Yudhi Agustia

From: Aditya Putra <[email protected]>


Sent: 18 September 2023 17:14
To: [email protected]
Subject: FW: Scan Approved RC-1, 2, 3, 4 - Penutupan Jalan

From: Andriyas [JPK‐Utara] <[email protected]>


Sent: 23 May 2023 9:00
To: 'Fadhilah Maulana' <[email protected]>; Sukri Mulyadi [JPK‐Utara] <[email protected]>; Defriwilman [JPK‐Utara] <[email protected]>; 'Nur Rahman' <[email protected]>;
[email protected]; Andriyas [JPK‐Utara] <[email protected]>; Nova Rizon [JPK‐Utara] <[email protected]>; Safruddin [JPK‐Utara] <[email protected]>; Farian Albajili [JPK‐Utara] <[email protected]>
Subject: Fwd: Scan Approved RC‐1, 2, 3, 4 ‐ Penutupan Jalan

Dh..
Untuk informasi

Salam
Andriyas # 122021
Construction Supervision FE North Team
Tripatra ‐ Pertamina Hulu Rokan
Mobile 0813‐7151‐8753
Pari 2 Office
Email : [email protected]

Dari: Ridwan Amba [JPK‐Utara] <[email protected]>


Terkirim: Kamis, 18 Mei 2023 19.05
Kepada: Andriyas [JPK‐Utara] <[email protected]>; Sukri Mulyadi [JPK‐Utara] <[email protected]>; [email protected] <[email protected]>; [email protected]
<[email protected]>; Defriwilman [JPK‐Utara] <[email protected]>
Cc: Fauzi [JPK‐Utara] <[email protected]>; 'Wisnu PS' <[email protected]>
Subjek: Fwd: Scan Approved RC‐1, 2, 3, 4 ‐ Penutupan Jalan

Info persetujuan utk road crossing 1,2 & 3, jika ada perubahan silakan infokan utk direvisi,

Salam, RA

Dapatkan Outlook untuk Android

From: Saiful Andhi <[email protected]>


Sent: Wednesday, May 17, 2023 4:08:05 PM
To: Faisal <[email protected]>
Cc: [email protected] <[email protected]>; Triyanto <[email protected]>; Indra Setiawan <[email protected]>; Akmal <[email protected]>; Ridwan Amba [JPK‐Utara] <[email protected]>;
Eko Aji Prabowo <[email protected]>; Rangga Budi Aditya <[email protected]>; Bangun Prayogi <[email protected]>; Sutarno <[email protected]>; Ilham <[email protected]>;
Santoso <[email protected]>; Abdi Yustita Marbun <[email protected]>; Slamet Irianto <[email protected]>; Hardiyanto <[email protected]>; Isdon Handoko
<[email protected]>
Subject: RE: Scan Approved RC‐1, 2, 3, 4 ‐ Penutupan Jalan

[EXTERNAL EMAIL] Be alert of any suspicious message, attachment, link, or request for sensitive information. If any or in doubt, please contact your IT Service Desk.

Selamat sore Komandan.


Siap security akan back up kegiatan tersebut .
1
Terimakasih
Salam
Saiful

Sent from Android device

Pada tanggal 17 Mei 2023 15.18, Faisal <[email protected]> menulis:

Pak Saiful dan Aswin,

Mohon support keamanan untuk kegiatan ini.

Thank’s

Faisal

From: Rangga Budi Aditya <[email protected]>


Sent: Wednesday, May 17, 2023 3:03 PM
To: Bangun Prayogi <[email protected]>; Sutarno <[email protected]>; Ilham <[email protected]>; Santoso <[email protected]>; Abdi Yustita Marbun <[email protected]>; Faisal
<[email protected]>; Slamet Irianto <[email protected]>; Hardiyanto <[email protected]>
Cc: Triyanto <[email protected]>; Indra Setiawan <[email protected]>; Akmal <[email protected]>; Ridwan Amba [JPK‐Utara] <[email protected]>; Eko Aji Prabowo
<[email protected]>
Subject: RE: Scan Approved RC‐1, 2, 3, 4 ‐ Penutupan Jalan

Mas @Bangun Prayogi ysh,

1. Fabrikasi spool dilakukan di luar area road crossing dan hanya menyisakan welding di ujung pipa.
2. Sesuai kontrak, kondisi jalan akan dikembalikan ke kondisi semula oleh PT WKS.

