Weekly Progress Report - 27-Nov-23
Weekly Progress Report - 27-Nov-23
Weekly Progress Report - 27-Nov-23
Client: Bulleh Shah Packaging (Pvt.) Ltd. Mobilization Start Date: 20/Aug/22
Project Description : Finishing and Warehouse Building Direct Work Start Date: 6/Sep/22
Brief Scope: Construction of Finishing and Warehouse Building Civil Works Project Completion Date: 30/Apr/23
Location: Bulleh Shah Packaging , Kasur, Pakistan BL-1 Completion Date: 20/Jul/23
LF Completion Date: 30/Jan/24
2. Progress
Note:-LF S-Curve preparation is inprogress.
Project To Date
Description
Plan Actual
Overall Progress (%) 87.7 81.2
CCTR Description Unit BOQ Quantity Progress (This Week) Progress (To Date)
21880 Demolition m3 8,754 218 2.5% 7,942 90.7%
21122 Fixed Section Excavation m3 48,812 419 0.9% 44,412 91.0%
21133 Fixed Section Back Filling m3 38,112 323 0.8% 31,543 82.8%
21210 Cement Concrete Production and Supply at Location m3 22,611 301 1.3% 17,063 75.5%
21220 Concrete Placing in Sub-Structure m3 8,729 115 1.3% 5,362 61.4%
21230 Concrete Placing in Sup-Structure m3 8,830 89 1.0% 8,084 91.5%
21240 Concrete Flooring m3 5,051 96 1.9% 3,617 71.6%
21410 Steel Rebar ton 2,587 22 0.8% 2,176 84.1%
21510 Masonry (Brick) Work m3 4,562 106 2.3% 3,167 69.4%
21525 Plaster / Pointing Work m2 2,116 - 0.0% 1,430 67.6%
21810 Doors, Windows, Cabinets, Hand Rail m2 3,385 22 0.6% 2,313 68.3%
21840 Water Proofing / Roof Treatment m2 50,665 640 1.3% 37,235 73.5%
4. Manpower
Ratio
Added During Total
Description As of Last Week (Direct/Indir
Week (No's) (Nos.)
ect)
Total 331 -2 329
Zone-01&02:
-Line#F~C Plinth Beam Rebar, Formwork & Concrete is inprogress.
-Line#F~C Column Elevation ±199.65 To ±209.10 Rebar, Formwork & Concrete is inprogress.
-Line#A~C Bracing Beam Rebar, Formwork & Concrete is inprogress.
-Line#F~C Grid 6~7 Valley Beam Rebar, Formwork & Concreteis inprogress.
-Line#F~C Grid 7 Diaphragm Rebar, Formwork & Concrete is inprogress.
-Floor Chipping, Drilling, Lean Concrete, Rebar Fixing & Concrete is inprogress.
-Alumunium & Fixed Glass Work is inprogress.
-Brick work is inprogress.
-Backfilling Is Inprogress.
Drinage:
-Excavation is inprogress.
-Lean Concrete is inprogress.
-Footing Rebar, Formwork & Concrete is inprogress.
-Wall Rebar, Formwork & Concrete is inprogress.
-Slab Rebar, Formwork is inprogress.
Road:
-Demolation is inprogress.
-Excavation is inprogress.
CTMP:
-Footing Rebar, Formwork is inprogress.
-Beam Rebar, Formwork & Concrete is inprogress.
30 January, 2024
Planned Project Completion Date
81.2% 93%
0% 100% 0% 100%
120
Progress Completion
100 CTMP
100.0 30%
94.2 Ext Work 100%
80 87.7
79.6 Road 14%
72.2
68.6
60 64.7 Drainage 42%
61.1
54.2 Zone‐01&02 67%
40 46.7
Zone‐04 100.0%
39.7
20 31.0 Zone‐05 99.8%
20.7
14.6 Zone‐03 97%
8.6
0 4.0
‐20% 0% 20% 40% 60% 80% 100%
Series1 Remaining %
CCTR Summary Report Project To Date : 27‐Nov‐23
Descon Engineering Ltd. This Week : 66
Finishing and Warehouse Building Civil Works This Month : 15
Bulleh Shah Packaging , Kasur
Project Todate: 1
Project Todate Qty.
Sr. No Item Description Unit Std. Mhr Weeks Cum.
