Power Transmission Line Proposal
Power Transmission Line Proposal
ABBREVIATIONS III
I. PROJECT DESCRIPTION 1
II. IMPLEMENTATION PLANS 3
A. Project Readiness Activities 3
B. Overall Project Implementation Plan 4
III. PROJECT MANAGEMENT ARRANGEMENTS 6
A. Project Implementation Organizations: Roles and Responsibilities 6
B. Key Persons Involved in Implementation 6
C. Project Organization Structure 7
IV. COSTS AND FINANCING 10
A. Detailed Cost Estimates by Expenditure Category ($ million) 11
B. Allocation and Withdrawal of Loan Proceeds 12
C. Detailed Cost Estimates by Financier ($ million) 13
D. Detailed Cost Estimates by Outputs/Components ($ million) 14
E. Detailed Cost Estimates by Year ($ million) 15
F. Contract and Disbursement S-Curve 16
G. Fund Flow Diagram 17
V. FINANCIAL MANAGEMENT 18
A. Financial Management Assessment (Historical) 18
B. Action Plan 23
C. Disbursement 26
D. Accounting 26
E. Auditing 26
VI. PROCUREMENT AND CONSULTING SERVICES 27
A. Advance Contracting and Retroactive Financing 27
B. Procurement of Goods, Works, and Consulting Services 28
C. Procurement Plan 29
D. Methods, Thresholds, Review and 18-Month Procurement Plan 29
E. Indicative List of Packages Required Under the Project 31
F. List of Awarded, Ongoing, and Completed Contracts 31
G. Non-ADB Financing 35
VII. SAFEGUARDS 36
VIII. GENDER AND SOCIAL DIMENSIONS 40
IX. PERFORMANCE MONITORING, EVALUATION, REPORTING, AND COMMUNICATION 41
A. Project Design and Monitoring Framework 41
B. Monitoring 44
C. Evaluation 45
D. Reporting 45
E. Stakeholder Communication Strategy 45
X. ANTICORRUPTION POLICY 46
XI. ACCOUNTABILITY MECHANISM 47
XII. RECORD OF THE PROJECT ADMINISTRATION MANUAL CHANGES 47
ii
1. The project administration manual (PAM) describes the essential administrative and
management requirements to implement the project on time, within budget, and in accordance
with Government and Asian Development Bank (ADB) policies and procedures. The PAM
should include references to all available templates and instructions either through linkages to
relevant URLs or directly incorporated in the PAM.
2. JSC National Electric Grid of Uzbekistan (NEGU), the executing agency, is wholly
responsible for the implementation of ADB financed project, as agreed jointly between the
borrower and ADB, and in accordance with government and ADB’s policies and procedures.
ADB staff is responsible to support implementation including compliance by NEGU of its
obligations and responsibilities for project implementation in accordance with ADB’s policies
and procedures.
3. At Loan Negotiations the borrower and ADB shall agree to the PAM and ensure
consistency with the Loan agreement. Such agreement shall be reflected in the minutes of the
Loan Negotiations. In the event of any discrepancy or contradiction between the PAM and the
Loan Agreement, the provisions of the Loan Agreement shall prevail.
4. After ADB Board approval of the project's report and recommendations of the President
(RRP) changes in implementation arrangements are subject to agreement and approval
pursuant to relevant government and ADB administrative procedures (including the Project
Administration Instructions) and upon such approval they will be subsequently incorporated in
the PAM.
iii
ABBREVIATIONS
1. Project's rationale, location, and beneficiaries. The objectives of the proposed project
as originally approved were to (i) improve power transmission network capacity and reliability in
the northwest region of the country, the Karakalpakstan and Khorezm regions; (ii) reduce
transmission losses; and (iii) improve the operational efficiency of the power sector. The project
will strengthen energy security through improved power system reliability and efficiency by
constructing a new domestic transmission line without passing through any other country. 1 The
new line will evacuate power from Takhiatash Thermal Power Plant (TPP). 2 The project will also
increase power supply reliability for the Karakalpakstan 3 and Khorezm 4 regions in the
northwestern part of Uzbekistan where major investments are scheduled, benefiting at least three
million people. The project’s scope has been expanded to include two additional transmission
investments: (i) the restoration of 64.5 kilometers (km) of the 500-kilovolt (kV) transmission line
between the Guzar substation in the Surkhandarya region to the border with Tajikistan for
reconnection to the Regar substation in Tajikistan, and (ii) expansion of transmission capacity to
serve the growing demand in the Jizzakh region through the construction and
expansion of substations and the construction of a 142 km double-circuit 220 kV transmission line
between substations in Syrdarya and Zafarabad. The project title will change to “Uzbekistan
Power Transmission Improvement Project.” The expanded scope will be financed through surplus
loan proceeds through a major change in scope approved by the Board.
2. Impact and Outcome. The project’s impact will be adequate and reliable power supply in
Uzbekistan by 2023. The outcome will be an expanded and modernized high-voltage transmission
grid in Uzbekistan.
3. Outputs. The proposed change in scope will produce two additional outputs: (i) 64.5 km
of the Guzar-Regar 500 kV transmission line restored, and (ii) 142-km double-circuit 220 kV
transmission line between the Syrdarya TPP and the Zafarabad substation in the Jizzakh region
constructed. Transmission capacity of the Guzar-Regar line will increase to 900 MW.
Transmission capacity to the Jizzakh region from the Syrdarya TPP complex will increase from
325 MW to 525 MW. The project outputs will now consist of the following components:
1 The existing transmission line from Takhiatash to Navoi passes through Turkmenistan. Although the transmission
assets belong to Uzbekistan, the difficulty to maintain them causes frequent and prolonged outage which brings
down production rate, and hampers development of small-scale businesses which lead to people’s dissatisfaction.
2 Takhiatash TPP is the main source of power supply in the Karakalpakstan and Khorezm regions. The existing
Takhiatash TPP has installed capacity of 870 megawatt (MW). Two new CCGT of 250 MW have been planned for
Takhiatash TPP. With the proposed project, the surplus power can be reliably transmitted to the load centers.
3 Karakalpakstan is about 37% of the land area of Uzbekistan and has a population of 1.7 million people and is rich in
natural resources.
4 Khorezm has a population of 1.6 million people. It is one of the agro-industrial regions.
2
Original Scope
2015 2016 Responsible Agency
Indicative Activities
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Advance action for recruitment of project
supervision and management consultants X X X EA-PMU
Procurement of goods contracts X EA-PMU
Loan negotiations X EA
ADB Board approval X ADB
Loan signing X ADB-GOU
Government Legal opinion provided X GOU
Government budget inclusion X GOU
Loan effectiveness X GOU-ADB
ADB = Asian Development Bank, EA = Executing Agency, GOU = Government of Uzbekistan, PMU = project
management unit, Q = quarter.
B. Project Outputs
[Physical]
1 220 kV Transmission Line
1.1 Bidding Documents and Specification Preparation
1.2 Bidding Period
1.3 Bid Evaluation
1.4 Contract Negotiation and Award
1.5 Site Preparation and Civil Works
1.6 Manufacturing Materials and Equipment
1.7 Construction and Installation
1.8 Commissioning and Final Test
1.9 Completion of Contract
[Non-physical]
3 Project Supervision and Management Consultants
3.1 RFP issued
3.2 Proposal evaluation
3.3 Contract negotiation and award
3.4 Consulting team mobilization
3.5 Project supervision and management
C. Loan Closing
ADB = Asian Development Bank, kV = kilovolt, RFP = request for proposal.
