Biomass Process Flow Calculations: Allen Wiley, P.E
Biomass Process Flow Calculations: Allen Wiley, P.E
1.0 PURPOSE
1.1 The purpose of this Design Course is to provide a systematic method for process
flow design calculations for biomass and similar projects. This guideline is mainly
applicable to the dry processing portion of a project. For example, on a biomass to
liquids project, it would be applicable only to the delivery, storage and preparation
of biomass and may not be applicable to the fuel conversion process. For a wood
pellet plant, it would be applicable from start to finish of the process. These
calculations are intended to be done on Excel spreadsheets.
2.0 ABSTRACT
2.1 Biomass projects require specialized calculations to determine expected and design
flowrates for overall process design and for sizing of equipment. The calculations
are complicated by the fact that moisture contents, bulk densities and operating
hours may vary as material moves through the process.
3.1 The difference between block flow diagrams and process flow diagrams is mainly
one of detail. The process flow diagram will have more detail than the block flow
diagram.
3.2.2 Processing centers are grouped into blocks. Conveyors are not shown.
3.2.3 Flow between blocks and branch flows are shown with labeled flow
identifiers.
3.3.1 Purpose is to identify each major piece of equipment and to provide enough
data to size the equipment. This approach allows systematic and easily
identified equipment sizing criteria.
3.3.3 Flow identifiers between equipment are shown to verify flows, to parse out
flows between processing units and as a calculation aid.
3.3.4 Flow identifiers attached to the equipment are for sizing equipment.
3.4.1 The Block Flow Diagram should be performed and approved by the Client
before any other drawings are started. It will be started after a Design
Criteria is created.
3.4.2 The Process Flow Diagram will be done somewhat concurrently with the
General Arrangement Drawings as they affect each other.
4.1 Usually, the material balance calculation will begin at the end of the process, or
close to the end where a single stream of finished product can be identified. This
is because the Client has identified a process goal in terms of finished product
output, and it is the Engineer’s job to help him to achieve this and to identify
material inputs and equipment requirements to achieve this goal. The annual
production flow is normally given by the client on a wet basis. It must be shown
as wet basis, but corrected to oven-dry basis.
4.2 The material balance calculations are done on an annual, oven-dry basis. Changes
in moisture content and uptime hours are accounted for separately at each flow
identifier. This renders material balances generally very straight forward, easy to
check, and easy for the client to follow.
4.3 All calculations at each flow identifier are based on the annual oven-dry flow and
are all done the same way. Therefore, each column, headed by a flow identifier can
be simply copied to an adjacent column. The material balance calculation is
adjusted as required by the process. Then the input variables (annual uptime hours,
bulk density, moisture content and design factor) are adjusted appropriately.
EXAMPLE:
Flow Identifier: 2
Annual Uptime Hours: hr 7500
Bulk Density, Dry Basis: PCF 9.0
Moisture Content % 8.0%
Design Factor 1.33
Notes:
• Metric tons (2204 pounds/ton) are often used by clients with
European delivery contracts.
• DB means “Dry Basis”, WB means “Wet Basis”.
• Volumetric flow is the same whether calculated wet basis or dry
basis as long as bulk density basis is consistent. This is because the
moisture has minimal effect on volume.
• Fiber flow represents flow on an oven-dry basis. Wet flow is fiber
flow with moisture included.
• The calculations above are done as formulas in Excel spreadsheet
cells. The Annual Flow, DB is calculated as a multiple of another
cell and is the basis of the material balance. Cells below this are
calculated based on the Annual Flow, DB and the data above this
cell. As a result, columns can be copied and only the Annual Flow,
DB calculation changed. The input data is changed to reflect
characteristics of the process at the particular flow location.
4.4 Storage: There will usually be several places in the process where material is
temporarily stored in open piles, silos, bins, etc. The storage requirement is usually
provided by the Client in terms of hours or days of storage. The block flow or
process flow diagram should identify these and include a calculation of total
volume and weight of material stored. The Client should clarify whether his storage
requirement is “full-to-empty” or if it is between two operational points in the
storage unit. Calculation columns for storage are handled separately in the
spreadsheet.