Total Balance
Planned Earned Planned Earned
1 Demolition M3 4.63 8,754 57 218 7,675 7,942 812
2 Fixed Section Excavation M3 0.66 48,812 25 419 44,650 44,412 4,400
3 Fixed Section Back Filling M3 0.63 38,112 6 323 35,646 31,543 6,568
4 Cement Concrete Production and Supply at Location M3 1.13 22,611 230 301 18,594 17,063 5,548
5 Concrete Placing in Sub‐Structure M3 5.21 8,729 135 115 6,291 5,362 3,367
6 Concrete Placing in Sup‐Structure M3 7.46 8,830 22 89 8,087 8,084 747
7 Concrete Flooring M3 24.60 5,051 45 96 4,158 3,617 1,434
7 Steel Rebar Ton 61.38 2,587 13 22 2,318 2,176 411
8 Masonry (Brick) Work M3 14.01 4,562 73 106 3,869 3,167 1,395
9 Plaster / Pointing Work M2 1.60 2,116 22 ‐ 1,978 1,430 686
10 Doors, Windows, Cabinets, Hand Rail M2 1.51 3,385 75 22 2,914 2,313 1,072
11 Water Proofing / Roof Treatment M2 1.13 50,665 516 640 44,167 37,235 13,430
Area Wise Civil Qty. Report Project To Date : 27‐Nov‐23
Descon Engineering Ltd. This Week : 66
Finishing and Warehouse Building Civil Works This Month : 15
Bulleh Shah Packaging , Kasur Project Todate: 1
100 100.0
94.2
90
87.7
80 79.6
70 72.2
68.6
64.7
Progress Percentage %
60 61.1
54.2
50
46.7
40 39.7
30 31.0
20 20.7
14.6
10 8.6
4.0
0 0.42
Sep‐22 Oct‐22 Nov‐22 Dec‐22 Jan‐23 Feb‐23 Mar‐23 Apr‐23 May‐23 Jun‐23 Jul‐23 Aug‐23 Sep‐23 Oct‐23 Nov‐23 Dec‐23 Jan‐24
Planned BL‐1 0.46 4.4 9.4 15.9 23.3 33.3 45.6 60.3 80.3 92.9 100.0
Planned LF 0.42 4.0 8.6 14.6 20.7 31.0 39.7 46.7 54.2 61.1 64.7 68.6 72.2 79.6 87.7 94.2 100.0
Cum. Actual 0.42 4.0 8.6 14.6 20.7 31.0 39.7 46.7 54.2 61.1 64.7 68.6 72.2 76.1 81.2
Manpower Strength
DATE 27‐Nov‐23
INDIRECT Total DIRECT Total
Sr # Craft DESIGNATION G‐Total
ABSENT PRESENT ABSENT PRESENT
1 M SITE MANAGER ‐ 1 ‐ ‐ 1
2 M CONSTRUCTION MANAGER ‐ 1 ‐ ‐ 1
3 M INCHARGE CIVIL ‐ 1 ‐ ‐ 1
4 M INCHARGE PLANNING ‐ 1 ‐ ‐ 1
5 M INCHARGE ADMIN ‐ 1 ‐ ‐ 1
6 M INCHARGE STORE 1 ‐ ‐ ‐ 1
7 M INCHARGE HSE ‐ 1 ‐ ‐ 1
8 M INCHARGE E&P ‐ 1 ‐ ‐ 1
9 M INCHARGE QA.QC ‐ 1 ‐ ‐ 1
10 M HSE SUPERVISOR ‐ 3 ‐ 2 5
11 N DISPENSER (QUALIFIED) ‐ 2 ‐ ‐ 2
12 M CIVIL QS/AREA PLANNER ‐ 3 ‐ ‐ 3
13 N ASSISTANT/STORE KEEPER 1 4 ‐ ‐ 5
14 M SURVEYOR CIVIL ‐ ‐ ‐ 2 2
15 M SUPERVISOR CIVIL ‐ ‐ 2 7 9
16 M SUPERVISOR RIGGING ‐ ‐ ‐ 1 1
17 N LEAD MAN ‐ ‐ ‐ 11 11
18 N MASON ‐ ‐ 2 17 19
19 N CARPENTER ‐ ‐ 2 41 43
20 N STEEL FIXER ‐ ‐ 1 24 25
21 N SCAFFOLDER/Helper ‐ ‐ 6 62 68
22 N LABOUR/HELPER ‐ ‐ 10 63 73
23 N FABRICATOR ‐ ‐ ‐ 2 2
24 N FITTER/Welder ‐ ‐ 1 14 15
25 N RIGGER ‐ ‐ 1 7 8
26 N ELECTRICIAN ‐ ‐ ‐ 2 2
27 N Admin Staff ‐ ‐ 3 7 10
28 N EQUIPMENT OPERATOR / DRIVER ‐ ‐ 2 15 17
Grand Total 2 20 30 277 329
Equipment Status
Date: 27-Nov-23
Break
Sr. No Description Unit Deployed Working Remarks
Down
1 Concrete Batching Plant 30 Cum / Hr No's 1 1 -
2 Concrete Transit Mixer Mobile 6.0 M3 No's 2 2 -
3 Concrete Pump No's 1 1 -
4 Crane 45 Ton Truck Mounted No's 1 1 -
