PS 1
PS 1
A. 6,845. 28 m C. 6,845.44 m
B. 6,845.34 m D. 6,845.54 m
A. 10,756.80 m C. 10,755.20 m
B. 10,756.20 m D. 10,755.80 m
1. To get the probable error of the mean of a set of 9. The elevation above mean sea level of the two endpoints
measurements, the probable err or of the same set must of a baseline for a triangulation system as determined by
be multiplied by differential leveling are 3,615.45 m and 3,615.22 m,
respectively. Determine the mean sea level length of the
A. 1/݊ C. 1/(݊ − 1) line if its actual measured horizontal length is 4,125.25
m. Assume that the radius of the earth at the vicinity of
B. 1/√𝑛 D. 1/√݊ – 1
the base line is 6,367.349 m.
A. 4,123.51 m C. 4,128.19 m
2. The sum of the squared residuals o f five (5) B. 4,123.19 m D. 4,128.51 m
measurements of line AB is 0.0322. What is the probable
error of line AB?
10. A two-base barometric leveling was conducted using three
altimeters. The elevations of Base A and Base B are 100 feet
A. ±0.037 C. ±0.017 and 200 feet above MSL, respectively. The altimeter
readings on the base stations and on another field station, C,
B. ±0.032 D. ±0.027 located in between the bases, are: A = 750 feet, B = 855 feet,
and C = 790 feet. What is the elevation of station C?
3. According to DMC 2010-23, which of the following is the A. 162 feet above MSL C. 238 feet above MSL
MINIMUM ALLOWABLE probable error value for
B. 138 feet above MSL D. 62 feet above MSL
electronic total station measurements?
A. ±(5mm + 2ppm) C. ±(10mm + 2ppm)
B. ±(5mm + 5ppm) D. ±(10mm + 5ppm) 11. NAMRIA stands for National __________ and Resource
Information __________.
A. Mapping; Administration
4. A 600-meter line is measured with an electronic t ot al B. Mapping; Authority
station. If the vendor’s accuracy specification of the C. Maps; Administration
instrument is ± (5mm + 5ppm), calculate the precision of D. Maps; Authority
the measured distance to the nearest thousands.
A. 1/75,000 C. 1/85,000
B. 1/80,000 D. 1/90,000
Situation 1. A geodetic leveling team physically recovered three (3)
NAMRIA benchmarks for a first order leveling densification project.
5. A 100-m line is measured with an electronic total station. The published elevations are as follows: BM4 = 21.688m, BM5 =
24.034m and BM6 = 29.404m. The team conducted differential
If the vendor’s accuracy specification of the instrument is
leveling (see field notes below) to determine which of the
± (2.5mm + 2 ppm), calculate the precision of t h e
benchmarks might be used as reference stations for the project.
measured distance to the nearest thousands.
A. 1/36,000 C. 1/35,000
Field Notes
B. 1/37,000 D. 1/38,000 Station BS (m) FS (m)
1.621
BM4 1.455
6. From point P on a level ground, the angle of elevation of the 1.289
top tower is 30º. If the tower is 100m high, then the distance 1.783 1.594
of point P from the foot of the tower is TP1 1.540 1.428
1.299 1.264
A. 57.74 m C. 173.21 m 1.346 1.566
B. B. 115.47 m D. 200.00 m TP2 1.200 1.290
1.054 1.014
1.717 1.426
TP3 1.584 1.290
1.451 1.154
PROBLEM SET 1
A. ±0.047 C. ±0.067
B. ±0.057 D. ±0.077
A. ±0.213 C. ±0.233
B. ±0.223 D. ±0.243
A. 1/39,000 C. 1/59,000
B. 1/49,000 D. 1/69,000