℎ𝑒𝑐𝑘:
M8-1 DIFFERENTIAL LEVELING. Preparing and complete the differential level notes
for the information shown in the accompanying figure. Include the customary
arithmetic check.
References
La Putt, J.P. (1987). Elementary Surveying (3rd ed.). Baguio City, Philippines: Baguio
Research & Publishing Center
Disclaimer
This module may contain copyrighted material, the use of which may not have been
specifically authorized by the copyright owner. However, this module was created
and made to serve as a tool for educational purposes only and will be distributed
without any profit.