M/S RAB NAWAZ CO.
EXTENSION OF MEHMOOD TEXTILE MILLS (UNIT-III) MUZAFFARGARH- MULTAN
Tentative / Proposed Construction Schedule for Spinning Unit & A.C Plant
Days Jul-23 Jul-23 Jun-22 Jul-22 Aug-22 Sep-22 Jul-23 Jul-23 Jun-22 Jul-22 Aug-22 Sep-22
Sr. No. Description / Activity
Consumed 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4
1 Mobilization 2
Clearance of Site
2 (By Client) 7
3 Layout, Excavation & Compaction of Bed for P.C.C. 7
4 Footing P.C.C 3
5 Frame Work of Building upto Plinth Level 28
6 Construction of Situ Wall, Plinth Beam, & Column above F.F.L 45
7 Construction of Air Ducts & Compaction of Floor and P.C.C. 28
8 Formwork & Steel Fixing for Roof & Beams Grid 12-09 7
9 Slab & Beam Concrete Pouring Grid 12-09 1
10 Formwork & Steel Fixing for Roof & Beams Grid 9-5 7
11 Slab & Beam Concrete Pouring Grid 9-5 1
12 Brick Masonry of Building 30
13 Plastering & Stcuk Pointing of Building 30
14 Fixing of Doors & Widows / Ventilators 7
15 Painting of Building 21
16 Tile Fixing 14
17 Roof Treatment 21
18 Cleaning of Site. 7
EXTENSION OF MEHMOOD TEXTILE MILLS (UNIT-III) MUZAFFARGARH- MULTAN
Tentative / Proposed Construction Schedule for Spinning Unit & A.C Plant BALANCE ACTIVITIES
Days Sep-22 Oct-22
Sr. No. Description / Activity Consumed Start Date End Date REMARKS
2 3 4 1 2 3
1 Completion of Granolitic Floors 15 - 25.09.22 Work is in Progress.
2 Paint Work of Building 25 - 05.10.22 Work is in Progress.
3 Roof Treatment 25 20.09.22 15.10.22
4 Completion of S.A Ducts with A.C Frame & Rotary 20 - 20.10.22 Work is in Progress.
EXTENSION OF MEHMOOD TEXTILE MILLS (UNIT-III) MUZAFFARGARH- MULTAN
Tentative / Proposed Construction Schedule for Construction of Stitching Unit (26000 Sft) at MTM Muzaffargarh
Days Jul-23 Aug-23 23-Sep
Sr. No. Description / Activity Consume
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4
d
1 Mobilization 1
Clearance of Site
2 (By Client) 2
3 Layout, Excavation & Compaction of Bed for P.C.C. 5
4 Footing P.C.C 6
5 Footing Concrete 12
6 Column Padestal upto Plinth 15
7 Back Filling of Foundations 12
8 Column Concrete above Plinth 15
9 Brickwork Below Plinth 10
10 Casting of Plinth Beam 7
11 Brick Work above Plinth 14
12 Casting of Pad Beam 10
13 Internal Plastering for Walls 10
14 Compaction for P.C.C Floor 3
15 3" P.C.C Flooring 7
16 1st Installation of Pre-Cast Slab 4
17 3" P.C.C Flooring 7
18 2nd Installation of Pre-Cast Slab 4
19 3" Thick R.C.C Floor 14
20 Roof Treatment 15
21 Closing & Handing 1
NOTE: No work will be carried out at Site on 24.07.2023 due to local holiday of Muharram as notified by Government.