An Assessment of Risk Factors Involved I
An Assessment of Risk Factors Involved I
of
Held at
Many models have been developed to assist contractors and clients in their cash flow
forecasting. The majority of these have been based on standard cash flow S-curves,
developed using the traditional manual approach, mathematical and statistical models.
Many of these models failed to consider and analyse the factors responsible for the
considerable variations in the modelled cash flow profiles. This study as a first step in
a knowledge-based expert system (KBES) modelling of construction cash flow to
incorporate risk and uncertainties, identified and assessed the risk factors responsible
for the variation in construction cash flow profiles. The study was conducted through
a questionnaire survey administered on contracting organisations. Analyses were
carried out using mean response and univariate analysis of variance (ANOVA).
Results showed that the major risk factors involved in cash flow forecasting relate to
changes in the design or specifications, contract conditions pertaining to cash in flow,
interim valuations and certificates and construction programming issues such as
inclement weather. Results also indicated that cash flow forecasting modelling that
incorporates risk would need to consider categorisation along the groupings of firm
size, procurement methods and construction duration.
INTRODUCTION
Financial Management has long been recognised as an important tool in construction
(Peer, 1982; Hendrickson et. al., 1987; Teicholz, 1987 and Carr, 1993). However, the
construction industry suffers the largest rate of insolvency of any sector of the
economy. Companies fail because of poor financial management, especially
inadequate attention to cash flow forecasting (Boussabaine and Kaka, 1998; Calvert,
1986; Harris and McCaffer, 1995). The major problem that construction managers
encounter in making financial decisions involves both the uncertainty and ambiguity
surrounding expected cash flows (Eldin, 1989). In the case of complex projects, the
problem of uncertainty and ambiguity assumed even greater proportion because of the
difficulty in predicting the impact of unexpected changes on construction progress and
consequently, on cash flows (Boussabaine and Elhag, 1999). The uncertainty and
ambiguity are caused not only by project-related problems but also by the economical
and technological factors (Laufer and Coheca, 1990).
1
E-mail: [email protected]
2
E-mail: [email protected]
2
Lowe (1987) argued that the factors responsible for variation in project cash flow
could be grouped under five main headings of contractual, programming, pricing,
valuation and economic factors. Harris and McCaffer (1995) identified the factors that
affect capital lock-up which ultimately affect project cash flow profile to include the
margin (profit margin or contribution), retention, claims, tender unbalancing, delay in
receiving payments from clients and delay in paying labours, plant hirers, materials
suppliers and subcontractors. Calvert (1986) identified other factors to include
seasonal effects on construction works, variability in preliminary expenses, contract
extensions of time for inclement weather and valuation of variations. Kaka and Price
(1993) in developing a model for cash flow forecasting identified other risk factors
affecting cash flow profiles to include estimating error, tendering strategies, cost and
duration variances. The identified risk factors have been reported to affect cash flow
profiles as well as significantly impacting on the modelling of cash flow. However the
perception of the contractors to the likelihood of the risk factors occurring in different
project types and of varying scope and duration is yet to be investigated. This then is
the focus of this study and it is a first step in a programme of research that intends to
develop a cash flow forecasting model that incorporates risk and uncertainty using the
knowledge-based expert system.
Several attempts have also been made at computer modelling of cash flow forecast
(Kaka and Boussabaine, 1999 and Lowe and Lowe, 1986). Some of the models were
based on computer simulations while others were based on value curves. Berny and
Howes (1982) and Kenly and Wilson (1986) took the ideographic approach to cash
flow forecasting by maintaining that value curves are generally unique and should be
modelled separately.
They insisted that a curve should be fitted for each project as opposed to the
nomothetic models, which aggregate groups of projects in order to develop a single
standard curve to produce typical value curves. Kaka and Boussabaine (1999)
however maintained that ideographic models are only useful for analytical purposes.
As such, they argued that forecasting requires the use of standard curves developed
out of a group of projects similar to the one to be executed (nomothetic models). They
therefore have developed cash flow models based on standard cost / value flow curves
using logit transformation to fit the data.
