SOP-0017-Standard Operating (Work) Procedure - Stringing
SOP-0017-Standard Operating (Work) Procedure - Stringing
STRINGING Sheet No 1 of 36
STRINGING Sheet No 2 of 36
CONTENTS
I COVER SHEET 1
II CONTENTS 2
III ABBREVIATIONS 3
1 PURPOSE 4
2 SCOPE 4
3 EXCLUSION 4
4 APPLICABILITY 4
5 REFERENCE DOCUMENTS 4
6 RESPONSIBILITY 4
7 PREREQUISITE 4
8 EQUIPMENTS 5
9 PROCEDURE 5 to 18
10 ACCEPTANCE CRITERIA 18
11 SAFETY MEASURES/PRECAUTIONS 18 to 19
12 RECORDS 19
13 ANNEXURE I 20
14 ANNEXURE II 21 to 29
15 ANNEXURE III 30 to 31
16 ANNEXURE IV 31 to 33
17 ANNEXURE V 34 to 36
KEC-Q-TL-SOP-
Standard Operating (Work) Procedure Document No.
0017
STRINGING Sheet No 3 of 36
ABBREVIATIONS
STRINGING Sheet No 4 of 36
1. PURPOSE:
This document describes the step wise work procedure to carry out the stringing work of 132 / 220 / 400 / 765 kV
D/C, 800 kV HVDC or other kind of Transmission Line work in planned and controlled manner with reference to the
drawings, technical specification and standards.
2. SCOPE:
It includes stringing methods for all types of Towers as indicated on Technical Specification / Drawing. The work shall
be carried out in accordance with the specification and corresponding approved drawings.
3. EXCLUSION :
In case of very specific & mandatory customer’s need their processes & formats can be followed as a part or in full.
However in case of any conflict most stringent norms must be followed.
4. APPLICABILITY:
This procedure is primarily developed for Transmission works but same can be used in similar kind of Railway &
Distribution works, at sites across all locations as per specification.
5. REFERENCE DOCUMENTS:
Following Documents / Drawings / Codes have been referred for the preparation of this procedure:-
a) IS : 5613 (Part 2 / Section 2) - 1985, IS : 5613 (Part 3 / Section 2) – 1989 (Installation of lines)
b) IS: 4082-1986 (Storage of construction material at site)
c) IS: 7293-1974 (Safety code for working with construction machineries)
d) Welding specs as per requirement
e) IS: 13416 Part1- 1992 (Falling material hazards prevention), IS: 13416 Part2- 1992 (Fall Prevention)
f) A few international standards and recommendation from (Saudi, Africa etc) were referred.
6. RESPONSIBILITY:
Responsibility of implementation of this procedure rest with below mentioned officials
a) PRIMARY: Section In-Charge, Stringing Supervisor, Stringing Engineer
b) SECONDARY: Project Manager, Store In-charge (SI), Quality Control Engineer (QCE)
7. PREREQUISITE:
a) Generic Contract Documents (as applicable)
b) Field Quality Plan (FQP)
c) Approved sag charts & profile drawings
d) Approved insulator assembly drawings
e) Stringing Schedule
f) Drum Schedule
g) Tower completion & inspection report.
h) Tested handling equipments, Tools & Tackles.
i) Availability of skilled manpower.
j) Availability of all PPEs.
KEC-Q-TL-SOP-
Standard Operating (Work) Procedure Document No.
0017
STRINGING Sheet No 5 of 36
9. PROCEDURE:
9.1 INSULATOR HOISTING:
Ensure complete and apposite assembly of insulator with accessories as per the approved drawing on the
ground before lifting.
Ensure that the assembly is done on clean and dry surface.
Ensure that no damaged insulator is taken for assembly.
Ensure insulator handling as per recommended by the OEM (Original Equipment Manufacturer).
Clean each insulator before hoisting, in such a manner that it will not scratch damage or spoil the surface of
the insulator, but in no case oil should be used for cleaning. (IS5613 15.1)
The corona rings shall be fully installed on their respective hardware before such hardware or insulator
assembly is installed on the structure as per requirement.