4.5 Dryers: Dryers are handled somewhat differently. Here, the main problem is
usually to predict the fuel flow to the dryer. Often, when tree stems are being
processed, this will be supplied partly from bark from the debarker and partly from
purchased fuel. The oven-dry flow of dryer furnish into the dryer is equal to the
flow leaving the dryer. The wet-basis flow is reduced however, due to elimination
of water. The difference in annual wet-basis flow represents the annual moisture
removal. Dryer suppliers will normally provide a rating in terms of Btu, hot gas
entering the dryer, per pound of moisture evaporated. This is usually about 1600
to 1700 for Btu/pound for green wood chips dried in rotary drum dryers. The flow
of bark to the dryer is calculated based on the oven-dry heating value of the bark,
corrected for moisture content. Annual purchased fuel becomes the difference
between fuel requirement and fuel supplied by the debarker from purchased tree
stems.
EXAMPLE:
Notes:
• Lower heating value of fuel is used. This is because the dryer temperature
remains above the temperature required to condense water vapor formed in
Where 1.0 and 0.49 are the heat capacities of water and steam, respectively.
The heat required to evaporate water at atmospheric pressure is found in
steam tables to be 970 BTU/LB.
5.2.1 There are two ways to refer to moisture content in the wood products
industry:
Where:
Ww = weight of water in a sample.
Wod = weight of oven-dry wood in a sample.
MCwb = MCdb/(1+MCdb)
Or:
MCdb = MCwb/(1-MCwb)
Dry basis moisture content is used mainly by solid wood processors such
as sawmills and plywood plants. Biomass facilities usually use wet basis
moisture content, but it is a good idea to be conversant in both and be sure
that you and your client are using the same terminology. Dry basis
moisture content can often be above 100%, which may be confusing to the
“uninitiated”.
5.2.2 Oven-dry: This is effectively the same as “bone dry”, but reflects a
particular way of drying a sample in an oven at 101-105C until constant
5.2.3 If the client can provide moisture contents, this is best. The following are
some typical moisture contents for southern tree species.
5.3.1 Most published data for wood is in terms of oven-dry specific gravity of
solid wood. When wood is run through a chipper, it experiences an
expansion factor that is approximately constant for all species, but
increases as target chip size decreases. Historically, most wood has been
chipped to a ¾” target size for paper-mill chips. However, in biomass
applications, a smaller target size is often sought and chippers may be set
up to produce 3/8” and some for ¼” chips. Expansion factors for these
chip sizes are 2.8, 3.08 and 3.42 respectively. Some useful rules of thumb
for chip bulk densities follow:
The advantage of working with oven-dry bulk density is that it does not
change with moisture content, and as the project progresses, the moisture
5.3.1 Bark: Bark for Southern Pines is usually assumed to have a wet bulk
density of 16 PCF, or 8 PCF dry bulk density.
5.4 Design Factor: A design factor is a factor, usually greater than 1.0 that is
multiplied by the average flow to obtain design flow. Several issues may be
considered in determining the design factor. Among these are:
5.4.1 Lack of certainty regarding input data (moisture content, bulk density,
uptime rate).
5.4.2 Lack of certainty that the vendor design will be adequate. Under bidding
conditions, vendors will typically bid to the bare minimum.
5.4.3 Natural process variations. For example, log feed to a chipper is not
constant and may vary by as much as +/- 50%. So the chipper discharge
conveyors should be designed to handle the higher rate. On the other
hand, chips are fed from a silo at a steady rate.
The calculations are basically simple, but the convolutions of the process can
make the overall spreadsheet complex and there are many opportunities for errors
of neglect. This type of error can be reduced by arranging the flow identifiers as
much as possible in the order of process flow. During the course of the project
the need to insert flow identifiers inevitably arises, and with it, a new calculation
column. By starting with 1 on each PFD sheet, the re-work involved is
minimized. This of course means that each data point will not have a unique
identifier. It must be identified by both its number and the PFD number. This
does not normally have any negative consequences. However, some clients that
come from chemical process industries will object and insist that no flow
identifier be re-used. In this case, the Engineer will have to “bite the bullet” and
do as the Client wishes.
There are many opportunities for errors to manifest themselves both due to neglect and
logics in the material balance. One way to check for errors is to check for overall
balances. Each sheet should be checked that:
The overall balance should also be checked to verify that flow entering the process equals
flow leaving.
