11 - 2023 - The Impact of Detailed Distribution System Representation in Dynamic Sub-Transmission-Distribution Co-Simulation
11 - 2023 - The Impact of Detailed Distribution System Representation in Dynamic Sub-Transmission-Distribution Co-Simulation
ABSTRACT There has been a significant growth in the distributed energy resources (DERs) connected
to the distribution networks in recent years, increasing the need for modeling the distribution networks in
detail in conjunction with the sub-transmission/transmission networks. This paper models a real distribution/
sub-transmission network using a three-phase/three-sequence co-simulation. One of the modeled distribution
feeders has a high penetration of DERs with significant reverse power flow and is modeled including the
secondary network. Custom user-defined models are used to represent the solar photovoltaic (PV) units on
the feeder including advanced controls and abnormal voltage responses from IEEE 1547-2018 standard. The
co-simulation framework developed supports power flow/steady state as well as dynamic analysis. Using
this developed framework, this paper studies the impact of balanced and unbalanced faults applied to the
distribution and sub-transmission networks. The impacts of the faults on the feeder with the high penetration
of DERs are studied in terms of the solar PV units tripping due to under/overvoltages and the resulting
change in the feeder-head flow. It is seen that the detailed modeling of the distribution network is needed
for accurately capturing the response from the distribution-connected DERs during fault events both on the
distribution as well as sub-transmission networks.
INDEX TERMS Co-simulation, distributed energy resources, distribution systems, integrated transmission-
distribution analysis, power system dynamic simulation.
transmission/sub-transmission and distribution networks in The authors of [15] model the combined T&D system
an integrated fashion. using MATLAB/Simulink and study the impact of aggregate
The authors of [6] adopt a coupled simulation approach DERs including protection settings on dynamic stability for
for studying the impact of DERs on the fault induced delayed load changes and balanced/unbalanced faults using small test
voltage recovery. The coupling approach entails recording the networks. The authors of [16] simulate the combined T&D
responses from one domain/simulation to update the other system using DIgSILENT PowerFactory to study the bulk
domain/simulation. The drawback of the coupled simulation system impact of DERs and dynamic motor loads and use
approach is that due to the coupling process, each domain the simulation to parameterize the equivalent models to be
simulation has to be run multiple times before reaching used instead of a detailed distribution feeder representation.
convergence. Another approach for integrating the distribu- They model the transmission system in positive sequence
tion and sub-transmission/transmission is to model the entire and use a small test system to represent each feeder. The
system using a single modeling framework [7] or using authors of [17] consider the impact of solar PV units on
a single commercial software, such as ePHASORSIM [8]. stability using T&D co-simulation for different disturbances
However, a large number of available tools for transmission and different PV penetration levels. They consider a lim-
and distribution systems do not support integrated modeling ited number of large (∼100kW) DERs - this may not be
of both systems in the requisite detail, hence, co-simulation the case in a more residential area with a high number of
is seen as a suitable approach which allows the use of exist- small rooftop solar PV units. In [18], the load tap opera-
ing established software with the domain-specific modeling tions due to DER generation intermittency and the voltage
capabilities, features and algorithms while analyzing the dif- recovery after a fault event in presence of DER ride-through
ferent systems in an integrated fashion. are studied using T&D co-simulation. The authors rep-
Using either the co-simulation approach or the integrated resent a real transmission network in positive sequence
modeling approach, several works have been published and the distribution network in three phase detail, but the
in recent years discussing dynamic simulations involving DER units are represented using an aggregate model. The
models of both transmission/sub-transmission and distri- authors of [19] develop a two-level Schur-complement based
bution grids. The authors of [9] model the entire net- domain decomposition method including parallel processing
work (transmission/sub-transmission and distribution) using to simulate the differential-algebraic equations corresponding
dynamic phasors and validate the simulation results with to the combined transmission-distribution system. A case
detailed MATLAB/Simulink models for a small synthetic study on the expanded Nordic system showing a long term
test case. On the other hand, the authors of [8] create a voltage instability after a fault event is presented using
combined transmission-distribution (T&D) model for power this algorithm. In [20], dynamic equivalents of distribu-
flow and dynamic studies using ePHASORSIM for a real tion networks are formed though Monte-Carlo simulations
system. In [10] a scalable multi-timescale dynamic T&D using multiple disturbances to account for the uncertainty
co-simulation formulation is presented. The authors of [11] in the inverter based generation parameters. The perfor-
describe dynamic T&D co-simulation approaches with series mance of dynamic equivalents is compared with the detailed
and parallel solution schemes, and consider the impact of distribution system representation both with and without
the integration time step on the T&D co-simulation for both considering disconnections from inverter based generation.
approaches. The focus in these papers is on developing the These inverter based resources are shown to provide trans-
integrated modeling framework rather than the examination mission voltage support during and after clearing the fault.