The insulator assembly shall be attached to the structure as indicated on the applicable drawing.
Insulator assembly shall be carefully pulled up using pulling arrangement at the place of installation.
Once it reaches its position it should be firmly fitted as per drawing.
An insulator consisting of multiple insulator units, which shall be supported and protected during installation
to prevent damage.
STRINGING Sheet No 6 of 36
In addition, tall trees outside the area, of such height that they could fall within three meters of conductors
shall be cut down after obtaining necessary permission.
Before commencement of any tree cutting operation proper approval from authorized department has to be
taken.
STRINGING Sheet No 7 of 36
If substantial line angles are involved, two rollers in tandem may be required to reduce the bending radius of
the conductor or the load on each traveler, or both.
The running blocks shall be suspended in a manner to suit the design of the cross-arm.
All running blocks especially those eat the tensioning and, will be fitted on the cross-arms with jute cloth
wrapped over the steel work and under the slings to avoid damage to the slings as well as to the protective
surface finish of the steel work.
The rollers/travelers shall be having a groove to accommodate a semi circular section of conductor and larger
than the diameter of the conductor/earthwire with enough space for free movement of the conductor wire
inside it, so that it does not slip over or rub against the sides.
The rollers/traveler’s groove shall be lined with hard rubber or neoprene to avoid damage to conductor and
shall be mounted on properly lubricated bearings.
STRINGING Sheet No 8 of 36
Equipment Placement/Location
Once the pull sections are identified the placement of the puller, tensioner, reel stand etc can be
done.
1) Drum:
The drum is placed at the selected site (with the space required for its location) so that the cable
outlet is on the upper part and aligned with the planned laying direction.
The drum must be located at a suitable distance from the tensioner to allow enough fleet angle
for the conductor leaving the reel and entering the bullwheel of the tensioner, so that no damage
or scuffing of the conductor can occur.
The lifting components usually used are hydraulic jacks and a bar with the suitable dimensions
inserted in the central opening of the drum.
The drum must be located at a sufficient height from the ground for free rolling movement.
Level of the surface should be such that while rolling movement of the drum due to conductor
pull is done it should not be unbalanced.
Care shall be taken to insure that the conductors from the reels carry no dirt. Reels shall be
properly cleaned before starting stringing operations for any line section.
Before placing the drum reconfirm the length.
2) Puller & Tensioner:
Either the puller & the tensioner must be placed at a minimum distance from the tower equal to
or more than twice the tower’s height at respective positions.
The tensioner as well as the puller should be placed aligned with the conductors.
Tensioner machine will be anchored using spikes driven in the ground to counter the pull force.
Care will be taken to ensure the Tensioner is positioned on almost level ground level and also at
minimum off-set from centre line as far as possible.
Care has to be taken to minimize the angle of pull line with a maximum limitation of thirty degree
from centreline axis of stringing section.
STRINGING Sheet No 9 of 36
Grounding Equipments
Temporary electrical grounds shall be placed at both ends of the section and at intervals along
the line, which is under construction.
The grounding sets installed at both ends of the section shall remain in place until the completion
of the work and shall be removed as the last phase of the cleanup.
Hot stick shall be used for installing and removing the grounding sets.
All temporary grounds installed for protection shall be clearly visible for inspection and shall be
flagged by use of a red cloth placed at the point of grounding.
All pulling and tensioning equipment shall be bonded and effectively grounded with approved
type driven grounds securely attached to the equipment.
At least two driven grounds shall be used at both the pulling and tensioning setup.
All conductive parts of the tensioning setup and equipment shall be operated from grounded or
insulated platform.
All existing lines, which are de-energized for crossing, shall be short circuited and grounded at
each side of the crossing. Use of discharge rod is necessary at both the ends of a line crossing.
All grounds, except those placed at both ends of the section, and red flags shall be removed when
they are no longer needed for protection.
Guy wire or temporary guy wire shall not be used for grounding.
The pulley block on each tower must be earthed and grounding roller to be used on drum side to
ensure grounding of any induction current developed during installation.
