Strata Control and Monitoring Plan
Strata Control and Monitoring Plan
BY
OM SUNIL KAITADE
PRIYANSHU SHARMA
NUTAN KUMAR YADAV
RAHUL KUMAR YADAV
H. O. D Course Incharge
Prof. ANAND KUMBHARE Prof. KHEMLAL JANGHEL
DATE : -
PLACE : - BHILAI
ACKNOWLEDGEMENT
Our heart pulsates with the thrill for tendering gratitude to those persons who helped us in the
completion of the project. The most pleasant point of presenting a thesis is the opportunity to
thank those who have contributed to it. Unfortunately, the list of expressions of thank no
matter how extensive is always incomplete and inadequate. Indeed, this page of
acknowledgment shall never be able to touch the horizon of generosity of those who tendered
their help to us. First and foremost, we would like to express our gratitude and indebtedness
to Prof. Khemlal Janghel for his kindness in allowing us for introducing the present topic and
for his inspiring guidance, constructive criticism and valuable suggestion throughout this
project work. We are sincerely thankful to him for his able guidance and pain taking effort in
improving our understanding of this project. We are also grateful to Prof. Anand Kumbhare
(Head of the Department) for assigning us this interesting project and for his valuable
suggestions and encouragements at various stages of the work. An assemblage of this nature
could never have been attempted without reference to and inspiration from the works of
others whose details are mentioned in reference section. We acknowledge our indebtedness to
all of them. Last but not least, our sincere thanks to all of our friends who have patiently
extended all sorts of help for accomplishing this undertaking.
Om Sunil Kaitade
Priyanshu Sharma
Bhilai - 490024
ABSTRACT
1 INTRODUCTION 01
CMRI-ISM GEOMECHANICS
4 CLASSIFICATION SYSTEM
06
8 BIBILOGRAPHY 29
1
INTRODUCTION.
EXAMPLE.
A granite rock mass containing 3 joint sets, average ROD is 88%,
average joint spacing is 0.24 m, joint surfaces are generally stepped
and rough, tightly closed and unweathered with occasional stains
observed, the excavation surface is wet but not dripping, average rock
material uniaxial compressive strength is 160 MPa, the tunnel is
excavated to 150 m below the ground where no abnormal high in situ
stress is expected.
Rock material strength 160 mpa Ratings 12
RQD (%) 88% Ratings 17
Joint spacing 0.24 m Ratings 10
Rough, unweathered,
Conditions of spacing Ratings 30
no separation
Ground water Wet Ratings 7
7
CMRI-ISM GEOMECHANICS
CLASSIFICATION SYSTEM.
This CMRI-ISM geomechanics classification system is developed by
Shri. Venkateshwarlu (former Director of CMRI) in 1989. It is based
on the Bieniawski’s RMR System. In this system, following five
parameters are used to classify a rockmass using the RMR System,
for designing the support system in underground coal mines. Each of
the five parameters Is assigned a value corresponding to the
characteristics of the rock. These values are derived From the field
surveys and laboratory tests. The sum of the five parameters is the
RMR value Which lies between 0 and 100.
1. Layer thickness (30)
2. Structural features (25)
3. Weatherability of rock (20)
4. Strength of rock (15)
5. Groundwater seepage (10)
The following table gives the CMRI-ISM geomechanics classification
system applicable for coal mine in India.
8
3. Weatherability of Rock :-
Weatherability is expressed in terms of the Slake Durability
Index.
For this, the standard laboratory slake durability test should be
carried out on fresh samples of roof rock collected from the
field.
Weigh exactly ten pieces of the irregular sample; place them in
the test drum immersed in water, rotate for 10 minutes; dry, and
weigh the material retained in the drum; take mean of three
values of the first cycle slake durability index (in %).
4. Rock strength :-
11
Rock load
16
(1) (a) The owner, agent and manager of every mine shall Prepare,
formulate and implement a Strata Control and Monitoring Plan
(SCAMP) based on scientific study Considering the geotechnical data,
information and the method of development and extraction of coal or
the Excavation required therefrom, which also includes a support plan
to secure the roof and sides of Belowground workplaces, and shall be
subject to revision with change in condition, for all workings
Belowground.
