Drawing No. Drawing Title Revision: Notes
Drawing No. Drawing Title Revision: Notes
Drawing No. Drawing Title Revision: Notes
10
11
12
13
14
NOTES:-
15
16 A
B
CONTRACTOR'S VERIFICATION STAMP
We, Habtoor Leighton Group, verify that this contractor's document: * Has been produced and checked in accordance with contractor's quality assurance plan. * Is of a standard that will enable the employer to accept it in accordance with the contract. * Complies with all requirements of the contract. Following deviations to contract are referenced for which a dispensation has been accepted by the employer: Other related letters/CTI's which document clarifications associated with this document are listed below:
Brett Bass
Signature A B C
HLG Design Status HLG Approved - For Issue to ADPC HLG Approved with Comments - For Issue to ADPC Reject by HLG, Re-submit for Approval ADPC Status Stamp Code 1 Code 2 Code 3 DO NOT SCALE FROM THIS DRAWING Works May Proceed.
Revise & resubmit. Work may proceed subject to incorporation of comments indicated. Revise & Resubmit Works May not Proceed. Review not required. Work may proceed
DRAWING NO.
E 1000-208-VW-4200-20610 1000-208-VW-4200-20611 1000-208-VW-4200-20612 1000-208-VW-4200-20613 F 1000-208-VW-4200-20614 1000-208-VW-4200-20615 1000-208-VW-4200-20616 1000-208-VW-4200-20617 1000-208-VW-4200-20618 G 1000-208-VW-4200-20620 1000-208-VW-4200-20621 1000-208-VW-4200-20622
DRAWING TITLE
REVISION
Code 4
The statement "Work may proceed" applies to the following work activities associated with the matters contained within the contractor's document.
IRRIGATION PUMP STATION RESERVOIR LIST OF DRAWINGS SHEET 1 OF 1 IRRIGATION PUMP STATION RESERVOIR LOCATION PLAN SHEET 1 OF 1 IRRIGATION PUMP STATION AND RESERVOIR LAYOUT PLAN SHEET 1 OF 1 IRRIGATION PUMP STATION AND RESERVOIR SECTION SHEET 1 OF 1 IRRIGATION PUMP STATION AND RESERVOIR ELECTRICAL SYMBOLS AND LEGEND SHEET 1 OF 1 IRRIGATION PUMP STATION PROCESS AND INSTRUMENT DIAGRAM SYMBOLS AND LEGEND SHEET 1 OF 1 IRRIGATION PUMP STATION PROCESS AND INSTRUMENT DIAGRAM SHEET 1 OF 1 IRRIGATION PUMP STATION AND RESERVOIR ELECTRICAL SINGLE LINE DIAGRAM SHEET 1 OF 1 IRRIGATION PUMP STATION AND RESERVOIR LIGHTING AND SMALL POWER SYMBOLS AND LEGEND SHEET 1 OF 1 IRRIGATION PUMP STATION AND RESERVOIR PLAN GRP KIOSK PLANS AND SECTIONS SHEET 1 OF 1 IRRIGATION PUMP STATION AND RESERVOIR EXTERNAL LIGHTING AND CABLE ROUTING SHEET 1 OF 1 IRRIGATION PUMP STATION AND RESERVOIR EXTERNAL POWER AND CONTROL CABLE ROUTING SHEET 1 OF 1
C01 C01 C01 C01 C01 C01 C01 C01 C01 C01 C01 C00
C01
Design/ Procurement/ Construction/ All Activities * (*Delete/Amend/Add as applicable) Any review, comment or acceptance by employer under this contract with respect to any of contractor's documents shall not in any way be, or deemed to be, an approval of any works or an acceptance that the contractor's documents meet the requirements of the contract, as contractor has the sole responsibility for performing the works in accordance with the requirements of this contract.
Date
C01 26.09.11 REVISED AS CLOUDED RAC SA ATB C00 19.05.11 ISSUED FOR CONSTRUCTION RAC SA ATB Rev Date Description Drawn Chkd Appr Drawn by / Date Checked by / Date Approved by / Date A.A.N 19.05.11 F.B 19.05.11 A.Bitar 19.05.11 Client
Mohanr
Copyright Abu Dhabi Ports Company (ADPC), 2011. All Rights Reserved.
Project / Contract
KHALIFA PORT & INDUSTRIAL ZONE H CONTRACT No. 1000-208 KPIZ ONSHORE CIVIL AND BUILDING WORKS
Independent Checking Engineer Signature Contractor
AL HABTOOR LEIGHTON
J
Consultant
Al Habtoor Leighton Group (Al Habtoor Engineering Enterprises Co. L.L.C. and Leighton Contracting (Abu Dhabi) L.L.C. Joint Venture) P.O. BOX 94267 TEL. NO. +97126998400 FAX NO. +97126760899
Sub-Consultant / Sub-Contractor
K
COID Zone 000 Entity - 000 Element 000 00000
00
1000-208-VW-4200-20610-C01.dwg
Drawing Title
A1
M
1000-208-VW-4200-20610
15 16
C01
1 A
10
11
12
13
14
NOTES:-
15
16 A
Scale Bar
60
120
240
360
480m
Brett Bass
Signature A B C
HLG Design Status HLG Approved - For Issue to ADPC HLG Approved with Comments - For Issue to ADPC Reject by HLG, Re-submit for Approval ADPC Status Stamp Code 1 Code 2 Code 3 DO NOT SCALE FROM THIS DRAWING Code 4
A CCE SS ROA D 33
Works May Proceed. Revise & resubmit. Work may proceed subject to incorporation of comments indicated. Revise & Resubmit Works May not Proceed. Review not required. Work may proceed
The statement "Work may proceed" applies to the following work activities associated with the matters contained within the contractor's document. Design/ Procurement/ Construction/ All Activities * (*Delete/Amend/Add as applicable) Any review, comment or acceptance by employer under this contract with respect to any of contractor's documents shall not in any way be, or deemed to be, an approval of any works or an acceptance that the contractor's documents meet the requirements of the contract, as contractor has the sole responsibility for performing the works in accordance with the requirements of this contract.
Date
G
Mohanr
C01 26.09.11 REVISED AS PER COMMENTS RM VP ATB C00 19.05.11 ISSUED FOR CONSTRUCTION RM VP ATB Rev Date Description Drawn Chkd Appr Drawn by / Date Checked by / Date Approved by / Date Reji.M 19.05.11 Vijay.P 19.05.11 A.Bitar 19.05.11 Client
07
Copyright Abu Dhabi Ports Company (ADPC), 2011. All Rights Reserved.
Project / Contract
P = 100
A CCE SS ROA D 34
KHALIFA PORT & INDUSTRIAL ZONE H CONTRACT No. 1000-208 KPIZ ONSHORE CIVIL AND BUILDING WORKS
Independent Checking Engineer Signature Contractor
AL HABTOOR LEIGHTON
J
Consultant
Al Habtoor Leighton Group (Al Habtoor Engineering Enterprises Co. L.L.C. and Leighton Contracting (Abu Dhabi) L.L.C. Joint Venture) P.O. BOX 94267 TEL. NO. +97126998400 FAX NO. +97126760899
Sub-Consultant / Sub-Contractor
K
CT 100 1-260
100 1-260
K
COID Zone 000 Entity - 000 Element 000 00000
E XTE NT OF CONTRA
E XTE NT OF CONTRA CT
00
1000-208-VW-4200-20611-C01.dwg
A CCE SS ROA D 28
Drawing Title
L
A CCE SS ROA D 30
C H. 0 +0 00 .000 C H. 0 +0 39 .091
A1
M
M 1 2 3 4 5 6 7 8 9 10 11 12
Drawing No.
