5.1 MAINTENANCE SCHEDULE
5.1. List of Required Regular Maintenance Works
A regular maintenance helps to minimize standstill periods, to maximize life of components and of the overall
plant and to maintain a high level of performance.
Please note that the information in the following table must be regarded as GENERAL RECOMMEN-
DATIONS which cannot allow for individual conditions and therefore need to be updated and com-
pleted according to own experiences of the operator.

Information supplied separately or in the appendices of this manual may contain


further required works.

Component Required works Recommended interval Page

Batch funnel Free sieve grizzle (if installed) from Daily -


large stones
Clean batch funnel Before material change or standstill, also -
whenever regarded necessary
Parallel-shaft helical Clean gear and change oil Every 2 years (with synth. oils: every 4 5.3.1-2
gear unit years)
Check oil level Weekly -

Replace and re-grease rolling bear- Every 4 years 5.3.1-1


ings
Vibration motor Replace rolling bearing - At 100% vibration intensity: after 5.3.3-3
approx. 3,000 operating hours or
every 18 months
- At 50% vibration intensity: after
approx. 24,000 operating hours or
after 12 years
1)
Outlet belts Re-grease drive and return Weekly 5.3.5-1
drums on grease fittings
1)
Short material detector Re-grease grease fittings on Weekly 5.4.1-1
transmitter bearing
Check function and free movement Daily -
Watch if vibration motor reacts on Daily -
short material detector
Tackle line emergency General inspection every 200 operating hours or monthly 5.3.4-3
switch
Trunk conveyor Check the head scrapers. Replace, every 200 operating hours or monthly -
if necessary
Check belt run Twice daily -
Re-grease drive and return drums Weekly 5.3.5-1
on grease fittings
Clean belt rollers Weekly -
Check belt for damage Daily -
Check feeding funnel. Clean, if Twice daily
necessary
Clean the floor below the cleaning Twice daily
unit and the feeding funnel
________________________________________________________________________________________________
1) Recommended lubricants: Standard Multi-purpose Grease (See table below for examples of suitable trade marks))

Version: 150304a LINTEC GmbH & Co. KG

You might also like