Mas @Slamet Irianto & mas @Faisal,

Mohon supportnya terkait pekerjaan Road Crossing Bekasap Off Plot sesuai TMP terlampir.

Terima kasih.

Salam,

Rangga Budi Aditya

PHR WK Rokan-FE-FIC
2
From: Bangun Prayogi <[email protected]>
Sent: Wednesday, May 17, 2023 1:39 PM
To: Rangga Budi Aditya <[email protected]>; Sutarno <[email protected]>; Ilham <[email protected]>; Santoso <[email protected]>; Abdi Yustita Marbun <[email protected]>; Faisal
<[email protected]>; Slamet Irianto <[email protected]>; Hardiyanto <[email protected]>
Cc: Triyanto <[email protected]>; Indra Setiawan <[email protected]>; Akmal <[email protected]>; Ridwan Amba [JPK‐Utara] <[email protected]>; Eko Aji Prabowo
<[email protected]>
Subject: RE: Scan Approved RC‐1, 2, 3, 4 ‐ Penutupan Jalan

Mas Rangga,

Concern saya ada di spot 1 dan 3, untuk yg 2 spt biasa mohon dibantu utk akses kawan‐kawan operasi saat cek lokasi.

Untuk spot 1 dan 3;

1. mohon dioptimize fabrikasi spool di luar area RC ini sehingga pada saat penutupan ini bisa maksimalkan pekerjaan lowering pipa/spool hasil fabrikasi. Harapannya waktu penutupan jalan bisa diminimize

2. Libatkan team Corsec dan Security karena akan banyak parties yg akan terdampak baik masyarakat, project, operation, D&C, maintenance (IM, FUM) dll.

3. Nanti setelah pekerjaan, bagaimana perbaikan hasil open cut jalan ini? Harapannya bisa dikembalikan seperti kondisi semula (aspal, padat) sehingga resiko/hazard berkendara terkait jalan rusak sisa open cut bisa ditiadakan.

Kawan‐kawan FON, Corsec, IM, Security, FYI/A

bangun

From: Rangga Budi Aditya <[email protected]>


Sent: Wednesday, May 17, 2023 12:22 PM
To: Bangun Prayogi <[email protected]>
Cc: Triyanto <[email protected]>; Indra Setiawan <[email protected]>; Akmal <[email protected]>; Ridwan Amba [JPK‐Utara] <[email protected]>; Eko Aji Prabowo
<[email protected]>
Subject: FW: Scan Approved RC‐1, 2, 3, 4

Mas @Bangun Prayogi ysh,

Kami dari tim Project WIP rencana akan melakukan pekerjaan road crossing di area Bekasap Off Plot dengan rincian sebagai berikut :

3
1. Road Crossing (RC#1) tanggal 24 ‐ 26 May 2023 (buka tutup jalan)
2. Road Crossing (RC#2) tanggal 20 – 23 May 2023 (buka tutup jalan)
3. Road Crossing (RC#3) tanggal 27 ‐ 28 May 2023 (buka tutup jalan)

Mohon review dan approval TMP untuk pekerjaan tersebut (terlampir) untuk selanjutnya akan kami ajukan ke tim IT agar dapat dibuatkan Broadcast.

Terima kasih.