Revision
1000-208-VW-4200-20611
13 14 15 16
C01
1 A
10
11
12 NOTES
13
14
NOTES:-
15
16 A
E 267690.355 N 2742696.047
160 HDPE
1. ALL DIMENSIONS ARE IN MILLIMETERS AND ALL LEVELS ARE IN METERS UNLESS STATED OTHERWISE . 2. ALL PIPES AND FITTINGS INSIDE PUMP STATION SHALL BE D.I. 3. PIPES & FITTINGS ARE INDICATIVE ONLY, SHALL BE FINALIZED ACCORDING TO ACTUAL EQUIPMENT SELECTED 4. PUMP DUTY SHALL BE 5.32 L/S AT 50m HEAD. 5. FOR ARCHITECTURAL DETAILS, REFER TO DWGS NO. 1000-208-VB-8100-23601-C01 TO 1000-208-VB-8100-23690-C01. 6. FOR STRUCTURAL DETAILS , REFER TO DWGS. NO. 1000-208-VS-8100-23601 TO 1000-208-VS-8100-23680. 7. THE COVER SHALL BE 1X1m AND PROVIDED BY RESERVOIR MANUFACTURER ACCORDING TO THE REQUIREMENTS. 8. FOR SLIDING GATE DETAIL REFER TO DRAWING No.1000-208-VZ-1000-20228.
TO IRRIGATION NETWORK
B
CONTRACTOR'S VERIFICATION STAMP
We, Habtoor Leighton Group, verify that this contractor's document: * Has been produced and checked in accordance with contractor's quality assurance plan. * Is of a standard that will enable the employer to accept it in accordance with the contract. * Complies with all requirements of the contract.
2600
33 32
R4
PRESSURE VESSEL
25
DN 150 DI.
QTY
2 2 2 2 2 2 1 2 1 1 1 1 1 1 1 3 2 2 3 3
REMARKS
Following deviations to contract are referenced for which a dispensation has been accepted by the employer: Other related letters/CTI's which document clarifications associated with this document are listed below:
C
0.3% ROLLING SHUTTER DOOR RAMP SLOPE 1:5 8200
16
1 2 3 4 5
Brett Bass
Signature A B C
MANHOLE MH100-2 CHAIN LINK FENCE REFER TO FENCING PACKAGE SEE DRAWING No.1000-208-VZ-1000-20201.
6 7 8 9
HLG Design Status HLG Approved - For Issue to ADPC HLG Approved with Comments - For Issue to ADPC Reject by HLG, Re-submit for Approval ADPC Status Stamp Code 1 Code 2 Code 3 Code 4 Works May Proceed.
GRP KIOSK PRE-FABRICATED RAMP SLOPE 1:5 400mm DEEP 500mm WIDE CABLE TRENCH 10 8 6 DN 80 D.I C01 4 2 BOX - OUT FOR CABLES & MOTOR CONTROL CENTRE 5 3 8 NOS. 100mm DIA DUCTS. 8 NOS. 100mm DIA DUCTS. 1 DN 100 D.I IRRIGATION 17 18 PUMPS 19 SEE NOTE 5 & 6 300x300 SUMP 20 21 22 19 DN 100 D.I 23 20 DN 100 D.I 17 20
13 PT 12 7 11
10 11 12
Revise & resubmit. Work may proceed subject to incorporation of comments indicated. Revise & Resubmit Works May not Proceed. Review not required. Work may proceed
13 14
The statement "Work may proceed" applies to the following work activities associated with the matters contained within the contractor's document. Design/ Procurement/ Construction/ All Activities * (*Delete/Amend/Add as applicable) C01 Any review, comment or acceptance by employer under this contract with respect to any of contractor's documents shall not in any way be, or deemed to be, an approval of any works or an acceptance that the contractor's documents meet the requirements of the contract, as contractor has the sole responsibility for performing the works in accordance with the requirements of this contract.
15 16 17 C01 18 19 20 21 22 23 24 25
F
22000
Date
160 HDPE
24
G
Mohanr 26 0.3% 27 28 29
RAC SA ATB C01 26.09.11 REVISED AS CLOUDED RAC SA ATB C00 19.05.11 ISSUED FOR CONSTRUCTION Rev Date Description Drawn Chkd Appr Drawn by / Date Checked by / Date Approved by / Date G Raymondo 19.05.11 S.Amine 19.05.11 A.Bitar 19.05.11 Client
Copyright Abu Dhabi Ports Company (ADPC), 2011. All Rights Reserved.
C01
Project / Contract
H
GATCH SURFACE
30 31
KHALIFA PORT & INDUSTRIAL ZONE H CONTRACT No. 1000-208 KPIZ ONSHORE CIVIL AND BUILDING WORKS
C01 Independent Checking Engineer Signature
Al Habtoor Leighton Group (Al Habtoor Engineering Enterprises Co. L.L.C. and Leighton Contracting (Abu Dhabi) L.L.C. Joint Venture) P.O. BOX 94267 TEL. NO. +97126998400 FAX NO. +97126760899
32 33
J
Consultant
SEE NOTE - 8
Sub-Consultant / Sub-Contractor
K
COID Zone 00 Entity - 000 Element 00000
1000-208-VW-4200-20612-C01.dwg
000
A1
M
Drawing Status
M 1 2 3 4 5 6 7 8 9 10 11
1000-208-VW-4200-20612
12 13 14 15 16
C01
1 A
10
11
12 NOTES
13
14
NOTES:-
15
16 A
1. ALL DIMENSIONS ARE IN MILLIMETERS AND ALL LEVELS ARE IN METERS UNLESS STATED OTHERWISE . 2. ALL PIPES AND FITTINGS INSIDE PUMP STATION SHALL BE D.I. 3. PIPES & FITTINGS ARE INDICATIVE ONLY, SHALL BE FINALIZED ACCORDING TO ACTUAL EQUIPMENT SELECTED 4. PUMP DUTY SHALL BE 5.32 L/S AT 50m HEAD. 5. ALL VALVES WHICH ARE NOT ACCESSIBLE SHALL BE CHAIN OPERATED. 6. REFER TO DRAWING NO. 1000-208-VW-4200-20612 FOR MATERIAL LIST.
