PM Project
PM Project
Project Management
Bank (AAA) Website Development
Supervisor:
Dr. Abdallah AL-Alawin
Name Student ID
Tala Dabbas 2035451
Marwan Hejazin 2042242
Omar Zaben 1837742
PROJECT CHARTER
1. PROJECT GOALS
This project aims to create a functional and user-friendly website that will serve as an
informational platform. It automates some or part of Bank AAA processes services such as online
account opening, loan applications, credit card applications, and a loan calculator tool, it will
showcase banking services, contact information.
This will help Bank AAA to adapt to the modern customer needs, elevate their services and
enhance communication between the bank and its customer by making the information accessible.
This project will put Bank AAA in a competitive position in the banking industry.
2. DELIVERABLES
3. SCOPE DEFINITION
The project will be a website and its main objective is to implement automation for specific functionalities.
This project will include automation of the online account registration and verification, automation of loan
application processes with a form and document submissions, automation of credit card application
processes with a form and necessary verification steps, and a loan calculator integrated into the website to
users accurately estimate loans terms and payment. This website should be flexible, available, reliable,
efficient, responsive, and easy to use.
Page 1
4. PROJECT MILESTONES
5. ASSUMPTIONS, CONSTRAINTS
Constraints:
7. PROJECT TEAM
Role Name
Project manager Tala Dabbas
Project Coordinator Marwan Hejazin
Technical Lead Omar Zaben
8. PROJECT AUTHORIZATION
Page 2
Approved by: Signature:
Dr. Abdallah Al-Alawin
Stakeholders analysis:
Page 3
might take part in
hiring and preparing
staff for the project.
Quality assurance Internal Tests the website to Medium High Keep informed
team ensure it meets
quality standards
and requirements.
IT support team Internal Provide technical Medium Medium Keep satisfied
support for the
website.
Finance External manages the Low Low Monitor
department project budget to
make sure the
project stays within
the resources
provided.
Page 4
Requirement:
Trainer 1.2.2.2 HR
4
Page 5
Scope statement:
Product
Acceptance • ensuring stakeholder approval before progressing to the subsequent stage.
Project • The project assumes the availability of essential content and information the
Page 6
Work Process Structure:
54 $6,450.00 17
Bank Website
Work Packages
Development
Time Cost Resources
1.1 •Initiation
• get necessary
1.1.1 7 $400.00 1
approval
•conduct
1.1.2 4 $200.00 2
feasibility test
1.2 •Planning
•Recruitment
1.2.1
vacancies
• Job
1.2.1.1 3 $300.00 1
advertisement
1.2.1.2 • job interviews 2 $400.00 2
1.2.2 •employee
1.2.2.1 •training 1 $500.00 1
•provide
1.2.2.2 4 $1,500.00 3
necessary equipment
1.3 •Executing
1.3.1 •implementation
•online account
1.3.1.1 registration and 3 $500.00 1
verification
Page 7
•loan
1.3.1.2 3 $500.00 1
application processes
•credit card
1.3.1.3 3 $650.00 1
application processes
1.3.1.4 •loan calculator 5 $900.00 1
•Monitoring &
1.4
Controlling
•users acceptance
1.4.1 7 $400.00 1
testing
•conduct soft
1.4.2 12 $200.00 2
lunch
1.5 •Closing
•archive required
1.5.1 7 $500.00 2
documentation
Activity Flow:
Page 8
Activity On Arrow:
Activity On Node:
Critical Path(s):
A-B-D-F-J-K-L-M
A-C-D-F-J-K-L-M
Page 9
Gantt Chart:
Estimation:
Top-Down (Approach Mehod):
Page 10
Bottom-UP:
Activities a m b Te V
Get necessary approval 2 7 9 7 1.361
Conduct feasibility test 3 4 10 5 1.361
Job advertisements 2 3 5 3 0.25
Job interviews 1 2 4 2 0.25
Provide necessary equipment 1 1 7 2 1.174
Training 2 4 8 5 1
Online account registration
3
and verification 2 7 4 0.694
Loan application processes 2 3 7 4 0.694
Credit card application
3
processes 2 7 4 0.694
Loan calculator 3 5 8 5 0.694
Users’ acceptance testing 4 7 10 7 1
Conduct soft lunch 10 12 15 12 0.694
Archive require
7
documentation 3 9 7 1
Total 67 10.87
𝑇𝑆 −𝑇𝐸
𝑧= Z=1.645
√∑𝜎𝑡𝑒2
𝑇𝑆 − 67
4.645 =
√∑10.872
𝑇𝑆 = 72 𝑑𝑎𝑦𝑠
Page 11
Communication plan:
Risk Assessment:
3 Frequent changes in
regulations L H Avoid
4 Rapid pace of
technological innovation H M Enhance
Page 12
Crash 10% for time:
Normal Crash
Activity Duration Duration Normal Cost Crash Cost
A 7 7 $ 400.00 $ 550.00
B 4 4 $ 200.00 $ 300.00
C 3 2 $ 300.00 $ 500.00
D 4 4 $ 1,500.00 $ 1,700.00
E 2 1 $ 400.00 $ 500.00
F 1 1 $ 500.00 $ 700.00
G 3 2 $ 500.00 $ 700.00
H 3 2 $ 500.00 $ 700.00
I 3 2 $ 500.00 $ 700.00
J 5 3 $ 900.00 $ 1,200.00
K 7 7 $ 400.00 $ 600.00
L 12 12 $ 200.00 $ 300.00
M 7 6 $ 500.00 $ 850.00
Page 13