3
Boussabaine and Kaka (1998) have also attempted to model cash flow forecast using
artificial neural networks, which simulates neuronal systems of the brain. Boussabaine
and Elhag (1999) also applied fuzzy set theory to model movement of cash flow at
valuation periods. Attempts have also been made in modelling cash flow forecast
using expert system. Efforts in this regard include that of Brandon, 1988; Saleh, 1991;
Moussa, 1992; Lowe et. al., 1993 and Lowe and Lowe, 1997. While some of these
expert system models focused on the construction contractors, others focused on the
clients. The models however have not taken risk and uncertainty into consideration
and it is expected that this research effort will focus on this in the next few years.
Table 1: Surveyed firms’ turnover in the last Table 2: Project procurement options employed
financial year
About 68% of the respondents are in senior management position, 61% have higher
education and about 94% are professionally qualified. The mean experience of the
respondents is 26.94 years with a standard deviation of 8.19 years. This background
information regarding the respondents indicated that responses provided by them
could be relied upon for this study.
The questionnaire listed 21 risk factors derived from literature as potentially affecting
cash flow forecasting. Contractors were then asked to provide opinion regarding the
likelihood of each factor occurring. The scoring was done on a 0 to 5 Likert scale
(Holt, 1997) so as to accommodate the instances where the risk factors identified are
not applicable by assigning a score of zero. The highest likelihood of a risk factor
occurring was assigned a score of 5. In order to obtain a more focussed and targeted
4
scoring, contractors were requested to base their scoring on one recently completed or
an on-going project. With reference to the chosen project, respondents were requested
to supply further details. This included project type, construction duration, project
value, procurement option and nature of project client. Some of these project details
which have been used for the analysis are shown in Tables 2 to 4
Analyses of risk factors were carried out based on some grouping categories. These
included size of construction firms, building types, procurement options, client types,
project duration and project value. The main risk factors influencing variations in cash
flow forecasting as shown in Table 5 include: architect’s instructions, provision for
interim certificate, receiving interim certificates, agreeing interim valuations on site,
retention, delay in agreeing variations/ day works, delay in settling claims, inclement
weather, etc. and problem with the foundations. Three of these key factors, namely:
architect’s instructions, delay in agreeing variations/ dayworks and delay in settling
claims could be grouped under ‘changes in the design or specification’. Since changes
in design or specification is usually unforeseen until there is an architect’s instruction
and their effects could be remarkable on the cash flow profile, it is therefore not
surprising that contractors scored them high overall. Two of these major risk factors,
namely: provision for interim certificate and retention could be grouped under
‘contract condition’ as far as cash flow consideration is concerned. The fact that
contractors scored these factors high overall indicated that they were sensitive to the
provision of the contract conditions as they affect cash in flow and capital lock-up.
Furthermore another two of the identified major risk factors namely: receiving interim
certificates and agreeing interim valuation on site could be grouped under ‘interim
valuation and certificates’. Since this is the means whereby contractors receive cash
inflows, it is not surprising therefore that contractors scored the factors high overall as
well. ‘Inclement weather, etc.’ relates to the issue of construction programming while
‘problems with foundations’ relates to site conditions. These two factors could have
5
Table 5: Ranking of risk factors influencing variations in cash flow forecasting utilising construction
firms size grouping
Factors Overall Rank Small Rank Medium Rank Large Rank F Stat. Level of
mean firms’ firms’ firms’ significance
score mean mean mean ( p values)
Architect’s instructions 3.58 1 3.47 1 3.90 2 3.33 2 0.462 0.635
Provision for interim certificate 3.26 2 3.47 1 3.50 4 2.33 12 0.896 0.420
Receiving interim certificates 3.19 3 2.75 5 4.00 1 3.00 7 3.388 0.048 *
Agreeing interim valuations on 3.03 4 2.47 9 3.80 3 3.17 4 3.962 0.031 *
site
Retention 2.94 5 3.33 3 2.70 8 2.33 12 0.724 0.494