B
CONTRACTOR'S VERIFICATION STAMP
We, Habtoor Leighton Group, verify that this contractor's document: * Has been produced and checked in accordance with contractor's quality assurance plan. * Is of a standard that will enable the employer to accept it in accordance with the contract. * Complies with all requirements of the contract. Following deviations to contract are referenced for which a dispensation has been accepted by the employer:
C
8000
FOR ARCHITECTURAL DETAILS , REFER TO ARCHITECTURAL DWG.NO. 1000-208-VB-8100-23630 1200 FOR STRUCTURAL DETAILS, REFER TO DWG. NO. 1000-208-VS-8100-23611 & 1000-208-VS-8100-23640
Other related letters/CTI's which document clarifications associated with this document are listed below:
+7.05
Brett Bass
Signature A B C
HLG Design Status 1700 HLG Approved - For Issue to ADPC HLG Approved with Comments - For Issue to ADPC Reject by HLG, Re-submit for Approval IRRIGATION PUMP 850 PRESSURE VESSEL (750 L) 1900 PRESSURE VESSEL (750 L) C01 170 IL.+3.90 170 IL.+3.90 ADPC Status Stamp Code 1 Code 2 DN 100 709 DO NOT SCALE FROM THIS DRAWING 584 615 625 735 500 DN 150/80 D.I Code 3 Code 4 IL.+3.80 Works May Proceed.
D
FOR ARCHITECTURAL DETAILS , REFER TO ARCHITECTURAL DWG.NO. 1000-208-VB-8100-23630 3000
3250
Revise & resubmit. Work may proceed subject to incorporation of comments indicated. Revise & Resubmit Works May not Proceed. Review not required. Work may proceed
300
160 HDPE
F.G.L. +3.65
+3.80
900
+3.80
The statement "Work may proceed" applies to the following work activities associated with the matters contained within the contractor's document. 1082 Design/ Procurement/ Construction/ All Activities * (*Delete/Amend/Add as applicable) Any review, comment or acceptance by employer under this contract with respect to any of contractor's documents shall not in any way be, or deemed to be, an approval of any works or an acceptance that the contractor's documents meet the requirements of the contract, as contractor has the sole responsibility for performing the works in accordance with the requirements of this contract.
NETWORK TO IRRIGATION
1082
2000
2600
160 HDPE
SECTION D-D
C01
Date
HAND HOLD 500 500 C01 20mm DIA SOLID GRP ROD RUNG (NON SLIP FINISH)
G
Mohanr
RAC SA ATB C01 26.09.11 REVISED AS CLOUDED RAC SA ATB C00 19.05.11 ISSUED FOR CONSTRUCTION Rev Date Description Drawn Chkd Appr Drawn by / Date Checked by / Date Approved by / Date G Raymondo 19.05.11 S.Amine 19.05.11 A.Bitar 19.05.11 Client
Copyright Abu Dhabi Ports Company (ADPC), 2011. All Rights Reserved.
Project / Contract
H
DN 150 D.I. OVER FLOW PIPE
750
25mm DIA RUNG PULTRUDED WITH ROUGH FINISH 50x50 SQ. TUBE
4325
KHALIFA PORT & INDUSTRIAL ZONE H CONTRACT No. 1000-208 KPIZ ONSHORE CIVIL AND BUILDING WORKS
Independent Checking Engineer Signature Contractor
AL HABTOOR LEIGHTON
C01
J
750 GRP LADDER BRACKET (TYP) DN 100 D.I. DRAIN PIPE 750 Consultant
Al Habtoor Leighton Group (Al Habtoor Engineering Enterprises Co. L.L.C. and Leighton Contracting (Abu Dhabi) L.L.C. Joint Venture) P.O. BOX 94267 TEL. NO. +97126998400 FAX NO. +97126760899
DN 160 HDPE
Sub-Consultant / Sub-Contractor
225
K
75 COID Zone 00 Entity - 000 Element 00000
SECTION B-B
1000-208-VW-4200-20613-C01.dwg
000
LADDER DETAILS
A1
M
1000-208-VW-4200-20613
15 16
C01
1 A
10
11
12
13
14
NOTES:-
15
16 A
PFC
REVERSIBLE DIRECT ON LINE STARTER SINGLE POLE WITH NEUTRAL DESCRIPTION AIR CIRCUIT BREAKER VACUUM CIRCUIT BREAKER GAS INSULATED CIRCUIT BREAKER SS D MOULDED CASE CIRCUIT BREAKER / MINIATURE CIRCUIT BREAKER VFD CONTACTOR
DO NOT SCALE FROM THIS DRAWING
SELECTOR SWITCH
SOFT STARTER
Brett Bass
Signature A B C
HLG Design Status HLG Approved - For Issue to ADPC HLG Approved with Comments - For Issue to ADPC Reject by HLG, Re-submit for Approval
FUSE
ADPC Status Stamp Code 1 Code 2 Code 3 Works May Proceed. Revise & resubmit. Work may proceed subject to incorporation of comments indicated. Revise & Resubmit Works May not Proceed. Review not required. Work may proceed
STAR DELTA STARTER E VACUUM CONTACTOR WEATHER PROOF PUSHBUTTON STATION C/W ISOLATOR, PLUG AND SOCKET OUTLET SYMBOL * A F V Hr PF W Hz G PM SYMBOL # Ah # Wh VArh kWh DESCRIPTION AMMETER VOLTMETER HOURRUN METER POWER FACTOR METER POWER METER FREQUENCY METER kW, kVA, kVAr, V, I, COS, THD V, THD I DESCRIPTION AMPERE HOUR METER WATT HOUR METER VOLT AMPERE REACTIVE HOUR METER KILOWATT HOUR METER SSCD SLIP RING SHORT CIRCUITING DEVICE HEATER THERMISTOR REMOTE START/STOP/EMERGENCY STOP PUSH BUTTON STATION PLUG & SOCKET T/S
SWITCH FUSE
Code 4
The statement "Work may proceed" applies to the following work activities associated with the matters contained within the contractor's document. Design/ Procurement/ Construction/ All Activities * (*Delete/Amend/Add as applicable) Any review, comment or acceptance by employer under this contract with respect to any of contractor's documents shall not in any way be, or deemed to be, an approval of any works or an acceptance that the contractor's documents meet the requirements of the contract, as contractor has the sole responsibility for performing the works in accordance with the requirements of this contract.
EARTH
TIME SWITCH
Date
PLUG & SOCKET OUTLET C/W REMOTE START/STOP/EMERGENCY STOP PUSHBUTTON STATION
C01 26.09.11 REVISED AS PER COMMENTS RAC SA ATB C00 19.05.11 ISSUED FOR CONSTRUCTION RAC SA ATB Rev Date Description Drawn Chkd Appr Drawn by / Date Checked by / Date Approved by / Date G Raymondo 19.05.11 S.Amine 19.05.11 A.Bitar 19.05.11 Client
Mohanr
Copyright Abu Dhabi Ports Company (ADPC), 2011. All Rights Reserved.