5
[Non-physical]
4 Project Supervision and Management Consultants
4,1 Consulting team mobilization
4.2 Project supervision and management
5 External Auditing
5.1 RFP issued
5.2 Proposal evaluation
5.3 Contract negotiation and award
5.4 External auditing
C. Loan Closing
ADB = Asian Development Bank, HVL= high-voltage line, kV=kilovolt, RFP = request for proposal, TPP = thermal power plant.
6
Project Implementation
Organizations Management Roles and Responsibilities
• MOF on behalf of the Borrower
Republic of Uzbekistan
MOF representing for external borrowing
Ensuring loan proceeds are used in accordance with the
Loan Agreement
Handling of issues pertaining to project-related taxes and
duties
Electricity tariff setting
• ADB Lender
Main project financier
ADB = Asian Development Bank, MOF = Ministry of Finance, NEGU = Joint-Stock Company National Electric
Grid of Uzbekistan, PMU = project management unit.
a On 27 March 2019, the Presidential Resolution No. PP-4249 decree reorganized Joint-Stock Company (JSC)
Uzbekenergo into three joint-stock companies: (i) JSC Thermal Power Plants (TPP)to manage thermal
power plants that generate electricity and thermal power; (ii) NEGUto manage main electric networks; and
(iii) JSC Regional Electrical Networks (REN)to manage territorial electric networks enterprise distribution to
end-users.
Executing Agency
JSC NEGU Officer's Name Mr. Dadajon Isakulov
Position Chairman of the Board
Telephone (+998 71) 2336128
Email address NEGU PMU <[email protected]>
Office Address JSC NEGU
Osiyo str. 42, Tashkent, 100084, Uzbekistan
ADB
Division Director Staff Name Joonho Hwang
Position Director, Energy Division, Central and West Asia
Department (CWRD/CWEN)
Telephone No. +63-2-8632-6387/4479
Email address [email protected]
4. Joint-Stock Company (JSC) National Electric Grid of Uzbekistan (NEGU), the project
executing agency, has established a dedicated full-time project management unit (PMU). The
PMU will administer all consulting and procurement contracts on behalf of NEGU.
5. The PMU Manager will be supervised by the Deputy Chairman of the Board of
Investments/Head of Department for Attraction of Foreign Investments and Implementation of
Investments Projects who will report to the Chairman of JSC NEGU. The PMU will be the main
point of contact for working communication between JSC NEGU and the Asian Development
Bank (ADB). The PMU will coordinate the consultants and contractors.
6. The PMU, assisted by the consultants, will prepare and submit the necessary project
plans, request for proposal and bidding documents, proposal and bid evaluation reports, progress
reports, applications for withdrawal of funds, and any other required reports to ADB.
7. The PMU Manager will have appropriate academic qualifications with experience of
working on large investment project implementation and/or operations. The PMU will comprise of
(i) a dedicated manager, (ii) procurement specialists, (ii) transmission engineers, (iii) substation
engineers, (iv) accountant, (v) social and environmental specialists, and (vii) interpreters.
8. The PMU will include the positions with the following terms of reference:
10. The project costs consist of (i) goods and works contracts for construction of 220 kV and
500 kV transmission lines; (ii) goods and works contracts for rehabilitation, expansion, and
construction of five substations; (iii) consulting services; (iv) institutional capacity development;
(v) environmental impact mitigation; (vi) land acquisition and resettlement; (vii) taxes and duties;
(viii) recurrent costs; and (ix) financial charges. ADB loan will cover the entire costs for goods
contracts; works contracts associated with outputs 4 and 5; consulting service contracts; and
capacity building contracts, excluding taxes and duties, which will be covered by the Government.
NEGU will finance the costs of the entire civil works, environmental impact mitigation, land
acquisition and resettlement, financing charges, and PMU recurrent costs.
11
(OCR) loan. Commitment charges for ADB's OCR loan are 0.15% per year to be charged on the undisbursed loan amount.
Source: Asian Development Bank estimates.
12
aExclusive of taxes and duties imposed within the territory of the borrower.
Source: Asian Development Bank estimates.
13
a Original project costs in 2015 prices, revised project costs at actual cost or 2020 prices.
b Physical contingencies on the new components computed at 10%. Price contingencies computed at 1.1% on foreign exchange costs and 10.0% on local currency;
includes provision for potential exchange rate fluctuation under the assumption of a purchasing power parity exchange rate.
c Includes interest and commitment charges. Interest during construction has been calculated using the existing interest rate for ADB's ordinary capital resources
(OCR) loan. Commitment charges for ADB's OCR loan are 0.15% per year to be charged on the undisbursed loan amount.
Source: Asian Development Bank estimates.
14
Takhiatash-Khorezm-Ell Substations and Institutional Developmen220kV Transmission Lines Substations and Syrdarya TPP – Zafarab Guzar-Regar Institutional Development
Switching Stations Switching Stations
% Cost % Cost % Cost % Cost % Cost % Cost
Total Amount Category Amount % Cost Category Amount Category Amount Category Amount % Cost Category Amount Category Amount Category Amount Category Total
a
A. Investment Costs 211.18 147.79 70% 61.82 29% 1.57 1% 82.08 38% 36.77 17% 77.26 36% 17.60 8% 0.94 0% 214.66
1 Goods 123.75 84.02 68% 39.73 32% - 0% 27.80 59% 19.14 41% - 0% - 0% - 0% 46.95
a. Output 1 (Takhiatash-Khorezm) 84.02 84.02 100% 0% 0% 27.80 100% 0% 0% 0% 0% 27.80
b. Output 2 (Substations) 39.73 0% 39.73 100% 0% 0% 19.14 100% 0% 0% 0% 19.14
2 Civil Works 60.59 46.33 76% 14.26 24% - 0% 46.33 76% 14.26 24% - 0% - 0% - 0% 60.59
a. Output 1 (Takhiatash-Khorezm) 46.33 46.33 100% 0% 0% 46.33 100% 0% - 0% 0% 0% 46.33
b. Output 2 (Substations) 14.26 0% 14.26 0% 0% 0% 14.26 0% 0% 0% 0% 14.26
3 Works - - - - - 0% - 0% 66.63 82% 14.80 18% - 0% 81.42
c. Output 3 (Syrdarya-Zararobod) - 0% 0% 0% 66.63 100% 0% 0% 66.63
d. Output 4 (Guzar-Regar) - 0% 0% 0% 0% 14.80 100% 0% 14.80
4 Environmental impact mitigation 1.26 1.00 79% 0.26 21% 0% 1.00 49% 0.26 13% 0.40 19% 0.40 19% 0% 2.05
5 Land acquisition and resettlement 0.33 0.33 100% - 0% 0% 0.33 43% - 0% 0.29 38% 0.14 19% 0% 0.76
6 Taxation 25.25 16.11 64% 7.57 30% 1.57 6% 6.62 29% 3.11 14% 9.95 43% 2.27 10% 0.94 4% 22.89
B. Recurrent Costs 1.31 0.88 67% 0.37 28% 0.06 5% 0.88 67% 0.37 28% 0% 0% 0.06 5% 1.31
C. Institutional Development 8.33 - 0% - 0% 8.33 100% - 0% - 0% - 0% - 0% 9.31 100% 9.31
a. Project implementation consulting servic 2.50 0% 0% 2.50 100% 0% 0% 0% 0% 4.47 100% 4.47
