Satech Sabic BP 82 2012 005
Satech Sabic BP 82 2012 005
Satech Sabic BP 82 2012 005
Dear Sir,
With reference to the project and subject bid under Ref. # MPP-12-0988 dated 13 th June 2012;
please clarify the following.
3. Payment Terms:
(i) As per table 4/F the milestone payment indicates 5% of the payment shall be
released on contract award for development work. The award of contract for
development work may be delayed due to any reason. Hence we request to add
this 5% under approval of 10% of Drawings from RC to make it 15% payment.
(ii) Please confirm that the Agreement Document clause 8.4.5 also includes the
payment of retention money (10% of contract value).
4. Agreement document:
ARTICLE # 20 – INSURANCE:
(i) 20.1.1 - Comprehensive General Liability
(ii) 20.1.2 – Third Party Motor Liability
(iii) 20.1.3 – Workmen’s Compensation Insurance
(iv)20.1.4 – Employer’s Liability Insurance
All the above are generally not required for this type of project. Please clarify
5. Inputs required:
Please confirm that for the successful bidder, the company shall provide
(i) Structure Layout Drawings (in Auto CAD format)
(ii) UTM Grid coordinates of the site
(iii) Topographical Survey of the site
(iv)Geotechnical Investigation report (detailed)
Page 2 of 3
However, if we can be of further assistance, please do not hesitate in contacting us.
S. V. Ramesha
Engineering Manager
Mob # 0567145662
RC
CC: Mr. Khaled A. Mukahal/ Ahmed Mukahal
Page 3 of 3