Project / Contract
KHALIFA PORT & INDUSTRIAL ZONE H CONTRACT No. 1000-208 KPIZ ONSHORE CIVIL AND BUILDING WORKS
Independent Checking Engineer Signature
POTENTIAL TRANSFORMER J
DCV
Contractor
AL HABTOOR LEIGHTON
Al Habtoor Leighton Group (Al Habtoor Engineering Enterprises Co. L.L.C. and Leighton Contracting (Abu Dhabi) L.L.C. Joint Venture) P.O. BOX 94267 TEL. NO. +97126998400 FAX NO. +97126760899
CURRENT TRANSFORMER
MV
MOTORISED VALVE
Sub-Consultant / Sub-Contractor
UPS
MCF
K
COID Zone 00 Entity - 000 Element 00000
1000-208-VW-4200-20614-C01.dwg
M BATTERY
MOTOR
000
M SSCD
A1
M
MPR M 1 2 3 4 5 6
Drawing Status
1000-208-VW-4200-20614
7 8 9 10 11 12 13 14 15 16
C01
1 A
10
11
12
13
14
NOTES:-
15
16 A
X SOLENOID ACTUATED VALVE SIGHT FLOW INDICATOR CHLORINE GAS FILTER NON-CYLINDRICAL TANK Y Z VACUUM RELIEF VALVE PITOT TUBE CRUSHER METERING PUMP KLAXON
LOCAL INDICATION ORIFICE PLATE FLOWMETER LIFTING DAVIT/SLEW JIB HEATER REMOTE INDICATION ROTAMETER
G
Mohanr
C01 26.09.11 REVISED AS PER COMMENTS RAC SA ATB C00 19.05.11 ISSUED FOR CONSTRUCTION RAC SA ATB Rev Date Description Drawn Chkd Appr Drawn by / Date Checked by / Date Approved by / Date G Raymondo 19.05.11 S.Amine 19.05.11 A.Bitar 19.05.11 Client
AIR RELIEF VALVE SUBMERSIBLE PUMPS HOIST / CRANE PRESSURE RELIEF VALVE
REDUCER
CONTROL FUNCTION
LEVEL ELECTRODE
Copyright Abu Dhabi Ports Company (ADPC), 2011. All Rights Reserved.
ORIFICE PLATE
Project / Contract CENTRIFUGAL PUMP MIXER VACUUM CHANGOVER UNIT INSERTION TYPE FLOW SENSOR BULK WATER METER
(IN LINE)
BACK PRESSURE VALVE MULTISTAGE CENTUFUGAL PUMP STATIC MIXER DESICCANT DRYER PARSHALL FLUME WATER TRAP SUBMERSIBLE MIXER PROGRESSIVE CAVITY PUMP ALTITUDE VALVE EJECTOR MAIN PROCESS LINE A C CA CC AUTOMATIC CLOSE CONTROL AVAILABLE COMMAND CENTRE DUTY DISTRIBUTION BOARD EMPTY FAILED FLOW CONTROL FULL HIGH PRESSURE INSTRUMENT PANEL LOCAL CONTROL PANEL LCP MANUAL ULTRASONIC LEVEL SENSOR ELECTROMAGNETIC FLOWMETER
KHALIFA PORT & INDUSTRIAL ZONE H CONTRACT No. 1000-208 KPIZ ONSHORE CIVIL AND BUILDING WORKS
Independent Checking Engineer Signature Contractor
AL HABTOOR LEIGHTON
J
PRESSURE REDUCING OR REGULATING VALVE (AS APPLICABLE)
ABBREVIATIONS
Consultant M MCC N NCA NFC O OV PLC PLCM R S SA SP V PLC MANUAL START/RUNNING STOP/STOPPED SEMI-AUTOMATIC SUPERVISORY PANEL VALVE Drawing Status MANUAL MOTOR CONTROL CENTRE NON-DUTY NO CONTROL AVAILABLE NO FLOW CONTROL OPEN/OPENED COID OVERFLOW Zone 00 000 Drawing Title Entity - 000
Al Habtoor Leighton Group (Al Habtoor Engineering Enterprises Co. L.L.C. and Leighton Contracting (Abu Dhabi) L.L.C. Joint Venture) P.O. BOX 94267 TEL. NO. +97126998400 FAX NO. +97126760899
Sub-Consultant / Sub-Contractor
AIR COMPRESSOR GLOBE VALVE OVERFLOW / DRAIN WASTE LINE DIAPHRAGM VALVE E AIR BLOWER FAN & MOTOR NEEDLE VALVE SIGNAL LINE AIR LINE F FC FL HP ANGLE VALVE FLEXIBLE HOSE IP LCP EXHAUST FAN BELLOW JOINT LCPM D DB
K
Element 00000
000
1000-208-VW-4200-20615-C01.dwg
IRRIGATION PUMP STATION PROCESS AND INSTRUMENT DIAGRAM SYMBOLS AND LEGEND (SHEET 1 OF 1)
Sheet Scale N.T.S Paper Size
A1
M
1000-208-VW-4200-20615
15 16
C01
1 A
10
11
12
13
14
NOTES:1.
15
16 A
2. 3.
P & ID SHALL BE READ IN CONJUNCTION WITH CONCERNED PIPING DRAWINGS AND SPECIFICATIONS. REFER TO P & I DIAGRAM SYMBOLS AND LEGEND ON DRAWING No.1000-208-VW-4200-20615. PUSH BUTTON STATION WITH SELECTION SWITCH AND EMERGENCY STOP WILL BE PROVIDED NEXT TO EACH PUMP SET.
C01
HS 01
LOCAL / REMOTE
B
CONTRACTOR'S VERIFICATION STAMP
We, Habtoor Leighton Group, verify that this contractor's document: * Has been produced and checked in accordance with contractor's quality assurance plan. * Is of a standard that will enable the employer to accept it in accordance with the contract. * Complies with all requirements of the contract. Following deviations to contract are referenced for which a dispensation has been accepted by the employer: Other related letters/CTI's which document clarifications associated with this document are listed below:
RTU 01
C
PLC 01 C01 PT 1001 DN 150 DI FIT 1001 DN 150 DI CONNECT TO IRRIGATION NETWORK PI 3001 PI 3002 C01
Brett Bass
Signature A B C
HLG Design Status HLG Approved - For Issue to ADPC HLG Approved with Comments - For Issue to ADPC Reject by HLG, Re-submit for Approval ADPC Status Stamp Code 1 Code 2 Code 3 Code 4 Works May Proceed.
D
FM DN 80 DI DN 80 DI PI 2001
C01
C01 PI 1001
Revise & resubmit. Work may proceed subject to incorporation of comments indicated. Revise & Resubmit Works May not Proceed. Review not required. Work may proceed
C01
LIT 1001
DN 100 DI
DN 60 DI
M 001 DN 60 DI
DN 80 DI
The statement "Work may proceed" applies to the following work activities associated with the matters contained within the contractor's document. Design/ Procurement/ Construction/ All Activities * (*Delete/Amend/Add as applicable)
P-002 (STANDBY) 5.32 L/S @50m FROM TANKERS DN 80 DI Any review, comment or acceptance by employer under this contract with respect to any of contractor's documents shall not in any way be, or deemed to be, an approval of any works or an acceptance that the contractor's documents meet the requirements of the contract, as contractor has the sole responsibility for performing the works in accordance with the requirements of this contract.
C01
F
DN 100 DI PROPOSED GRP WATER TANK
Date
C01
G
Mohanr
PI 1002
C01
PI 2002
RAC SA ATB C01 26.09.11 REVISED AS CLOUDED C00 08.02.11 ISSUED FOR CONSTRUCTION RAC SA ATB Rev Date Description Drawn Chkd Appr Drawn by / Date Checked by / Date Approved by / Date G Raymondo 08.02.11 S.Amine 08.02.11 A.Bitar 08.02.11 DN 80 DI Client
M 002 DN 60 DI DN 100 DI OVER FLOW PIPE DN 150 D.I. DRAIN PIPE DN 100 D.I. DN 60 DI
Copyright Abu Dhabi Ports Company (ADPC), 2011. All Rights Reserved.
