0% found this document useful (0 votes)
433 views3 pages

Construction Schedule

The document provides a tentative construction schedule for extending Mehmood Textile Mills (Unit III) in Muzaffargarh, Multan. The schedule outlines 21 activities from July 2023 through September 2023, including mobilization, site clearance, excavation, concrete work, brick masonry, plastering, painting, and roof treatment. It also provides a balance activities schedule for finishing work in September and October 2022, including flooring, ductwork, and roof treatment. The schedule is intended to guide completion of the textile mill extension and a proposed construction schedule is also included for a new 26,000 square foot stitching unit at the same location from July through September 2023.

Uploaded by

rabnawaz.company
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
433 views3 pages

Construction Schedule

The document provides a tentative construction schedule for extending Mehmood Textile Mills (Unit III) in Muzaffargarh, Multan. The schedule outlines 21 activities from July 2023 through September 2023, including mobilization, site clearance, excavation, concrete work, brick masonry, plastering, painting, and roof treatment. It also provides a balance activities schedule for finishing work in September and October 2022, including flooring, ductwork, and roof treatment. The schedule is intended to guide completion of the textile mill extension and a proposed construction schedule is also included for a new 26,000 square foot stitching unit at the same location from July through September 2023.

Uploaded by

rabnawaz.company
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

M/S RAB NAWAZ CO.

EXTENSION OF MEHMOOD TEXTILE MILLS (UNIT-III) MUZAFFARGARH- MULTAN

Tentative / Proposed Construction Schedule for Spinning Unit & A.C Plant

Days Jul-23 Jul-23 Jun-22 Jul-22 Aug-22 Sep-22 Jul-23 Jul-23 Jun-22 Jul-22 Aug-22 Sep-22
Sr. No. Description / Activity
Consumed 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4
1 Mobilization 2
Clearance of Site
2 (By Client) 7
3 Layout, Excavation & Compaction of Bed for P.C.C. 7
4 Footing P.C.C 3
5 Frame Work of Building upto Plinth Level 28
6 Construction of Situ Wall, Plinth Beam, & Column above F.F.L 45
7 Construction of Air Ducts & Compaction of Floor and P.C.C. 28
8 Formwork & Steel Fixing for Roof & Beams Grid 12-09 7
9 Slab & Beam Concrete Pouring Grid 12-09 1
10 Formwork & Steel Fixing for Roof & Beams Grid 9-5 7
11 Slab & Beam Concrete Pouring Grid 9-5 1
12 Brick Masonry of Building 30
13 Plastering & Stcuk Pointing of Building 30
14 Fixing of Doors & Widows / Ventilators 7
15 Painting of Building 21
16 Tile Fixing 14
17 Roof Treatment 21
18 Cleaning of Site. 7
EXTENSION OF MEHMOOD TEXTILE MILLS (UNIT-III) MUZAFFARGARH- MULTAN

Tentative / Proposed Construction Schedule for Spinning Unit & A.C Plant BALANCE ACTIVITIES

Days Sep-22 Oct-22


Sr. No. Description / Activity Consumed Start Date End Date REMARKS
2 3 4 1 2 3
1 Completion of Granolitic Floors 15 - 25.09.22 Work is in Progress.

2 Paint Work of Building 25 - 05.10.22 Work is in Progress.

3 Roof Treatment 25 20.09.22 15.10.22

4 Completion of S.A Ducts with A.C Frame & Rotary 20 - 20.10.22 Work is in Progress.
EXTENSION OF MEHMOOD TEXTILE MILLS (UNIT-III) MUZAFFARGARH- MULTAN
Tentative / Proposed Construction Schedule for Construction of Stitching Unit (26000 Sft) at MTM Muzaffargarh

Days Jul-23 Aug-23 23-Sep


Sr. No. Description / Activity Consume
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4
d
1 Mobilization 1

Clearance of Site
2 (By Client) 2

3 Layout, Excavation & Compaction of Bed for P.C.C. 5

4 Footing P.C.C 6

5 Footing Concrete 12

6 Column Padestal upto Plinth 15

7 Back Filling of Foundations 12

8 Column Concrete above Plinth 15

9 Brickwork Below Plinth 10

10 Casting of Plinth Beam 7

11 Brick Work above Plinth 14

12 Casting of Pad Beam 10

13 Internal Plastering for Walls 10

14 Compaction for P.C.C Floor 3

15 3" P.C.C Flooring 7

16 1st Installation of Pre-Cast Slab 4

17 3" P.C.C Flooring 7

18 2nd Installation of Pre-Cast Slab 4

19 3" Thick R.C.C Floor 14

20 Roof Treatment 15

21 Closing & Handing 1

NOTE: No work will be carried out at Site on 24.07.2023 due to local holiday of Muharram as notified by Government.

You might also like