Salam,

Rangga Budi Aditya

PHR WK Rokan-FE-FIC

From: Ridwan Amba [JPK‐Utara] <[email protected]>


Sent: Wednesday, May 17, 2023 10:24 AM
To: Rangga Budi Aditya <[email protected]>; Aditya Putra <[email protected]>; [email protected]; 'Fadhilah Maulana' <[email protected]>
Cc: wisnups <[email protected]>; [email protected]; Andriyas [JPK‐Utara] <[email protected]>; Akmal <[email protected]>; Indra Setiawan <[email protected]>; Defriwilman [JPK‐
Utara] <[email protected]>; Fauzi [JPK‐Utara] <[email protected]>; Andri Apriandi [JPK‐Utara] <[email protected]>; Ridwan Pohan [JPK‐Utara] <[email protected]>; Triyanto <[email protected]>;
Sukri Mulyadi [JPK‐Utara] <[email protected]>
Subject: RE: Scan Approved RC‐1, 2, 3, 4

Mas Rangga,

Terlampir untuk data UG Facility termasuk SOP di RC#1,2 & 3, sedangkan untuk RC#4 akan menyusul setelah clear data nya,

Untuk Rencana pelaksanaan pekerjaan install Road Crossing RC#1,2 3 adalah sbb:

1. Road Crossing (RC#1) : TMP Buka Tutup : 24 ‐ 26 May 2023


2. Road Crossing (RC#2) : TMP Buka Tutup : 20 – 23 May 2023
3. Road Crossing (RC#3) : TMP BukaTutup : 27 ‐ 28 May 2023

Terimakasih banyak atas perhatian dan Kerjasamanya

The link ed image cannot be


display ed. The file may hav e
been mov ed, renamed, or
deleted. Verify that the link
points to the correct file and
location.

Ridwan Amba#122009

4
Lead Construction Non Well Tripatra Engineering & Construction (JPK‐Utara)

Facility Improvement Construction & Program Construction Team

Pertamina Hulu Rokan Project – Riau – Indonesia

Peri#2 Office – Room – P2‐10D – KM 125 – Duri

0812‐7019‐1360 : [email protected]

From: Rangga Budi Aditya <[email protected]>


Sent: Wednesday, May 17, 2023 8:35 AM
To: Ridwan Amba [JPK‐Utara] <[email protected]>; Aditya Putra <[email protected]>; Triyanto <[email protected]>; [email protected]; 'Fadhilah Maulana' <[email protected]>
Cc: wisnups <[email protected]>; [email protected]; Andriyas [JPK‐Utara] <[email protected]>; Akmal <[email protected]>; Indra Setiawan <[email protected]>; Defriwilman [JPK‐
Utara] <[email protected]>; Fauzi [JPK‐Utara] <[email protected]>; Andri Apriandi [JPK‐Utara] <[email protected]>; Ridwan Pohan [JPK‐Utara] <[email protected]>
Subject: Re: Scan Approved RC‐1, 2, 3, 4

[EXTERNAL EMAIL] Be alert of any suspicious message, attachment, link, or request for sensitive information. If any or in doubt, please contact your IT Service Desk.

Pak Ridwan,

Mohon lampirkan SOP dan dokumen pendukung yg lain untuk persetujuan UG Detection.

Silakan lampirkan TMP untuk pekerjaan road crossing ini.

Terima kasih.

Salam

Rangga Budi Aditya

From: Ridwan Amba [JPK‐Utara] <[email protected]>


Sent: Tuesday, 16 May 2023, 08:37
To: Aditya Putra <[email protected]>; Rangga Budi Aditya <[email protected]>; Triyanto <[email protected]>; [email protected] <[email protected]>; 'Fadhilah Maulana'
<[email protected]>
Cc: wisnups <[email protected]>; [email protected] <[email protected]>; Andriyas [JPK‐Utara] <[email protected]>; Akmal <[email protected]>; Indra Setiawan
5
<[email protected]>; Defriwilman [JPK‐Utara] <[email protected]>; Fauzi [JPK‐Utara] <[email protected]>; Andri Apriandi [JPK‐Utara] <[email protected]>; Ridwan Pohan [JPK‐Utara]
<[email protected]>
Subject: RE: Scan Approved RC‐1, 2, 3, 4