Delay in agreeing variation/ 2.94 5 2.93 4 3.00 5 2.83 8 0.029 0.971
daywork
Delay in settling claims 2.90 7 2.67 7 3.00 5 3.33 2 0.405 0.671
Inclement weather, strikes, etc. 2.68 8 2.73 5 2.30 10 3.17 4 0.850 0.438
Problems with the foundations 2.61 9 2.47 9 2.80 7 2.67 10 0.154 0.858
Delays in payments from client 2.52 10 2.40 12 2.70 8 2.50 11 0.124 0.884
Extent of float in contract 2.48 11 2.47 9 2.30 10 2.83 8 0.610 0.550
schedule
Tender unbalancing 2.26 12 2.00 14 1.90 15 3.50 1 3.481 0.045 *
Estimating error 2.26 12 2.53 8 2.10 12 1.83 16 0.975 0.390
Provisions for phased handover 2.06 14 2.13 13 1.90 15 2.17 14 0.081 0.922
Level of inflation 2.00 15 1.47 15 2.10 12 3.17 4 4.232 0.025 *
Listed buildings 1.55 16 1.27 16 1.80 17 1.83 16 0.429 0.655
Archaeological remains 1.39 17 1.00 17 2.00 14 1.33 21 2.040 0.149
Changes in interest rates 1.35 18 0.87 18 1.60 18 2.17 14 2.423 0.107
Provision for fluctuation 1.03 19 0.80 19 1.00 19 1.67 18 0.758 0.478
payments
Tree preservation orders 0.94 20 0.80 19 0.80 20 1.50 20 1.412 0.260
Changes in currency exchange 0.68 21 0.40 21 0.50 21 1.67 18 3.074 0.062
rates
* Significant at 5 % level
substantial impacts on the cash flow profile. It is therefore not surprising that they
ranked fairly high by the contractors overall scoring.
In spite of the major risk factors identified by overall ranking, analysis based on
grouping categories showed that significant difference of opinion are observable.
These have been presented in the following sections.
Analysis of risk factors based on the size of construction firms is shown in Table 5.
From the table, opinions pertaining to four risk factors were shown to have statistical
significant difference (P = 0.050). These included: receiving interim certificate,
agreeing interim valuations on site, tender unbalancing and level of inflation.
‘Receiving interim certificates’ ranked 3rd overall; it however ranked 1st under
medium firm while it ranked 5th and 7th under small and large firms respectively.
‘Agreeing interim valuation on site’ ranked 4th overall; it however ranked 3rd under
medium firm while it ranked 9th and 4th under small and large firms respectively.
These two factors have earlier been categorised under ‘interim valuations and
certificates’ which is the contractors’ means of cash in flow. The fact that there was a
statistical significant difference in their scoring of these important and high ranking
factors showed that they perceived the factors differently and perhaps have different
strategies of dealing with them. ‘Tender unbalancing’ had an overall rank of 12; it
however ranked 1st under large firms while it ranked 14 and 15 under the small and
medium firms respectively. This is an indication that while tender unbalancing is a
major tool utilised by large firms to manipulate cash flow, it appears not so used for
that purpose by small and medium firms. Moreover, while ‘level of inflation’ was
6
considered a major risk factors by large firms (ranked 4), it ranked 15th overall and
15th and 12th by small and medium firms respectively. This is an indication that due to
huge cash outlay for projects undertaken by large firms, the level of inflation is for
them a major risk factor, which is not the case for small and medium firms.
It is obvious from the foregoing that perception of risk factors between varying sizes
of construction firms is different. While there is similarity of opinions between the
small and medium firms in few cases, there are significant differences of opinions
between them and large firms on major factors. As such, categorisation according to
firm size grouping may need to be considered in modelling cash flow forecasting that
incorporates risk and uncertainty.
An analysis using the same data set but based on procurement options grouping is
presented in Table 6. The questionnaire survey targeted various procurement options,
however, responses were received regarding three procurement routes only (Table 2).
Due to scanty data available on management procurement option, this analysis was
based on traditional and design and build options only.
As evident from Table 6, opinion regarding three risk factors were significantly
different (P = 0.050) among procurement grouping sub-categories. These are:
architect’s instructions, delay in settling claims and delay in agreeing
variations/dayworks. These three factors had earlier been classified under ‘changes in
design or specification’. While changes in design or specification occasioned by the
architect’s instructions are paramount in traditional procurement route, they are less
likely under design and build option where design is fused into the construction outfit.
