Method Statement For Placing Boom

This document provides a method statement for using a concrete placing boom on the Al Hitmi Residential Building project in Doha, Qatar. It outlines the responsibilities of Higgs & Hill and their subcontractors in installing, using, replacing as needed, and removing the boom. It also identifies the personnel and their roles, as well as the equipment needed. Safety is a priority and the appropriate documents outlining safety plans and inspections will be followed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
550 views6 pages

Method Statement For Placing Boom

This document provides a method statement for using a concrete placing boom on the Al Hitmi Residential Building project in Doha, Qatar. It outlines the responsibilities of Higgs & Hill and their subcontractors in installing, using, replacing as needed, and removing the boom. It also identifies the personnel and their roles, as well as the equipment needed. Safety is a priority and the appropriate documents outlining safety plans and inspections will be followed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 6

Doc.

No : HRB-H&H-SGE-G00 -M -0002

Project : Al Hitmi Residential Building, Doha Qatar Rev. No : 00

Client : Ali Bin Khalifia Al Hitmi & Co Date : 4 November 2007

Engineer : Norr Group Consultants International Ltd in association with Page : 1 of 6


Diwan Architect, Engineers & Planners
Contractor: Higgs & Hill

Method Statement
for
Concrete Placing Boom

Reference sheet
Document number Description
HRB-H&H-QAS-G00-Q-0009 Preparation of Method statements
HRB-H&H-QAS-G00-Q-0012 Inspection and Testing

Revision History

00 14 Nov 2007 FPJ For Approval RSR EAA EKW


Revision Date Prepared by Description Checked by Approved by
Total no of pages [incl Att]
©…….. H&H 56
TABLE OF CONTENTS

1. SCOPE............................................................................................................................. 3
2. INTRODUCTION.............................................................................................................. 3
3. DEFINITIONS................................................................................................................... 3
4. REFERENCES................................................................................................................. 3
5. RESPONSIBILITIES........................................................................................................ 3
6. ORGANISATION.............................................................................................................. 4
7. TOOLING AND EQUIPMENT........................................................................................... 4
8. WORKFORCE.................................................................................................................. 4
9. METHOD.......................................................................................................................... 5
9.1 Site set-up........................................................................................................................ 5
9.2 Assembly, installation, erection and safety methods..........................................................5
10. QUALITY AND TESTING................................................................................................. 5
11. SAFETY........................................................................................................................... 6
12. EMERGENCY PROCEDURE AND CONTACTS...............................................................6
13. RISK ANALYSIS AND CONTENGENCY PLAN...............................................................6
14. APPENDICES.................................................................................................................. 6

Project : Al Hitmi Residential Building, Doha Qatar Date : 14 Nov 2007


Doc. Title : Method statement for Concrete placing boom Rev. no : 00
Doc No : HRB-H&H-SGE-G00-M-0002 Page : Page 2 of 6
1. SCOPE

The scope of work described in this Method Statement involves the sequence of works, the
precautionary measures, safety procedures, technical details and execution of works of the
concreting placing boom “Al Hitmi Residential Building” project. (Main contractor Higgs & Hill)

2. INTRODUCTION

The following Method Statement will focus on the installation, use (including several replacements)
and finally the removal of the concrete placing boom. This document should be read in conjunction
with the following documents:

 Method Statements for General concrete works- Doc ref:HRB-H&H-SGE-G00-M-0005


 Risk assessment plan for General concrete works-Doc ref:HRB-H&H-SAF-G00-Q-0001
 Inspection & Test Plan for General concrete works- Doc ref: HRB-H&H-QCO-G00-Q-0004

Safe access to and egress from work platforms will be provided as required and in accordance
with statutory regulations, depending on location. Proper edge protection shall be provided, if it is
not practicable to provide edge protection, safety harnesses will be worn, fixed to suitable anchor
points.

All operations will be completed during the designated site hours and all relevant noise regulations
will be observed. Where it is necessary to work extended hours then the appropriate request forms
will be submitted in advance.