Mas Aditya P,

Terimakasih banyak informasi untuk rencana excavation Road Crossing (RC#1,2,3 & 4) di Bekasap Off Plot Area dan kan kita kordinasikan dengan PHR FIC untuk mendapatkan persetujuan,

Mas Rangga/Mas Triyanto,

Mohon support nya untuk bisa direviw dan persetujuan rencana excavation Road Crossing di Bekasap Off Plot sbb:

1. Road Crossing #1 : (TMP Buka Tutup)


Penggalian dilakukan dengan menggunakan equipment kecuali di Area yang dekat dengan existing Pipeline 12” (700 mm dari pinggir galian) dilakukan dengan manual,
Methode exwcution dalam peklaksnaan nantinya adalah menggunakan TMP dengan menggunakan setengah badan jalan untuk bisa dilalui,
The link ed image cannot be The link ed image cannot be
display ed. The file may hav e display ed. The file may hav e
been mov ed, renamed, or been mov ed, renamed, or
deleted. Verify that the link deleted. Verify that the link
points to the correct file and points to the correct file and
location. location.

2. Road Crossing#2 (RC#2) : (TMP Buka tutup):


Penggalian dilakukan dengan menggunakan equipment kecuali di Area yang dekat dengan existing Pipeline 12” (500 mm dari pinggir galian) dilakukan dengan manual,
Methode exwcution dalam peklaksnaan nantinya adalah menggunakan TMP dengan menggunakan setengah badan jalan untuk bisa dilalui,

The link ed image cannot be The link ed image cannot be


display ed. The file may hav e display ed. The file may hav e
been mov ed, renamed, or been mov ed, renamed, or
deleted. Verify that the link deleted. Verify that the link
points to the correct file and points to the correct file and
location. location.

3. Road Crossing#3 (RC#3) : Full Jalan ditutup saat execution,


Penggalian dilakukan dengan menggunakan equipment kecuali di Area yang dekat dengan existing Pipeline 12” (700 mm dari pinggir galian) dilakukan dengan manual
The link ed image cannot be The link ed image cannot be
display ed. The file may hav e display ed. The file may hav e
been mov ed, renamed, or been mov ed, renamed, or
deleted. Verify that the link deleted. Verify that the link
points to the correct file and points to the correct file and
location. location.

4. Road Crossing#4 (RC#4) : TMP Buka tutup jalan,


Dari data dibawah ini, ada lokasi menggunakan equipment dan dan harus manual, terutama dengan berdekatan exisitng facility seperti dibawah ini
The link ed image cannot be The link ed image cannot be The link ed image cannot be
display ed. The file may hav e display ed. The file may hav e display ed. The file may hav e
been mov ed, renamed, or been mov ed, renamed, or been mov ed, renamed, or
deleted. Verify that the link deleted. Verify that the link deleted. Verify that the link
points to the correct file and points to the correct file and points to the correct file and
location. location. location.

The link ed image cannot be The link ed image cannot be


display ed. The file may hav e display ed. The file may hav e
been mov ed, renamed, or been mov ed, renamed, or
deleted. Verify that the link deleted. Verify that the link
points to the correct file and points to the correct file and
location. location.

Mas Aditya/bang Jecky,

Silakan persiapkan TMP nay serta termasuk schedule dalam pelaksanaan nya

Terimakasih banyak atas perhatian dan Kerjasamanya

6
The link ed image cannot be
display ed. The file may hav e
been mov ed, renamed, or
deleted. Verify that the link
points to the correct file and
location.