b. Transmission system planning 0.53 0% 0% 0.53 100% 0% 0% 0% 0% - 0% -
c. Asset Management system 4.80 0% 0% 4.80 100% 0% 0% 0% 0% - 0% -
d. External audit 0.50 0% 0% 0.50 100% 0% 0% 0% 0% 0.50 100% 0.50
e. Asset maintenance and management - 0% 0% 0% 0% 4.35 100% 4.35
TOTAL BASE COST (A+B+C) 220.82 148.67 67% 62.19 28% 9.96 82.96 37% 37.14 16% 77.26 34% 17.60 8% 10.32 5% 225.28
b
D. Contingencies 26.18 17.63 7.37 1.18 5.48 2.29 8.75 46% 1.99 10% 0.63 19.14
1 Physical 20.42 13.75 67% 5.75 28% 0.92 5% 4.33 27% 1.81 11% 7.73 48% 1.76 11% 0.52 3% 16.15
2 Price 5.76 3.88 67% 1.62 28% 0.26 5% 1.15 38% 0.48 16% 1.02 34% 0.23 8% 0.11 4% 2.99
c
E. Financing Charges During Implementation 7.96 5.36 2.24 0.36 1.31 0.54 1.15 34% 0.26 8% 0.12 3.40
1 Interest during implementation 7.31 4.92 67% 2.06 28% 0.33 5% 0.66 30% 0.28 13% 0.95 44% 0.22 10% 0.07 3% 2.19
2 Commitment charges 0.65 0.44 68% 0.18 28% 0.03 5% 0.65 54% 0.27 22% 0.20 17% 0.05 4% 0.05 4% 1.21
Total Project Cost (A+B+C+D+E) 254.96 171.66 67% 71.80 28% 11.50 5% 89.76 36% 39.98 16% 87.17 35% 19.86 8% 11.07 4% 247.82
a Original project costs in 2015 prices, revised project costs at actual cost or 2020 prices.
b Physical contingencies on the new components computed at 10%. Price contingencies computed at 1.1% on foreign exchange costs and 10.0% on local currency;
includes provision for potential exchange rate fluctuation under the assumption of a purchasing power parity exchange rate.
c Includes interest and commitment charges. Interest during construction has been calculated using the existing interest rate for ADB's ordinary capital resources
(OCR) loan. Commitment charges for ADB's OCR loan are 0.15% per year to be charged on the undisbursed loan amount.
Source: Asian Development Bank estimates.
15
a Original project costs in 2015 prices, revised project costs at actual cost or 2020 prices
b Physical contingencies on the new components computed at 10%. Price contingencies computed at 1.1% on foreign exchange costs and 10.0% on local currency;
includes provision for potential exchange rate fluctuation under the assumption of a purchasing power parity exchange rate.
c Includes interest and commitment charges. Interest during construction has been calculated using the existing interest rate for ADB's ordinary capital resources
(OCR) loan. Commitment charges for ADB's OCR loan are 0.15% per year to be charged on the undisbursed loan amount.
Source: Asian Development Bank estimates.
16
1.00
2016 2017 2018 2019 2020 2021 2022 2023 2024
Year
Contract Awards (in USD million) Total Disbursements (in USD million) Total
17
Loan Agreement
Republic of Uzbekistan
(Ministry of Finance)
Subsidiary Loan
Agreement
Invoice/Receipt
Contractors
Direct Payment and
Commitment Procedure
Invoice/Receipt
Project Supervision
and Management
Consultants
18
V. FINANCIAL MANAGEMENT
11. A financial management assessment (FMA), including assessed risks and mitigation
measures, analysis on historical financial performance, and projections of financial statements,
was conducted during preparation of the originally-approved project. Uzbekenergo, the executing
agency (EA) of the project at the time of its preparation and commencement, was a 100% state-
owned holding company responsible for operation of Uzbekistan’s power generation,
transmission system, and distribution in Uzbekistan. It was established in August 2001 after the
public sector reorganization and is the legal successor of the former Ministry of Energy and
Electrification. Incorporated as an open joint-stock company (JSC), Uzbekenergo had 54
subsidiaries with its shares ranging from 51% to 100% in each subsidiary. These subsidiaries
included power generation, transmission, and distribution and supply companies. Most of those
subsidiaries were incorporated as separate JSCs.
12. At the time of the original FMA’s preparation, Uzbekenergo’s financial management risk
was considered high. The need was identified for Uzbekenergo to strengthen its financial
management capacity. Uzbekenergo’s accounting policies, procedures, and financial reporting
followed the National Accounting Standards of Uzbekistan and National Standards on Auditing.
Under Presidential Resolution No. 48 Article 442 of 2010, Uzbekenergo was also required to
adopt international auditing standards for external auditing of its financial statements during the
period 2011–2015. In order to comply with this resolution and to enhance its financial
management, Uzbekenergo undertook an external audit based on International Standards on
Auditing issued by the International Assurance Auditing Standards Board of its financial
statements from the fiscal year (FY) ending on 31 December 2011. The results of the audit
indicated the need for further improvements in areas such as the classification methods and
impairment provisions on account receivables, the scope of account consolidation, and the
accounting system.
13. Uzbekenergo started adopting the International Financial Reporting Standards (IFRS)
conversion since the FY ending on 31 December 2012 and planned to complete full conversion
to cover all subsidiaries for the FY ending 31 December 2015. Uzbekenergo produced audited
entity financial statement (AFS) for FY2015, which were prepared based on the IFRS. FY2016
and FY2017 were to follow. The capacity development plan under other ADB loan projects 5 and
World Bank projects were expected to address the training of the IFRS specialists as well as the
strengthening of Uzbekenergo’s information systems, with the objective of improving its financial
management capability.
5 ADB. 2010. Report and Recommendation of the President to the Board of Directors: Proposed Loans and
Administration of Loan to the Republic of Uzbekistan for the Talimarjan Power Project. Manila (Loans 2629-UZB,
2630-UZB, and 8944-UZB).
19
15. Table 1 summarizes the financial management risks of Uzbekenergo and mitigation
measures prescribed at the time of the original loan preparation.
16. Based on this assessment, action plans to improve financial management capacity of
Uzbekenergo are the following:
17. In 2019, Uzbekenergo was legally unbundled along functional lines. JSC National Electric
Grid of Uzbekistan (NEGU) was established as a 100% state-owned company responsible for
operation of Uzbekistan’s transmission system, and for coordinating power generation dispatch.
(Generation and distribution assets of Uzbekenergo were assigned to other new state-owned
enterprises.)
18. In preparation for the major change of the project’s scope to include Output 4 and Output
5, a supplemental FMA was prepared specifically for NEGU.
19. Financial management risks are evident in NEGU, where specific intervention is
warranted.