3. DEFINITIONS

Client : Ali Bin Khalifa Al-Hitmi & Co

Client’s Representative : Norr Group Consultants International Ltd

The Engineer : Diwan Architect, Engineers & Planners

Contractor : Higgs & Hill Qatar W.L.L.

Concrete boom supplier : Arabian mix

4. REFERENCES

 none

5. RESPONSIBILITIES

Higgs &Hill responsibilities:

The Project Manager shall review the resources & methodology, which are implemented in safe
and efficient manner to carryout the works.

The Construction Manager is responsible for the coordination of interfaces with subcontractor
disciplines on the construction site and to ensure that the subcontractor workforce is executing the
work in a correct and safe manner to meet the programmes and schedules as per the construction
programme. To ensure clear unobstructed access and area for materials and equipment transfer to
the site so as to achieve concrete operations in safe and efficient manner.

The Section Engineer / Site Engineers are responsible for day to day supervision, coordination and
control of subcontractor and interfaces to monitor the subcontractor workforce is sufficient to

Project : Al Hitmi Residential Building, Doha Qatar Date : 14 Nov 2007


Doc. Title : Method statement for Concrete placing boom Rev. no : 00
Doc No : HRB-H&H-SGE-G00-M-0002 Page : Page 3 of 6
execute work timely, correctly and in a safe manner to meet the programmes and schedules as
per the construction programme. Carrying out the inspection upon satisfaction of works
completion, initiate that applicable work inspection request WIR sheet for the section of works duly
completed in advance of 24 hours as per the Inspection & Test Plan and forward the same to the
QA/QC Inspector for follow up inspection. Attend all inspections of works with the Engineer’s
representative.

The Surveyor is responsible in carrying out all survey, setting out and alignment checks, line and
level is carried out as per the current approved drawings for construction.

The Foreman will be responsible for carryout the work in safe manner and control of the work force
together with the proper execution and monitoring of concreting works. Adequate work plot forms
to be provided for access to all concrete pour locations for proper discharge and compaction.
Ensure that workforce is wearing correct PPE. Sufficient light and safety at site has to be
arranged.

The Safety Officer will be responsible for conducting safety inspections and verifying the work to
meet the standard safety requirement, risk assessment, risk management at site, and
environmental issues which shall comply with Project HSE Plan.

6. ORGANISATION

The following personnel will be involved in the operation:

Execution & supervision - Higgs & Hill


Sl No Name Designation Mobile contact no
1 Evangelo Argiroudis Construction Manager 5541495
2 Vinggur Site Engineer 6623079
3 Renato Site Engineer 6883470
4 Magno Foreman 5658094
5 Rogaciano Reyas Surveyor 5590974
6 Vijaya Balan QA/QC Inspector 5595063
7 Rajesh Safety Officer 6736368
8 Charge-hands and labourers

7. TOOLING AND EQUIPMENT

 Concrete placing boom (Schwing SPB30)


 For other tools to be used: see Attachment 3.

8. WORKFORCE

Sufficient experienced work force will be engaged to carryout this task. No special requirements for
(additional) workforce.

Project : Al Hitmi Residential Building, Doha Qatar Date : 14 Nov 2007


Doc. Title : Method statement for Concrete placing boom Rev. no : 00
Doc No : HRB-H&H-SGE-G00-M-0002 Page : Page 4 of 6
9. METHOD

This chapter describes all activities for installing (and re-installing) of the concrete placing boom.

9.1 SITE SET-UP FOR CONCRETE PLACING BOOM

Site set-up for concrete placing boom will be as per attachment #1&2 is shown in the plan and
sectional elevation. The concrete placing boom will be placed in the centre of the corridor between
the elevators. The concrete supply pipe will connect the boom with the concrete pump.

9.2 ASSEMBLY, INSTALLATION, ERECTION AND SAFETY METHODS

The documents of attachment # 3 explain clearly the method for assembly and installation of all the
parts of the concrete placing boom. The documents of attachment # 4 explain the technical details
of the concrete placing boom
Erection will be undertaken by specialist erection crew, employed directly by concrete supplier,
who is also owner of the equipment. It is their responsibility to operate and maintain the unit.

