CMPM Report
CMPM Report
2. Introduction
Pre–planning is the key element in ensuring a successfully delivered project. It is at this stage
that potential risks are forecast and analyze together with establishing the mitigating
measures to prevent it. This stage helps the construction activities on schedule and move
along as efficiently as possible.
3. Learning Outcomes
4. Learning Content
It contains readings and discussions that students can work on individually or ingroups.
Topic 1: Planning
Topic 3: Worksheet
Topic 4: Timetable
Topic 1: Planning
The pre-planning stage establishes and determines the direction and success of any
construction project. Unfortunately, it seems that some engineers and contractors have not given
the pre-planning special emphasis despite their one direction of going there.
Past experience has proven that there are no shortcuts to sound construction pre-planning.
There is no new procedure to replace the following four basic rules for any job:
1. The construction superintendent should be included in the consultation at the very start of
the planning stage. Do not just present him later the finished plan and say: “here is the
plan for you to implement”
2. Make a job breakdown into components. This will simplify the whole program.
3. Prepare a construction plan that will be consulted constantly. Do not just file it in a
drawer only to accumulate dust.
4. Take advantage of new tools, which have demonstrated in saving time, money or
confusion.For instance, a computer can be used to layout on one sheet a detailed schedule
according to number of days, crafts, man-hours, costs, procurement and completion of a
process.
1. We are planning for the owners of the company when we plan to achieve a profit by
operating at the minimum capacity, utilizing the available resources.
2. We are planning for the employees when we plan to create or maintain jobs.
Four Dimensions of Planning Functions
The central figure in a project is the project manager. He bears the ultimate responsibility
for the success or failure of the project. His role in the construction is one of an organizer, a
person who is capable of working through others to accomplish the objectives of the project.
The job of project manager can be both difficult and rewarding. However, the rewardof
the job of project manager comes from:
Topic 3: Worksheet
The first step in construction pre-planning is to prepare a graph and plotting the
anticipated date of delivery of all major equipment at the site. The optimum time for each
construction activity could be analyzed. Severe craft peaks and uneconomical use of equipment
will appear on the projected graph, which could then be adjusted to prevent future conflicts in the
field.
By working backward from the expected completion date, the experienced project
manager can predict the latest possible starting date for any of the activities that make up the
whole construction project. The worksheet represents a plan of action presented graphically by a
critical sequence of functions of subsidiary activities contained within a compact period of time.
The initial move to get the project underway is for the Project Manager to convene a
preliminary discussion on the documents, and to gather more information as may be available at
the early stage. There should be additional and pre-planning information available such as, the
client's required operational date.
The project manager should conduct one or more informal sessions with key personnel assigned
to the project such as:
Then sequence of construction activities, which are related to optional early and late
starts, will serve as a running list of individual job components, with notations to work activities
with greater importance and priority over the others.
Specifications for equipment and materials, which are in the development, should be
processed according to their importance or urgency in the overall project. The design and
drafting effort can be organized, to produce those drawings that are necessary at the early stage
of the construction program for field installation or to complement an urgent purchase of
materials.
At this early stage of construction development, it is essential and timely for the
procurement committee to place orders for long term delivery of items at an early phase of
the project. The relative urgency of the on-site receipt as scheduled, may be used in establishing
a shop fabrication schedule with the supplier.
By manual method, it takes more time but results in a more accurate and realistic
summary as an anticipation of the need without reverting to an average manpower distribution.
On the other hand, manpower distribution by computer, lessens the engineers time but the
result is less realistic because it is applied on the average manpower loadings to the computer.
The manpower summary result will be lower than might be realistically anticipated. Where time
is available, the manual method prepared by an experienced engineer is preferred.
In either case, what is needed is the rate of anticipated manpower expenditure on the
basis of work category or classification or on the basis of crafts. In addition, it is a worthwhile
instrument in establishing the limit extremes of manpower application to summarize the
manpower loading in two ways:
Invariably, this review will result in a minor revision of the schedule. After gathering
most of the detailed information and made part of the timetable, the entire program is broken
down into several component parts.
After the projects have been delineated on the timetable as a separate job with minor
qualifications, it can be considered as a project itself. As the project becomes an active
construction program in the field, its progress, man-hour utilization, field labor expenditures,
quality and quantity of suspension, and major material status are all monitored and recorded at
the field and home office.
The manpower assignment for each activity on the timetable is then translated into a
graphical presentation, showing the anticipated manpower expenditures and the target progress
of the work in percentages.
By close control and evaluation of field cost and man-hour expenditures it can easily detect
the following:
A daily look at the graph, alerts the Project Manager and his home office to the possible need for
a radical action such as:
A periodic visit to the construction site is necessary for the various members of the central
construction department staff to audit the program so that:
1. A first hand review of the progress is made and the general status of the work is
compared with the timetable and discussed with the key field supervisory staff.
2. Home office assistance is offered to the field superintendent in pushing particular phases
of the project that may be held up in such areas as drafting of procurement.