20. Existing PMU staff for the Northwest transmission project are largely to be transferred to
the PMU for this project. While the PMU staff have experience in managing ADB procedures,
further improvements in the quality of reporting is required. ADB training to the PMU should
continue to enhance capacity in procurement, finance, and contract management issues
associated with internationally financed projects, and in ADB procedures, especially in the move
to using the ADB’s Client Portal for Disbursement.
21. NEGU has existing plans to facilitate the introduction of IFRS accounting and spread of
International Standards on Auditing. Significant hands-on training and support is still needed, both
for staff in the IFRS Unit and to enable accountants that are currently focusing on statement
21
prepared under the National Accounting Standards to gain necessary exposure in the IFRS. It is
also critical that NEGU develops its IFRS accounting policies and procedures as proposed.
22. There is an urgent need to populate the internal audit unit and strengthen its role to support
business modernization. Terms and conditions of employment should be reviewed to promote the
use of full-time staff paid at market-based rates. Training on internal auditing and risk
management is also important for recruited staff to ensuring the internal audit role is highly
proactive, understood by management, and reflects accounting trends towards the IFRS.
23. Budget monitoring is focused on the annual shareholder meeting, with an urgent need for
enhanced in-year monitoring and regular management reporting, together with control procedures
for spending above business plan allocations. NEGU needs to develop medium-term forecasting
capability, which is especially critical given uncertainty over its regulatory model, the requirements
of the Corporate Code, and the expectations that a multiyear tariff methodology may be
introduced from 2023. At the same time, supportive risk management procedures and processes
should be implemented.
24. The FMA has considered two types of risks: (i) inherent risks, i.e., risks outside the direct
control of the entity financial management; and (ii) control risks, i.e., risks concerning the internal
functioning and control of the entity’s accounts division and related financial divisions. Table 2
identifies the following key risks:
ADB = Asian Development Bank, ERP = enterprise resources planning, IFRS = International Financial Reporting
Standards, ISA = International Standards on Auditing, JSC = Joint-Stock Company, NAS = National Accounting
Standards, NEGU = JSC National Electric Grid of Uzbekistan, PFM = public financial management, PMU = project
management unit.
Source: ADB.
B. Action Plan
25. The development of an Action Plan reflecting the above considerations needs to take into
account broader reforms required of NEGU, including the need for regulatory reform to support
its independence and sustainability of its transmission business. Based on this assessment, the
following Action Plans are presented to improve financial management capacity in NEGU.
NEGU/PMU to PwC
Academy, Uzbekistan
webinars on IPSAS, IFRS NEGU financial
and ACCA’s financial management and
reporting webinarsb disbursement staff are
required to complete
NEGU financial NEGU/PMU the self-study within 2
management staff to self- months upon
study Loan Disbursement recruitment.
Handbook 2017,c which is
also available in Russian
language, and avail of e-
Learning/self-study
modules of the ADB Client
Portal for Disbursements
systemd
4 Difficulties with staff PMU to ensure continuity PMU/NEGU Continuous
retention in financial and propose actions to
management positions improve staff retention in
financial management
functions
5 Limited knowledge in Further training to NEGU NEGU Training ongoing
the IFRS, impeding on IFRS is being provided during duration of
the required by the World Bank. World Bank support
implementation of (footnote 8)
accounts under the
IFRS
6 Limited knowledge in NEGU to prepare Annual NEGU Annual IFRS reports
preparing accounts IFRS report starting from to be issued
under the IFRS FY2019 and unaudited consistent with
quarterly IFRS reports statutory timeframes,
starting from FY2021 unaudited quarterly
financial statements
and reports within 2
months of the end of
the quarter
7 Outdated accounting Update internal accounting NEGU Within 6 months of
policies and policies and manuals to effectiveness of Major
procedures designed reflect the revised Change loan
for JSC Uzbekenergo organizational amendment
arrangements, including
transition to the IFRS
Source: ADB.
26
C. Disbursement
26. The Loan proceeds will be disbursed in accordance with ADB’s Loan Disbursement
Handbook (2017, as amended from time to time), 6 and detailed arrangements agreed upon
between the government and ADB.
27. A project management and supervision consultant (project implementation consultant) will
be recruited to assist NEGU in project management, including preparing disbursement
projections, collecting supporting documents, and preparing and sending withdrawal applications
to ADB.
28. Direct payment and commitment procedure will be adopted for the procurement of goods
and consulting services contracts.
29. Before the submission of the first withdrawal application, the Ministry of Finance (MOF)
should submit to ADB sufficient evidence of the authority of the person(s) who will sign the
withdrawal applications on behalf of the borrower, together with the authenticated specimen
signatures of each authorized person. The minimum value per withdrawal application is
US$100,000 equivalent. Individual payments below this amount should be paid by the
government or NEGU and subsequently claimed to ADB through reimbursement, unless
otherwise accepted by ADB. National companies are paid into national bank accounts for
nationally based work. Payments will be made only into countries in which the contractor,
subcontractor, or supplier is incorporated. It will not be allowed to pay into third country bank
accounts or pay into bank account of non-ADB member country.
D. Accounting
30. NEGU will cause the PMU to maintain separate project account and records by funding
source for all expenditures incurred on the project. The PMU will prepare consolidated project
financial statements in accordance with the government’s accounting laws and regulations, which
are consistent with international accounting principles and practices, in accordance with the
International Public Sector Accounting Standards, “Financial Reporting under the Cash Basis of
Accounting.” The annual entity’s financial statements will follow international accounting principles
and practices in accordance with the IFRS.
E. Auditing
31. NEGU will cause the detailed consolidated project financial statements to be audited, in
accordance with the International Standards on Auditing and with the government's audit
regulations, by an independent auditor acceptable to ADB. The audited project financial
statements will be submitted in the English language to ADB within 6 months of the end of the
fiscal year by the executing agency.
32. NEGU will also cause the entity-level financial statements to be audited, in accordance
with the International Standards on Auditing and with the government's audit regulations, by an
independent auditor acceptable to ADB. The audited entity-level financial statements, together
with the auditors’ report and management letter, will be submitted in the English language to ADB
within 1 month after their approval by the competent authority.
6 ADB. 2017. Loan Disbursement Handbook 2017. Manila.
27
33. The annual audit report will include an audit management letter and audit opinions, which
cover (i) whether the project financial statements present a true and fair view or are presented
fairly, in all material respects, in accordance with the applicable financial reporting framework; (ii)
whether loan proceeds were used only for the purposes of the project or not; and (iii) the level of
compliance for each financial covenant contained in the legal agreements for the project.
34. Compliance with financial reporting and auditing requirements will be monitored by review
missions and during normal project supervision, and followed up regularly with all concerned,
including the external auditor.
35. The government, NEGU, and the PMU have been made aware of ADB’s policy on
delayed submission, and the requirements for satisfactory and acceptable quality of the audited
project financial statements. 7 ADB reserves the right to require a change in the auditor, in a
manner consistent with the constitution of the borrower or for additional support to be provided to
the auditor, if the audits required are not conducted in a manner satisfactory to ADB, or if the
audits are substantially delayed. ADB reserves the right to verify the project's financial accounts
to confirm that the share of ADB’s financing is used in accordance with ADB’s policies and
procedures.