5 Crane 25 Ton Truck Mounted No's 1 1 -
6 Loader Front End 2.75 M3 No's 1 1 -
7 Tractor Trolly No's 1 1 -
8 Welding Generator No's 1 1 -
9 Air Compressor No's 1 1 -
10 Roller 1 Ton No's 2 2 -
11 Concrete Cutter No's 1 1 -
12 Jackhammer Excavator No's 1 1 -
13 Excavator No's 1 1 -
14 Crane 5 Ton Truck Mounted No's 1 1 -
15 Tractor Trolly No's 3 3 -
16 Dump Truck No's 1 1 -
Total 20 20 0
Zone-01& 02 Foundation/Column
Progress Layout
1
1 1 1 1 1 1 1
Concrete Demolition 99 99 0
Excavation 99 97 2
Lean Concrete 99 94 5
Footing Rebar Fixing 99 96 3
Footing Concrete 99 94 5
Column Concrete Pour#1 129 121 8
Column Concrete Pour#2 129 118 11
1 Pour#3
Column Concrete 129 117 12
Column Concrete Pour#4 121 107 14
Zone-01 & 02 Plinth Beam Layout
Date: 27-Nov-23
Date: 27-Nov-23
Sep-22 295
1 Rain at different span period 11/Sep/22 12:00 PM 6:00 PM 6
2 Heavy rainfall over a variety of time periods 24/Sep/22 7:00 AM 7:00 PM 10
3 Heavy rainfall over a variety of time periods 25/Sep/22 7:00 AM 7:00 PM 10
Due to heavy rain to resume the direct work and cleaning
4 26/Sep/22 7:00 AM 7:00 PM 10
and dewatering
5 Due to rain, resume the direct work 15/Oct/22 8:00 AM 2:00 PM 6
6 BSP does not issue work at height permits during foggy con 07/Dec/22 8:00 AM 11:00 AM 3
7 BSP does not issue work at height permits during foggy con 13/Dec/22 8:00 AM 10:00 AM 2
8 BSP does not issue work at height permits during foggy con 15/Dec/22 8:00 AM 11:00 AM 3
9 BSP does not issue work at height permits during foggy con 16/Dec/22 8:00 AM 11:00 AM 3
10 BSP does not issue work at height permits during foggy con 17/Dec/22 8:00 AM 11:00 AM 3
11 BSP does not issue work at height permits during foggy con 18/Dec/22 8:00 AM 11:00 AM 3
12 BSP does not issue work at height permits during foggy con 19/Dec/22 8:00 AM 10:00 AM 2
13 BSP does not issue work at height permits during foggy con 20/Dec/22 8:00 AM 10:00 AM 2
14 BSP does not issue work at height permits during foggy con 21/Dec/22 8:00 AM 11:00 AM 3
15 BSP does not issue work at height permits during foggy con 22/Dec/22 8:00 AM 11:00 AM 3
16 BSP does not issue work at height permits during foggy con 23/Dec/22 8:00 AM 10:00 AM 2
17 BSP does not issue work at height permits during foggy con 23/Dec/22 6:00 PM 7:00 PM 1
18 BSP does not issue work at height permits during foggy con 24/Dec/22 8:00 AM 11:00 AM 3
19 BSP does not issue work at height permits during foggy con 25/Dec/22 8:00 AM 11:00 AM 3
20 BSP does not issue work at height permits during foggy con 26/Dec/22 8:00 AM 11:00 AM 3
21 BSP does not issue work at height permits during foggy con 27/Dec/22 8:00 AM 11:00 AM 3
22 BSP does not issue work at height permits during foggy con 28/Dec/22 8:00 AM 10:00 AM 2
23 Due to rain, resume the direct work 29/Dec/22 8:00 AM 7:00 PM 10
