Assignment 3
Assignment 3
Sheet 3
A- Answer the following questions
1- Define activity on node and activity on arc?
Answer:
-Activity on node: is represented by a node. The arcs then are used just to show the
precedence relationships between the activities.
-Activity on arc: is used to separate an activity (an outgoing arc) from each of its immediate
predecessors (an incoming arc).
7- Which of the following are claimed as advantages of the AON method over the
AOA method of network diagram notation?
A. Most computer software uses the AON approach.
B. AON do not need dummy activities to maintain the relationship logic.
C. AON diagrams have a clearer notation than AOA.
D. All the mentioned.
8- The successor activity cannot be finished until the predecessor activity starts. This is
an example of which kind of relationship:
A. Finish to Start (FS)
B. Finish to Finish (FF)
C. Start to Start (SS)
D. Start to Finish (SF)
C- State True/False
The Backward method begins with the initial event, marking the beginning of the project,
and proceeds forward till the end event is reached.
A. true B. false
Scheduling means the process of deciding how to arrange resources between varieties of
possible activities and tasks.
A. true B. false
A dummy activity is required when the network contains two or more activities that
have identical starting and ending events.
A. true
B. false
D- Answer the following questions:
Find out the completion time (days) for the following project:
Find out the completion time for the following project (Days):
A. = 37 Days B. = 38 Days C. = 39 Days D. = 40 Days