Epc Issues
Epc Issues
How are the PSA and PSC requirements on the Cover Page worksheet triggered? I
suspect that these would be triggered by the responses to Qs 17 & 21 but even
selecting the most severe answers didn't trigger this on a completed the Cover Page.
Q17 - based on the following definition "Work activity: There are activities which carry some risk but gener
Q18 - Are the conditions 'Or' or 'And'? If the former, then seems onerous to blanket require PM
Competency 3+ for all projects in CPI < 75.
Do I understand it correctly, then - any new SERA review & update after 24/11/2023 (the issue date of the
new Requirements) should be done using the new SRA (formerly SERA) template, Version 1.0?
Same for new PCM, Version 6.0 (the new Guidance on EPC was also issued on 24/11)?
What if, following a project audit after 24/11, nothing triggers a review & update of the PCM whereas
SERA needs to be updated as it is more than one-year-old?
My own view of the pre-population of the RCT from the PCM outputs was that it gave a list of
not-necessarily relevant aspects which didn't really help consider project-specific risks. However,
will be interesting to hear what the link between the PCM & RCT will be going forwards.
1. I like that there is transparency for the rules / criteria for what automatically triggers a LOC rating, but
I also feel this approach to ‘automatically trigger’ devalues the assessment in it’s entirety. If I answer one
question that is indicative of a LOC300, even if every other answer was LOC 100, it would still be LOC300.
Is that the intention because otherwise we may as well stop there in the assessment rather than spent
lots of time completing the whole form. Again considering what this tool is aiming to do is to get the
appropriate level of competency to manage the project. If it is deemed the current approach is
appropriate then we should just ignore any question where the max value is LOC200?
2. To do with column Z for the automatic update, there are some descriptors for dependent questions
which are inconsistent. See below (Q2, Q7, Q11, Q13)
@James Walton can you please also assist – Josh has a signed Framework agreement, as a result it is not a
signed contract with a fixed value – please advise what value he should include in the PCM? The
framework agreement is over a 5 year period and it is for a low risk project (water modelling and
monitoring).
Project Complexity Model – Consult the PSA box. Question 17 of the assessment tab, column G asks you
to ‘consult a PSA for advice and support’ so I think the ‘Consult a PSA’ box on the cover page is confusing.
I’m also unable to find the requirement to consult a PSA for advice and support on STEP. I believe it used
to be the case that a PSA had to be consulted with evidence kept of the discussion if no PSA/PSWR
needed? Grateful if you could advise. It would be good to have consistency here.
Reporter
Dominic Simpson
Dominic Simpson
Dominic Simpson
Dominic Simpson
Dominic Simpson
Dominic Simpson
Dominic Simpson
Dominic Simpson
Yavor Kehaiov
Dominic Simpson
Josh Foulkes
Josh Foulkes
Clare Nissen
Issue Reporter
Benyamin Tedjakusuma
Issue Reporter