Agile
Agile
2. Which is NOT one of the four corporate roles which could substitute for the Scrum Product Owner
role?
a. Project Manager
b. Service Owner
c. Process Owner
d. Service Manager
3. In a matrix-management structure, resources can split time between operational and project activities.
a. True
b. False
7. For which type of resistor is this an appropriate management response: organizations should change
team composition, model and praise the desired behaviour, involve followers in the process, and
determine the root cause of resistance, whether it is awareness, desire, or ability.
a. Follower
b. Saboteur
c. Diehard
d. Skeptic
10. A Gemba walk, involves Project team members going to where a process occurs and observing the
process in action.
a. True
b. False
13. Continuous Improvement specifically refers to the process of implementing incremental change that
reduces or eliminates waste.
a. True
b. False
18. Rather than identifying defects after a product has been completed, the goal is to minimize defects
from occurring in the first place by fixing the defect-causing behavior at its source. What does this
statement refer to?
a. Kaizen
b. Jidoka
c. Quality planning
d. Quality Testing
19. Team members see and contribute information at different times refers to what?
a. Co-located communication
b. Asynchronous communication
c. Synchronous communication
d. Osmotic communication
20. Like a traditional waterfall project charter, the Agile project charter authorizes the project work.
However, an Agile project charter provides detailed guidance to a project team. It helps focus the
work and provides a prescribed approach for the Agile project team.
a. True
b. False
22. In Scrum, "completed" means that the user story meet the following criteria:
a. Developed, Inspected, Trained
b. Developed, Inspected, Documented
c. Developed, Trained, Tested
d. Documented, Trained, Accepted
23. If the transferring element of the ADAPT framework is not done effectively, what force will bring the
enterprise back to the status quo?
a. Departmental memory
b. Organizational gravity
c. Functional norms
25. The goal of value stream mapping is to determine business objective value.
a. True
b. False
26. What is a key difference between wideband Delphi and planning poker approaches to estimation?
a. Estimates are expert driven.
b. Meeting occurs for clarifying questions.
c. Estimates are completed in real-time.
d. Steps in the process repeat until a consensus is reached.
28. The total story points completed at the end of a sprint is considered:
a. The baseline velocity
b. Timeboxing
c. Actual time to complete.
d. A product increment.
29. The preferred model of decision-making is through negotiation, where teams are free to negotiate a
user story to achieve a win-win outcome. This approach is called accommodating, which differs from
some waterfall approaches that use a collaborating approach. Collaborating approaches yield to the
customer, which can result in cost, scope, and schedule overruns.
a. True
b. False
31. Which is NOT one of the ADDITIONAL elements captures on a user story card?
a. Verification criteria
b. Size/points
c. Type of stakeholder
d. Business value
32. The backlog enables the development team to select user stories and begin work on them. The
development team does not have to wait for another dependency to be completed.
a. True
b. False
33. Muri is a Japanese term to ensure resource waste is minimized by working resources to their
maximum capabilities for extended periods of time.
a. True
b. False
34. Once the enterprise transition to Agile is complete, the Enterprise Transition Community should be
disbanded.
a. True
b. False
35. Story points are a pure estimate that does not have to factor in distraction or elapsed time.
a. True
b. False
38. Which Agile principle does a fixed price contract conflict with most?
a. Welcome changing requirements, even late in development. Agile processes harness
change for the customer's competitive advantage.
b. Build projects around motivated individuals. Give them the environment and support they
need and trust them to get the job done.
c. Our highest priority is to satisfy the customer through early and continuous delivery of
valuable software.
d. The most efficient and effective method of conveying information to and within a
development team is face-to-face conversation.
39. What does the following phenomenon describe: as more time elapses, more information is known
about the project, creating greater estimate accuracy?
a. Planning poker
b. Progressive elaboration
c. Wideband Delphi
d. Parkinson's Law
40. Which is NOT one of the strategies to create a productive distributed team?
a. Conducting scrums at times of the day when all teams can participate.
b. Ensuring online information is static.
c. Creating a shared online presence, such as a web page on an organization's intranet
d. Using Agile software tools
41. User stories are prescriptive to ensure the Development Team knows exactly what to do.
a. True
b. False
44. Building the ability to work in an Agile manner can be achieved through coaching and training,
sharing information, and setting reasonable targets.
a. True
b. False
45. Which is NOT one of the three Scrum questions?
a. What will you do today?
b. What will you do tomorrow?
c. Are there any impediments in your way?
d. What did you do yesterday?
46. Skilled generalists are highly specialized resources that are invaluable to an Agile project team.
a. True
b. False
47. What happens to user stories that are not completed during a sprint?
a. Not applicable. A sprint is not completed until all user stories are complete.
b. They are broken into smaller stories.
c. They are released and issues are treated as bugs.
d. They are moved to a future sprint.
