RUANG PACKING
100.0%
A PEKERJAAN RELOKASI INSTALASI HVAC
Bongkar instalasi pemipaan unit AC 1.0 ls 3.00% 80.0% 0.8% 0.8% 0.8% 0.8%
Bongkar instalasi kabel power dan komunikasi AC 1.0 ls 1.50% 0.4% 0.4% 0.4% 0.4%
Bongkar panel power AC 1.0 ls 1.00% 0.5% 0.5%
Bongkar unit AC 5.0 unit 8.50% 70.0% 2.8% 2.8% 2.8%
Bongkar jalur Tray pemipaan AC 1.0 ls 2.48% 0.8% 0.8% 0.8%
Bongkar bordes catwalk 1.0 ls 2.00% 0.7% 0.7% 0.7%
60.0%
Bongkar unit Air Cooler 2.0 unit E 2.98% 1.0% 1.0% 1.0%
Bongkar instalasi kabel power Air Cooler 1.0 ls X 1.00% 0.3% 0.3% 0.3%
I
2 PEKERJAAN PEMASANGAN KEMBALI INSTALASI HVAC S 50.0%
Instalasi ulang ducting PU 1.0 ls T 18.85% 3.8% 3.8% 3.8% 3.8% 3.8%
Instalasi ulang ducting BJLS 1.0 ls I 6.40% 1.6% 1.6% 1.6% 1.6%
N 40.0%
Instalasi ulang pemipaan unit AC 1.0 ls G 6.35% 1.6% 1.6% 1.6% 1.6%
Instalasi ulang kabel power dan komunikasi AC 1.0 ls 3.27% 0.8% 0.8% 0.8% 0.8%
Pasang ulang panel power AC 1.0 ls 2.00% 30.0% 1.0% 1.0%
Pasang ulang unit AC 5.0 unit 8.55% 2.1% 2.1% 2.1% 2.1%
Instalasi ulang jalur Tray pemipaan AC 1.0 ls 4.24% 0.8% 0.8% 0.8% 0.8% 0.8%
Pasang ulang bordes catwalk 1.0 ls 4.00% 1.0% 1.0% 1.0% 1.0%
20.0%
Pasang ulang unit Air Cooler 2.0 unit 3.98% 1.3% 1.3% 1.3%
Instalasi ulang kabel power Air Cooler 1.0 ls 1.38% 0.7% 0.7%
10.0%
3 TEST AND COMMISSIONING 1.0 ls 3.00% 0.8% 0.8% 0.8% 0.8%
0.0%