Complete One Way Slab Examples
Complete One Way Slab Examples
Concrete-1
Sixth Term
Civil Engineering
= 1.1747 MPa
⚫ fc = 18 MPa 17.27 MPa : fy = 280 MPa
⚫ = 0.005
As = 710 mm2
⚫ Using #13 bars: #13 @ 190 mm c/c provides
As = 679 mm2
Maximum preferred spacing: least of
i) 2h = 320 mm (Code value is 3h)
ii) 300 mm (Code value is 450 mm)
iii) 159,600 / fy − 2.5cc
= 159,600 / 280 − 2.5×20 = 520 mm
iv) 126,000 / fy = 126,000 / 280 = 450 mm
smax = 300 mm
160
3750
200 200
Bar Bending Schedule
⚫ Number of bars for M-1 = 10456 / 190 = (say 55)
⚫ Total length of bars M-1 = 3750 + 2 180 = 4110 mm
⚫ Length M-1 for estimation = 3750 + 2 (200 − 20)
+ 0.414 109 + 18 13
= 4.389 m
⚫ Number of bars for M-2 = 10456 / 380 2 = 55
⚫ Number of bars for D-1 = 3750 / 200 = 19 (say 51)
⚫ Bottom length of bars D-1 = 10000 − 530 + 180 = 9650 mm
⚫ Total length of bars D-1 = 10000 + 2 180 + 18 10
= 10.540 m
⚫ Length D-1 for estimation = 10360 + 0.414 86 = 10.40 m
⚫ Number of bars for D-2 = 3750 / 400 2 = 20
⚫ Length of bars D-2 and M-2 = 750 + 180 + 18 10 = 1.110 m
Table 6.3. Bar Bending Schedule For Example 6.1. Steel Grade: 300
S. Bar No. Len. Dia. Weight Of Bars Shape Of Bar
No. Desig- Of Of Of No.10 No.13
nation Bars Bar Bar
(m) (mm)
109
1 M-1 55 4.389 #13 240
3400 710
= 195 252
125 mm cantilever
h
L = 1000 + 1m
2
125
L = 1000 + = 1063mm 1.07m
2
Plain & Reinforced Concrete-1
Solution: (contd…)
L 1063
hmin = = = 89mm
12 12
Let us use the same thickness as of the room
h = 125mm h min
( )
w u = 1.2 573 + 1.6 300
9.81
1000
= 11.46kN / m 2
Pu = 1.2(0.25 11)1920
9.81
1000
= 5.65kN
Plain & Reinforced Concrete-1
Solution: (contd…)
Pu = 5.65kN
w u L2
M u = Pu L + w u = 11.46kN / m
2
11.46 1.07 2
= 5.65 1.07 + 1.07m
2
#10 @ 275c / c
Maximum preferred spacing: least of
i) 2.5h = 312 mm (Code value is 5h)
ii) 375 mm (Code value is 450 mm)
iii) 159,600 / fy−2.5cc
= 159,600 / 280 − 2.5×20 = 520 mm
iv) 126,000 / fy = 126,000 / 280 = 450 mm
smax = 375 mm
1500 mm
3.8 m
Table: Moment Coefficients for Slabs Having Spans
Lesser Than 3.0 m
1
2. Positive moment in end panel. wuln2
14
1
3. Positive moment in central panels. wuln2
16
Table: Moment and Shear Values for Beams
and Slabs Having Spans Greater Than 3.0 m.
1. Positive Moment
End spans:
1
If discontinuous end is unrestrained wuln2
11
1
If discontinuous end is integral with the support wuln2
14
1
Interior spans: 16
wuln2
2. Negative moment at exterior face of first interior support
1
Two spans: 9
wuln2
1
More than two spans: wuln2
10
1
3. Negative moment at other faces of interior supports wuln2
11
(ln in no. 3 is the average of clear spans of the two adjacent panels.)
4. Negative moment at interior faces of exterior supports for members
built Integrally with their supports:
1 wl2
The support is a spandrel beam or girder: 24
u n
1 wuln2
The support is a column: 16
wu l n
5. Shear in end members at first interior support 1.15
2
wu l n
6. Shear at all other supports
2
Factored Bending Moments
ln = 3.5 m
⚫ Exterior support Mu− = 1 / 24 qu ln2
= 13.48×3.52 / 24 = 6.88 kN-m / m
⚫ Exterior span Mu+ = 1 / 14 qu ln2
= 13.48×3.52 / 14 = 11.80 kN-m / m
⚫ First int. support Mu− = 1 / 10 qu ln2
#4 @ 6’’ c/c
Note: For slabs the distances ln/4 and ln/3 for top
extensions may be reduced to 0.22ln and 0.3ln,
respectively. Similarly, the bottom distance ln/4 may be
reduced to 0.22ln.
Type of Steel Reinforcement Value Length
(mm)
Top steel extension from face of exterior ln / 5 700
support, for short and long directions.
Top steel extension of bent-up bars on 0.3ln 1050
opposite side from face of supports.
Bottom bars bent-up point from face of 0.22ln 770
supports, for short and long directions.
Top extra steel on interior supports, on both 0.22ln 770
sides, from the face of supports.
#10 @ 500 c/c #10 @ 500 c/c
T
a) Incorrect Way
T
b) Correct Way
Example 6.4: Design the first flight of the stair shown
in Fig. 6.9, having a reinforced concrete footing at
the bottom. Use C − 18 concrete and Grade 280
steel. R = 180 mm and T = 260 mm. Select US
Customary reinforcement.
Solution:
⚫ L 1.2 + 3.12 = 4.32 m
⚫ hmin considering both ends continuous/fixed = L / 35
= 4320 / 35 = 124 mm
(say 125 mm)
⚫ d h − 27 = 98 mm
1.2 m 12 @ 0.26 m = 3.12 m
1.2 m
1.2 m
Mu 22.4 10 6
= = = 78mm
0.205 f cb 0.205 18 1000
Main Reinforcement
⚫ Mu / bd2 = 22.4×106 /(1000×982) = 2.3324 MPa
⚫ = 0.0103
⚫ 2 h = 300 mm (OK)
Temperature Reinforcement
⚫ Temperature steel: 0.002 b h
= 0.002 1000 125 = 250 mm2
⚫ Selected temperature reinforcement: #10 @ 275 mm c/c
Check For Shear
⚫ Vu = qu ( Ln / 2 − d)
ln / 5
Must read the book