3. Suggestions are made and discussed with the field organizations as to how its progress
can be improved.
Discussions and review of construction problems at the site assures a clearer understanding of
the work status for the following actions:
The site review gives everyone an opportunity for a general discussion of ideas and techniques
on concurrent construction work. The best pre-planning approach requires constant attention to a
construction project. Above all, pre-planning should be flexible enough to give it a chance to
adjust quickly and radically at any time when it is necessary.
The layout of these structures should be planned carefully, in anticipation of its removal
during the excavation of the permanent works more particularly, the storage and its contents,
which might cause disorganization and delays.
The job should be adequate, but not excessively staffed, to ensure efficient execution of
the work. Large construction work needs competent foramen. The contractor must be selective in
sending men of proven ability and qualification to start the work even if they are replaced later
by selected personnel engaged locally.
The construction site should be maintained in strict tidiness and in an orderly routine
because it has a psychological effect on the staff and workers, which promote conscientious
service Remember that the owner would like to see the actual work get- ting underway in its
fullest operation and orderliness.
In carrying out the construction work, idle time and unnecessary cost should be avoided.
Time saving devices such as telephone, loudspeakers, signal posts, traffic control, sign board
location and other economic measures should be installed immediately upon commencement of
the work. Before the work gets started, it should be first established from which the buildings
may be demarcated on the ground.
The excavator with his equipment should start cleaning, stripping and digging operations.
Material deliveries should also start as soon as possible and a labor force started the excavation
for the foundation work, etc. If all these operations get under way without undue delay, the job
will have a healthy aspect, high morale and satisfaction of all concerned from the owner to the
contractor and down to the lowly laborers.
The contractor should procure sufficient copies of the plan and specification to distribute
among his supervisory staff. This will thoroughly acquaint them with the details of the job.
Likewise, the subcontractors and consultant should be furnished with the plans and specifications
so that, there is no excuse for mistake and delay on this account.
1. Planning
2. Execution of major activities
3. Project phase out
Project construction life cycle requires various requirements such as:
Succession of personnel is the rotation of personnel who will be doing different kindsof job
according to their specialties. For instance:
1. Those doing the site relocation and preparation, and laying of foundation
2. Erecting the foundation and column, floor framework.
3. Constructing walls and partitions and roof
4. Plumbing and water supply connections including drainage system.
5. Mechanical equipment
6. Electrical and communication wiring system
7. Installation of kitchen, bathroom fixtures and appliances.
8. Interior finishing work
9. Doors and windows
10. Painting and varnishing, and other finishing works.
Organization of the work consists of making proper assignments and sequence of the
works in a systematic order aimed at making the best use of labor, materials and time. The
organization of the work is the responsibility of the contractor under the direction of the
supervising Architect or Engineer.
There are two independent but related spheres of control and responsibility that exist in
the project construction, namely:
Each has their own duties to perform in the interest of their employer - the owner. Most
of their respective duties and responsibilities were stipulated and defined in the contract, and all
will be better exercised if each one appreciates the duty and responsibility of the other. The
contractor is generally responsible to the owner for the following duties:
1. Providing and making access roads with due regards to the convenience of construction
2. Erection of site office in a central position to facilitate checking of all site activities.
3. Erection of store shed of adequate capacity to ensure:
a. Protection of materials against damage
b. Protection of materials against deterioration
c. Prevent materials from wastage and pilfering
4. Construction of temporary quarters and ancillaries for labor with due regard to site of
works, amenities and hygienic conditions.
5. Appointment of supervisory staff possessing technical knowledge and capable of
controlling the work and labor.
6. Early arrangement for construction equipment i.e.
a. Scaffolding
b. Formwork
c. Instruments and machinery with necessary screw fuel and parts etc.
d. Ladders
e. Tools
The Engineer or Architect on behalf of the owner is also responsible for the followingduties:
1. The preparation of a comprehensive time and progress chart for the execution of the
work.
2. The periodic revision of the chart as circumstances demand, and the regular comparison
of progress chart made with the program.
The project manager is required to prepare an approved time and progress chart, which is
generally part of the main contract documents.
1. The time and progress char must show an analysis of the chief elements and types of
construction involved in the project.
2. The scheduled dates of commencement and completion of every stage of the main
contract and of sub-contracts.
Without a proper program, the construction work can be disorderly. The time and
progress charts serve as the coordination and control of all the work under the different
subdivisions of the contract. With this time and progress chart it is easy to pinpoint where the
delay has occurred, and who is responsible for the delay.
Likewise, because of a clear definition of the dates, all parties concerned have to assume
their tasks making much easier for the contractor to finish the job on time.
Besides of being the standard requirement, the chart automatically shows and offer the
following information:
From this program, the owner can be furnished with particulars of the likely financial
requirements during the period of construction, and will be able to coordinate his program for
bringing the scheme into use.
Topic 9: Planning and Scheduling with Gantt Chart
The Gantt chart is a tool used for planning and scheduling simple projects. With the
chart, the project engineer can initially schedule project activities, and to monitor progress
overtime by comparing planned progress to actual progress.