24 BSP does not issue work at height permits during foggy con 31/Dec/22 8:00 AM 10:00 AM 2
25 BSP does not issue work at height permits during foggy con 01/Jan/23 8:00 AM 11:00 AM 3
26 BSP does not issue work at height permits during foggy con 02/Jan/23 8:00 AM 11:00 AM 3
27 BSP does not issue work at height permits during foggy con 03/Jan/23 8:00 AM 12:00 PM 4
28 BSP does not issue work at height permits during foggy con 03/Jan/23 6:00 PM 7:00 PM 1
29 BSP does not issue work at height permits during foggy con 04/Jan/23 8:00 AM 12:00 PM 4
30 BSP does not issue work at height permits during foggy con 05/Jan/23 8:00 AM 12:00 PM 4
31 BSP does not issue work at height permits during foggy con 06/Jan/23 8:00 AM 12:00 PM 4
32 BSP does not issue work at height permits during foggy con 08/Jan/23 8:00 AM 11:00 PM 3
33 BSP does not issue work at height permits during foggy con 09/Jan/23 8:00 AM 11:00 PM 3
34 BSP does not issue work at height permits during foggy con 10/Jan/23 8:00 AM 11:00 PM 3
35 BSP does not issue work at height permits during foggy con 11/Jan/23 8:00 AM 12:00 PM 4
36 BSP does not issue work at height permits during foggy con 11/Jan/23 8:00 AM 11:00 PM 3
37 BSP does not issue work at height permits during foggy con 18/Feb/23 8:00 AM 11:00 PM 3
38 BSP does not issue work at height permits during foggy con 27/Feb/23 8:00 AM 3:00 PM 7
39 Due to rain, resume the direct work 22/Mar/23 8:00 AM 2:00 PM 6
40 Due to rain, resume the direct work 01/Apr/23 8:00 AM 4:00 PM 8
41 Due to rain, resume the direct work 03/May/23 10:00 AM 4:00 PM 6
42 Due to rain, resume the direct work 04/May/23 2:00 AM 7:00 PM 5
43 Due to rain, resume the direct work 25/May/23 12:00 AM 3:00 PM 3
44 Due to rain, resume the direct work 26/May/23 7:00 AM 3:00 PM 8
45 Due to rain, resume the direct work 10/Jun/23 7:00 AM 12:00 PM 5
46 Due to rain, resume the direct work 15/Jun/23 7:00 AM 4:00 PM 9
47 Due to rain, resume the direct work 26/Jun/23 7:00 AM 11:00 PM 4
48 Due to rain, resume the direct work 05/Jul/23 7:00 AM 11:00 PM 10
49 Due to rain, resume the direct work 07/Jul/23 7:00 AM 11:00 PM 10
50 Due to rain, resume the direct work 08/Jul/23 7:00 AM 11:00 PM 10
51 Due to rain, resume the direct work 16/Jul/23 9:00 AM 1:00 PM 4
52 Due to rain, resume the direct work 22/Jul/23 7:00 AM 12:00 PM 10
53 Due to rain, resume the direct work 23/Jul/23 7:00 AM 12:00 PM 10
54 Due to rain, resume the direct work 27/Jul/23 7:00 AM 12:00 PM 10
55 Due to rain, resume the direct work 29/Jul/23 7:00 AM 12:00 PM 10
56 Due to rain, resume the direct work 09/Sep/23 3:00 PM 5:00 PM 2
57 Due to rain, resume the direct work 17/Sep/23 11:30 AM 12:30 PM 1
58 Due to rain, resume the direct work 16/Oct/23 7:00 AM 11:00 AM 4
59 Due to rain, resume the direct work 17/Oct/23 7:00 AM 10:00 AM 3
60 Due to rain, resume the direct work 10/Nov/23 7:00 AM 6:00 PM 10
Total 295