36. Public disclosure of the project financial statements, including the audit report on the
project financial statements, will be guided by ADB’s Public Communications Policy (2011). 8 After
review, ADB will disclose the project financial statements for the project and the opinion of the
auditors on the financial statements within 30 days of the date of their receipt by posting them on
the ADB’s website. The Audit Management Letter will not be disclosed.
37. All advance contracting will be undertaken in conformity with ADB’s Procurement
Guidelines (2015, as amended from time to time) 9 and ADB’s Guidelines on the Use of
Consultants and Its Borrowers (2013, as amended from time to time). 10 The issuance of invitations
to bid under advance contracting will be subject to ADB’s approval. The borrower and NEGU have
been advised that approval of advance contracting does not commit ADB to finance the project.
7 ADB’s policy on delayed submission of audited project financial statements include the following:
• When audited project financial statements are not received by the due date, ADB will write to the executing agency
advising that (i) the audit documents are overdue; and (ii) if they are not received within the next 6 months, requests
for new contract awards and disbursement, such as new replenishment of imprest accounts, processing of new
reimbursement, and issuance of new commitment letters, will not be processed.
• When audited project financial statements have not been received within 6 months after the due date, ADB will
withhold processing of requests for new contract awards and disbursement, such as new replenishment of imprest
accounts, processing of new reimbursement, and issuance of new commitment letters. ADB will (i) inform the
executing agency of ADB’s actions; and (ii) advise that the loan may be suspended, if the audit documents are not
received within the next 6 months.
• When audited project financial statements have not been received within 12 months after the due date, ADB may
suspend the loan.
8 ADB. 2011. Public Communications Policy 2011: Disclosure and Exchange Information. Manila.
9 ADB. 2015. Procurement Guidelines. Manila.
10 ADB. 2013. Guidelines on the Use of Consultants by Asian Development Bank and Its Borrowers. Manila.
28
38. Advance contracting will be undertaken by PMU for the recruitment of supervision and
project management consultants.
39. Retroactive financing is the financing of project expenditures incurred by the borrower prior
to the effective date of the related loan agreement (or amendment). Retroactive financing will be
employed to allow NEGU to recover eligible costs incurred in the 12 months preceding the
amendment to the loan agreement, up to a cumulative value not to exceed 20% of the total ADB
loan amount, in accordance with the ADB Loan Disbursement Handbook 2017 (footnote 6).
40. All procurement of goods and works will be undertaken in accordance with ADB’s
Procurement Guidelines (2015, as amended from time to time). Procurement of civil works, which
will be financed entirely by NEGU, will be subject to, and will be governed by, all applicable laws
and regulations of the Borrower relating to procurement and contract management.
42. International competitive bidding procedure will be used for goods contract estimated to
cost $2,000,000 or more. ADB's standard bidding documents for goods contract will be used.
43. An 18-month procurement plan indicating threshold and review procedures, goods, works,
and consulting service contract packages and national competitive bidding guidelines is in Section
C.
44. All consultants will be recruited according to ADB’s Guidelines on the Use of
Consultants. 11
46. Supervision and project management consultant: Major change in scope of the
project. An estimated 150 person-months (66 international, 84 national) of consulting services
are required to provide technical, financial, and administrative support to the PMU during (i) the
rehabilitation of the high-voltage line L507 (500 kV) Guzar (Republic of Uzbekistan)–Regar
(Republic of Tajikistan) Regional Power Transmission Line Project on the territory of the Republic
of Uzbekistan in Surkhandarya Region (Component 1), and (ii) the construction of the 220 kV
11 Checklists for actions required to contract consultants by method available in the e-Handbook on Project
Implementation. ADB. 2012. Handbook on Project Implementation. Manila.
29
Substation in Zafarobod, and two high-voltage Power Transmission Line Project (220 kV) Sirdarya
TPP–Substation Zafarobod in Jizzakh Region (the Component 2). Estimated contract duration is
24 months. Consulting firms will be engaged using the QCBS method with a standard quality–
cost ratio of 90:10, considering a high level of technical expertise and experience required for the
supervision consultancy. The supervision and project management consultant contract has been
awarded as advance action in March 2021 and will be financed through retroactive financing, with
endorsement from the State Committee of Investment.
C. Procurement Plan
Basic Data
Project Name: Northwest Region Power Transmission Line Project
Project Number: 47296-001 Approval Number: 3285
Country: Executing Agency:
Uzbekistan Joint Stock Company National Electric Grid of
Uzbekistan
Project Procurement Risk: Implementing Agency: N/A
High
Project Closing Date:
Project Financing Amount: $255,500,000 30 June 2021
ADB Financing: $150,000,000
Cofinancing (ADB Administered):
Non-ADB Financing: $105,500,000
47. Except as the Asian Development Bank (ADB) may otherwise agree, the following process
thresholds shall apply to procurement of goods and works.
Procurement of Goods and Works
Method Threshold Comments
International Competitive Bidding for $2,000,000 and above
Goods
Shopping for Goods Up to $900,000 Prior review required
International Competitive Bidding for $5,000,000 and above Prior review required
Works
Government Procedure for Works No threshold (allowed for any amount) To be entirely financed by JSC
National Electric Grid of Uzbekistan
Consulting Services
Method Comments
Consultant's Qualification Selection for Consulting Firm Prior review required
Quality- and Cost-Based Selection for Consulting Firm Prior review required
30
48. The following table lists goods and works contracts for which the procurement activity
is either ongoing or expected to commence within the next 18 months.
Advertisement
Package General Estimated Procurement Review Bidding Date
No. Description Value Method (Prior/ Post) Procedure (quarter/year) Comments
Package Construction of 40,000,000.00 ICB Prior 1S1E Q2 2021 Prequalification
5 220 kV of Bidders: N
Zafarabad
Substation and Domestic
two line-bay in Preference
the Sirdarya Applicable: N
TPP
Bidding
Document:
Plant
Bidding
Document:
Plant
HVL = high-voltage line, ICB = international competitive bidding, kV = kilovolt, Q = quarter, TPP = thermal power plant.
49. The following table lists consulting services contracts for which the recruitment activity is
either ongoing or expected to commence within the next 18 months.
Review Advertisement
Package Estimated Recruitment (Prior/ Date Type of
Number General Description Value Method Post) (quarter/year) Proposal Comments
CS-2 External audit (three 500,000.00 CQS Prior Q3 2021 BTP Assignment:
multiyear contracts) International
4. Goods and Works Contracts Estimated to Cost Less than $1 Million and
Consulting Services Contracts Less than $100,000 (Smaller Value Contracts)
50. The following table lists smaller-value goods, works, and consulting services contracts for
which the activity is either ongoing or expected to commence within the next 18 months.
31
Review Advertisement
Package General Estimated No. of Procurement (Prior/ Bidding Date
Number Description Value Contracts Method Post) Procedure (quarter/year) Comments
None
Consulting Services
Review Advertisement
Package General Estimated No. of Recruitment (Prior/ Date Type of
Number Description Value Contracts Method Post) (quarter/year) Proposal Comments
None
51. The following table provides an indicative list of goods, works, and consulting services
contracts over the life of the project, other than those mentioned in the previous sections (i.e.,
those expected beyond the current period).