Ridwan Amba#122009

Lead Construction Non Well Tripatra Engineering & Construction (JPK‐Utara)

Facility Improvement Construction & Program Construction Team

Pertamina Hulu Rokan Project – Riau – Indonesia

Peri#2 Office – Room – P2‐10D – KM 125 – Duri

0812‐7019‐1360 : [email protected]

From: Aditya Putra <[email protected]>


Sent: Monday, May 15, 2023 9:35 PM
To: Ridwan Amba [JPK‐Utara] <[email protected]>
Cc: 'Wisnu PS' <[email protected]>; [email protected]; Andriyas [JPK‐Utara] <[email protected]>; [email protected]
Subject: RE: Scan Approved RC‐1, 2, 3, 4

[EXTERNAL EMAIL] Be alert of any suspicious message, attachment, link, or request for sensitive information. If any or in doubt, please contact your IT Service Desk.

Dear pak Ridwan Amba,

FYR

Terlampir scan RC1, 2, 3, 4 yang berwarna

Thank You & Best regards

Aditya

From: Ridwan Amba [JPK‐Utara] <[email protected]>


Sent: 15 May 2023 9:57

7
To: Aditya Putra <[email protected]>
Cc: 'Wisnu PS' <[email protected]>; [email protected]; Andriyas [JPK‐Utara] <[email protected]>; [email protected]
Subject: RE: Scan Approved RC‐1, 2, 3, 4

Mas Aditya,

Tolong data diperjelas dengan PDF warna,karena tidak terbaca data yang dikirimkan

The link ed image cannot be The link ed image cannot be The link ed image cannot be The link ed image cannot be
display ed. The file may hav e display ed. The file may hav e display ed. The file may hav e display ed. The file may hav e
been mov ed, renamed, or been mov ed, renamed, or been mov ed, renamed, or been mov ed, renamed, or
deleted. Verify that the link deleted. Verify that the link deleted. Verify that the link deleted. Verify that the link
points to the correct file and points to the correct file and points to the correct file and points to the correct file and
location. location. location. location.

Terimakasih banyak atas perhatian dan Kerjasamanya

The link ed image cannot be


display ed. The file may hav e
been mov ed, renamed, or
deleted. Verify that the link
points to the correct file and
location.

Ridwan Amba#122009

Lead Construction Non Well Tripatra Engineering & Construction (JPK‐Utara)

Facility Improvement Construction & Program Construction Team

Pertamina Hulu Rokan Project – Riau – Indonesia

Peri#2 Office – Room – P2‐10D – KM 125 – Duri

0812‐7019‐1360 : [email protected]

From: Aditya Putra <[email protected]>


Sent: Saturday, May 13, 2023 6:51 AM
To: Ridwan Amba [JPK‐Utara] <[email protected]>
Cc: 'Wisnu PS' <[email protected]>; [email protected]; Andriyas [JPK‐Utara] <[email protected]>; [email protected]
Subject: Scan Approved RC‐1, 2, 3, 4

[EXTERNAL EMAIL] Be alert of any suspicious message, attachment, link, or request for sensitive information. If any or in doubt, please contact your IT Service Desk.

Dear pak Ridwan Amba

Terlampir adalah scan approved Road crossing 1, 2, 3, 4

8
Terima kasih

Aditya

***** This message may contain confidential and/or privileged information. If you are not the addressee or authorized to receive this for the addressee, you must not use, copy, disclose or take any action based on this message or any information
herein. If you have received this communication in error, please notify us immediately by responding to this email and then delete it from your system. PT Pertamina (Persero) is neither liable for the proper and complete transmission of the
information contained in this communication nor for any delay in its receipt. *****

***** This message may contain confidential and/or privileged information. If you are not the addressee or authorized to receive this for the addressee, you must not use, copy, disclose or take any action based on this message or any information
herein. If you have received this communication in error, please notify us immediately by responding to this email and then delete it from your system. PT Pertamina (Persero) is neither liable for the proper and complete transmission of the
information contained in this communication nor for any delay in its receipt. *****