Project Planning - Fabrication of 22M Long Reach Boom
Project Planning - Fabrication of 22M Long Reach Boom
Project Planning - Fabrication of 22M Long Reach Boom
ID Task Task Name Duration Jan 10, '21 Jan 17, '21 Jan 24, '21 Jan 31, '21 Feb 7, '21
Mode S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
1 FABRICATION OF 22M LONG REACH BOOM/ARM FOR CAT345BL 21 days
2 Preliminary 6 days
3 - Engineering studies and Production of shop drawings 1 day
4 - Material Purchases 5 days
5 Prefabrication in the Workshop 13 days
6 - Cutting of assorted pieces from design 6 days
7 - Welding and assembling of structure 4 days
8 - Sandblasting and Priming of Prefabricated profiles 2 days
9 - Mobilization to site for installation 1 day
10 Installation on site 3 days
11 - Mounting of Boom/Arm on the Catapiller 345 engine. 3 days
12 Demobilization from site 1 day
13 - Housekeeping and Transportation of equipment from site 1 day
Project: Project Planning Split External Tasks Inactive Summary Manual Summary Progress
Date: Mon 1/4/21 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only