It is therefore not surprising that while these three factors ranked 1st, 2nd and 3rd
respectively under the traditional procurement route, they ranked 4th, 11th and 10th
respectively under the design and build procurement option. In view of this, it is
revealing that any successful modelling of cash flow forecasting that incorporates
Factors Overall Rank Tradit- Rank Design & Rank F Stat. Level of
mean ional build significance
score mean mean (p values)
Architect’s instructions 3.52 1 4.071 1 2.93 4 6.689 0.015 *
Delay in settling claims 2.86 6 3.53 2 2.14 11 7.073 0.013 *
Delay in agreeing variations/ 2.86 6 3.40 3 2.29 10 6.659 0.016 *
daywork
* Significant at 5 % level
risk factors may need to consider categorisation along procurement routes. This aligns
with Kaka and Dawood’s (2000) finding that the type of procurement route had effect
on the shape of the cash flow S-curves.
Using the same data set, an analysis was carried out based on construction duration
categorisation (Table 7). The construction duration range of 25-36 months (Table 3)
was not included in the analysis because only one project fell into that category.
7
Table 7: Ranking of risk factors utilising construction duration categorisation
Factors Overall Rank 0-6 Rank 7-12 Rank 13-24 Rank F Stat. Level of
mean months months months significance
score duration duration duration ( p values)
mean mean mean
Inclement weather, 2.70 8 1.50 15 3.00 4 3.00 4 3.691 0.038 *
strike, etc.
Level of inflation 2.03 15 1.33 16 1.73 15 3.00 4 4.258 0.025 *
* Significant at 5 % level
Table 7 indicates that opinions regarding two risk factors were significantly different
among construction duration grouping sub-categories. These are inclement weather,
etc and level of inflation. The first relates to the issue of construction programming.
While it ranked fairly high overall (rank of 8), it ranked 15th under projects of 0-6
months duration while it ranked 4th under both projects of 7-12 months and 13-24
months duration. This is not unexpected because the longer it takes to complete a
construction project, the more it is exposed to the vagaries of weather conditions,
labour actions, etc. It is therefore not surprising that while the factor ranked very low
under the project of shorter duration, it ranked higher under projects of longer
duration. The 2nd risk factor is economic-related. While it ranked very low overall
(rank of 15), it however ranked very high under projects of more than one-year
duration (rank of 4). This is not surprising because the longer the construction
duration of a project, the more susceptible it is to inflation. Therefore these are
pointers to the fact that any successful modelling of cash flow forecasting that
incorporates risk may need to consider categorisation along construction duration
route.
8
Table 8: Ranking of risk factors utilising construction project type grouping
Factors Overall Rank Commercial/ Rank Public & Rank F Statistic Level of
mean industrial community significance
Mean mean ( p values)
Problems with the 2.79 5 3.00 5 2.45 12 1.106 0.303
foundations
Archaeological remains 1.32 17 1.71 16 0.73 18 4.410 0.046 *
Changes in currency 0.50 21 0.76 21 0.09 21 4.388 0.046 *
exchange rates
* Significant at 5 % level
reference ranked low overall and under the grouping sub-categories, it cannot be
concluded that this categorisation be taken into consideration in cash flow forecasting
modelling. Moreover, more data would need to be collected on other construction
project type sub-categories not represented in this analysis in reaching a conclusion.
Results of analyses based on categorisations of client types and project values did not
suggest that modelling of cash flow forecasting be grouped along these categories. As
such, the analyses have not been presented in this paper.
CONCLUSION
The emphasis of this paper has been the identification and analysis of the risk factors
affecting construction cash flow forecasting. The identified risk factors have been
analysed by ranking the mean score and analysis of variance to examine the
significant differences of the mean scores between the subcategories of the various
groupings identified.
Within the limitations of the data, results showed that the major risk factors affecting
cash flow forecasting are: architects instructions, provision for interim certificate,
receiving interim certificates, agreeing interim valuation on site, retention, delay in
agreeing variations/dayworks, delay in settling claims, inclement weather, etc, and
problems with the foundation. Results from the analyses based on various groupings
indicated that a successful modelling of cash flow that incorporates risks and
uncertainties may need to consider the modelling along the categorisation of firm size,
procurement options and construction duration. A definite conclusion could not be
reached however regarding construction project type grouping. The research however
is an on-going one and it is expected that as more data are sourced, a definite
conclusion on that would be reached.