of system response for specific disturbances or for examining Here, the residential rooftop installations are considered to
the impact of DERs on system performance. trip immediately after the inception of a fault, and sustained
One application of T&D dynamic co-simulation is to response from only larger installations is considered. The
enhance the load model representation of the distribu- authors of [21] consider a dynamic T&D co-simulation using
tion feeders. The authors of [12] use T&D dynamic HELICS and study frequency regulation/response from the
co-simulation to estimate static load parameters represent- DERs including application to a large synthetic network. The
ing the distribution feeders. The co-simulation formulation considered disturbances do not lead to low voltages where
from [11] is utilized in [13] to determine the composite load DER over/undervoltage trip/no trip characteristics would be
model parameters for capturing response from a specific important.
feeder. In [14] a three-phase/three-sequence dynamic T&D This study aims to model a real sub-transmission and dis-
co-simulation algorithm is developed using multi-area tribution network in detail (including the secondary network
Thévenin equivalent approach. This paper considers balanced and detailed models for rooftop solar PV units existing at
as well as unbalanced faults. The authors of [7] model the each residential location) using a three-phase/three-sequence
entire transmission-distribution network using a three-phase co-simulation framework and study the behavior of the mod-
formulation for a utility network and consider an unbalanced eled network for different balanced and unbalanced faults,
fault. However, these references do not consider the impacts considering the solar PV trip/no trip characteristics and
of DERs connected to the distribution feeders. advanced controls. The study establishes the importance of
FIGURE 15. The voltage profile for Feeder 4 and Feeder 5 with a
balanced three-phase to ground fault on Feeder 1.
FIGURE 13. The post-fault clearance ground current for Feeder 1
after applying a SLG fault for different solar PV penetration
cases.
FIGURE 29. The reactive power injected into the network by the
inverters at three distribution transformers for ‘‘primary’’ and
FIGURE 31. Feeder-head active power for ‘‘primary’’ and
‘‘secondary’’ models.
‘‘secondary’’ model during a balanced fault on the
sub-transmission model.
VII. CONCLUSION
This paper models a real sub-transmission-distribution net-
work in three-sequence/three-phase detail using a T&D
co-simulation formulation. The formulation is utilized to
study the impacts of different faults on the network. The
modeled network has a high penetration level of residential
rooftop solar PV generation. It is seen that under faults,
a large portion of these DERs may disconnect due to low or
FIGURE 30. Feeder 1 voltages for ‘‘primary’’ and ‘‘secondary’’ high voltage trips. Such trips may result in the active power
model during a balanced fault on the sub-transmission model.
flow at the feeder-head changing from reverse direction to
forward direction. If two of the three phases experience
transformer is shown as a bar chart in Fig. 29 for three trans- low/high voltages that cause solar PV generation trips, it is
formers connected to Feeder 1. Considering all the solar PV seen that at higher penetration levels the feeder may trip even
units, the combined reactive power injected from all the solar after the fault is cleared with the ground protection at the
PV units is different by 68 kVAr for the selected operating feeder-head with the present settings. Further, it is seen that
point (∼10% of the total reactive power from all the inverters advanced controls (such as volt-VAr) and advanced abnormal
or 14% of the feeder-head reactive power for this operating voltage responses as defined in the IEEE 1547-2018 standard
point). may alleviate some of the loss of solar PV generation. It is
For several balanced/unbalanced faults applied on the dis- observed that different feeders at the same substation may
tribution and sub-transmission systems, the response for both have very different responses for the same fault, indicating
the models is similar. However, for certain faults, the voltage the need to model different feeders at a substation sepa-
at the inverter terminal is above 0.45 p.u. after capturing the rately. By comparing two different network models, with
voltage rise across the secondary network whereas it is below and without the secondary network modeled in detail, it is
0.45 p.u. for the primary model – resulting in a difference in found that without modeling the secondary network, some
the number of solar PV units which are registered as tripped in overvoltages may not be captured in steady state, and that
both models. For one such case, where a balanced three-phase there may be an error in the estimated the reactive power from
to ground fault on the sub-transmission system is applied in the inverters operating in advance control modes such as volt-
the middle of one of the sub-transmission lines, the Feeder 1 VAr. Furthermore, by comparing the fault response for the
voltage profile and the feeder-head active power are shown in distribution feeder with and without modeling the secondary
Fig. 30 and Fig. 31, respectively. network, it is shown that the loss of solar PV generation may
Note that for this study the inverters are kept at unity be estimated incorrectly if the secondary network is ignored.
power factor mode. For this fault, in the primary model,
the solar PV generation tripped in Phases A, B and C are ACKNOWLEDGMENT
1219 kW, 1335 kW and 1175 kW respectively, while in The authors acknowledge the team at Arizona Public Service
the secondary model, the tripped generation are much less, for providing various inputs and for their work towards the