Tbs M Work Breakdown Structure
Tbs M Work Breakdown Structure
[AGENCY NAME]
[PROJECT NAME]
12/30/1899
TABLE OF CONTENTS
USING THIS TEMPLATE.....................................................................................................................1
REVISIONS........................................................................................................................................2
INTRODUCTION.................................................................................................................................3
OUTLINE VIEW.................................................................................................................................3
HIERARCHICAL STRUCTURE.............................................................................................................5
TABULAR VIEW................................................................................................................................6
TREE STRUCTURE VIEW...................................................................................................................7
WBS DICTIONARY...........................................................................................................................8
GLOSSARY OF TERMS.....................................................................................................................11
Work Breakdown Structure
[PROJECT NAME]
1
Work Breakdown Structure
[PROJECT NAME]
REVISIONS
2
Work Breakdown Structure
[PROJECT NAME]
INTRODUCTION
The Work Breakdown Structure (WBS) is a view into the project which shows what work the
project encompasses. It is a tool which helps to easily communicate the work and processes
involved to execute the project. The Project Manager and project team use the WBS to develop
the project schedule, resource requirements and costs. The objective should be to capture 100%
of the work for the project.
There are many ways to present the WBS for a project and this template provides many of the
most popular layouts from which to choose. Depending on where the WBS is placed in the
project plan, a different layout may be more suitable. For instance, many Project Managers
include a high level WBS within the project plan, and a more detailed version as an appendix to
the plan.
To save space in this template, WBS examples are developed to the third level only. In most
projects, the approach to the WBS use the 8 to 80 rule, which states that the WBS should be
decomposed down to a work package containing between 8 and 80 hours of work to complete.
The Work Breakdown Structure (WBS) presented in this document represents the work required
to complete [PROJECT NAME].
OUTLINE VIEW
The outline view presents an easy to view and understand layout for the WBS. It is also a good
layout to use when developing the WBS because changes can easily be made, especially since
the Microsoft Word auto numbering feature updates the WBS Code automatically.
3
Work Breakdown Structure
[PROJECT NAME]
4
Work Breakdown Structure
[PROJECT NAME]
HIERARCHICAL STRUCTURE
The hierarchal structure is similar to the outline view but without indentation. Although this
format is more difficult to read, it may be useful where there are many levels. Indenting each
level may potentially cause the table to be too sizable to fit into a document.
5
Work Breakdown Structure
[PROJECT NAME]
TABULAR VIEW
The Tabular View is a nicely organized table view of the WBS. It is a good option for
organizations that prefer table formats.
6
Work Breakdown Structure
[PROJECT NAME]
User Training
1.3.8
Go Live
1.3.9
7
Work Breakdown Structure
[PROJECT NAME]
WBS DICTIONARY
The WBS Dictionary contains all the details of the WBS which are necessary to successfully
complete the project. Most importantly it contains a definition of each Work Package, which can
be thought of as a mini scope statement. Resources on the project will review the WBS
dictionary to determine the scope of the Work Package they've been assigned, so it is important
to be clear when writing the definition. Most WBS dictionaries contain more information than is
shown in this sample, such as level of effort, cost control numbers, resource assignments,
responsibility assignments, etc.
WBS Dictionary
Level WBS Element Name Definition
Code
1 1 Widget Management System All work to implement a new widget
management system.
2 1.1 Initiation The work to initiate the project.
3 1.1.1 Evaluation & Recommendations Working group to evaluate solution sets
and make recommendations.
3 1.1.2 Develop Project Charter Project Manager to develop the Project
Charter.
3 1.1.3 Deliverable: Submit Project Project Charter is delivered to the
Charter Project Sponsor.
3 1.1.4 Project Sponsor Reviews Project Project sponsor reviews the Project
Charter Charter.
3 1.1.5 Project Charter Signed/Approved The Project Sponsor signs the Project
Charter which authorizes the Project
Manager to move to the Planning
Process.