Goods and Works
Estimated Estimated
Package General Value Number of Procurement Review Bidding
Number Description (cumulative Contracts Method (Prior/Post) Procedure Comments
None
Consulting Services
Package General Estimated Number of Recruitment Review Type of
Number Description Value Contracts Method (Prior/ Post) Proposal Comments
None
52. The following tables list the awarded, ongoing, and completed contracts.
8.4. Coupling
connecting wires
8.11. Digital
dynamometer with
sensor
8.18. Anemometer
Pkg Lot 10.1. - Hydraulic 289 000.00 551,090.00 Shopping Q3 2019 21 Sep 2020 Xinjiang
3-Lot presses with a set of Qibao Trade
10 dies – 9 Co. Ltd
(PRC)
Lot 10.2 - Mobile
welding machines
Consulting Services
Awarded Date of ADB
Estimated Contract Advertisement Approval of
Package Value Value Recruitment Date Contract
Number General Description ($) ($) Method (quarter/year) Award Comments
PIC-01 Project 3,000,000.00 2,460,778.47 QCBS Q1 2015 30 Sep 2016 Awarded to
Implementation “Fichtner
Consultant GmbH”
(Germany)
CS-PIC 03 Project 2.000,000.00 EUR1,084,648 QCBS Q2 2020 PIC signed co
Implementation $730,360 ntract
Consultant for the submitted to
construction of ADB on 7
Guzar–Regar and April 2021
Zafarabad–
Syrdarya transmission
lines
2. Completed Contracts
Consulting Services
Date of ADB
Packa
Awarded Advertisement Approval of
ge
General Estimated Contract Procurement Date Contract
Numb
Description Value Value Method (quarter/year) Award Comments
er
G. Non-ADB Financing
53. The following table lists goods, works and consulting services contracts over the life of the
project, financed by Non-ADB sources.
54. ADB will review contract modifications in accordance with the procedures set forth in the
loan agreement between the borrower and ADB.
36
VII. SAFEGUARDS
55. Pursuant to ADB's Safeguard Policy Statement (2009) (SPS), ADB funds should not be
applied to the activities described on the ADB Prohibited Investment Activities List set forth at
Appendix 5 of the SPS. The government, through the NEGU, will ensure that all safeguard
requirements prescribed for the project that have been prepared will be implemented. The project,
in accordance with ADB SPS (2009), was categorized as “B” for environment, as “B” for
involuntary resettlement, and as “C” for indigenous peoples. Therefore, the following safeguard
documents were prepared for the original scope during project preparation:
(i) The initial environmental examination (IEE) report, including its environmental
management plan (EMP), was prepared. The IEE report identified potential impacts
related with the project and proposed mitigation measures and monitoring plan that were
presented in the EMP. The IEE report also includes the findings from the environmental
compliance audit report and recommended corrective actions for the existing facilities.
(ii) The land acquisition and resettlement plan (LARP).
56. The expansion of the scope of the project to include Output 4 (restoration of the 500 kV
line from Guzar to Regar) and Output 5 (construction of a 220 kV line from Syrdarya to the
Zafarabad substation in the Jizzakh region) does not change the environmental safeguard
categorization (Category B) and required preparation of discrete IEEs for each of these
subprojects, including critical habitats screening and preparation of framework biodiversity action
plans (F-BAPs) that were incorporated into the respective EMPs for these subprojects.
57. These two additional subprojects will involve both permanent and temporary land
acquisition. Approximately 8.06 ha will be permanently affected while 684.39 ha will be
temporarily affected. Most of the affected land are agriculture lands. Most affected households
are losing marginal portions of their agricultural land. However, eight households (with 48
members) located within the safety corridor will be physically displaced and are considered as
experiencing major impacts. These incremental impacts do not change the involuntary
resettlement category B of the Project. Separate draft LARPs were prepared for each subprojects.
Updated section-wise LARPs and social due diligence report (SDDR) will be prepared following
detailed design.
58. The government, through NEGU, is obliged to implement the recommendations from the
aforementioned IEEs (and their EMPs) and LARPs that were prepared with adequate consultation
with the people living in areas surrounding each subproject. The following paragraphs describe
briefly the activities to be implemented during project implementation and operation.
(i) Environment
59. Potential environmental impacts from all project activities, area of impact influence, project
alternatives, and their potential impacts were examined. Each discrete subproject’s EMP includes
the proposed mitigation measures, environmental monitoring and reporting requirements, related
institutional or organizational arrangements, capacity development and training measures,
implementation schedule, cost estimates, and performance indicators at each stage of the project
cycle. If any unanticipated environmental risks or impacts arise during construction,
implementation, or operation of each subproject that were not considered in the IEE and the EMP,
an update of the environmental assessment and EMP is required.
37
60. Environmental impacts are not expected to be significant and can be managed at all
stages: pre-construction, construction, operation and maintenance, and decommissioning.
61. Preconstruction activities have minor impact to soil, air quality, terrestrial vegetation, and
land use. Also, some noise and vibration are caused in this phase of the project. All these adverse
impacts can be minimized by mitigation measures proposed in the EMP, e.g., detailed planning
of the overhead line (OHL) corridor location, careful planning and execution of works, and by
selecting low-emission equipment. Permanent loss of agriculture land shall be minimized by
detailed planning of the OHL corridor location and compensated to the affected households
according to the LARP. The overall impact of the preconstruction phase is minor.
62. Most of the environmental impacts of the subprojects take place during the construction
of the OHLs and the expansion and rehabilitation of related substations and switchyards. Major
potential environmental impacts during the construction activities include limited impacts on land,
hydrology, soil erosion, and water quality, terrestrial and aquatic ecology, air quality and noise,
waste generation and disposal, oil management, historical and cultural resources, traffic
disturbance, health, and safety issue to workers and to the local communities.
63. The EMPs define required mitigation measures for adverse impacts of the construction of
the OHLs and related substations and switchyards. These measures include detailed planning of
the structures and routes, timing of the construction works, careful planning and execution of
works, selecting a low-emission equipment, health and safety training of the personnel and
informing local residents, and application of waste management good practices.
64. During the operation and maintenance phase, main impacts are noise from transformers
and wires, electromagnetic field, soil contamination due to spills, and occupational health and
safety risk. All these impacts can be minimized by careful planning of the structures and by proper
safety and accident prevention training of the personnel.
65. Environmental impacts caused by decommissioning activities are related to the waste
disposal, possible spills, and occupational health and safety issues. Proper waste management
practices, safety and accident prevention training of the personnel, and accurate planning and
execution of demolition works will be used to mitigate these possible adverse impacts. The overall
impact of the decommissioning phase is minor.
66. To assess and mitigate physical and economic involuntary displacement impacts caused
by the project and provide adequate displacement and rehabilitation assistance to the affected
households, a Land Acquisition and Resettlement Plan (LARP) was prepared. The LARP includes
the Entitlements Matrix summarizing all compensation and assistance provided in this project,
resettlement budget and financing plan, as well as implementation schedule for the land
acquisition and resettlement activities. The LARP is based on the pre-project design documents
and needs to be updated after approval of the detailed design.
38
(i) Permanent land acquisition for the construction of transmission line towers for the
erection of OHL towers permanently: 13.32 hectares (ha) of land will be required, from
which 4.35 ha are occupied by affected households (AHs); 118 AHs in Khorezm Province
and 36 in Karakalpakstan will be the objects of the permanent impact; and 8.97 ha of the
permanently affected land is state-owned, reserved, forest, and other land.