Project / Contract
KHALIFA PORT & INDUSTRIAL ZONE H CONTRACT No. 1000-208 KPIZ ONSHORE CIVIL AND BUILDING WORKS
Independent Checking Engineer Signature Contractor
AL HABTOOR LEIGHTON
J
Consultant
Al Habtoor Leighton Group (Al Habtoor Engineering Enterprises Co. L.L.C. and Leighton Contracting (Abu Dhabi) L.L.C. Joint Venture) P.O. BOX 94267 TEL. NO. +97126998400 FAX NO. +97126760899
Sub-Consultant / Sub-Contractor
K
COID Zone 00 Entity - 000 Element 00000
MANHOLE 1000-208-VW-4200-20616-C01.dwg
000
L
CONNECT TO MAIN DRAIN SYSTEM
A1
M
M 1 2 3 4 5 6 7 8
1000-208-VW-4200-20616
9 10 11 12 13 14 15 16
C01
1 A
10
11
12 NOTES:1. 2. 3.
13
14
NOTES:-
15
16 A
4. 5.
6.
ALL SIZES , RATINGS AND QUANTITIES SHOWN ARE INDICATIVE. RTU AND MODEM MAY BE INSTALLED INSIDE PANEL. INCOMING POWER SUPPLY IS TO BE TAKEN FROM SUBSTATION SS-3 LOCATED OUTSIDE PUMPING STATION BOUNDARY. CONTRACTOR TO LIAISE WITH ADDC, OTHER CONSULTANTS AND CONTRACTORS TO CONFIRM CONNECTION POINT AND ROUTE. POWER FACTOR CORRECTION CAPACITOR PANEL NOT SHOWN BUT SHALL BE PROVIDED. REFER TO RESERVOIR ELECTRICAL SYMBOLS DRAWING NO. 1000-208-VW-4200-20614 KILOWATT HOUR METER TO BE PROVIDED BY THE CONTRACTOR AND WILL BE SUBJECT TO ADDC APPROVAL.
B
CONTRACTOR'S VERIFICATION STAMP
We, Habtoor Leighton Group, verify that this contractor's document: * Has been produced and checked in accordance with contractor's quality assurance plan. * Is of a standard that will enable the employer to accept it in accordance with the contract. * Complies with all requirements of the contract. Following deviations to contract are referenced for which a dispensation has been accepted by the employer: Other related letters/CTI's which document clarifications associated with this document are listed below:
FROM ST01/03
C
1x4Cx50mm XLPE/SWA/PVC
Brett Bass
Signature A B C
HLG Design Status 4NOS. 63/5 A CL.1 kWh 63A TPN MCCB INTERLOCKED DO NOT SCALE FROM THIS DRAWING PM HLG Approved - For Issue to ADPC HLG Approved with Comments - For Issue to ADPC Reject by HLG, Re-submit for Approval ADPC Status Stamp 63A TPN MCCB PM 4NOS. 63/5 A CL.1 16A TPN Q0 MCCB Q1 16A TPN MCCB Q2 16A TPN MCCB Q3 32A TPN MCCB Q4 16A TPN MCCB Q5 400V TPN 50KA 1 SEC. 10A SPN MCCB Q6 16A TPN MCCB Q7 16A TPN MCCB Q8 32A TPN MCCB V Code 1 Code 2 Code 3 Code 4 Works May Proceed.
C01
Revise & resubmit. Work may proceed subject to incorporation of comments indicated. Revise & Resubmit Works May not Proceed. Review not required. Work may proceed
The statement "Work may proceed" applies to the following work activities associated with the matters contained within the contractor's document. Design/ Procurement/ Construction/ All Activities * (*Delete/Amend/Add as applicable) Any review, comment or acceptance by employer under this contract with respect to any of contractor's documents shall not in any way be, or deemed to be, an approval of any works or an acceptance that the contractor's documents meet the requirements of the contract, as contractor has the sole responsibility for performing the works in accordance with the requirements of this contract.
Date
G
Mohanr
C01 29.06.11 REVISED AS CLOUDED RAC SA ATB C00 19.05.11 ISSUED FOR CONSTRUCTION RAC SA ATB Rev Date Description Drawn Chkd Appr Drawn by / Date Checked by / Date Approved by / Date G Raymondo 19.05.11 S.Amine 19.05.11 A.Bitar 19.05.11 Client
C01
Copyright Abu Dhabi Ports Company (ADPC), 2011. All Rights Reserved.
Project / Contract
H
1kVA UPS 10A SPN MCCB 240V AC
KHALIFA PORT & INDUSTRIAL ZONE H CONTRACT No. 1000-208 KPIZ ONSHORE CIVIL AND BUILDING WORKS
Independent Checking Engineer Signature Contractor
AL HABTOOR LEIGHTON
J
UPS 6A SPN M 1C 25mm ECC STREET LIGHT DB 2kW IRRIGATION PUMP NO.1 5.5kW M MCB 3C 2.5mm PVC/SWA/PVC IRRIGATION PUMP NO.2 5.5kW 4C 10mm XLPE/SWA/PVC + 1C 10mm ECC LIFT CRANE 4kW 4C 10mm XLPE/SWA/PVC + 1C 10mm ECC 4C 6mm XLPE/SWA/PVC + 1C 6mm ECC 4C 6mm XLPE/SWA/PVC + 1C 6mm ECC 7C 2.5mm PVC/SWA/PVC SMDB (BY BUILDING SERVICES) 3kW 3C 4mm XLPE/SWA/PVC + 1C 4mm ECC MCB MCB MCB MCB MCB MCB 6A SPN 6A SPN 6A SPN 6A SPN 6A SPN 6A 4C 6mm XLPE/SWA/PVC + 1C 6mm ECC Consultant SPN
Al Habtoor Leighton Group (Al Habtoor Engineering Enterprises Co. L.L.C. and Leighton Contracting (Abu Dhabi) L.L.C. Joint Venture) P.O. BOX 94267 TEL. NO. +97126998400 FAX NO. +97126760899
SPARE
SPARE
Sub-Consultant / Sub-Contractor
K
COID Zone 00 Entity - 000 Element 00000
MODEM
PRESSURE TRANSMITTER
PLC
FLOW METER
HMI
RTU
1000-208-VW-4200-20617-C01.dwg
000
0.5 KW UPS DB
7 KVAr
A1
M
1000-208-VW-4200-20617
15 16
C01
1 A
10
11
12
13
14
NOTES:-
15
16 A
CP
CONTROL PANEL
DIRECT LINE
CONTRACTOR'S VERIFICATION STAMP
We, Habtoor Leighton Group, verify that this contractor's document: * Has been produced and checked in accordance with contractor's quality assurance plan. * Is of a standard that will enable the employer to accept it in accordance with the contract. * Complies with all requirements of the contract. Following deviations to contract are referenced for which a dispensation has been accepted by the employer:
DB
DISTRIBUTION BOARD
F16
DISTRIBUTION BOARD / CONTROL BOARD / SUB-SWITCHBOARD (W INDICATE WEATHER PROOF TYPE) SPLIT A/C UNIT
F17
Other related letters/CTI's which document clarifications associated with this document are listed below:
F18
F19
1 x 36W WALL MOUNTED FLUORESCENT LIGHT FITTING WITH PRISMATIC DIFFUSER 1 x 36W CEILING RECESSED FLUORESCENT LIGHT FITTING WITH REFLECTOR AND PRISMATIC DIFFUSER 1 x 18W CEILING RECESSED FLUORESCENT LIGHT FITTING WITH REFLECTOR AND PRISMATIC DIFFUSER 3 x 36W CEILING RECESSED FLUO. LIGHT FITTING WITH REFLECTOR AND ALUMINIUM LOUVRES 1 x 150W OUTDOOR WEATHER PROOF SPOTLIGHT FITTING
HLG Approved - For Issue to ADPC HLG Approved with Comments - For Issue to ADPC Reject by HLG, Re-submit for Approval ADPC Status Stamp Code 1 Code 2 Code 3 Works May Proceed.