(b) The owner, agent and manager shall submit a copy of the Strata
Control and Monitoring Plan (SCAMP) to the Regional Inspector who
may, at any time by an order in writing, require such modification As
he may specify therein.
(3) The manager shall, at least thirty days before the commencement
of any operation, submit a copy f the support plan framed under sub-
regulation (2) to the Regional Inspector who may at any time, by an
order in writing, require such modification in the plan as he may
specify therein.
(4) The Manager shall hand over copies of the support plan framed
under sub-regulation (1) and (2), in English as well as in a local
17
(6) The support plan shall include inter alia, system of, monitoring of
the support performance, measurement of strata behaviour, re-setting
of supports, provision of temporary support, replacement of old
supports, withdrawal of supports and clearing of falls of ground.
(7) The support plan shall also include the implementation strategy of
the plan, training and inspection And supervision policies.
1) SCOPE &APPLICABILITY:-
This plan is called Strata Control Monitoring Plan (SCAMP) and is applicable
on workable seams of Saoner Mine No.2 i.e. Seam V, Seam IV (M) and Seam
IV (B) considering geotechnical data which includes support plan to secure the
roof and sides of below ground workplaces and shall be subject to revision with
change in condition, for all workings belowground.
The provisions of the Support Plan hereby framed under Reg. 123(2) of CMR-
2017 shall be applicable to the development working of the Seam V, Seam
IV(M) & Seam IV(B) as per the recommendation of suggested support system
based on the determination of RMR report vide letter no.
20
at an Interval not more than 1m, connecting the higher and lower levels of
the ledges along length of the gallery ensuring maximum contact between
the Open sides of the ledges and the W-strap.
III. Wherever the sides of pillars have a tendency to spall, the sides shall be
kept supported by bolting with W-straps in 1m x 1m grid pattern.
IV. All overhangs, which cannot be dressed and made safe, shall be kept
Supported by additional bolting with W-straps at an interval not more
than 1m.
V. All faults, visible slips, break and other geological disturbances in the
roof shall be supported by cogs at interval OF 2.4m on either sides of
such disturbances and with cross-bars across there at intervals not
exceeding 1.2m Or By roof bolting with W-straps in 1m x 1m grid
pattern.
VI. Positive support such as timber props and steel cogs or wooden sleepers
in combination with steel cogs shall be erected as and when necessary.
VII. Main roadways requiring permanent supports with bad roof conditions
shall be kept supported by cross steel girders placed on steel posts Or by
roof bolting with W-straps at an interval not more than 1m.
VIII. Rope stiching with cement capsule in addition to the normal support
whenever necessary in side and roof.
4) METHODS OF WORKS:-
In Saoner Mine No. 02 all the working seams are developed by Board & Pillar
Method.
II. All concerned persons such as dressers, supports men, shotfirer, Mining
Sirdar, Overman, Assistant Manager including person empanelled for
engagement as substitute supports men or dresser shall be made fully
conversant with this code of standing order by giving training, issuing
copies of this Safe Operating Procedures (SOP) in English and Hindi
language and also by posting this code of standing order at conspicuous
places and miners stations of the mine.
Erected support shall be checked at regular interval. Shall be reset as and when
required as per regulation 124 of CMR 2017 and concerned section in charge
will be responsible for the same.
Pit prop wooden chock and wooden prop shall be erected as temporary support
and concerned section in charge will be responsible for the same.
As and when required fresh roof bolting with W-strap shall be done whenever
any old unused working is reopened for work or whenever working commences
in any old district and concerned section in charge will be responsible for the
same.
Withdrawal of support shall be done in accordance with the method which shall
be specified in manager’s standing order as per reg. 125 of CMR 2017 and
concerned section in charge will be responsible for the same.
Mining Sirdar appointed under Reg. 129 of CMR 2017, Overman appointed
under Reg. 33 of CMR 2017 and Assistant Manager appointed under Reg. 30 of
CMR 2017 implement the support plan as framed in all working places.
The support shall be used in accordance with support plan and the workmanship
installing supports shall be the sole responsibility of support personnel
appointed under Reg. 35 of CMR 2017, However the efficiency shall be
checked and tested when necessary by officials appoint under Reg. 129, Reg. 33
and Reg. 30 of CMR 2017.
BIBILOGRAPHY.
ROCK-MECHANICS-FOR-ENGINEERS
BY-B.P VERMA