REFERENCES
Akintoye, A. (2000) Analysis of factors influencing project cost estimating practice.
Construction Management and Economics, 18(1), 77-89.
9
Berny, J. and Howes, R. (1982) Project management control using real time budgeting
and forecasting models. Construction Papers 2, 19-40.
Boussabaine, A.H. and Kaka A.P. (1998) A neural networks approach for cost flow
forecasting. Construction Management and Economics, 16, 471-479.
Boussabaine, A.H. and Elhag, T. (1999) Applying fuzzy techniques to cash flow
analysis. Construction Management and Economics, 17, 745-755.
Brandon, P.S. (1988) Expert systems for financial planning. Transactions of the Tenth
International Cost Engineering Congress, New York, vol. D4, 1-9.
Carr, R.I. (1993) Cost, schedule and time variances and integration. Journal of
Construction Engineering and Management – ASCE, 119(2), 245-265.
Edwards, P. and Bowen, P. (1998) Note: Risk and risk management in construction:
towards more appropriate research techniques. Journal of Construction
Procurement. University of Glamorgan. 4(2), November, 103-115.
Eldin, N. (1989) Cost control systems for PMT use. Transactions of the AACE, F3.1 -
F3.5.
Hendrickson, C., Au, T. and Martinelli, D. (1987) Spreadsheet aids for financial
planning for construction projects. Transportation Research Record, 1126,
100-109.
Kaka, A.P. and Price, A.D.F. (1993) Modelling standard cost commitment curves for
contractors’ cash flow forecasting. Construction Management and
Economics, 11, 271-283.
Kaka, A.P. and Boussabaine, A.H. (1999) Updating techniques for cumulative cost
forecasting on construction projects. Journal of Construction Procurement.
University of Glamorgan. 5(2), November, 141-158.
Kaka, A.P. and Dawood, N. (2000) Assessing the need to consider cash flow as a
factor in deciding what type of procurement system the client should
implement, in Proceeding of the CIB W92 Procurement System Symposium
10
on Information and Communication in Construction Procurement. Santiago,
Chile, 24-27 April, pp. 657-665.
Lowe, J.G. and Lowe, H.C (1986) Cash flow forecasting and the building client, a
simulation approach, in Brandon, P.S. (ed.) Building Cost Modelling and
Computers, E & FN Spon, London, pp. 503-511.
Lowe, J.G. (1987) Cash flow and the construction client – a theoretical approach, in
Lansley, P.R. and Harlow, P.A. (Eds.) Managing Construction Worldwide, E
& FN Spon, London, volume 1, pp. 327-336.
Lowe, J.G, Moussa, N. and Lowe, H.C (1993) Cash flow management: an expert
system for the construction client. Journal of Applied Expert Systems, 1(2)
pp. 134-152.
Lowe, J.G. and Lowe, H.C (1997) An expert system to manage cash flow for the
construction client. BSU Research Paper No 3, Dept. of Building and
Surveying, Glasgow Caledonian University, Glasgow.
Moussa, N. (1992) Cash flow forecasting and the client: an integrated database –
expert system model. M. Sc. dissertation, Dept. of Building Engineering
and Surveying, Heriot-Watt University, Edinburgh.
Saleh, S.O. (1991) Developing an expert system model for cash flow forecasting in
the construction industry. M. Sc. dissertation, Dept of Building Engineering
and Surveying, Heriot-Watt University, Edinburgh.
Singh, S. ( 1987) A computer model for financial resource planning of high rise
building projects, in Lansley, P.R. and Harlow, P.A. (eds.) Managing
Construction Worldwide, E & FN Spon, London, volume 1, pp. 337-348.
Teicholtz, P.M. (1987) Current needs for cost control systems, in Ibbs, C.W. and
Ashrey, D.B. (eds.), Project Controls: Needs and Solutions, New York,
ASCE, pp.47-57.
11