F20
DISTRIBUTION PANEL
Revise & resubmit. Work may proceed subject to incorporation of comments indicated. Revise & Resubmit Works May not Proceed. Review not required. Work may proceed
F21
MDF
Code 4
The statement "Work may proceed" applies to the following work activities associated with the matters contained within the contractor's document.
13A FLUSH MOUNTED TYPE SWITCHED SOCKET OUTLET 13A SURFACE MOUNTED TYPE SWITCHED SOCKET OUTLET
F22 EXHAUST FAN F1 1 x 36W SURFACE MOUNTED BARE CHANNEL FLUORESCENT LIGHT FITTING
EXTERNAL CABLE
Design/ Procurement/ Construction/ All Activities * (*Delete/Amend/Add as applicable) Any review, comment or acceptance by employer under this contract with respect to any of contractor's documents shall not in any way be, or deemed to be, an approval of any works or an acceptance that the contractor's documents meet the requirements of the contract, as contractor has the sole responsibility for performing the works in accordance with the requirements of this contract.
D1
INTERNAL CABLE
F2
D2
Date
W G
Mohanr
F3
D3
WALL MOUNTED FLOODLIGHT FITTING WITH 70W HIGH PRESSURE SODIUM LAMP
SC
SWITCH CENTRE
F4
2 x 36W CEILING SUSPENDED BARE CHANNEL FLUORESCENT LIGHT FITTING 1 x 36W WALL MOUNTED FLUORESCENT LIGHT FITTING WITH ANGLE REFLECTOR 2 x 36W WALL MOUNTED FLUORESCENT LIGHT FITTING WITH ANGLE REFLECTOR 2 x 36W WALL MOUNTED ANTI CORROSION FLUORESCENT LIGHT FITTING 2 x 36W CEILING SUSPENDED FLUORESCENT LIGHT FITTING WITH REFLECTOR 2 x 36W CEILING SUSPENDED ANTI CORROSION FLUORESCENT LIGHT FITTING 2 x 36W SURFACE MOUNTED FLUORESCENT LIGHT FITTING WITH PRISMATIC DIFFUSER 1 x 36W SURFACE MOUNTED BARE CHANNEL FLUORESCENT LIGHT FITTING WITH WIRE GUARD 2 x 36W SURFACE MOUNTED BARE CHANNEL FLUORESCENT LIGHT FITTING WITH WIRE GUARD 1 x 18W CEILING RECESSED FLUORESCENT LIGHT FITTING WITH REFLECTOR AND ALUMINIUM LOUVRES 2 x 18W CEILING RECESSED FLUORESCENT LIGHT FITTING WITH REFLECTOR AND ALUMINIUM LOUVRES EL1
D4
C01 26.09.11 REVISED AS PER COMMENTS RAC SA ATB C00 19.05.11 ISSUED FOR CONSTRUCTION RAC SA ATB Rev Date Description Drawn Chkd Appr Drawn by / Date Checked by / Date Approved by / Date G Raymondo 19.05.11 S.Amine 19.05.11 A.Bitar 19.05.11 Client
TELEPHONE POLE
HIGH BAY LIGHT FITTING WITH 250W HIGH PRESSURE MERCURY LAMP LOW BAY LIGHT FITTING WITH 250w HIGH PRESSURE MERCURY LAMP WITH POLYCORBONATE DIFFUSER HIGH BAY LIGHT FITTING WITH 400W HIGH PRESSURE MERCURY LAMP CEILING RECESSED DOWNLIGHT FITTING WITH 1 x 26W COMPACT FLUORESCENT LAMP CEILING RECESSED DOWNLIGHT FITTING WITH 70W HID METAL HALIDE LAMP P1 PERIMETER LIGHT FITTING WITH 2 x 150W SON-T LAMP ON LIGHTING COLUMN STREET LIGHT FITTING WITH 1 x 70W SON-T LAMP ON LIGHTING COLUMN POST TOP COMPOUND LIGHT FITTING WITH 150W HIGH PRESSURE SODIUM LAMP
F5
D5
Project / Contract
F6
D6
KHALIFA PORT & INDUSTRIAL ZONE H CONTRACT No. 1000-208 KPIZ ONSHORE CIVIL AND BUILDING WORKS
Independent Checking Engineer Signature
F7
D7
WALL MOUNTED BULK HEAD LIGHT WITH 50W MBF LAMP 150mm x 150mm x 50mm JUNCTION BOX WALL MOUNTED FLOODLIGHT FITTING WITH 250W MBF LAMP 25mm x 75mm PVC FLOOR TRUNKING 1 x 250W MBF FLOODLIGHT MOUNTED ON 8M HIGH LAMP POLE 1 x 250W HPI-T METAL HALIDE LAMP, BUILT-IN GEAR, IP55 FLOOD LIGHT FITTING MOUNTED ON 3M HIGH LAMP POLE 1 x 250W HPI-T METAL HALIDE LAMP, BUILT-IN GEAR, OUTDOOR WEATHER PROOF FLOOD LIGHT FITTING MOUNTED AT WALL, SOFFIT OR ROOF EDGE 1 x 8W FLUORESCENT SELF CONTAINED TYPE EMERGENCY LIGHT FITTING 1 x 13W FLUORESCENT SELF CONTAINED TYPE EMERGENCY LIGHT FITTING 1 x 8W FLUORESCENT SELF CONTAINED ANTI CORROSION TYPE EMERGENCY LIGHT FITTING TELEPHONE
Contractor
AL HABTOOR LEIGHTON
4 J
F8
D8
Al Habtoor Leighton Group (Al Habtoor Engineering Enterprises Co. L.L.C. and Leighton Contracting (Abu Dhabi) L.L.C. Joint Venture) P.O. BOX 94267 TEL. NO. +97126998400 FAX NO. +97126760899
F9
D9
F10
D10
P.O. Box 43266, Abu Dhabi, United Arab Emirates T +971 2 414 6000 F +971 2 414 6001
Sub-Consultant / Sub-Contractor
K H1
1000-208-VW-4200-20618-C01.dwg
COID
F11
D11
Entity - 000
000
Element 00000
F12
E1
1 x 8W FLUORESCENT SINGLE SIDED ' EXIT ' SIGN LIGHT FITTING WITH DIFFUSER ARROW 1 x 8W FLUORESCENT DOUBLE SIDED ' EXIT ' SIGN LIGHT FITTING WITH DIFFUSER ARROW
EL2
F13
E2
EL3
A1
M
F14
M 1 2 3 4 5 6 7 8 9 10 11 12 13 14
1000-208-VW-4200-20618
15 16
C01
1 A
10
11
12 DETAILS
13
14
NOTES:-
15
16 A
1. ALL SIZES,RATINGS AND QUANTITIES SHOWN ARE INDICATIVE. 2. REFER TO SMALL POWER SYMBOLS & LEGEND DRAWING No.1000-208-VW-4200-20618.