(ii) Permanent land acquisition for a new switch substation at Sarimay: land for a new 220
kV switching station at Sarimay will be allocated from state reserve land.
(iii) Temporary land acquisition for stringing the conductor cables of the transmission line:
temporarily affected area will be 536.01 ha in total; the AH’s land is 158.73 ha; 133 AHs
in Khorezm Province and 36 in Karakalpakstan will be the objects of the permanent
impact; and 377.28 ha of the temporarily affected area is state-owned, reserved, forest,
and other land.
68. AHs incurring impact on their cropping farmlands will not experience significant impact
since the impact in terms of percentage consists of a maximum 8.4%. There are no significantly
vulnerable AHs affected. Three disabled affected persons were identified in two AHs in
Karakalpakstan and one female-headed household in Khorezm.
69. For this project, the compensation for agricultural land is based on monetary
compensation only. The LARP sets eligibility and entitlement provisions establishing
compensation rates in accordance with guidelines from the Government of Uzbekistan and ADB’s
SPS 2009.
70. Under this project, AHs will not experience a significant loss of their productive assets. On
this basis, the income restoration and rehabilitation measures are not applicable for these
households, as described in the draft LARP. Livelihood improvement measures will be undertaken
under existing governmental social support scheme. If based on updated LARP, there arises a
need to develop income restoration program. NEGU will work closely with local community-based
organizations and authorities to provide the necessary support and develop income restoration
program.
71. The tentative LARP budget, based on compensation calculations for losses to agricultural
land, forestry trees and plants, agricultural land replacement, and support allowances, is
estimated to be $ 330,000. In order to ensure that sufficient funds are available for land acquisition
and resettlement tasks, NEGU, as the executing agency (EA), will allocate 100% of the cost of
compensation at replacement cost and expected allowances estimated in each LARP, plus
contingencies before LARP implementation.
72. The EA and ADB agreed to split project components into seven sections. The draft LARP
prepared during project processing stage have been updated into section-specific LARPs and
SDDRs. Social Due Diligence Reports for Sarimay and Khorezm substations were prepared and
endorsed by ADB. Also, ADB cleared Sections 2a and 6, as the LARP was updated and
implemented. The contractor started civil works on cleared sections. Submission of the LARP
update for (i) section 1 by 20 August 2019, (ii) section 2b by 11 September 2019, (iii) section 3 by
13 September 2019, and (iv) section 5 by 31 August 2019. After some delays, LARPs for these
remaining 4 sections were completed in April 2021 as confirmed by an independent monitor
engaged by ADB. LARP completion reports have been prepared for all the section-LARPs.
39
73. Separate LARPs were prepared for Output 4 and Output 5. ADB cleared the draft LARP
for Guzar-Regar transmission line rehabilitation in April 2020 and the draft LARP for Zafarabad-
Sirdarya transmission line and associated substation in November 2020.
74. Output 4 will require permanent land acquisition of 2.48 ha from 28 AHs. Additionally,
there will be temporary requisition of 171 ha from 21 AHs. The cost of compensation to affected
households is estimated at $0.143 million and will be the responsibility of NEGU.
75. Output 5 will require permanent land acquisition of 2.65 ha and temporary land requisition
of 306.69 ha. All land acquisition and requisition will be from agricultural lands and orchards, with
the exception of 0.34 ha from residential landholdings. One dwelling will be demolished, with one
AH to be relocated. The cost of compensation to AHs and landowners is estimated at $0.287
million and will be the responsibility of NEGU.
76. Section-wise LARPs and social due diligence reports (SDDRs) will be prepared following
the detailed design. In sections without LAR impacts, ADB approval of the SDDR is a condition
for commencing civil works, Compensation and other assistances prescribed in respective
subprojects’ LARPs will be scheduled and paid, in full, to the AHs prior to commencement of civil
works. The PMU will develop compensation payment plans after receiving the final design and
confirmation of amount of affected assets and number of AHs and landowners. PMU, with support
from its consultants, will closely monitor the EPCM contractors’ activities to ensure that works are
done only in sections without LAR impacts or in sections where LARP has been fully implemented.
In sections where compensation payments have been completed, PMU will prepare a LARP
implementation completion report that confirms and documents the completion of disbursement
of compensation. Monitoring of unanticipated LAR impacts during construction and grievances
from affected people will be done. Related to this, semi-annual social monitoring reports will be
prepared and submitted to ADB throughout project implementation which will be disclosed on the
ADB website.
77. No special action is required concerning Indigenous Peoples safeguards under this project
since there were no ethnic groups identified, which maintains cultural and social identities
separate from the mainstream Uzbek society, fitting the ADB definition of Indigenous Peoples in
the context of the project’s area of influence.
78. NEGU will have the overall responsibility to implement the EMP as the EA. The PMU
within NEGU hired Safeguards Specialist who is responsible for the EMP implementation,
monitoring, and reporting tasks set forth in the IEE.
79. The Project Management Consultant (PMC), recruited by NEGU, assisted the PMU in the
project implementation, monitoring, and reporting of the implementation of the EMP during the
construction phase. During the operation and maintenance phase, NEGU is responsible for
ensuring that the EMP implemented by the operators of the substations and the OHL. The PMC
is providing guidance to contractors in preparing site-specific EMPs (SEMPs) and endorse
SEMPs for NEGU approval before construction or physical work.
40
80. NEGU have overall responsibility to implement the LARP as the EA. The PMU is
responsible for the day-to-day management of the LARP implementation. The PMU team will
consist of Resettlement Expert responsible for planning, implementation, and monitoring of the
LARP. The PMU works closely with relevant government agencies and community-based
organizations. The PMU Resettlement Expert is carrying out internal monitoring routinely in close
coordination with local khokimiyat (government).
81. The PMU established a simple and accessible grievance redress mechanism (GRM) to
address grievances and complaints of any affected person in a timely and satisfactory manner.
NEGU will ensure the GRM is properly staffed and working on ground and that the procedure to
resolve issues will be followed strictly based on the five levels of grievance redressal.
82. The IEE report will be translated into Uzbek language and disclosed at project sites. The
English version of the IEE report will be posted on the ADB website. Public consultation is being
conducted along the transmission line route and in the communities where the substations are
located. Records of the consultation will be attached to the final draft IEE.
83. The public consultation process is an ongoing process, continuing throughout the project
phases and beyond. NEGU will do its best during construction, operation, and maintenance to
inform the public of major environmental issues and concerns related to its operation through
mass media and local community networks.
84. Nine consultations were carried out with the AHs during the LARP preparation. Similar
consultations need to be carried out after the LARP is updated and before starting payment of
compensations.
85. Disclosure meeting describing the final LARP will be organized to all AHs and respective
community-based organizations and local authorities during the LARP evaluation stage. A leaflet
in local language will be distributed to the AHs, relevant agencies, and civil society organizations
during the disclosure meeting. The draft and final LARP documents will be disclosed on the
websites of the NEGU and ADB upon approval by both ADB and the EA.
86. The project GRM will be disseminated via the LARP leaflet that will be distributed to the
AHs through local khokimiyat, the mahalla (local community), village assembly of citizens, or
farmers councils during the disclosure process.