A client wishes to construct a wood fuel pellet plant to produce 300,000 metric tons (MT)
per year of pellets at 8 percent moisture content.
Input Data
Uptime hours
Storage Requirements
Raw material
Moisture contents:
Wood: 50%
Bark: 50%
Dry wood: 8%
Pellets: 8%
Pellets: 39.48 (Note that the client will usually provide a target
pellet density with moisture included, in this case, 42.0 pcf).
Truck loads
Log trucks: 20 MT
Bark delivery trucks: 20 MT
Pellet shipping trucks: 20 MT
Storage requirements are indicated in yellow, columns 5S, 9S, 11S, 13S,
17S and 22S. The volumetric requirements are used to make a
preliminary assessment of the yard areas that must be allotted for tree
stems, green chips and bark fuel, and the size of silos required for dry
chips and pellets.
The overall balance should be checked. Flow into the process is found in
columns 3 (tree stems) and 4 (purchased bark). Flow out is found in
column 17 (pellets). Material consumed is in column 23 (bark burned).
Confirming that:
TRUCKS TRUCKS 5S 9S
CHIP
SCALE 1 LOGS 3 STEM 5 DEBARK 6 7 STORAGE 9
CHIP
STORAGE
TRUCKS 20
22S
BARK 4 HOG 21 BARK 22 RECLAIM 23 BURNER
2
STORAGE
11S
16 FINES
NOTE: 1.) WHERE COLUMNS ARE HEADED BY "TRUCKS", WEIGHTS REFER TO TRUCK LOADS AND "ANNUAL WET" IS THE NUMBER OF TRUCK LOADS
FLOW IDENTIFIER 1 2 3 4 5 5S 6 7 9 9S 10 11 11S 12 13 13S
STEMS CHIPS DRY CHP DRY FIB
UNITS TRUCKS TRUCKS
ANNUAL UPTIME HR 2,980 2,980 2,980 7,560 3,149 3,149 3,149 8,002 8,002 8,002 7,589 7,589
BULK DENS., DB LB/CF N/A N/A 21.80 8.00 21.80 10.13 10.13 10.13 10.13 10.13 9.11 9.11
BULK DENS., WB LB/CF N/A N/A 43.60 16.00 43.60 20.26 20.26 20.26 11.01 11.01 9.69 9.69
MC WET BASIS % N/A N/A 50.0% 50.0% 50.0% 50.0% 50.0% 50.0% 8.0% 8.0% 6.0% 6.0%
AN'L FLOW, DB MT/YR N/A N/A 313,636 18,961 313,636 276,000 276,000 276,000 276,000 276,000 276,000 290,526
AN'L FLOW, WB MT/YR 31,364 1,896 627,273 37,922 627,273 552,000 552,000 552,000 300,000 300,000 293,617 309,071
FLOW, DB MT/HR N/A N/A 105.2 2.5 99.6 87.6 87.6 34.5 34.5 34.5 36.4 38.3
FLOW, WB MT/HR 10.52 0.64 210.5 5.0 199.2 175.3 175.3 69.0 37.5 37.5 38.7 40.7
BULK FLOW, CFH CFH N/A N/A 9,675 628 9,156 17,339 17,339 6,823 6,823 6,823 8,000 8,421
STARAGE CAP. HR N/A 72 8 8
WEIGHT STORED MT 13,068 4,967 310 326
VOLUME STORED CF 600,657 540,313 60,035 67,371
As in most chemical process projects, a biomass project will require creation of a block flow
diagram (BFD) or a process flow diagram (PFD), or both. The block flow diagram is usually
created in the earlier engineering stages to help firm up the basic process and to get the client and
engineer both thinking along the same lines. The BFD will include groupings of equipment
represented by blocks, whereas the PFD will show every major piece of processing equipment
with associated design flow.
Biomass projects differ from most chemical process projects in that some key variables such as
daily operating hours, moisture content and bulk density of the material vary at different stages
of the process, making calculations based on hourly flow difficult. The calculations are greatly
simplified by balancing the mass flow based on annual dry mass. Adjustments then are made
simply at each designated flow point by incorporating the correct parameters. For the purpose of
sizing equipment and writing equipment specifications, a carefully selected design factor can be
incorporated into the PFD calculations.