1. STAINLESS STEEL HINGES (SS 316). 2. STAINLESS STEEL WINDSTAYS (SS 316). 3. HEAVY DUTY HANDLE LOCK WITH STAINLESS STEEL RODS & CAMS (SS 316). 4. STAINLESS STEEL TOWERBOLTS (SS 316). 5. STAINLESS STEEL EYEBOLT. 6. 2 NOS. ALUMINUM LOUVERS WITH FILTER, SIZE 400 (H) x 600 (W) mm ON LEFT HAND SIDE.
LEGEND
EMERGENCY STOP PT PRESSURE TRANSMITTER
3050 4300
Brett Bass
Signature A B C
HLG Design Status HLG Approved - For Issue to ADPC HLG Approved with Comments - For Issue to ADPC Reject by HLG, Re-submit for Approval 3 2500 ADPC Status Stamp Code 1 Code 2 Code 3 DO NOT SCALE FROM THIS DRAWING Code 4 6 Works May Proceed.
Revise & resubmit. Work may proceed subject to incorporation of comments indicated. Revise & Resubmit Works May not Proceed. Review not required. Work may proceed
E
4
The statement "Work may proceed" applies to the following work activities associated with the matters contained within the contractor's document. Design/ Procurement/ Construction/ All Activities * (*Delete/Amend/Add as applicable) Any review, comment or acceptance by employer under this contract with respect to any of contractor's documents shall not in any way be, or deemed to be, an approval of any works or an acceptance that the contractor's documents meet the requirements of the contract, as contractor has the sole responsibility for performing the works in accordance with the requirements of this contract.
1950
F
1:20 1:20
Date
G
Mohanr
C01 26.09.11 REVISED AS CLOUDED RAC SA ATB RAC SA ATB C00 19.05.11 ISSUED FOR CONSTRUCTION Rev Date Description Drawn Chkd Appr Drawn by / Date Checked by / Date Approved by / Date G Raymondo 19.05.11 S.Amine 19.05.11 A.Bitar 19.05.11 Client
C01 C01
Copyright Abu Dhabi Ports Company (ADPC), 2011. All Rights Reserved.
5 PIN INDUSTRIAL TYPE WEATHER / EXPLOSION PROOF SOCKET OUTLET WITH ISOLATOR FOR PORTABLE GENERATOR STREET LIGHTING DB
Project / Contract
KHALIFA PORT & INDUSTRIAL ZONE H CONTRACT No. 1000-208 KPIZ ONSHORE CIVIL AND BUILDING WORKS
Independent Checking Engineer Signature
Contractor DB
AL HABTOOR LEIGHTON
J
1000 8Nos. 100mm DUCTS 8Nos. 100mm DUCTS 3050 ANODISED ALUMINIUM CHEQUER PLATE WITH SUPPORT TO SUIT Consultant
Al Habtoor Leighton Group (Al Habtoor Engineering Enterprises Co. L.L.C. and Leighton Contracting (Abu Dhabi) L.L.C. Joint Venture) P.O. BOX 94267 TEL. NO. +97126998400 FAX NO. +97126760899
C01
750
Sub-Consultant / Sub-Contractor
K
1150 COID Zone 00 Entity - 000 Element 00000
1000-208-VW-4200-20620-C01.dwg
000
4300
7mm THICK APPROVED TANKING MATERIAL AND 4mm THICK PLYWOOD PROTECTION BOARD OR SIMILAR TO COVER ALL UNDERGROUND STRUCTURE
1 : 25
A1
M
GRP KIOSK
M 1 2 3 4 5 6 7 8 9
GRP KIOSK
1000-208-VW-4200-20620
10 11 12 13 14 15 16
C01
1 A
10
11
12
13
14
NOTES:-
15
16 A
E 267690.355 N 2742696.047
1. ALL DIMENSIONS ARE IN MILLIMETERS AND ALL LEVELS ARE IN METERS UNLESS STATED OTHERWISE . 2. REFER TO SMALL POWER SYMBOLS & LEGEND DRAWING No.1000-208-VW-4200-20618. 3. WALL MOUNTED SUPPORT WILL BE PROVIDED IN THE CABLE TRENCH. 4. YARD CABLING TO BE IN DUCTS (NOT DIRECT BURIED)
LEGEND
EMERGENCY STOP
B
D9 D9 D9 16A 4P MCB
B
CONTRACTOR'S VERIFICATION STAMP
We, Habtoor Leighton Group, verify that this contractor's document: * Has been produced and checked in accordance with contractor's quality assurance plan. * Is of a standard that will enable the employer to accept it in accordance with the contract. * Complies with all requirements of the contract.
16A TPN
PC
M A
Following deviations to contract are referenced for which a dispensation has been accepted by the employer: Other related letters/CTI's which document clarifications associated with this document are listed below:
C
TO NEUTRAL 16A 4P 100mA RCCB
B1 10 A TPN MCCB
Y1 10 A TPN MCCB
Brett Bass
Signature A B C
HLG Design Status HLG Approved - For Issue to ADPC HLG Approved with Comments - For Issue to ADPC Reject by HLG, Re-submit for Approval ADPC Status Stamp Code 1 Code 2 Code 3 Works May Proceed.
Revise & resubmit. Work may proceed subject to incorporation of comments indicated. Revise & Resubmit Works May not Proceed. Review not required. Work may proceed
GRP KIOSK 4C 6mm XLPE/SWA/PVC + 1C 6mm ECC 4C 6mm XLPE/SWA/PVC + 1C 6mm ECC 4C 6mm XLPE/SWA/PVC + 1C 6mm ECC
Code 4
The statement "Work may proceed" applies to the following work activities associated with the matters contained within the contractor's document. 2 NOS. D9 TYPE Design/ Procurement/ Construction/ All Activities * (*Delete/Amend/Add as applicable) Any review, comment or acceptance by employer under this contract with respect to any of contractor's documents shall not in any way be, or deemed to be, an approval of any works or an acceptance that the contractor's documents meet the requirements of the contract, as contractor has the sole responsibility for performing the works in accordance with the requirements of this contract.