To prepare the chart, the project manager has to identify the major activities that would
be required. Estimates for each activity are made and the sequence was determined. Once
completed, the chart indicates which activities were to occur including their planned duration,and
when they were to occur.
As the project progresses, the project manager would be able to see which activities were
ahead of schedule and which activities were delaying the project. This will enable the project
manager to direct attention where it was needed most to speed up the project to catch up with the
schedule.
The advantage of the Gantt chart is its simplicity, making it very popular. Gantt charthow
ever, fails to reveal certain relationships among activities that can be crucial to effective project
management. For instance, if one of the early activities would have to be delayed, it is because
they could not start until that activity was completed. Conversely, some activities may be
delayed without affecting the overall project schedule.
A Gantt chart does not directly reveal this information. Gantt charts are useful for simple
projects where activities are simultaneous or where a string of sequential activities are involved.
On more complex projects, Gantt charts can be useful for initial project planning, which then
gives way to the use of networks called PERT and CPM which will be discussed in Chapter 4 to
Chapter 8.
With their knowledge of the problems and the feeling of being part in setting the goal and
limitation of the department, the personnel give more effective consideration and cooperation on
the budget preparation.
The head of the department may act as the chairman of the department committee, but in
no case of a large department. He should delegate responsibility for the gathering details for the
committee. In other words, he should have an organization within his own department for the
preparation of the budget that follows the general patterns of the budget organization for the
company as a whole.
This organization will not only lead to a better budget preparation but will also serve asa
mechanism for budget control.
Financial budget represents a summary of the anticipated income and disbursement for
the budget period. The purpose is to plan for the allocations of working capital as presented by
the current assets of the company. Data for the financial budget are derived from the budget as
prepared by the different departments.
The financial budget must anticipate the cash receipt by months, quarter or other
designated period and make allowance for the raising of additional fund if needed to meet the
current expenses. This means that income from accounts receivables, notes receivables, cash
transaction and others, must be budgeted as accurately as possible.
1. The absolute necessities of the budget of various departments such as weekly or monthly
requirements of materials for construction, payroll etc.
2. Limitation of available cash.
It is not considered good management to have large amounts of cash lying idle to meet
unusually large expenditures. The interest being paid for such idle money has to be considered.
There are many problems arising out of attempted control of working capital, but these problems
must be anticipated and alternatives are selected to meet them.
In project construction, the importance of the procurement liability for getting the right
materials delivered from the suppliers to the site on time, cannot be taken for granted. A minor
item or low value material not available when needed can stop the construction activities, put
people out of work and delay of completion. For instance, in the absence of a common wire nails
carpentry work activities could be paralyzed. In general, the purchasing agent is made
responsible for maintaining the following major procurement factors:
1. Know and maintain records showing the materials and their possible substitute, sources
of supply, prices and quantities available.
2. Review specifications for possible simplifications and standardization of materials as
for unreasonable requirements.
3. Negotiate with suppliers for possible extension of credit.
4. Gather and analyze price quotations and fluctuations.
5. Place orders, with suppliers
6. Follow up purchase orders for delivery as specified
7. Audit invoices to check compliance with agreed terms and conditions
8. Maintain records of all purchases
9. Coordinate with other departments on all matters pertaining to procurement.
The prerequisite of any purchasing contract is meeting of the minds as to the exact nature
of the materials required and to be furnished. Material standard which defines the major
requirements such as: size, color, forms, composition, performance of the materials and also
the state acceptance terms and shipping conditions requires purchase specifications. There
are materials which are purchased by catalogue number, description or by its name. This practice
is practically simple but because of specifications of branded catalogue items are often subject to
change.
Purchase order usually starts from a purchase requisition. It specifies the kind, quantity
and when is to be delivered. Purchase requisitions are serially numbered as an aid in filing and
follow up. For items ordered regularly, a traveling requisition is used. This is a card-carrying the
usual information on the purchase requisition but with space for the word "repeat order". This is
used over and over again without the retrying data. This procedure, eliminate clerical works and
the need for a separate purchase history record.
Materials bought under continuing contract or those purchased repeatedly do not require
quotations from the supplier since all the necessary information is already available to both
parties. In case of repeat order, the purchase order form might include the phrase "as previously
furnished on our PO No.____. The unit price and discount expected will likewise be shown as
with the purchase order number and that of the original requisition.
Safety in the project construction must be given primary considered from the mechanical
side to the legal angles of workmen's compensation or even as a matter of training and
motivation toward safe work practices for workers.
The immediate supervisor's responsibility is to see to it that the working place is properly
arranged and maintained wherein the equipment, scaffoldings and the like are all Insafe
operating conditions. He should strictly see to it, that all workers do follow the safe working
habits.
A safety minded project engineer will make adequate provisions for safety measures to:
8. Assessment Task
In your own words, explain the stages of pre-planning, the importance of pre-planning in
construction and differentiate the role of a project manager to a project engineer.
9. References