STRINGING Sheet No 10 of 36
It is recommended to provide Green / Red flag in each & every tower of the stringing section.
For stringing of bundled conductors with running board, it will be desirable to observe the running
board as it passes through each traveler so in case of any blockage the observer can communicate
to the puller & tensioner end.
A back up communication system must be available during actual stringing, in case if one of it fails
during the work.
STRINGING Sheet No 11 of 36
Full tension joints shall be pressed during paying our and covered with joint protectors which will
be removed at the end of the pull before sagging.
After being pulled the conductor/ earthwire shall not be allowed to hang in the stringing blocks
for more than 96 hours before being pulled to the specified sag. (IS5613- 17.1.1)
Splicing/Joints
All the joints on the conductor and earthwire shall be of compression type, in accordance with
the recommendations of the manufacturer for which all necessary tools and equipment like
compressors dies process, etc, shall have to be arranged in advance.
Each part of the joint shall be cleaned by wire brush to make it free of rust or dirt, etc. and properly
greased with anticorrosive compound before the final compression is done with the compressors.
All joints or splices shall be made at least 30 metre away from the structures. (IS5613-18.2)
No joints or splices shall be made in spans crossing over main roads, railways, small rivers in
tension spans.
Not more than one joint per sub-conductor shall be allowed in one span.
The compression type fitting used shall be of self-centering type or care shall be taken to mark
the conductors to indicate when the fitting is centered properly.
During compression or splicing operation, the conductor shall be handled in such a manner as to
prevent lateral or vertical bearing against the dies.
After pressing the joint the aluminum sleeve shall have all corners rounded, burrs and sharp edges
removed and smoothened.
Considerations on Crossings
Scaffoldings are to be used wherever there is road crossing, line crossing, railway lines etc are to
be crossed during the stringing operations.
It is to be ensured that the other work (viz. road traffic flow, etc) isn’t affected due to stringing of
the tower.
It is to be ensured that the scaffolding provided for the crossing is of adequate strength so as to
bear the loads of stringing operation.
STRINGING Sheet No 12 of 36
Ensure that the shutdown permission is obtained from the concerned authority in case of electric
line crossing.
The shutdown procedure as stated below shall be followed.
Ensure that the DB is switched off with a person present at DB all time possessing communication
equipment (two way radios/mobile).
Ensure that for each line conductor there are 2 discharge rods available for shutdown.
Electrical rubber hand gloves with rod for discharging cable fitting should be present at the
site/location.
First grounding/earthing of the mild steel (MS) rod should be done as shown overleaf.
STRINGING Sheet No 13 of 36
All the shutdown procedure form/ Permit to work form should be submitted by the
supervisor/Engineer.
Sagging
Sagging processes consist of sag matching with the sag details mentioned in sag chart. The following
considerations are to be made before sagging.
Regulating spans or sag sighting spans identified.
Sag Section.
Sagging is generally carried out by Sagging winch and a 4 way + 4 way pulley arrangement.
Sagging thermometers shall be installed sufficiently prior to the actual sagging operation to allow
temperature stabilization and shall be mounted far enough above the ground to avoid the effect
of ground heat radiation.
Thermometers shall be inserted in a conductor section (about 0.5 m in length) to represent the
temperature internal to the conductor. Two thermometers shall be used in the sag spans, which
are near, or at the ends of the sag section.
One steel wire rope lead is passed through an equalizing pulley, of diameter equal to the sub –
conductor spacing, and its ends are connected to both the come along clamps on the conductors.
This is done so that the tension on both the conductors remains the same. The equalizing pulley
is connected to one end of the pulley system.
The other end of the pulley system is connected to the dynamometer. The double tension
hardware is hoisted and anchored on the cross arm. The dynamometer is connected to the yoke
plate of the double tension hardware.
The running blocks, when suspended from the transmission structure for sagging shall be so
adjusted that the conductors on running blocks will be at the same height as the suspension clamp
to which it is to be secured.
Two leads and two pulley systems, one for each conductor, can be used in place of equalizing
pulley. Both the pulley systems are connected to the yoke plate of the double tension hardware
and tensioned together one by one as shown in following figures.