10. QUALITY AND TESTING

Upon arrival of the mixer truck on site the delivery ticket of each ready mixed concrete truck will be
checked and noted to confirm correct mix being supplied.

The slump test or visual assessment will be carried out on each load of concrete delivered to site.
Slump tests will be conducted from the Mixer truck prior to discharge on to pump in accordance
with BS 1881: Pt 102: 1983.

Slumping and concrete cube sampling testing are to be carried out by a concrete technician. The
concrete Technician will take cubes at the required frequency for each type of concrete delivered
to the site, each of these loads will also have a slump test taken from it.

Slump rate for concrete pours: 1 test / each truck. Each truck is then visually checked with an
estimated value noted on the concrete pour record sheet.

Any suspect load of truck, slump tested to confirm compliance is not meeting the specified slump
requirements, shall be retested in twice this also acts as a check to confirm accuracy of the visual
checks.

If a concrete delivery is found to be out of specification it will be rejected and sent back to the
Batching Plant. The next load of concrete delivered will not be placed until the slump test is
completed and found to be within specification.
The slump of the concrete is to be within the limits as per the approved mix design.

Traceability of all concrete placed on site will be recorded on the Concrete pour record sheets and
marked up on record drawings. These documents will be cross referenced to Work inspection
requests (WIR) and concrete test cubes

The concrete ticket number, slump achieved, number of cubes made and other relevant
information will also be noted on the Concrete pour record sheet.

The Batching Plant will supply delivery dockets for each load of concrete; these will be checked by
Higgs & Hill and forwarded to the Engineer.

Project : Al Hitmi Residential Building, Doha Qatar Date : 14 Nov 2007


Doc. Title : Method statement for Concrete placing boom Rev. no : 00
Doc No : HRB-H&H-SGE-G00-M-0002 Page : Page 5 of 6
11. SAFETY

The specific safety instructions and precautions for installation methods are explained in the
attachment# 5

The general safety and Risk assessment aspects are explained in the “Method statement for
General concrete works”.

All operatives will be given a general site induction by safety officer; the Site Supervisors will also
conduct a series of Tool Box talks and method statement briefings to the personnel involved in
operation. Attendance records will be regularly updated.

General PPE for all operatives will consist of safety footwear and safety helmets. Specific PPE will
be issued as necessary. Operatives working with concrete will use rubber gloves and will wear
rubber boots. Other PPE requirements will be addressed as the work proceeds and other hazards
become a factor i.e. working at the leading edge of a slab.

Extra lightning will be arranged, including mobile/handheld lights (two gensets to be arranged to
generate power for additional lightning)

Traffic control / management will be in place prior to and during pouring.

12. EMERGENCY PROCEDURE AND CONTACTS

There is qualified Male nurse available at “Al Hitmi Office building” site office for first aid treatment.

In the event of accidents immediately notify to the Project Manager, Construction Manager and
Safety officer as mentioned in section 6.0 Organisation. The accident file, which is situated in the
Site Office, must be filled in, if an accident occurs.

Evacuation from the work area should be via designated routes leading to the designated muster
points.

13. RISK ANALYSIS AND CONTENGENCY PLAN

The Specific Safety risks and precautionary methods are explained in the attachment# 5

14. APPENDICES

Attachments # 1 : Ground floor plan


Attachments # 2 : Sectional elevation of ground floor
Attachments # 3 : Assembly & installation method statement for concrete placing boom
Attachments # 4 : Technical details of concrete placing boom
Attachments # 5 : safety instructions and precautionary measures

Project : Al Hitmi Residential Building, Doha Qatar Date : 14 Nov 2007


Doc. Title : Method statement for Concrete placing boom Rev. no : 00
Doc No : HRB-H&H-SGE-G00-M-0002 Page : Page 6 of 6