MS - Concrete Repair Work
MS - Concrete Repair Work
MS - Concrete Repair Work
PROJECT
FGD –FGC PACKAGE FOR 2x660 MW TPP (UNIT – 3 &4)
OWNER
ODISHA POWER GENERATION CORPORATION LIMITED
OWNER'S
STEAG ENERGY SERVICES, NOIDA
CONSULTANT
REVIEWED BY Mr.RaghabaPradhan
APPROVED BY
TABLE OF CONTENTS
SL.NO DESCRIPTION
1.0 Objectives
2.0 Scope
3.0 Reference
5.0 Equipment
7.0 Safety
8.0 Supervision
1.0 Objectives :
2.0 Scope :
The procedure is applicable for all concrete surface honeycomb repair subject to
depth of honey comb up to 50 MM.
3.0 Reference :
● Contract Specification
● Relevant IS Codes
● Approved Drawing
4.0 Materials to be used :
5.0 Equipment :
● Wire Brush
● Chisel
● Hammer
● Plumb Bob
● Trowel
● For repairing of surface air voids cement mix can be used by the ratio of 1.2 where
cement is 1 part and sand is 2 part.
● Loose particles to be removed from the honeycomb area by hammer and wire brush.
● Surface of the pocket shall be made wet and cement slurry to be applied over it.
● Most of the tamping should be directed at a slight angle towards the side of the
pocket to ensure maximum compaction and bond.
Providing Safe access i.e Ladders, Stair Cases and Platforms to go to the work place
Providing first aid and ambulance facility round the clock during concrete
8.0 Supervision :
The RCM shall be over all in charge of all activities assisted by Construction Manager &
Senior Engineers. Supervision shall be arranged by two shifts. The chart showing the
names of individuals with shift duties shall be submitted two days before
commencement of work.
Control room shall be set up at a convenient place near work location to monitor and
co-ordinate all activities. Mobile phones shall be issued to all key personnel for timely
interaction with each other.