However, dynamometer is used only on one conductor and the sag on the other conductor is
matched with the sag of the first conductor.
A come along clamp is fitted on each rough sagged conductor at a distance from the tower on
which the final sagging is being carried out.
The come along clamp is then connected to the pulley arrangement which is being used for final
sagging through a steel wire rope which is generally referred to as “lead”.
The length of this lead is such that, after final sag, the come along clamp remains far enough from
the tower so that the loose portion of the conductor on the tower side can be pulled up to the
cross arm for the purpose of measurement.
Now the tensioning is done in the wires so as to provide final sag, which is measured to complete
the sagging of conductor/earthwire/OPGW.
The conductors shall be pulled up to the desired dag and left in running blocks for at least one
hour after which the sag shall be rechecked and adjusted. If necessary, before transferring the
conductors from the running blocks to be suspension clamps.
The conductors shall be clamped within 56 hours of sagging in. (IS5613-19.1)
The sag will be checked in the first and the last span of the section in case of sections up to eight
spans and in one intermediate span also for sections with more than eight spans.
The sag shall also be checked when the conductors have been drawn up and transferred from
running blocks to the insulator clamps.
KEC-Q-TL-SOP-
Standard Operating (Work) Procedure Document No.
0017
STRINGING Sheet No 14 of 36
KEC-Q-TL-SOP-
Standard Operating (Work) Procedure Document No.
0017
STRINGING Sheet No 15 of 36
Figures Above Show the Sagging Arrangement Using 4 Ways + 4 Ways Pulley Arrangement
Measurement of Sag
Sag can be measured by one of the following methods (at site as agreed by Engineer).
Using sagging transit and sag board for
- Equivalent span method
- Maximum span method
STRINGING Sheet No 16 of 36
Now from bottom cord of middle cross arm extend a steel measuring tape up to the required
length as per chart.
Now fix the sag boards at that position, taking care that it should be easily visible & horizontal.
While measurement of sag see whether the conductor’s sagged portion is in line with the markers
visually.
If sagged portion is above the markers, loose the conductor or if below then tighten the
conductor.
Once the final sagging of each span is completed the rollers can be lowered down using the slings.
The maximum tolerance in final still air sag at maximum temperature shall be ±4 percent of such sag, in
any span as obtained from the sag tension chart.
The sag of any conductor in a span shall not depart from the mean sag of all conductors in the same span
by more than 3 percent or as specified by the client. (IS5613-5.1)
STRINGING Sheet No 17 of 36
Overview of Stringing
Clipping In
Clipping of the conductors in position shall be done in accordance with the recommendations of
the manufacturer.
Conductor shall be fitted with armour rods where it is made to pass through suspension clamps.
The jumpers at the section and angle towers shall be formed to parabolic shape to ensure
maximum clearance requirements.
Pilot suspension insulator string shall be used, if found necessary, to restrict the jumper swings to
the design values.
The security clip shall be properly opened and sprung into position.
Fittings/Accessories Installation
Spacers, spacer dampers, vibration dampers and other conductor and earthwire accessories shall
be installed as per the design requirements and respective manufacturer’s instructions.
Spacers shall be fitted within 24 hours of the conductor clamping. (IS5613-22.1)
While installing the conductor and earthwire accessories proper care shall be taken to ensure that
the surfaces are clean and smooth and no damage shall occur to any part of the accessories.
Fasteners in all fittings and accessories shall be secured in position using torque wrench.
Spacing bicycle/ trolley may also be used for fixing conductor accessories.
KEC-Q-TL-SOP-
Standard Operating (Work) Procedure Document No.
0017
STRINGING Sheet No 18 of 36
STRINGING Sheet No 19 of 36
Loading and unloading o f OPGW drums shall be done using suitable arrangement / crane.
Ensure water shall not penetrate in to the OPGW cable.
While working near moving/ rotating equipment special care has to be taken & close proximities to be avoided
while the instrument is running.
