TSH-IP-00.0081 - 02 First and LST Article Inspection

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

For PVD Qualification

Prepared by: Reviewed by: Approved by:

Rubén Stubelt Michael Soptick Daniel Baiz


Premium Connections Premium Connections Premium Connections
Manufacturing Services Coordinator Manufacturing Services Specialist Manufacturing Engineering Manager
Tenaris Tenaris Tenaris

Inspection Procedure

First and Last Article Inspection

Document Number TSH-IP-00.0081


Revision 02
Revision Date 06-Apr-2009
Effective Date 13-Apr-2009
Page(s) 4

This document as well as the information or data contained herein are confidential and shall not be copied, recopied,
reproduced, transmitted, disclosed or distributed to others or otherwise used for any purpose without the express, prior
and written permission of Tenaris Connections AG and/or Hydril Company and/or its affiliated companies ("Tenaris").
This document as well as the information or data contained herein are the exclusive property of Tenaris, and are to be
returned upon request therefore. All rights in proprietary and novel features of the subject matter are expressly reserved
by Tenaris. Recipient’s agreement to the foregoing is indicated by acceptance of this document. Copyrighted 2009 as an
unpublished work. ALL RIGHTS RESERVED.
For PVD Qualification Document Type Inspection Procedure
Document Number TSH-IP-00.0081
First and last Article Inspection Revision 02

Page Number 2

1. REVISION HISTORY

Effective
Rev. # Change Referenced Sections Prepared By: Reviewed by: Approved By:
Date

20-Oct-2008 01 New Document New Document


Name: R. Stubelt Name: M. Soptick Name: D. Baiz

13-Apr-2009 02 Correction 8.1.3


Name: R. Stubelt Name: M. Soptick Name: D. Baiz

Document Change

Disposition of
Affected Material

Raw Material X
In Process X
Completed X
For PVD Qualification Document Type Inspection Procedure
Document Number TSH-IP-00.0081
First and last Article Inspection Revision 02

Page Number 3

2. PURPOSE

2.1 The Purpose of this document is to explain the inspection of the First and Last Article.

3. PERSONS AFFECTED

3.1 This document is applicable to all:


3.1.1 All Tenaris Premium Connections Manufacturing Services Personnel.
3.1.2 Facilities licensed to thread TenarisHydril connections.

4. REFERENCES

4.1 Not Applicable.

5. DEFINITIONS AND ABBREVIATIONS

5.1 Definitions and abbreviations are defined in the most current revision of TenarisHydril document
TSH-GP-00.0001.

6. RESPONSIBILITIES

6.1 Responsibilities are defined in the most current revision of TenarisHydril document
TSH-GP-00.0002.

7. PERSONNEL QUALIFICATION

7.1 Personnel qualification is defined in the most current revision of TenarisHydril document
TSH-GP-00.0003.

8. PROCEDURES

8.1 Inspection

One (1) first and one (1) last article inspection shall be performed to all orders containing lots in
excess of 10 connections, from each threading machine per lot producing connections for full
length, coupling, and accessories.

8.1.2 First Article Inspection:

8.1.2.1 First article inspection shall be performed at the following frecuency:


- Start of Production
- Following any equipment changes, i.e. tooling (insert change is not considered
tooling), machine crash, cold start, etc.
- Following any change in machining personnel, i.e. shift change, etc.
- Following any delay in production equal to or greater than eight (8) hours.
For PVD Qualification Document Type Inspection Procedure
Document Number TSH-IP-00.0081
First and last Article Inspection Revision 02

Page Number 4

8.1.2.2 All product characteristics identified in the connections procedure and inspection
report (including visual and Overlay inspection) shall be evaluated on the first
article.

8.1.3 Last Article Inspection:

8.1.3.1 The last article shall be taken from one (1) of the last five (5) connections from
each machine. The last part produced shall be inspected 100% following the
requirements of 8.1.2.2.

8.2 Acceptance / Rejection Criteria

8.2.1 All dimensions shall be aimed to nominal, however, shall be within the tolerance window.
8.2.1.1 If the part offered for first article is found to be out of tolerance in any parameter,
the part shall be discarded and a new part shall be submitted for first article
inspection.

8.2.1.2 If the last article part is rejected, the inspector shall evaluate as many additional
parts as necessary to ensure that all defective items have been located and
identified.

8.3 Records

First and Last article inspections shall be documented in the applicable Inspection report form.
The lastest version of the applicable Inspection Report Form can be downloaded from
www.tenaris.com

9. ANNEX

9.1 Not Applicable.