49. For large and complex projects, the development team may need to include a number of roles. As a
result, the size of the team should be as large as needed to ensure the quality of deliverables.
a. True
b. False
50. The sprint review should only review features or outcomes that have been completed during the
sprint.
a. True
b. False
53. Could-have requirements should not exceed 20 percent of the overall distribution. Why?
a. Numerous superficial features or requirements are being implemented.
b. Could have requirements represent scope creep and should be avoided.
c. Too many could have requirements could jeopardize project release date.
d. More than this would indicate that the project may not be achieving business value.
54. In Michael Cohn's ADAPT framework, ETC and IC are acronyms for:
a. Enterprise Transition Committee and Improvement Committee
b. Enterprise Transition Community and Improvement Community
c. Enterprise Transfer Committee and Integration Committee
d. Enterprise Transfer Community and Integration Community
56. If an organization is procuring an outside service or product from a vendor, it may be appropriate for
the vendor to designate an external product owner or owners to the team.
a. True
b. False
58. Which factor DOES NOT need to be fulfilled before a user story can be removed from the backlog?
a. It is in the right priority.
b. The development team member understands the story enough to perform the work.
c. The development team member has enough work cycles.
d. The product owner assigns it to the development team member.
59. Incremental methodology = each step in the process is dependent on the previous one. If steps are not
complete, it could delay the start of the next iteration.
a. True
b. False
61. What does the following phenomenon describe: as more time elapses, more information is known
about the project, creating greater estimate accuracy.
a. Planning poker
b. Wideband Delphi
c. Progressive elaboration
d. Parkinson's Law
64. Which business function can benefit greatest by having priority, value and efficiency captured in a
user story?
a. Accounting
b. Procurement
c. Human resources
66. For which type of resistor is this an appropriate management response: appoint a champion. This will
help solicit peer anecdotes as well as build awareness. Organizations should provide training to as
well as continuing to push the desire for change.
a. Diehard
b. Follower
c. Skeptic
d. Saboteur
68. The MOSCOW prioritization model was developed under the Dynamic Systems Development
Method (DSDM) Agile framework.
a. True
b. False
71. Osmotic communication refers to knowledge being acquired simply by hearing team member
conversations.
a. True
b. False
73. Both Agile and PMI recommends a dedicated project team when a project is high priority and cannot
afford timeline variation.
a. True
b. False
77. Lean was developed by Taichi Ohno in the 1950's. Lean was developed to: support mass production
in automotive sector.
78. Using software to manage a backlog is recommended when: The backlog is large and complex.
79. The scrum master must monitor and ensure that the team is functioning and therefore the
development team members' manager…
a. True
b. False
80. What is the Japanese term for eliminating waste that comes from unevenness? Mura
83. Which is NOT part of the scrum master's role as a servant leader?
a. Facilitate scrums and other Scrum events.
b. Prioritize backlog items.
c. Remove obstacles.
d. Coach the team about the Agile process.
84. What are the three sections associated to the Agile Project Charter?
a. Goals Objectives Values
b. Scope Budget Schedule
c. Mission, Vision Success Criteria
d. Inclusions Exclusions, Risks
85. What type of relationship exists between uncertainty and project program.
a. Reverse
b. Indirect
c. Direct
d. Inverse
86. Which Scrum event supports the following Agile principle At regular intervals, the team reflects on
how to become more effective, then tunes and adjusts its behaviour accordingly,
a. Sprint Retrospective
b. Continuous Improvement
c. Sprint Review
d. Lesson Learned
88. Suggest that: following a plan, processes and tools, comprehensive documentation and contract
negotiation are not valued and should be eliminated as forms of
a. True
b. False
92. User stories aren't the only form in which requirements can be represented in Agile frameworks.
a. True
b. False
93. In a large enterprise project what should be the maximum number of Scrum teams running
concurrently?
a. As many as needed
b. 1
c. 10
d. 8
96. What percentage of Must Have requirements should NOT be exceeded according to the MoSCoW
model?
a. 50
b. 60
c. 70
d. 80
99. These types of qualities are often functional in nature and specific to a project. For example, an
organizational unit being able to generate automated reports that were once manual illustrates
customer expectations. If the project does not fulfill the expectation, the customer will be dissatisfied
with the project. Which Kano model category does this best fit?
a. One-dimensional or wants qualities.
b. Attractive or delighter qualities
c. Performance qualities
d. Must-be or needs qualities.
100. If a story does not contribute to the removal of waste or fulfill one of the Kano model's needs or
wants, then it does not have a clear business value.
a. True
b. False