While laying the conductor/earthwire/OPGW care shall be taken that it doesn’t rub to the ground at any point
of work.
Proper and sufficient anchors & back stays are provided to the equipment under load.
Equipment to be handled as per the manufacturer’s instructions.
Ensure that shutdown is obtained prior to starting of stringing work near power line crossings till the completion
of final sagging activity.
Earthing shall be done at both the sides of phases before fixing the roller.
Both sides of the winch machine shall be earthed.
Equipment like OPGW, existing ground wire and pulley block are to be connected to Individual copper cable and
connect to the tower earthing.
Grounding clamp shall be cleaned well and ensure proper contact.
Grounding is to be perfectly done to ensure safe level of working. Proper grounding is to be ensured during
operation like clamping work to avoid fault current likely to be encountered.
Grounding cables shall be connected to the ground source first and then to the equipment. When removing the
grounds, the ground must be removed from the equipment first and then from the ground source.
Ensure that only a competent & authorized person is operating the equipment.
12. RECORDS :
Stringing Checklist Conductor/Earthwire (KEC-Q-TL-SA-CL-0018, Annexure II)
Stringing Checklist OPGW (KEC-Q-TL-SA-CL-0018, Annexure II)
KEC-Q-TL-SOP-
Standard Operating (Work) Procedure Document No.
0017
STRINGING Sheet No 20 of 36
ANNEXURE I
Special Recommendation for Transporting & Handling of Conductor/OPGW
STRINGING Sheet No 21 of 36
ANNEXURE II
Checklists:
STRINGING Sheet No 22 of 36
Checklists:
Details of Earthwire
Make
Batch No
Quantity and Location
Dimension-Recorded. Yes/No.
M.S. Joint has been provided at least 30 meters away from tower. Yes/No.
There is no M.S. Joint over railway/River/Main road crossing. Yes/No.
Not more than one M.S. joint provided in one span for each
Yes/No.
earthwire/conductor.
Repair sleeve shall be used if number of damaged strands is not more than
1/6th of the total strands in the outer layer. If damage is more, than the Yes/No.
damaged portion shall be removed and M.S. Joint provided.
KEC-Q-TL-SOP-
Standard Operating (Work) Procedure Document No.
0017
STRINGING Sheet No 23 of 36
Details of Conductor
Make
Batch No
Quantity and Location
STRINGING Sheet No 24 of 36
Joints Details
Section Phase Conductor Wire No.
No. of Joint Between Loc No.
Dimension-Recorded. Yes/No.
M.S. Joint has been provided at least 30 meters away from tower. Yes/No.
There is no M.S. Joint over railway/River/Main road crossing. Yes/No.
Not more than one M.S. joint provided in one span for each
Yes/No.
earthwire/conductor.
Repair sleeve shall be used if number of damaged strands is not more than
1/6th of the total strands in the outer layer. If damage is more, then the Yes/No.
damaged portion shall be removed and M.S. Joint provided.
Dimension-Recorded. Yes/No.
Not more than one M.S. joint provided in one span for each
Yes/No.
earthwire/conductor.
KEC-Q-TL-SOP-
Standard Operating (Work) Procedure Document No.
0017
STRINGING Sheet No 25 of 36
Details of Insulators
Make
Batch No
Electro Mechanical Strength
Quantity and Location
Insulators are completely cleaned with soft cloth. Glazing is proper. There is
Yes/No.
no crack, scratch or white spot on its surface
‘R’ clips in insulators are fitted properly, while hoisting, no damage caused to
Yes/No.
insulators
STRINGING Sheet No 26 of 36
No. of Fittings
S.N. Loc No. Phases Remarks
Top Middle Bottom
STRINGING Sheet No 27 of 36
S.N. Fixed on Loc. No. Fixed towards Loc. No. Phase/wire No. No. of Vibration Damper.
STRINGING Sheet No 28 of 36
Sag
Tension
Sag
Tension
KEC-Q-TL-SOP-
Standard Operating (Work) Procedure Document No.
