Updated Schedule - Sample
Updated Schedule - Sample
Updated Schedule - Sample
Primary Baseline Remaining Work Baseline Milestone Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work Milestone © Oracle Corporation
AVR - Baseline Schedule Rev.08 Update as of 19-Jan-24 Before
Event - Longest Path
Activity ID Activity Name Original Early Start Early Finish Total Float 2023 2024 2025 2026 2027
Duration Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
PR-ARC-MD-14340 Materials Fabrication, Shipment & Delivery - Skylights Steel Structure - Skylight S16 98 22-Aug-24 27-Nov-24 85
PR-ARC-MD-14330 Materials Fabrication, Shipment & Delivery - Skylights Steel Structure - Skylight S18 98 12-Jul-24 17-Oct-24 75
Glass Skylights 305 07-Apr-24 05-Feb-25 150
Clerestory Curtainwall 220 08-Jul-24 12-Feb-25 101
ETFE Skylights 260 20-Aug-24 06-May-25 166
Canopies 240 18-Sep-24 15-May-25 204
The Souk 776 19-Jan-24 19-Jul-25 118
Grand Avenue/Urban Walk 901 19-Jan-24 18-Oct-25 89
Prestige/Electra 777 19-Jan-24 26-Nov-25 55
Oasis 768 19-Jan-24 07-Oct-25 105
Grand Plaza 1059 19-Jan-24 06-Nov-25 89
External Areas Works 618 20-Jan-24 17-Sep-25 106
Module 6 & Facade (MEP) 252 11-Nov-24 20-Jul-25 164
Mock-Up Schedule 621 19-Jan-24 05-Nov-24 308
AOR / TIE IN 314 19-Jan-24 26-Jul-24 410
Provisional Sum Items (Bill no.09) 1234 19-Jan-24 17-Feb-26 42
Primary Baseline Remaining Work Baseline Milestone Page 2 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work Milestone © Oracle Corporation