2 1.2 Planning The work for the planning process for
the project.
3 1.2.1 Create Preliminary Scope Project Manager creates a Preliminary
Statement Scope Statement.
3 1.2.2 Determine Project Team The Project Manager determines the
project team and requests the resources.
3 1.2.3 Project Team Kickoff Meeting The planning process is officially
started with a project kickoff meeting
which includes the Project Manager,
Project Team and Project Sponsor
(optional).
3 1.2.4 Develop Project Plan Under the direction of the Project
Manager the team develops the project
plan.
8
Work Breakdown Structure
[PROJECT NAME]
WBS Dictionary
Level WBS Element Name Definition
Code
3 1.2.5 Submit Project Plan Project Manager submits the project
plan for approval.
3 1.2.6 Milestone: Project Plan Approval The project plan is approved and the
Project Manager has permission to
proceed to execute the project according
to the project plan.
2 1.3 Execution Work involved to execute the project.
3 1.3.1 Project Kickoff Meeting Project Manager conducts a formal kick
off meeting with the project team,
project stakeholders and project
sponsor.
3 1.3.2 Verify & Validate User The original user requirements is
Requirements reviewed by the project manager and
team, and then validated with the
users/stakeholders. This is where
additional clarification may be needed.
3 1.3.3 Design System The technical resources design the new
widget management system.
3 1.3.4 Procure Hardware/Software The procurement of all hardware,
software and facility needs for the
project.
3 1.3.5 Install Development System Team installs a development system for
testing and customizations of user
interfaces.
3 1.3.6 Testing Phase The system is tested with a select set of
users.
3 1.3.7 Install Live System The actual system is installed and
configured.
3 1.3.8 User Training All users are provided with a four hours
training class. Additionally, managers
are provided with an additional two
hours class to cover advanced reporting.
3 1.3.9 Go Live System goes live with all users.
2 1.4 Control The work involved for the control
process of the project.
3 1.4.1 Project Management Overall project management for the
project.
3 1.4.2 Project Status Meetings Weekly team status meetings.
9
Work Breakdown Structure
[PROJECT NAME]
WBS Dictionary
Level WBS Element Name Definition
Code
3 1.4.3 Risk Management Risk management efforts as defined in
the Risk Management Plan.
3 1.4.4 Update Project Management Plan Project Manager updates the Project
Management Plan as the project
progresses.
2 1.5 Closeout The work to close-out the project.
3 1.5.1 Audit Procurement An audit of all hardware and software
procured for the project. Ensures that all
procured products are accounted for and
in the asset management system.
3 1.5.2 Document Lessons Learned Project Manager along with the project
team performs a lessons learned
meeting and documents the lessons
learned for the project.
3 1.5.3 Update Files/Records All files and records are updated to
reflect the widget management system.
3 1.5.4 Gain Formal Acceptance The Project Sponsor formally accepts
the project by signing the acceptance
document included in the project plan.
3 1.5.5 Archive Files/Documents All project related files and documents
are formally archived.
10
Work Breakdown Structure
[PROJECT NAME]
GLOSSARY OF TERMS
It is important to provide a glossary of terms as some of the terms are not well understood by
persons without a project management background. For instance the PMI Practice Standard for
Work Breakdown Structures reference to the ‘WBS Code’ is commonly referred to as the ‘WBS
number’.
Term Definition
Level of Effort Level of Effort (LOE) is how much work is
required to complete a task.
WBS Code A unique identifier assigned to each element
in a Work Breakdown Structure for the
purpose of designating the elements
hierarchical location within the WBS.
Work Package A Work Package is a deliverable or work
component at the lowest level of its WBS
branch.
WBS Component A component of a WBS which is located at
any level. It can be a Work Package or a
WBS Element as there's no restriction on
what a WBS Component is.
WBS Element A WBS Element is a single WBS component
and its associated attributes located anywhere
within a WBS. A WBS Element can contain
work, or it can contain other WBS Elements
or Work Packages.
11