0017
STRINGING Sheet No 29 of 36
(Site Supervisor / Engineer) (QA / Q C Engineer) (Site Supervisor / Engineer) (QA / QC Engineer)
for KECIL for KECIL For CLIENT FOR CLIENT
KEC-Q-TL-SOP-
Standard Operating (Work) Procedure Document No.
0017
STRINGING Sheet No 30 of 36
ANNEXURE III
Checklists:
2 ORANGE
3 GREEN
KEC-Q-TL-SOP-
Standard Operating (Work) Procedure Document No.
0017
STRINGING Sheet No 31 of 36
4 BROWN
5 GRAY
6 WHITE
7 RED
BLUE
8 BLACK
9 YELLOW
10 VIOLET
11 PINK
12 AQUA
13 BLUE
14 ORANGE
15 GREEN
16 BROWN
17 GRAY
ORANGE
18 WHITE
19 RED
20 BLACK
21 YELLOW
22 VIOLET
23 PINK
24 AQUA
STRINGING Sheet No 32 of 36
ANNEXURE IV
Dos & Don’ts:
Right Wrong
STRINGING Sheet No 33 of 36
DOs DON’Ts
Checking of tower for proper fitment before starting Stringing work directly started without checking
the stringing work. the towers to be stringed.
All material like drums, insulators, equipment are
Material is brought to the site at last moment of
transported at required location before
commencing the work.
commencement of work.
Conductors & Insulators are handled as per the
storage & handling instructions form OEM or Materials handled roughly and carelessly.
standard procedure.
Tractor is used for pulling of the pilot line or
Pullers are used to pull the conductors, pilot lines.
conductors.
Ground rollers are used to avoid conductor’s
Conductors are dragged along the ground
contact with ground.
While working on insulators ladder or a safe
Insulators are used for ascending & descending
arrangement for descending and ascending is
for stringing work.
used.
Sag boards are fixed at the specified location as Sag boards are fixed at different location than
per chart. stated in chart.
Device used to measure the temperature is Non calibrated or faulty device used for
calibrated and in good working condition. temperature measurement.
Proper communication is held at every time while Communication is vague and sometimes
working thru walkie-talkie. communicated thru signs instead of 2 way radios.
While stringing all safety precautions as mentioned
Safety instructions are neglected while working.
in the manuals & standards are taken care off.
There are missing components/accessories (viz.
All components/ accessories are starkly fitted.
split pins, nuts etc)
Proper crimping & clipping is done. Improper clipping & crimping done.
Wires are not bent over the specified radius Wires are bent over the specified radius.
KEC-Q-TL-SOP-
Standard Operating (Work) Procedure Document No.
0017
STRINGING Sheet No 34 of 36
ANNEXURE V
Pre-Inspection Checklist:
KEC/Corp EHS/FT-005/Rev-00
Date of Inspection :
Name of Section/Line and Location Number :
Manpower Strength :
PM/Construction Manager/Engineer :
EHS Manager /Engineer/Officer :
S. NO. Check point Status Remark, IF Any
Winch Machine Final sag work should be carried out with Winch
2
Machine only.
STRINGING Sheet No 35 of 36
Visual Inspection of wire rope slings before use like sling not
15
corrosion, bend without cracking, no wire cut etc.
Visual Inspection of four sheave pulley, equalizer pulley, pulley
before use like side flat size not more than 08 mm, gap between
16
roller and side not more than 33mm, proper locking and safety
pin in open type pulley.
Visual inspection of all winch machines, pilot wire, head board
17
before use for Stringing work.
Visual Inspection of D-shackle before use like pin in seated,
18
identification of load, check the wear etc.
Availability of sufficient winch machine with required load
19
capacity for Sagging work..
STRINGING Sheet No 36 of 36
Not Applicable for Stringing work. However any well / pit nearby
34
the Stringing site should be properly barricaded.
35 Any other:
36 Any other:
37 Any other:
Comments / Remarks:
Note : No work carried out with short contingency deviation, It must cascaded to senior management, so if it is minor
deviation than need to be approval from Regional EHS Manager / RM, or if it is major deviation than need to be approved
corporate South Asia / T&D-EHS.