3 NOS. D9 TYPE
SUMP
3 NOS. D9 TYPE
F
22000
Date
G
Mohanr
C01 26.09.11 REVISED AS CLOUDED RAC SA ATB RAC SA ATB C00 19.05.11 ISSUED FOR CONSTRUCTION Rev Date Description Drawn Chkd Appr Drawn by / Date Checked by / Date Approved by / Date G Raymondo 19.05.11 S.Amine 19.05.11 A.Bitar 19.05.11 Client
LOAD DISTRIBUTION SCHEDULE INCOMER ELCB/RCD CIRCUIT REF.NO. R1 PROTECTION MCCB, TPN, 10A MCCB, TPN, 10A MCCB, TPN, 10A
DB / STREET LIGHTING CONDUCTOR SIZE 6 SQ MM 6 SQ MM 6 SQ MM CIRCUIT NAME/DESCRIPTION 3 3 2 TOTAL Nos. D9 TYPE Nos. D9 TYPE Nos. D9 TYPE
Project / Contract
B1 Y1
KHALIFA PORT & INDUSTRIAL ZONE H CONTRACT No. 1000-208 KPIZ ONSHORE CIVIL AND BUILDING WORKS
Independent Checking Engineer Signature Contractor
AL HABTOOR LEIGHTON
J
Consultant
Al Habtoor Leighton Group (Al Habtoor Engineering Enterprises Co. L.L.C. and Leighton Contracting (Abu Dhabi) L.L.C. Joint Venture) P.O. BOX 94267 TEL. NO. +97126998400 FAX NO. +97126760899
Sub-Consultant / Sub-Contractor
K
COID D9 4C 6mm XLPE/SWA/PVC + 1C 6mm ECC 1000-208-VW-4200-20621-C01.dwg D9 D9 Zone 00 Entity - 000 Element 00000
000
5200
E 267676.012 N 2742679.412
19000
E 267690.418 N 2742666.989
IRRIGATION PUMP STATION AND RESERVOIR EXTERNAL LIGHTING AND CABLE ROUTING (SHEET 1 OF 1)
Sheet Scale 1:50 Drawing Status Paper Size
A1
M
1000-208-VW-4200-20621
15 16
C01
1 A
10
11
12
13 LEGEND:
IB
14
NOTES:-
15
16 A
12 WAY INSTRUMENT EARTH BAR WITH 2 DISCONNECTING LINKS 12 WAY ELECTRICAL EARTH BAR WITH 2 DISCONNECTING LINKS EMERGENCY STOP
E 267690.355 N 2742696.047
E 267704.768 N 2742683.666
EB
1. ALL DIMENSIONS ARE IN MILLIMETERS AND ALL LEVELS ARE IN METERS UNLESS STATED OTHERWISE . 2. REFER TO SMALL POWER SYMBOLS & LEGEND DRAWING No.1000-208-VW-4200-20618. 3. WALL MOUNTED SUPPORT WILL BE PROVIDED IN THE CABLE TRENCH. 4. YARD CABLING TO BE IN DUCTS (NOT DIRECT BURIED)
B
CONTRACTOR'S VERIFICATION STAMP
We, Habtoor Leighton Group, verify that this contractor's document: * Has been produced and checked in accordance with contractor's quality assurance plan. * Is of a standard that will enable the employer to accept it in accordance with the contract. * Complies with all requirements of the contract.
SLIDING GATE
Following deviations to contract are referenced for which a dispensation has been accepted by the employer: Other related letters/CTI's which document clarifications associated with this document are listed below:
NONE Contractor's Project Manager: 0.3% ROLLING SHUTTER DOOR RAMP SLOPE 1:5 Brett Bass MANHOLE MH100-2 Signature A B C Date Code Initial HLG Design Status IB HLG Approved - For Issue to ADPC HLG Approved with Comments - For Issue to ADPC Reject by HLG, Re-submit for Approval ADPC Status Stamp Code 1 400mm DEEP 500mm WIDE CABLE TRENCH MANHOLE Code 2 Code 3 1 NO. 300 POWER CABLE TRAY + ECC 1 NO. 100 CONTROL CABLE TRAY Code 4 Works May Proceed. Revise & resubmit. Work may proceed subject to incorporation of comments indicated. Revise & Resubmit Works May not Proceed. Review not required. Work may proceed
8200
16A ISOLATOR FOR LIFTING CRANE 4C 6mm2 XLPE/SWA/PVC + 1C 6mm2 ECC 1 NO. 300mm POWER CABLE TRAY + ECC 1 NO. 100mm CONTROL CABLE TRAY 8 NOS. 100mm DIA DUCTS. RAMP SLOPE 1:5 SEPARATE EARTH PIT FOR PORTABLE GENERATOR
GRP KIOSK 4C 6mm2 XLPE/SWA/PVC + 1C 6mm2 ECC 3C 2.5mm2 PVC/SWA/PVC 7C 2.5mm2 PVC/SWA/PVC
The statement "Work may proceed" applies to the following work activities associated with the matters contained within the contractor's document. Design/ Procurement/ Construction/ All Activities * (*Delete/Amend/Add as applicable) Any review, comment or acceptance by employer under this contract with respect to any of contractor's documents shall not in any way be, or deemed to be, an approval of any works or an acceptance that the contractor's documents meet the requirements of the contract, as contractor has the sole responsibility for performing the works in accordance with the requirements of this contract.
8Nos. 100mm DUCTS INCOMING LOW VOLTAGE CABLE FROM ST01/03 1 NO. 4C 70mm XLPE/SWA/PVC 600
SUMP
F
2000 22000 750mm WIDE, 700mm DEEP CABLE TRENCH 1 NO. 150mm POWER CABLE TRAY + ECC 1 NO. 100mm CONTROL CABLE TRAY EB
Abu Dhabi Ports Company 1 NO. 600mm POWER CABLE TRAY + ECC 1 NO. 200mm CONTROL CABLE TRAY IB
Date
G
ULTRASONIC LEVEL TRANSMITTER Mohanr 3C 2.5mm2 PVC/SWA/PVC 1C 1.5mm2 PVC/SWA/PVC (SCREENED)
C00 26.09.11 ISSUED FOR CONSTRUCTION RAC SA ATB Rev Date Description Drawn Chkd Appr Drawn by / Date Checked by / Date Approved by / Date G Raymondo 26.09.11 S.Amine 26.09.11 A.Bitar 26.09.11 Client
Copyright Abu Dhabi Ports Company (ADPC), 2011. All Rights Reserved.
Project / Contract
KHALIFA PORT & INDUSTRIAL ZONE H CONTRACT No. 1000-208 KPIZ ONSHORE CIVIL AND BUILDING WORKS
Independent Checking Engineer GRP WATER TANK Signature Contractor
AL HABTOOR LEIGHTON
J
Consultant
Al Habtoor Leighton Group (Al Habtoor Engineering Enterprises Co. L.L.C. and Leighton Contracting (Abu Dhabi) L.L.C. Joint Venture) P.O. BOX 94267 TEL. NO. +97126998400 FAX NO. +97126760899
Sub-Consultant / Sub-Contractor
K
COID Zone 00 Entity - 000 Element 00000
1000-208-VW-4200-20622-C00.dwg
000
5200
E 267676.012 N 2742679.412
19000
E 267690.418 N 2742666.989
IRRIGATION PUMP STATION AND RESERVOIR EXTERNAL POWER AND CONTROL CABLE L ROUTING (SHEET 1 OF 1)
Sheet Scale 1:50 Drawing Status Paper Size
A1
M
1000-208-VW-4200-20622
15 16
C00