87. A poverty and socioeconomic assessment report was prepared. The increased efficiency
and reliability of power supply resulting from the project will have a positive impact on economic
growth, poverty reduction, and social services such as schools, colleges and kindergartens,
clinics, and shops, which ultimately will improve well-being and community welfare. Improved
energy supply will have a positive effect on business development and, thus, supports new job
creation. The project has no gender issues envisaged during the project construction and
implementation. The improvement in the delivery of electricity will equally benefit households and
businesses run by women.
41
88. The revised design and monitoring framework strikes out content for deletion and
underlines content to be added.
Data Sources
and Reporting Risks and Critical
Results Chain Performance Indicators Mechanisms Assumptions
3. Support for a. At least 50 staff (at least 20% a.–b. NEGU’s
institutional women) trained in key aspects of project completion
development transmission network operation and report
and capacity maintenance by 2023 (2014
building baseline: 0)
3. NEGU’s capacities for project supervision and management enhanced and operational
efficiency improved
3.1 Project supervision and management consultants engaged by December 2015 (completed)
3.2 Staff from project management unit trained in procurement, contract management, financial
management, safeguards, and overall project management by project supervision and
management consultants by June 2021
3.3 Selection of new project supervision and management consultant by December 2020 (completed)
3.4 Execution of contract and consultant mobilization by April 2021 (completed)
5. Double-circuit 220 kV transmission line (142 km) between the Syrdarya TPP and the
Zafarabad substation in the Jizzakh region constructed
5.1 Tender documents finalized and issued by April 2021 for substations (completed)
5.2 Tender documents finalized and issued for high-voltage line by June 2021
5.3 EPC contract awarded for substation construction package by September 2021
5.4 Advance payment to EPC contractor for substation construction by September 2021
5.5 EPC contract awarded for high-voltage line construction package by December 2021
5.6 Advance payment to EPC contractor for high-voltage line construction by December 2021
5.7 EPC contractors for both packages mobilized by January 2022
5.8 LARP implementation completion reported by April 2022
5.9 Construction, commissioning, and final tests completed by December 2023
B. Monitoring
89. Project performance monitoring. The following indicators will be updated in the
quarterly progress reports and at the time of the semiannual meetings and the midterm review
expected approximately 12 months from the date of effectiveness of the loan amendment.
Financial indicators will be monitored annually at the time of submission of the annual financial
reports.
Financial Indicators
• Net income after tax – annually
• Debt service coverage ratio of NEGU (the ratio of cash flow from operations to annual
debt service obligations) – annually
• Self-financing ratio (the ratio of cash flow from operations to average capital
expenditures) – annually
• Days in receivables (average accounts receivable x 360 days/revenues)
91. Safeguards monitoring will be performed by the project supervision and project
management consultant and the PMU. The monitoring results will be included in the quarterly
progress reports, and semiannual environmental reports. Within 3 months after completion of all
civil works, a report on the project's environmental compliance performance (including lessons
learned that may help the PMU in their environmental monitoring of future projects) will also be
prepared. This report will be part of the input to the overall project completion report. The PMU
will prepare and submit to ADB semiannual environmental monitoring reports until ADB’s project
completion report is issued. The reports will be disclosed on the ADB website. The relevant
information of the reports in Russian and Uzbekistan languages will also be disclosed to the
affected people by posting on the NEGU website. In addition to the above-mentioned reports, in
case of any accident related to occupational and community health and safety, the PMU is
expected to (i) report to ADB within 72 hours, and (ii) prepare and submit an incident report with
45
action plan within 7 days of the occurrence. The project management consultant will support the
PMU in preparing such reports.
C. Evaluation
92. Inception Mission. ADB will field an inception mission after loan signing to (i) establish a
working relationship between ADB and the EA, and (ii) to ensure that the borrower and the EA
understand ADB's procedures.
93. Review Missions. ADB will field review missions at least once a year to review the overall
implementation of the project and update project implementation schedule based on mission
findings.
94. Midterm Review Mission. ADB will field a midterm review mission after approximately 12
months from the effectiveness of the loan amendment to allow the loan to finance Output 4 and
Output 5 to assess whether attainment of the project’s objectives (purpose in terms of the design
and monitoring framework) is still likely.
95. Project Completion Review Mission. ADB will field a project completion review mission
upon physical completion of the project to commence preparation of ADB's project completion
report. NEGU will submit a project completion report to ADB within 6 months of physical
completion of the project. 12
D. Reporting
96. NEGU will provide ADB with (i) quarterly progress reports in a format consistent with
ADB's project performance reporting system and containing sections on compliance with
safeguard requirements; (ii) consolidated annual reports including (a) progress achieved by
output as measured through the indicator's performance targets, (b) key implementation issues
and solutions, (c) updated procurement plan, and (d) updated implementation plan for the next
12 months; (iii) semiannual environmental monitoring reports starting from the contract award to
be submitted to ADB in January and July (within 1 month after each half calendar year) until ADB’s
project completion report is issued; 13 and (iv) a project completion report within 2 months of
physical completion of the project. To ensure projects to continue to be both viable and
sustainable, project accounts and the executing agency AFSs, together with the associated
auditor's report, should be adequately reviewed.
97. Project information will be strategically disseminated through media at main milestones
including loan signing, contract awards, and project completion. The GRM will be established at
the PMU and each relevant PES and distribution service centers, by phone and email, and
through public consultation events.
98. In compliance with the minimum requirements of ADB’s Public Communications Policy
(2011), the NEGU will designate an officer as focal point for regular contact with project-affected
people and other stakeholders at the PMU. The designated officer will be responsible for obtaining
the information from the complainant to identify source of the problem and verify the complaint.
The PMU shall provide project performance updates on progress every 6 months.
99. The work plan on public information program is summarized under XIII Gender and Social
Dimensions.
X. ANTICORRUPTION POLICY
100. ADB reserves the right to investigate, directly or through its agents, any violations of the
Anticorruption Policy relating to the project. 14 All contracts financed by ADB shall include
provisions specifying the right of ADB to audit and examine the records and accounts of the
executing agency and all project contractors, suppliers, consultants, and other service providers.
Individuals and/or entities on ADB’s anticorruption debarment list are ineligible to participate in
ADB-financed activity and may not be awarded any contracts under the project. 15
101. To support these efforts, relevant provisions are included in the loan agreement and/or
regulations and the bidding documents for the project. Procurement will follow ADB's
Procurement Guidelines (April 2015, as amended from time to time), consultant selection will
adopt ADB's Guidelines on the Use of Consultants (March 2013, as amended from time to time),
and disbursement will be made in accordance with ADB's disbursement policies, guidelines,
practices, and procedures.
102. People who are, or may in the future be, adversely affected by the project may submit
complaints to ADB’s Accountability Mechanism. The Accountability Mechanism provides an
independent forum and process whereby people adversely affected by ADB-assisted projects can
voice and seek a resolution of their problems, as well as report alleged violations of ADB’s
operational policies and procedures. Before submitting a complaint to the Accountability
Mechanism, affected people should make a good faith effort to solve their problems by working
with the concerned ADB operations department. Only after doing that, and if they are still
dissatisfied, should they approach the Accountability Mechanism. 16
103. All revisions and updates during the course of implementation should be retained in this
Section to provide a chronological history of changes to implemented arrangements recorded in
the project administration manual.